You are on page 1of 5

Design and Construction of the Millennium Dome, UK

Ian Liddell, Civil Eng.


Paul Westbury, Civil Eng.
Buro Happold, Bath, UK

Foundations and Anchorages

Ground investigation works were car-


ried out, including extensive bore-
holes, trial pitting, and the use of seis-
mic and geophysical techniques, to
evaluate existing structures. The aim of
the detailed investigation was to deter-
mine whether ground improvement
would be acceptable, or whether piling
into the terrace gravels below the silt,
or into the London clay below that, was
necessary. Since the exhibition was
intended to be temporary, it was at-
tempted to avoid covering the site with
piles that could hamper future rede-
velopment.
A critical finding of the investigation
was the extent and depth of spent lime.
Fig. 1: The Millennium Dome under construction Because of the loose nature of the top 4
m of fill and the 6 m of soft alluvium,
the anticipated settlements were of the
order of 300 mm. Because of this and
the requirements of the Environmen-
Introduction ber of old underground structures that tal Agency, which prohibited the use of
had to be broken out or reused.
vibro-replacement stone columns, dri-
The Millennium Experience is to be ven cast-in-situ piles were adopted for
held in the year 2000 on the Green- Highways Issues the general piling, with augered piles
wich Peninsula, London. After investi- adjacent to the Blackwall tunnel in dr-
A further constraint was the south-
gating ways of housing the exhibitions der to transfer the loads to a depth be-
bound carriageway of the Blackwall
in conventional halls, a large umbrella low the tunnel.
Tunnel, which pa>sesunder the site,
over the site was proposed. The struc- To resist the uplift forces from the ten-
with a vent structure that would be
ture, which is now complete, covers an sioned cable structure, screw-in an-
within the dome. The potential impact
enclosed area of 80000 m2 with a of the Dome foundations on the Tun- chors and grouted cable anchors were
polytetrafluoroethane (PTFE)-coated nel therefore had to be assessed. In ad- used. Mass concrete blocks were used
glass-fibre fabric roof (Fig. I). The pro- dition, the future construction of the as anchors in anticipation of the Third
ject has been the subject of continuous Third Blackwall Crossing, comprising Blackwall Tunnel.
controversy, but has already become an another tunnel between the two exist-
icon for the new millennium. This ing Tunnels, had to be taken into ac-
paper presents the design and con- count. Roof Structure
struction of the Dome, which are de-
scribed in more detail in [l].
Environmental Issues Engineering Concept
The Environment Agency required that Tension structures rely on the shape of
Site Constraints contaminant migration to the mi-nor the stressed surface for their perfor-
aquifer in the terrace gravel was mance under load. Forces are resisted
Site History eliminated, and all foundation solu- by the tension and the curvature; the
tions considered had to be evaluated on greater the curvature, the less the ten-
The site was used as a town gasworks environmental grounds. In addi-tion, sion required to resist a given load.
from the late 1880s until the early all works within 16 m of the river wall Over the past 25 years, the accepted
1970s. As a result, there was extensive required approval from the Envi- form for fabric structures had became
contamination due to deposition of ronment Agency. In the north-east sec- the anticlastic doubly curved surface;
waste and to leakage from under- tion of the site, one of the Dome an- however, the structural concept of the
ground tanks and pipes, which were re- chorages comes within this range, and Millennium Dome departs radically
moved during statutory remediation the construction works therefore had to from this form. The new concept is in-
works in 1996. There were also a num- be formally approved. novative, yet apparently very simple.

172 Structures for the Next Millennium Structural Engineering International


3/99
A total of 72 tensioned steel cables are cause as the span of the fabric panels
arranged radially on the surface of the increases, their deflection under load
dome, forming a structure with a diam- also increases. Circumferential cables
eter of 400 m. The cables are support- through the nodes were used to main-
ed at the nodes from external masts by tain their spacing. If these cables were
means of hangers and tie-down cables in the surface of the fabric they could
at 25-m intervals. Two rings of masts cause a dam at each circumferential
were proposed: a central ring of twelve line, possibly initiating ponding; there-
and an outer ring of 24 masts. The radi- fore, an arrangement was required that
al cable lines reduced from 72 at the would take these cables away from the
perimeter to 48 at the centre. The radi- surface. This was achieved by raising
al cable forces were to be taken at the the circumferential cables above the
perimeter by raking ground anchors in Fig. 2: Isometric of the cable net surface of the dome by means of with
a typical marquee arrangement. rigid members (wishbones) and con-
necting them to the nodes via bracing
The surface of the dome is defined as a cables. Lower circumferential cables
spherical cap. Between the cables, flat Design Development were also required to control the tie-
tensioned coated fabric is used as down cables; these were also distanced
cladding. Loads are carried by the ten- In the final design, the diameter of the from the surface, but without the use
sioned cables and the cladding through Dome to the walls was reduced from of bracing cables.
deflection, accompanied by some in- 400 to 320 m, and the internal height at
crease in tension. While this concept is the centre was fixed as 48 m. The main To control the deflection of the radial
simple, there are risks associated with inner masts were moved out and made cables, each of which spans 25 m, a
the resulting deflections, particularly higher (100 m), and the outer ring of pretension of 400 kN, about 70% of
from ponding of snow or heavy rain. To masts was eliminated (Fig. 2). To keep the ultimate strength, was used. The
ensure that the structure functions the tie-down cables clear of the prestreas in the fabric was planned to
satisfactorily, it is necessary to under- planned internal structures, the masts be 4 kN/m.
stand the behaviour of the materials and were supported on pyramidal bases 10
the structure as a whole, and to en-sure m high. The-radial cables run from the
that the geometry is correct. perimeter to a 30-m-diameter cen-tral Structural Detailing
The straight-cable concept was pro- ring consisting of 12 cables, each 48
posed in response to the designers idea mm in diameter (F&s. 3 and 4). At the With cable structures, it is essential
to provide a large umbrella over the perimeter, the radial cables are linked that the detailing respects the system
entire site. It was carried out at a stage via catenary cables to 24 an-, chorage lines and system points of the cables
when cost and time were critical. The points at ground level. To re-sist the and their intersections, as well as the
structural concept had already been cable forces, vertical anchors are likely rotations of the cables at the
used on two structures in the UK: one arranged with a ring beam in order connections. If the radial cables were
to take the horizontal component of,
encompassing tennis courts; the other 1 y continuous through the node points,
forming an audience tent of 18000 mZ. the forces. the flexing at those noints would cause
The latter had proved very economical the cables to fail due to fatigue. To
The straight-cable structure is very ef-
and successful in terms of construction avoid this flexing, the cables have to
ficient as far as strength is concerned,
time and ease of installa-tion. be terminated at each node and the
but it relies on deflections as part of its
Therefore, it was considered that the con-nection details have to allow for
load-carrying behaviour. Consequent-
Millennium Dome structure, which was rota-tion in the vertical and horizontal
ly, it is necessary to ensure that pond-
fivefold larger, could be devel-oped and planes. Barrel pins were used in clevis
ing under snow or rain does not occur.
constructed in the limited time scale and plate type fittings to provide for
In this respect, the roof shape, with ta-
available. these rotations.
pering segments, is advanmgeous be-

Fig.3: Detail of the central cable truss Fig. 4: Masts and cable net
during construction

Structural Engineering International 3199


Structures for the Next Millennium 173
Ground snow loading was derived that of daylight. The objective was to
__j__ Almnininm
from statistical analysis of snowfall have a total light transmission above
fabric clips data from the nearest stations. The roof 10%. A double skin construction was
accumulation factors were taken from required to minimise the risk of con-
Primary radial
cables the snow loading code and other densation, which would otherwise re-
references concerning snow drifting on duce the light transmission.
large roofs [3].
Fittingsto support The roof was originally designed with
raincap
mast
over The results of the analyses gave peak polyvinylchloride (PVC)-coated poly-
loads on the components that were de- ester. At this time, the Dome was ex-
Tensioning jack
tailed according to normal design rules. pected to be temporary and the aim
The masts were designed to re-sist was to minimise costs. However, in
Perimeter mast top wind and ice loads, as well as buck- June 1997 it was decided that all op-
ling. tions should be kept open regarding
Tieback cables the long-term use of the Dome, and a
Resistance of the whole structure to
accidental damage is provided by re- subsequent review concluded that
dundancy, i.e. the structure can toler- PTFE-coated glass fibre would be a
Plan
ate the loss of an individual compo- more appropriate material. The life
nent without collapse. This principle expectancy of the roof would be much
Section also applies to the support pyramids, longer, and PIPE-coated glass fibres do
not suffer from the dirt-retention and
which are designed to withstand the
discolouration problems experi-enced
Primary radial cable removal of a leg.
by PVC-coated polyester.
The overall diameter of the masts was
limited by transportation require-
ments, and a great deal of computer Steelwork Construction
calculation went into verifying their
load capacity. The limiting load was The steel contractor prepared shop
calculated using the LUSAS program drawings based on the engineers de-
in a non-linear mode. Since the masts sign drawings. These drawings, show-
are leaning, deflections under self- ing the dimensions of all the plates, as
% weight-and icing have to be taken into well as the welding and connection de-
A account, as well as initial out-of- tails, were reviewed and approved by
Elevation straightness. Wind loading is also sig- the engineer prior to the start of fabri-
nificant, but this does not occur simul- cation.
Fig. 5: Radial cable . taneously with the peak vertical loads
connections at the masts The cables were wound from wires that
from snow and ice. had been drawn and galvanised. Class
A galvanising, the lightest class
Selection of Cladding available, was specified for cables be-
Each mast was constructed from eight neath the roof, while Galfan, a mixture
323-mm-diameter steel tubes braced and the Internal Environment
of aluminium and zinc that is much
with rings at 2.5-m centres. The cables The roof is to providea controlled en- more durable than zinc alone, was
were connected to radial plates at the vironment for the exhibition and for specified for the external cables. Cable
top and bottom, which are arranged to any future use. It was desirable to have lengths were determined after pre-
ensure that the cables meet at a single a bright translucent roof (Fig. 6) with a stretching under a specified prestress
point (Fig. 5). The base of the mast is light spectrum as close as possible to load, in order to allow for stretching
supported on the pyramid with a rubber during construction.
pot bearing to allow a small amount of
rotation.
Erection
Design Verification
During the design development stages, The lifting of the masts (Fig. 7) was
the structure was analysed using soft- planned with great care. This involved
ware developed specifically for tension selecting a suitable crane and devising
structures. This software is able to han- lifting positions that would not over-
stress the masts. Each mast was lifted
dle large deflections of the structure
and guyed with two permanent back-
under load. It can also calculate the
stays and two temporary forestays.
form of the structure under specified
While the crane was being released,
tensions representing the prestressed
only one forestay could be used, and a
condition. short-term guy was therefore added
The wind loads were initially derived from the centre of the mast to the adja-
from published data [2]. Subsequently, cent base. While the mast was held by
they were confirmed by wind tunnel the temporary forestays, the central ring
testing, although the results from the was lifted by the permanent forestays.
tunnel tests were generally lower than Fig. 6: Interior of the dome during construc- During derigging of the crane and
those calculated. tion changing of the guy posi-
174 Structures for the Next Millennium
StmctumiEngineering International
3/W
dard method of representation using with clamp bars at the edges. The net
triangular elements. The basic geome- patterns were developed directly from
try patterns were converted by the the typical fabric patterns with the
contractor into cutting patterns, who boundary line defined to align with the
allowed for stretch compensations, top of the vent. The net was erected in
which were defined after biaxial tests the same way as the fabric, using the
on the production cloth and considera- same extruded hooks modified with a
tion of the edge details. steel plate to which the cable termina-
tions were attached.
The fabric attachment detail was a
double-luff groove extrusion fitted onto
the radial cable pairs to accept a roped
edge on the fabric. The contrac-tor Conclusions
proposed a 12-mm edge cable in the
The Millennium Experience, a tempo-
fabric, which would hook into spe-cial
rary exhibition to celebrate the new
clamps fixed to the cables. The clamps
millennium, has been surrounded in
were developed into two-part
controversy. However, the dome struc-
extrusions cut into 50-mm lengths and
ture that has been erected to enclose
retained by two 12-mm bolts. Fabric-
the exhibition is now a dominant land-
sealing flaps were closed over the tops
mark on the Greenwich Peninsula (see
Fig.7:Thr IOOmhigh n~(lsts of the site joints and sealed using an cover of this issue). The dome struc-
iron at 380C and an FEP (flourinated ture was completed, on schedule and
ethylene propylene) interlayer (Fig. 8). within budget, in December 1998, and
tions, the tensions in the guys had to be work is now progressing on the assem-
carefully controlled to maintain the bly of the internal features.
stability of the mast.
After lifting the ring, the guy system
was moved so that the rest of the cable References
net could be assembled and lifted into [l] LIDDELL, W. I.; MILLER, I? W. The
place. This was carried out using hy-
draulic cable jacks, with the hoisting desig n an d constructio n of the Millennium
cables running over sheaves on top of Dome. The Structural Engineer, Vol. 77, No.
the masts. 7,1999, pp. 18-25.
[2] COOK, N. J. The designers guide to wind
loading of building structures. Butterworths,
Final Tensioning
London, 1985.
When the net was completely assem- [3] LIDDELL, I. Minnesota Metrodome. A
bled and all the cable lengths checked,
each of the 72 pairs of radial cables had study of the behaviour of air supported roofs
under environmental loads. Structural Engi-
to be tensioned (Fig. 5). This was
,.i neering Review, Vol. 6, No. 3-4,1994, pp.
achieved in several steps using a 55-t
capacity pull jack in the jacking points SE1 Data Block
at the front of the perimeter masts. Be-
cause of the flexibility of the central
ring and the boundary cables, tension- Owner:
ing of the radial cables had to be per-
formed to specified dimensions rather The New Millennium
than to specified loads, with final ad- Experience Co. Ltd
justments made at the end of the pro- Architect:
cedure. Fig.8:Installatiorlofthefabric Imagination Ltd,
Richard Rogers Partnership
Str~rcturrrl design.

Fabric work Buro Happold


Tunnel Vent Area Contractors:
Because of the arrangement of the
panels within the cable net, and the fact A 50-m-diameter hole was required in McAlpinciLaing Joint Venture,
that the cloths were to be fitted into the roof around the Blackwall tunnel Watson Steel, Birdair
dead lengths, the patterns had to be vents in order to maintain the air sup-ply
Wind tmnrltevting:
extremely accurate. Since the warp to the ventilation structure. After
direction of the panels of the outer BMT
considering a number of ways of incor-
fabric ran radially along the roof with stcc1 (1): 2000
porating a hole in the fabric, a net of 8-
25-m-long cloths, it was necessary to mm cables at l-m centres was adopted, Fabric (111): 100 000
model the fabric as an equal mesh net which would replicate the stress-carry- ,
in order to represent the warp and fill ing capacity of the fabric yet would al- Total cost (USD millions): 60
lines of the cloth. This method is much low the air vent to pass through. The Service date: January 2000
more time consuming than the stan- cable net was attached to the fabric

Structural Engineering International 3199 Structures for the Next


Millennium 17.5

You might also like