Mundra LPG Pvt Ltd Classic Schedule Layout 12/Jun/2017 16:07

# Ac vity ID Ac vity Name Calendar Original Early Start Early Finish Late Start Late Finish Total 2017 2018
Float Apr M Jun Jul Aug Sep Oct N Dec Jan F M Apr M Jun Jul Aug Sep Oct N Dec
1 Project Management & Control LPG 5*8Dura382d
on 10/May/2017 09/Nov/2018 05/May/2017 06/Nov/2018 -1d 09/Nov/2018, Project Man

2 General Ac vi es & Milestones LPG 5*8 382d 10/May/2017 09/Nov/2018 05/May/2017 06/Nov/2018 -1d 09/Nov/2018, General Ac
3 Commons LPG 5*8 382d 10/May/2017 09/Nov/2018 05/May/2017 06/Nov/2018 -1d 09/Nov/2018, Commons
4 Milestones LPG 5*8 382d 10/May/2017 09/Nov/2018 05/May/2017 06/Nov/2018 -1d 09/Nov/2018, Milestones
5 GA1000 Issue of LOI (Zero Date) LPG 5*8 0d 10/May/2017 05/May/2017 -3d Issue of LOI (Zero Date), 10/May/2017
6 GA1002 First Issue of P&ID LPG 5*8 0d 14/Jul/2017 06/Nov/2018 333d First Issue of P&ID,
7 GA1004 First Issue of Equipment Layout Plan LPG 5*8 0d 10/May/2017 06/Nov/2018 381d First Issue of Equipment Layout Plan,
8 GA1006 Complete 30% 3D Modeling Review LPG 5*8 0d 08/Sep/2017 06/Nov/2018 295d Complete 30% 3D Modeling Review,
9 GA1008 Complete 60% 3D Modeling Review LPG 5*8 0d 06/Dec/2017 06/Nov/2018 235d Complete 60% 3D Modeling Review,
10 GA1010 Complete 90% 3D Modeling Review LPG 5*8 0d 01/Mar/2018 06/Nov/2018 175d Complete 90% 3D Modeling Review,
11 GA1012 Engineering Comple on LPG 5*8 0d 27/Apr/2018 06/Nov/2018 135d Engineering Comple on,
12 GA1014 Mechanical Comple on LPG 5*8 0d 10/Sep/2018 10/Sep/2018 0d Mechanical Comple on,
13 GA1016 Substan al Comple on LPG 5*8 0d 09/Nov/2018 06/Nov/2018 -1d Substan al Comple on,
14 Project Plans & Procrdures LPG 5*8 316d 10/May/2017 03/Aug/2018 05/May/2017 06/Nov/2018 65d 03/Aug/2018, Project Plans & Procrdures
15 GA1018 Mobiliza on of Core Team LPG 5*8 9d 10/May/2017 22/May/2017 05/May/2017 18/May/2017 -3d Mobiliza on of Core Team
16 GA1020 KOM LPG 5*8 2d 23/May/2017 24/May/2017 18/May/2017 22/May/2017 -3d KOM
17 GA1022 Project Planning Scheduling & Monitoring Procedure LPG 5*8 10d 25/May/2017 07/Jun/2017 06/Jul/2017 19/Jul/2017 30d Project Planning Scheduling & Monitoring Procedure
18 GA1023 Prepare & Issue Planning WBS - IFI LPG 5*8 5d 12/May/2017 18/May/2017 22/Jun/2017 28/Jun/2017 29d Prepare & Issue Planning WBS - IFI
19 GA1024 Overall Project Schedule (Level 1) - IFI LPG 5*8 2d 19/May/2017 22/May/2017 05/Nov/2018 06/Nov/2018 372d Overall Project Schedule (Level 1) - IFI
20 GA1028 Prepare & Submit Overall Project Schedule IFR/IFA LPG 5*8 15d 19/May/2017 08/Jun/2017 29/Jun/2017 19/Jul/2017 29d Prepare & Submit Overall Project Schedule IFR/IFA
21 GA1030 MLTPL Review Overall Project Schedule LPG 5*8 7d 09/Jun/2017 19/Jun/2017 21/Jul/2017 31/Jul/2017 30d MLTPL Review Overall Project Schedule
22 GA1032 Finalize Overall Project Schedule - IFI LPG 5*8 15d 20/Jun/2017 10/Jul/2017 01/Aug/2017 23/Aug/2017 30d Finalize Overall Project Schedule - IFI
23 GA1034 Prepare & Finalize PMS & S Curves - IFI LPG 5*8 25d 09/Jun/2017 13/Jul/2017 20/Jul/2017 25/Aug/2017 29d Prepare & Finalize PMS & S Curves - IFI
24 GA1036 Project Documents Controls Procedure - IFI LPG 5*8 10d 25/May/2017 07/Jun/2017 06/Jul/2017 19/Jul/2017 30d Project Documents Controls Procedure - IFI
25 GA1038 Project Execu on Methodology - IFI LPG 5*8 10d 25/May/2017 07/Jun/2017 06/Jul/2017 19/Jul/2017 30d Project Execu on Methodology - IFI
26 GA1040 Project Communica on Plan - IFI LPG 5*8 10d 25/May/2017 07/Jun/2017 06/Jul/2017 19/Jul/2017 30d Project Communica on Plan - IFI
27 GA1042 Project Risk Management Plan - IFI LPG 5*8 15d 25/May/2017 14/Jun/2017 29/Jun/2017 19/Jul/2017 25d Project Risk Management Plan - IFI
28 GA1044 Project Quality Management Plan - IFI LPG 5*8 10d 25/May/2017 07/Jun/2017 06/Jul/2017 19/Jul/2017 30d Project Quality Management Plan - IFI
29 GA1046 Project HSE Management Plan - IFI LPG 5*8 10d 25/May/2017 07/Jun/2017 06/Jul/2017 19/Jul/2017 30d Project HSE Management Plan - IFI
30 GA1048 Project Engineering Management Plan - IFI LPG 5*8 10d 25/May/2017 07/Jun/2017 06/Jul/2017 19/Jul/2017 30d Project Engineering Management Plan - IFI
31 GA1050 Project Procurement Management Plan - IFI LPG 5*8 15d 25/May/2017 14/Jun/2017 29/Jun/2017 19/Jul/2017 25d Project Procurement Management Plan - IFI
32 GA1052 Project Construc on Management Plan - IFI LPG 5*8 15d 25/May/2017 14/Jun/2017 09/Mar/2018 30/Mar/2018 200d Project Construc on Management Plan - IFI
33 GA1054 Project Change Management Plan - IFI LPG 5*8 10d 25/May/2017 07/Jun/2017 06/Jul/2017 19/Jul/2017 30d Project Change Management Plan - IFI
34 GA1056 Mobiliza on of Construc on Management Team LPG 5*8 45d 15/Jun/2017 18/Aug/2017 04/Sep/2018 06/Nov/2018 310d Mobiliza on of Construc on Management Team
35 GA1058 Method Statement & Construc on Procudures - IFI LPG 5*8 25d 15/Jun/2017 19/Jul/2017 02/Apr/2018 04/May/2018 200d Method Statement & Construc on Procudures - IFI
36 GA1060 Prepare & Submit WPR/ MPR - IFI LPG 5*8 290d 15/Jun/2017 03/Aug/2018 20/Jul/2017 10/Sep/2018 25d Prepare & Submit WPR/ MPR - IFI
37 Interfaces & Approvals LPG 5*8 26d 10/May/2017 14/Jun/2017 25/May/2017 06/Nov/2018 355d 14/Jun/2017, Interfaces & Approvals
38 GA1062 Graded Plot Handover by MLTPL for Warehouse Area LPG 5*8 0d 13/Jun/2017 21/Jul/2017 28d Graded Plot Handover by MLTPL for Warehouse Area,
39 GA1064 IBR/PESO Approval LPG 5*8 0d 10/May/2017 06/Nov/2018 381d IBR/PESO Approval, 10/May/2017
40 GA1074 MLTPL decision for Modelling So ware LPG 5*8 15d 25/May/2017 14/Jun/2017 25/May/2017 14/Jun/2017 0d MLTPL decision for Modelling So ware
41 Engineering LPG 5*8 236d 10/May/2017 13/Apr/2018 22/May/2017 06/Nov/2018 145d 13/Apr/2018, Engineering

42 Process LPG 5*8 178d 25/May/2017 06/Feb/2018 22/May/2017 06/Nov/2018 192d 06/Feb/2018, Process
43 Commons LPG 5*8 178d 25/May/2017 06/Feb/2018 22/May/2017 06/Nov/2018 192d 06/Feb/2018, Commons

Actual Level of Effort Remaining Work Milestone Page 1 of 30 TASK filter: All Activities
Actual Work Critical Remaining Work summary Oracle Corporation
Mundra LPG Pvt Ltd Classic Schedule Layout 12/Jun/2017 16:07
# Ac vity ID Ac vity Name Calendar Original Early Start Early Finish Late Start Late Finish Total 2017 2018
Float Apr M Jun Jul Aug Sep Oct N Dec Jan F M Apr M Jun Jul Aug Sep Oct N Dec
44 Overall LPG 5*8Dura178d
on 25/May/2017 06/Feb/2018 22/May/2017 06/Nov/2018 192d 06/Feb/2018, Overall
45 EP1000 Prepare & Issue Process Design Basis - IFR/IFA LPG 5*8 12d 25/May/2017 09/Jun/2017 22/May/2017 07/Jun/2017 -3d Prepare & Issue Process Design Basis - IFR/IFA
46 EP1002 MLTPL Review - Process Design Basis LPG 5*8 7d 12/Jun/2017 20/Jun/2017 28/Sep/2018 09/Oct/2018 331d MLTPL Review - Process Design Basis
47 EP1004 Finalize - Process Design Basis LPG 5*8 20d 26/Jun/2017 21/Jul/2017 10/Oct/2018 06/Nov/2018 328d Finalize - Process Design Basis
48 EP1006 Prepare & Issue Isola on Philosophy IFA/IFR LPG 5*8 15d 25/May/2017 14/Jun/2017 07/Sep/2018 27/Sep/2018 328d Prepare & Issue Isola on Philosophy IFA/IFR
49 EP1008 MLTPL Review - Isola on Philosophy LPG 5*8 7d 15/Jun/2017 23/Jun/2017 28/Sep/2018 09/Oct/2018 328d MLTPL Review - Isola on Philosophy
50 EP1010 Finalize - Isola on Philosophy LPG 5*8 20d 26/Jun/2017 21/Jul/2017 10/Oct/2018 06/Nov/2018 328d Finalize - Isola on Philosophy
51 EP1012 Prepare & Issue Drainage Philosophy IFA/IFR LPG 5*8 15d 25/May/2017 14/Jun/2017 07/Sep/2018 27/Sep/2018 328d Prepare & Issue Drainage Philosophy IFA/IFR
52 EP1014 MLTPL Review - Drainage Philosophy LPG 5*8 7d 15/Jun/2017 23/Jun/2017 28/Sep/2018 09/Oct/2018 328d MLTPL Review - Drainage Philosophy
53 EP1016 Finalize - Drainage Philosophy LPG 5*8 20d 26/Jun/2017 21/Jul/2017 10/Oct/2018 06/Nov/2018 328d Finalize - Drainage Philosophy
54 EP1018 Prepare & Issue - Surge Analysis Report - IFR/IFA LPG 5*8 15d 25/May/2017 14/Jun/2017 07/Sep/2018 27/Sep/2018 328d Prepare & Issue - Surge Analysis Report - IFR/IFA
55 EP1020 MLTPL Review - Surge Analysis Report LPG 5*8 7d 15/Jun/2017 23/Jun/2017 28/Sep/2018 09/Oct/2018 328d MLTPL Review - Surge Analysis Report
56 EP1022 Finalize - Surge Analysis Report LPG 5*8 20d 26/Jun/2017 21/Jul/2017 10/Oct/2018 06/Nov/2018 328d Finalize - Surge Analysis Report
57 EP1024 Prepare & Issue Cooldown Philosophy - IFR/IFA LPG 5*8 15d 25/May/2017 14/Jun/2017 07/Sep/2018 27/Sep/2018 328d Prepare & Issue Cooldown Philosophy - IFR/IFA
58 EP1026 MLTPL Review - Cooldown Philosophy LPG 5*8 7d 15/Jun/2017 23/Jun/2017 28/Sep/2018 09/Oct/2018 328d MLTPL Review - Cooldown Philosophy
59 EP1028 Finalize - Cooldown Philosophy LPG 5*8 20d 26/Jun/2017 21/Jul/2017 10/Oct/2018 06/Nov/2018 328d Finalize - Cooldown Philosophy
60 EP1030 Prepare & Issue PFD - IFR/IFA LPG 5*8 10d 12/Jun/2017 23/Jun/2017 07/Jun/2017 21/Jun/2017 -3d Prepare & Issue PFD - IFR/IFA
61 EP1032 MLTPL Review - PFD LPG 5*8 7d 26/Jun/2017 04/Jul/2017 28/Sep/2018 09/Oct/2018 321d MLTPL Review - PFD
62 EP1034 Finalize - PFD LPG 5*8 20d 05/Jul/2017 01/Aug/2017 10/Oct/2018 06/Nov/2018 321d Finalize - PFD
63 EP1036 Prepare & Issue H&MB - IFR/IFA LPG 5*8 10d 12/Jun/2017 23/Jun/2017 17/Aug/2018 30/Aug/2018 301d Prepare & Issue H&MB - IFR/IFA
64 EP1038 MLTPL Review - H&MB LPG 5*8 7d 26/Jun/2017 04/Jul/2017 28/Sep/2018 09/Oct/2018 321d MLTPL Review - H&MB
65 EP1039 Finalize - H&MB LPG 5*8 20d 05/Jul/2017 01/Aug/2017 10/Oct/2018 06/Nov/2018 321d Finalize - H&MB
66 EP1040 Prepare & Issue Hydraulic Summary Report- IFA/IFR LPG 5*8 20d 26/Jun/2017 21/Jul/2017 31/Aug/2018 27/Sep/2018 301d Prepare & Issue Hydraulic Summary Report- IFA/IFR
67 EP1041 MLTPL Review - Hydraulic Summary Report LPG 5*8 7d 24/Jul/2017 01/Aug/2017 28/Sep/2018 09/Oct/2018 301d MLTPL Review - Hydraulic Summary Report
68 EP1042 Finalize - Hydraulic Summary Report LPG 5*8 20d 02/Aug/2017 31/Aug/2017 10/Oct/2018 06/Nov/2018 301d Finalize - Hydraulic Summary Report
69 EP1043 Prepare & Issue Equipment Sizing Report - IFA/IFR LPG 5*8 10d 26/Jun/2017 07/Jul/2017 14/Sep/2018 27/Sep/2018 311d Prepare & Issue Equipment Sizing Report - IFA/IFR
70 EP1044 MLTPL Review - Equipment Sizing Report LPG 5*8 7d 10/Jul/2017 18/Jul/2017 28/Sep/2018 09/Oct/2018 311d MLTPL Review - Equipment Sizing Report
71 EP1045 Finalize - Equipment Sizing Report LPG 5*8 20d 19/Jul/2017 17/Aug/2017 10/Oct/2018 06/Nov/2018 311d Finalize - Equipment Sizing Report
72 EP1051 Prepare & Issue UFD - IFR/IFA LPG 5*8 10d 12/Jun/2017 23/Jun/2017 14/Sep/2018 27/Sep/2018 321d Prepare & Issue UFD - IFR/IFA
73 EP1052 MLTPL Review - UFD LPG 5*8 7d 26/Jun/2017 04/Jul/2017 28/Sep/2018 09/Oct/2018 321d MLTPL Review - UFD
74 EP1053 Finalize - UFD LPG 5*8 20d 05/Jul/2017 01/Aug/2017 10/Oct/2018 06/Nov/2018 321d Finalize - UFD
75 EP1054 Prepare & Issue MSD - IFR/IFA LPG 5*8 5d 26/Jun/2017 30/Jun/2017 21/Sep/2018 27/Sep/2018 316d Prepare & Issue MSD - IFR/IFA
76 EP1055 MLTPL Review - MSD LPG 5*8 7d 03/Jul/2017 11/Jul/2017 28/Sep/2018 09/Oct/2018 316d MLTPL Review - MSD
77 EP1056 Finalize - MSD LPG 5*8 20d 12/Jul/2017 09/Aug/2017 10/Oct/2018 06/Nov/2018 316d Finalize - MSD
78 EP1057 Prepare & Issue PDS - Packages - IFR/IFA LPG 5*8 10d 12/Jun/2017 23/Jun/2017 11/Jul/2017 24/Jul/2017 21d Prepare & Issue PDS - Packages - IFR/IFA
79 EP1058 MLTPL Review - PDS - Packages LPG 5*8 7d 26/Jun/2017 04/Jul/2017 28/Sep/2018 09/Oct/2018 321d MLTPL Review - PDS - Packages
80 EP1059 Finalize - PDS - Packages LPG 5*8 20d 05/Jul/2017 01/Aug/2017 10/Oct/2018 06/Nov/2018 321d Finalize - PDS - Packages
81 EP1060 Prepare & Issue P&ID - IFR/IFA LPG 5*8 15d 26/Jun/2017 14/Jul/2017 21/Jun/2017 12/Jul/2017 -3d Prepare & Issue P&ID - IFR/IFA
82 EP1062 MLTPL Review - P&ID LPG 5*8 7d 17/Jul/2017 25/Jul/2017 20/Apr/2018 30/Apr/2018 192d MLTPL Review - P&ID
83 EP1064 Finalize - P&ID LPG 5*8 30d 26/Jul/2017 07/Sep/2017 01/May/2018 11/Jun/2018 192d Finalize - P&ID
84 EP1066 Prepare & Issue PDS - Equipment - IFR/IFA LPG 5*8 15d 03/Jul/2017 21/Jul/2017 28/Jun/2017 19/Jul/2017 -3d Prepare & Issue PDS - Equipment - IFR/IFA
85 EP1068 MLTPL Review - PDS - Equipment LPG 5*8 7d 24/Jul/2017 01/Aug/2017 28/Sep/2018 09/Oct/2018 301d MLTPL Review - PDS - Equipment
86 EP1070 Finalize - PDS - Equipment LPG 5*8 20d 02/Aug/2017 31/Aug/2017 10/Oct/2018 06/Nov/2018 301d Finalize - PDS - Equipment

Actual Level of Effort Remaining Work Milestone Page 2 of 30 TASK filter: All Activities
Actual Work Critical Remaining Work summary Oracle Corporation
Mundra LPG Pvt Ltd Classic Schedule Layout 12/Jun/2017 16:07
# Ac vity ID Ac vity Name Calendar Original Early Start Early Finish Late Start Late Finish Total 2017 2018
Float Apr M Jun Jul Aug Sep Oct N Dec Jan F M Apr M Jun Jul Aug Sep Oct N Dec
87 EP1072 Prepare & Issue PDS - Instruments IFR/IFA LPG 5*8Dura10d
on 17/Jul/2017 28/Jul/2017 22/Aug/2017 05/Sep/2017 24d Prepare & Issue PDS - Instruments IFR/IFA
88 EP1074 MLTPL Review - PDS - Instruments LPG 5*8 7d 31/Jul/2017 09/Aug/2017 28/Sep/2018 09/Oct/2018 296d MLTPL Review - PDS - Instruments
89 EP1076 Finalize - PDS - Instruments LPG 5*8 20d 10/Aug/2017 07/Sep/2017 10/Oct/2018 06/Nov/2018 296d Finalize - PDS - Instruments
90 EP1078 Prepare & Issue PDS - Valves - IFR/IFA LPG 5*8 10d 17/Jul/2017 28/Jul/2017 14/Sep/2018 27/Sep/2018 296d Prepare & Issue PDS - Valves - IFR/IFA
91 EP1080 MLTPL Review - PDS - Valves LPG 5*8 7d 31/Jul/2017 09/Aug/2017 28/Sep/2018 09/Oct/2018 296d MLTPL Review - PDS - Valves
92 EP1082 Finalize - PDS - Valves LPG 5*8 20d 10/Aug/2017 07/Sep/2017 10/Oct/2018 06/Nov/2018 296d Finalize - PDS - Valves
93 EP1084 Prepare & Issue Equipment List - IFI LPG 5*8 5d 26/Jun/2017 30/Jun/2017 21/Jun/2017 28/Jun/2017 -3d Prepare & Issue Equipment List - IFI
94 EP1086 Prepare & Issue Fluid & Line List - IFR/IFA LPG 5*8 10d 31/Jul/2017 14/Aug/2017 11/Sep/2017 26/Sep/2017 28d Prepare & Issue Fluid & Line List - IFR/IFA
95 EP1088 MLTPL Review - Fluid & Line List LPG 5*8 7d 16/Aug/2017 24/Aug/2017 28/Sep/2018 09/Oct/2018 286d MLTPL Review - Fluid & Line List
96 EP1090 Finalize - Fluid & Line List LPG 5*8 20d 25/Aug/2017 25/Sep/2017 10/Oct/2018 06/Nov/2018 286d Finalize - Fluid & Line List
97 EP1092 Prepare & Issue Cause & Eect Diagram - IFA/IFR LPG 5*8 10d 26/Jul/2017 09/Aug/2017 17/Aug/2018 30/Aug/2018 269d Prepare & Issue Cause & Eect Diagram - IFA/IFR
98 EP1094 MLTPL Review - Cause & Eect Diagram LPG 5*8 7d 10/Aug/2017 21/Aug/2017 28/Sep/2018 09/Oct/2018 289d MLTPL Review - Cause & Eect Diagram
99 EP1096 Finalize - Cause & Eect Diagram LPG 5*8 20d 22/Aug/2017 18/Sep/2017 10/Oct/2018 06/Nov/2018 289d Finalize - Cause & Eect Diagram
100 EP1098 Prepare & Issue Tie-in point list - IFR/IFA LPG 5*8 10d 16/Aug/2017 29/Aug/2017 14/Sep/2018 27/Sep/2018 276d Prepare & Issue Tie-in point list - IFR/IFA
101 EP1100 MLTPL Review - Tie-in point list LPG 5*8 7d 30/Aug/2017 07/Sep/2017 28/Sep/2018 09/Oct/2018 276d MLTPL Review - Tie-in point list
102 EP1102 Finalize - Tie-in point list LPG 5*8 20d 08/Sep/2017 09/Oct/2017 10/Oct/2018 06/Nov/2018 276d Finalize - Tie-in point list
103 EP1104 Prepare & Issue HAZOP & SIL Procedure - IFR/IFA LPG 5*8 10d 10/Aug/2017 24/Aug/2017 14/Sep/2018 27/Sep/2018 279d Prepare & Issue HAZOP & SIL Procedure - IFR/IFA
104 EP1106 MLTPL Review - HAZOP & SIL Procedure LPG 5*8 7d 25/Aug/2017 04/Sep/2017 28/Sep/2018 09/Oct/2018 279d MLTPL Review - HAZOP & SIL Procedure
105 EP1108 Finalize - HAZOP & SIL Procedure LPG 5*8 20d 05/Sep/2017 04/Oct/2017 10/Oct/2018 06/Nov/2018 279d Finalize - HAZOP & SIL Procedure
106 EP1110 Prepare & Issue F&G Mapping - IFR/IFA LPG 5*8 10d 31/Jul/2017 14/Aug/2017 14/Sep/2018 27/Sep/2018 286d Prepare & Issue F&G Mapping - IFR/IFA
107 EP1112 MLTPL Review - F&G Mapping LPG 5*8 7d 16/Aug/2017 24/Aug/2017 28/Sep/2018 09/Oct/2018 286d MLTPL Review - F&G Mapping
108 EP1114 Finalize - F&G Mapping LPG 5*8 20d 25/Aug/2017 25/Sep/2017 10/Oct/2018 06/Nov/2018 286d Finalize - F&G Mapping
109 EP1116 Prepare & Issue Relief Load Summary IFA/IFR LPG 5*8 10d 29/Aug/2017 11/Sep/2017 14/Sep/2018 27/Sep/2018 267d Prepare & Issue Relief Load Summary IFA/IFR
110 EP1118 MLTPL Review - Relief Load Summary LPG 5*8 7d 12/Sep/2017 22/Sep/2017 28/Sep/2018 09/Oct/2018 267d MLTPL Review - Relief Load Summary
111 EP1120 Finalize - Relief Load Summary LPG 5*8 20d 25/Sep/2017 20/Oct/2017 10/Oct/2018 06/Nov/2018 267d Finalize - Relief Load Summary
112 EP1128 Prepare & Issue Dispersion & Radia on Report - IFR/IFA LPG 5*8 15d 29/Aug/2017 18/Sep/2017 07/Sep/2018 27/Sep/2018 262d Prepare & Issue Dispersion & Radia on Report - IFR/IFA
113 EP1130 MLTPL Review - Dispersion & Radia on Report LPG 5*8 7d 21/Sep/2017 29/Sep/2017 28/Sep/2018 09/Oct/2018 262d MLTPL Review - Dispersion & Radia on Report
114 EP1132 Finalize - Dispersion & Radia on Report LPG 5*8 20d 02/Oct/2017 30/Oct/2017 10/Oct/2018 06/Nov/2018 262d Finalize - Dispersion & Radia on Report
115 EP1140 Prepare & Issue - Control & shutdown Philosophy- IFA/IFR LPG 5*8 20d 10/Aug/2017 07/Sep/2017 31/Aug/2018 27/Sep/2018 269d Prepare & Issue - Control & shutdown Philosophy- IFA/IFR
116 EP1142 MLTPL Review - Control & Shutdown Philosophy LPG 5*8 7d 08/Sep/2017 18/Sep/2017 28/Sep/2018 09/Oct/2018 269d MLTPL Review - Control & Shutdown Philosophy
117 EP1144 Finalize - Control & Shutdown Philosophy LPG 5*8 20d 21/Sep/2017 18/Oct/2017 10/Oct/2018 06/Nov/2018 269d Finalize - Control & Shutdown Philosophy
118 EP1145 Prepare & Issue Alarm & Trip Set point List - IFI LPG 5*8 10d 08/Sep/2017 25/Sep/2017 24/Oct/2018 06/Nov/2018 286d Prepare & Issue Alarm & Trip Set point List - IFI
119 EP1146 Prepare & Issue Safety Study Report - IFI LPG 5*8 10d 08/Sep/2017 25/Sep/2017 24/Oct/2018 06/Nov/2018 286d Prepare & Issue Safety Study Report - IFI
120 EP1148 Prepare & Issue Euent Summary - IFI LPG 5*8 10d 24/Jul/2017 04/Aug/2017 24/Oct/2018 06/Nov/2018 318d Prepare & Issue Euent Summary - IFI
121 EP1152 Prepare & Issue Flare Header Calcula on Report - IFI LPG 5*8 10d 12/Sep/2017 27/Sep/2017 24/Oct/2018 06/Nov/2018 284d Prepare & Issue Flare Header Calcula on Report - IFI
122 EP1156 Prepare & Issue Chemical consump on Summary - IFI LPG 5*8 10d 08/Sep/2017 25/Sep/2017 24/Oct/2018 06/Nov/2018 286d Prepare & Issue Chemical consump on Summary - IFI
123 EP1158 Prepare & Issue QRA Study Report - IFR/IFA LPG 5*8 10d 08/Sep/2017 25/Sep/2017 12/Jun/2018 25/Jun/2018 192d Prepare & Issue QRA Study Report - IFR/IFA
124 EP1160 MLTPL Review - QRA Study Report LPG 5*8 7d 26/Sep/2017 04/Oct/2017 26/Jun/2018 04/Jul/2018 192d MLTPL Review - QRA Study Report
125 EP1162 Finalize - QRA Study Report LPG 5*8 20d 05/Oct/2017 02/Nov/2017 05/Jul/2018 01/Aug/2018 192d Finalize - QRA Study Report
126 EP1164 Prepare & Issue Pre-Commissioing/Commissioing Procedure - IFR/IFA LPG 5*8 20d 03/Nov/2017 30/Nov/2017 02/Aug/2018 30/Aug/2018 192d Prepare & Issue Pre-Commissioing/Commissioing Procedure - IFR/IFA
127 EP1166 MLTPL Review - Pre-Commissioing/Commissioing Procedure LPG 5*8 7d 01/Dec/2017 11/Dec/2017 31/Aug/2018 10/Sep/2018 192d MLTPL Review - Pre-Commissioing/Commissioing Procedure
128 EP1168 Finalize - Pre-Commissioing/Commissioing Procedure LPG 5*8 20d 12/Dec/2017 08/Jan/2018 11/Sep/2018 09/Oct/2018 192d Finalize - Pre-Commissioing/Commissioing Procedure
129 EP1170 Prepare & Issue Opera on Manual - IFI LPG 5*8 20d 09/Jan/2018 06/Feb/2018 10/Oct/2018 06/Nov/2018 192d Prepare & Issue Opera on Manual - IFI

Actual Level of Effort Remaining Work Milestone Page 3 of 30 TASK filter: All Activities
Actual Work Critical Remaining Work summary Oracle Corporation
Mundra LPG Pvt Ltd Classic Schedule Layout 12/Jun/2017 16:07
# Ac vity ID Ac vity Name Calendar Original Early Start Early Finish Late Start Late Finish Total 2017 2018
Float Apr M Jun Jul Aug Sep Oct N Dec Jan F M Apr M Jun Jul Aug Sep Oct N Dec
130 Civil & Structural LPG 5*8Dura210d
on 10/May/2017 07/Mar/2018 31/May/2017 06/Nov/2018 171d 07/Mar/2018, Civil & Structural
131 Commons LPG 5*8 199d 25/May/2017 07/Mar/2018 31/May/2017 06/Nov/2018 171d 07/Mar/2018, Commons
132 Overall LPG 5*8 199d 25/May/2017 07/Mar/2018 31/May/2017 06/Nov/2018 171d 07/Mar/2018, Overall
133 EC2000 Prepare & Issue Design Basis - Civil LPG 5*8 10d 25/May/2017 07/Jun/2017 31/May/2017 13/Jun/2017 4d Prepare & Issue Design Basis - Civil
134 EC2010 Prepare & Issue Standard Drawings - IFR/IFA LPG 5*8 20d 08/Jun/2017 05/Jul/2017 26/Jul/2017 24/Aug/2017 34d Prepare & Issue Standard Drawings - IFR/IFA
135 EC2020 MLTPL Review Standard Drawings LPG 5*8 20d 22/Jun/2017 19/Jul/2017 14/Sep/2018 12/Oct/2018 313d MLTPL Review Standard Drawings
136 EC2030 Finalize Standard Drawings LPG 5*8 30d 03/Jul/2017 14/Aug/2017 25/Sep/2018 06/Nov/2018 313d Finalize Standard Drawings
137 EC2040 Prepare & Issue Soil Tes ng Report - IFI LPG 5*8 5d 07/Jul/2017 13/Jul/2017 18/Aug/2017 24/Aug/2017 28d Prepare & Issue Soil Tes ng Report - IFI
138 EC2050 Prepare & Issue TopoGraphy Reports - IFI LPG 5*8 10d 14/Jul/2017 27/Jul/2017 24/Oct/2018 06/Nov/2018 324d Prepare & Issue TopoGraphy Reports - IFI
139 EC2060 Prepare & Issue Layouts - Security Gates, Boundary Walls, Parking, Site oce, Store, Approach
LPG 5*8
Road etc20d 08/Jun/2017 05/Jul/2017 16/Feb/2018 16/Mar/2018 175d Prepare & Issue Layouts - Security Gates, Boundary Walls, Parking, Site oce, Store, Approach Road etc
140 EC2070 MLTPL Review Layouts - Security Gates, Boundary Walls, Parking, Site oce, Store, Approach
LPGRoad
5*8 etc 7d 06/Jul/2017 14/Jul/2017 22/Mar/2018 30/Mar/2018 178d MLTPL Review Layouts - Security Gates, Boundary Walls, Parking, Site oce, Store, Approach Road etc
141 EC2080 Finalize Layouts - Security Gates, Boundary Walls, Parking, Site oce, Store, Approach Road
LPG
etc5*8 20d 17/Jul/2017 14/Aug/2017 02/Apr/2018 27/Apr/2018 178d Finalize Layouts - Security Gates, Boundary Walls, Parking, Site oce, Store, Approach Road etc
142 EC2085 Prepare & Issue Piling Layout drawings-IFR/IFA LPG 5*8 15d 14/Jul/2017 03/Aug/2017 25/Aug/2017 14/Sep/2017 28d Prepare & Issue Piling Layout drawings-IFR/IFA
143 EC2090 Prepare & Issue Architectural Drawings - Non Plant Buildings IFA/IFR LPG 5*8 30d 08/Jun/2017 19/Jul/2017 05/Jul/2017 17/Aug/2017 19d Prepare & Issue Architectural Drawings - Non Plant Buildings IFA/IFR
144 EC2092 MLTPL Review - Architectural Drawings - Non Plant Buildings LPG 5*8 30d 22/Jun/2017 02/Aug/2017 30/Aug/2017 12/Oct/2017 47d MLTPL Review - Architectural Drawings - Non Plant Buildings
145 EC2095 Finalize - Architectural Drawings - Non Plant Buldings LPG 5*8 40d 03/Jul/2017 29/Aug/2017 08/Sep/2017 07/Nov/2017 47d Finalize - Architectural Drawings - Non Plant Buldings
146 EC2096 Prepare & Issue Civil & Structural Drawings - Non Plant Buildings IFA/IFR LPG 5*8 30d 06/Jul/2017 18/Aug/2017 02/Aug/2017 14/Sep/2017 19d Prepare & Issue Civil & Structural Drawings - Non Plant Buildings IFA/IFR
147 EC2098 MLTPL Review - Civil & Structural Drawings - Non Plant Buildings LPG 5*8 30d 20/Jul/2017 01/Sep/2017 06/Sep/2017 19/Oct/2017 32d MLTPL Review - Civil & Structural Drawings - Non Plant Buildings
148 EC2099 Finalize - Civil & Structural Drawings - Non Plant Buildings LPG 5*8 40d 31/Jul/2017 28/Sep/2017 15/Sep/2017 14/Nov/2017 32d Finalize - Civil & Structural Drawings - Non Plant Buildings
149 EC2111 Prepare & Issue Architectural Drawings - Plant Buildings IFA/IFR LPG 5*8 45d 08/Jun/2017 10/Aug/2017 14/Jun/2017 17/Aug/2017 4d Prepare & Issue Architectural Drawings - Plant Buildings IFA/IFR
150 EC2112 MLTPL Review - Architectural Drawings - Plant Buildings LPG 5*8 45d 22/Jun/2017 25/Aug/2017 31/Jul/2017 05/Oct/2017 27d MLTPL Review - Architectural Drawings - Plant Buildings
151 EC2113 Finalize - Architectural Drawings - Plant Buildings LPG 5*8 60d 03/Jul/2017 28/Sep/2017 10/Aug/2017 07/Nov/2017 27d Finalize - Architectural Drawings - Plant Buildings
152 EC2114 Prepare & Issue Civil & Structural Drawings - Plant Buildings IFA/IFR LPG 5*8 45d 06/Jul/2017 08/Sep/2017 12/Jul/2017 14/Sep/2017 4d Prepare & Issue Civil & Structural Drawings - Plant Buildings IFA/IFR
153 EC2115 MLTPL Review - Civil & Structural Drawings - Plant Buildings LPG 5*8 45d 20/Jul/2017 26/Sep/2017 08/Aug/2017 12/Oct/2017 12d MLTPL Review - Civil & Structural Drawings - Plant Buildings
154 EC2116 Finalize - Civil & Structural Drawings - Plant Buildings LPG 5*8 60d 31/Jul/2017 27/Oct/2017 18/Aug/2017 14/Nov/2017 12d Finalize - Civil & Structural Drawings - Plant Buildings
155 EC2130 Prepare & Issue Layout - Roads & Paving, Pits, Basin layout IFA/IFR LPG 5*8 20d 10/Jul/2017 04/Aug/2017 08/Nov/2017 05/Dec/2017 82d Prepare & Issue Layout - Roads & Paving, Pits, Basin layout IFA/IFR
156 EC2140 MLTPL Review Layout - Roads & Paving, Pits, Basin layout LPG 5*8 20d 24/Jul/2017 22/Aug/2017 14/Sep/2018 12/Oct/2018 291d MLTPL Review Layout - Roads & Paving, Pits, Basin layout
157 EC2150 Finalize Layout - Roads & Paving, Pits, Basin layout LPG 5*8 30d 02/Aug/2017 14/Sep/2017 25/Sep/2018 06/Nov/2018 291d Finalize Layout - Roads & Paving, Pits, Basin layout
158 EC2160 Prepare & Issue GA & RF Drgs for Equipment Founda ons LPG 5*8 55d 31/Jul/2017 19/Oct/2017 15/Sep/2017 05/Dec/2017 32d Prepare & Issue GA & RF Drgs for Equipment Founda ons
159 EC2170 MLTPL Review GA & RF Drgs for Equipment Founda ons LPG 5*8 55d 10/Aug/2017 31/Oct/2017 13/Oct/2017 29/Dec/2017 43d MLTPL Review GA & RF Drgs for Equipment Founda ons
160 EC2180 Finalize GA & RF Drgs for Equipment Founda ons LPG 5*8 65d 22/Aug/2017 23/Nov/2017 24/Oct/2017 23/Jan/2018 43d Finalize GA & RF Drgs for Equipment Founda ons
161 EC2190 Prepare & Issue Layout - Storm Water System Layout IFR/IFA LPG 5*8 65d 10/Jul/2017 12/Oct/2017 01/Sep/2017 05/Dec/2017 37d Prepare & Issue Layout - Storm Water System Layout IFR/IFA
162 EC2200 MLTPL Review Layout - Storm Water System Layout LPG 5*8 65d 24/Jul/2017 27/Oct/2017 10/Oct/2017 09/Jan/2018 52d MLTPL Review Layout - Storm Water System Layout
163 EC2210 Finalize Layout - Storm Water System Layout LPG 5*8 65d 08/Aug/2017 10/Nov/2017 24/Oct/2017 23/Jan/2018 52d Finalize Layout - Storm Water System Layout
164 EC2280 Prepare & Issue Main Piperack GA & FDN. Drawings LPG 5*8 65d 10/Jul/2017 12/Oct/2017 01/Sep/2017 05/Dec/2017 37d Prepare & Issue Main Piperack GA & FDN. Drawings
165 EC2290 MLTPL Review Main Piperack GA & FDN. Drawings LPG 5*8 65d 24/Jul/2017 27/Oct/2017 28/Jun/2018 27/Sep/2018 236d MLTPL Review Main Piperack GA & FDN. Drawings
166 EC2300 Finalize Main Piperack GA & FDN. Drawings LPG 5*8 85d 02/Aug/2017 05/Dec/2017 09/Jul/2018 06/Nov/2018 236d Finalize Main Piperack GA & FDN. Drawings
167 EC2310 Prepare & Issue Layout - Trenche (Cable / Pipe) Layout A LPG 5*8 30d 27/Sep/2017 08/Nov/2017 09/Aug/2018 20/Sep/2018 223d Prepare & Issue Layout - Trenche (Cable / Pipe) Layout A
168 EC2320 MLTPL Review Layout - Trenche (Cable / Pipe) Layout A LPG 5*8 30d 11/Oct/2017 22/Nov/2017 24/Aug/2018 05/Oct/2018 223d MLTPL Review Layout - Trenche (Cable / Pipe) Layout A
169 EC2330 Finalize Layout - Trenche (Cable / Pipe) Layout A LPG 5*8 45d 20/Oct/2017 22/Dec/2017 04/Sep/2018 06/Nov/2018 223d Finalize Layout - Trenche (Cable / Pipe) Layout A
170 EC2340 Prepare & Issue Layout - Contaminated Raw water CRW/OWS LPG 5*8 30d 27/Sep/2017 08/Nov/2017 09/Aug/2018 20/Sep/2018 223d Prepare & Issue Layout - Contaminated Raw water CRW/OWS
171 EC2350 MLTPL Review Layout - Contaminated Raw water CRW/OWS LPG 5*8 30d 11/Oct/2017 22/Nov/2017 24/Aug/2018 05/Oct/2018 223d MLTPL Review Layout - Contaminated Raw water CRW/OWS
172 EC2360 Finalize Layout - Contaminated Raw water CRW/OWS LPG 5*8 45d 20/Oct/2017 22/Dec/2017 04/Sep/2018 06/Nov/2018 223d Finalize Layout - Contaminated Raw water CRW/OWS

Actual Level of Effort Remaining Work Milestone Page 4 of 30 TASK filter: All Activities
Actual Work Critical Remaining Work summary Oracle Corporation
Mundra LPG Pvt Ltd Classic Schedule Layout 12/Jun/2017 16:07
# Ac vity ID Ac vity Name Calendar Original Early Start Early Finish Late Start Late Finish Total 2017 2018
Float Apr M Jun Jul Aug Sep Oct N Dec Jan F M Apr M Jun Jul Aug Sep Oct N Dec
173 EC2370 Prepare & Issue Pipe Supports Drawings LPG 5*8Dura30d
on 14/Dec/2017 24/Jan/2018 14/Dec/2017 24/Jan/2018 0d Prepare & Issue Pipe Supports Drawings
174 EC2380 MLTPL Review Pipe Supports Drawings LPG 5*8 30d 25/Dec/2017 05/Feb/2018 25/Dec/2017 05/Feb/2018 0d MLTPL Review Pipe Supports Drawings
175 EC2390 Finalize Pipe Supports Drawings LPG 5*8 45d 03/Jan/2018 07/Mar/2018 03/Jan/2018 07/Mar/2018 0d Finalize Pipe Supports Drawings
176 MR/MTO for Material Procurement LPG 5*8 123d 10/May/2017 03/Nov/2017 19/Jun/2017 23/Mar/2018 98d 03/Nov/2017, MR/MTO for Material Procurement
177 Overall LPG 5*8 123d 10/May/2017 03/Nov/2017 19/Jun/2017 23/Mar/2018 98d 03/Nov/2017, Overall
178 C6108 Prepare & Issue MR for Soil Inves ga on. Topo/GeoTech Surveys LPG 5*8 10d 10/May/2017 23/May/2017 19/Jun/2017 30/Jun/2017 28d Prepare & Issue MR for Soil Inves ga on. Topo/GeoTech Surveys
179 C9164 Prepare & Issue MR for Enabling Works (Site Oce , Security Gate House , Car Parking, Approach
LPG 5*8Road, Boundary
5d 06/Jul/2017
Wall) 12/Jul/2017 19/Mar/2018 23/Mar/2018 175d Prepare & Issue MR for Enabling Works (Site Oce , Security Gate House , Car Parking, Approach Road, Bound
180 C9166 Prepare & Issue MR for Civil Work 1 (All Buildings) LPG 5*8 10d 11/Sep/2017 26/Sep/2017 15/Sep/2017 02/Oct/2017 4d Prepare & Issue MR for Civil Work 1 (All Buildings)
181 C9168 Prepare & Issue MR for Civil Work 2 (Roads, Founda ons, Drainages, U/G and A/G ServicesLPG
etc)5*8 10d 20/Oct/2017 03/Nov/2017 06/Dec/2017 19/Dec/2017 32d Prepare & Issue MR for Civil Work 2 (Roads, Founda ons, Drainages, U/G and A/G Services
182 C9174 Prepare & Issue MR for Structural Work (Steel Strl for Complete Plant with Piperack, Compressor/Pump
LPG 5*8 10d
house,
13/Oct/2017
Flare) 27/Oct/2017 06/Dec/2017 19/Dec/2017 37d Prepare & Issue MR for Structural Work (Steel Strl for Complete Plant with Piperack, Compre
183 Mechanical LPG 5*8 67d 19/Jun/2017 25/Sep/2017 18/Jul/2017 24/Jan/2018 86d 25/Sep/2017, Mechanical
184 Fast track Packages LPG 5*8 12d 19/Jun/2017 04/Jul/2017 18/Jul/2017 24/Jan/2018 141d 04/Jul/2017, Fast track Packages
185 AS (Agreed Specs) for Packages LPG 5*8 12d 19/Jun/2017 04/Jul/2017 18/Jul/2017 24/Jan/2018 141d 04/Jul/2017, AS (Agreed Specs) for Packages
186 EM1220 Prepare & Issue AS for Marine Unloading/Loading Arms IFI LPG 5*8 10d 19/Jun/2017 30/Jun/2017 18/Jul/2017 31/Jul/2017 21d Prepare & Issue AS for Marine Unloading/Loading Arms IFI
187 EM1222 Prepare & Issue AS for DM Water Package LPG 5*8 10d 21/Jun/2017 04/Jul/2017 11/Jan/2018 24/Jan/2018 141d Prepare & Issue AS for DM Water Package
188 EM1224 Prepare & Issue AS for Fire Figh ng/FW Package LPG 5*8 10d 21/Jun/2017 04/Jul/2017 17/Nov/2017 30/Nov/2017 102d Prepare & Issue AS for Fire Figh ng/FW Package
189 EM1226 Prepare & Issue AS for Boiler Package LPG 5*8 10d 20/Jun/2017 03/Jul/2017 06/Sep/2017 21/Sep/2017 54d Prepare & Issue AS for Boiler Package
190 EM1228 Prepare & Issue AS for Liquid Nitrogen Storage (2000-CL-01) LPG 5*8 10d 20/Jun/2017 03/Jul/2017 20/Oct/2017 03/Nov/2017 84d Prepare & Issue AS for Liquid Nitrogen Storage (2000-CL-01)
191 EM1230 Prepare & Issue AS for Flare Package (2000-BJ-01) LPG 5*8 10d 21/Jun/2017 04/Jul/2017 23/Aug/2017 05/Sep/2017 43d Prepare & Issue AS for Flare Package (2000-BJ-01)
192 EM1232 Prepare & Issue AS for Propane / Butane (IN-TANK) Pumps (FIM) LPG 5*8 10d 19/Jun/2017 30/Jun/2017 27/Sep/2017 10/Oct/2017 68d Prepare & Issue AS for Propane / Butane (IN-TANK) Pumps (FIM)
193 EM1234 Prepare & Issue AS for for Air Compressor System LPG 5*8 10d 19/Jun/2017 30/Jun/2017 28/Nov/2017 11/Dec/2017 111d Prepare & Issue AS for for Air Compressor System
194 EM1236 Prepare & Issue AS for BOG/FG Gas Compressors I/II LPG 5*8 10d 19/Jun/2017 30/Jun/2017 25/Sep/2017 06/Oct/2017 66d Prepare & Issue AS for BOG/FG Gas Compressors I/II
195 Sta c Equipment (HE, Vessels, Tanks) LPG 5*8 42d 24/Jul/2017 25/Sep/2017 08/Aug/2017 27/Nov/2017 44d 25/Sep/2017, Sta c Equipment (HE, Vessels, Tanks)
196 Sta c Blender(s) LPG 5*8 42d 24/Jul/2017 25/Sep/2017 28/Sep/2017 27/Nov/2017 44d 25/Sep/2017, Sta c Blender(s)
197 EM1238 Prepare & Issue MDS for Sta c Blender- I/II/III/IV(2000-FM-02/03/04/01) LPG 5*8 10d 24/Jul/2017 04/Aug/2017 28/Sep/2017 11/Oct/2017 44d Prepare & Issue MDS for Sta c Blender- I/II/III/IV(2000-FM-02/03/04/01)
198 EM1240 MLTPL Review MDS for Sta c Blender- I/II/III/IV(2000-FM-02/03/04/01) LPG 5*8 7d 08/Aug/2017 17/Aug/2017 12/Oct/2017 20/Oct/2017 44d MLTPL Review MDS for Sta c Blender- I/II/III/IV(2000-FM-02/03/04/01)
199 EM1242 Finalize MDS for Sta c Blender- I/II/III/IV(2000-FM-02/03/04/01) LPG 5*8 20d 18/Aug/2017 14/Sep/2017 23/Oct/2017 20/Nov/2017 44d Finalize MDS for Sta c Blender- I/II/III/IV(2000-FM-02/03/04/01)
200 EM1328 Prepare & Issue MR for Sta c Blender- I/ II/ III/ IV LPG 5*8 5d 15/Sep/2017 25/Sep/2017 21/Nov/2017 27/Nov/2017 44d Prepare & Issue MR for Sta c Blender- I/ II/ III/ IV
201 Propane/Butane Heater LPG 5*8 31d 24/Jul/2017 06/Sep/2017 05/Sep/2017 19/Oct/2017 29d 06/Sep/2017, Propane/Butane Heater
202 EM1244 Prepare & Issue MDS for Propane/Butane Heater- I/II (2000-EA-05/07/08/10A) LPG 5*8 13d 24/Jul/2017 10/Aug/2017 05/Sep/2017 25/Sep/2017 29d Prepare & Issue MDS for Propane/Butane Heater- I/II (2000-EA-05/07/08/10A)
203 EM1246 MLTPL Review MDS for Propane/Butane Heater- I/II (2000-EA-05/07/08/10A) LPG 5*8 7d 10/Aug/2017 22/Aug/2017 25/Sep/2017 04/Oct/2017 29d MLTPL Review MDS for Propane/Butane Heater- I/II (2000-EA-05/07/08/10A)
204 EM1248 Finalize MDS for Propane/Butane Heater- I/II (2000-EA-05/07/08/10A) LPG 5*8 6d 22/Aug/2017 30/Aug/2017 04/Oct/2017 12/Oct/2017 29d Finalize MDS for Propane/Butane Heater- I/II (2000-EA-05/07/08/10A)
205 EM1332 Prepare & Issue MR for Propane & Butane Heater- I/II LPG 5*8 5d 30/Aug/2017 06/Sep/2017 13/Oct/2017 19/Oct/2017 29d Prepare & Issue MR for Propane & Butane Heater- I/II
206 Propane Vaporizer LPG 5*8 31d 31/Jul/2017 13/Sep/2017 05/Sep/2017 19/Oct/2017 24d 13/Sep/2017, Propane Vaporizer
207 EM1250 Prepare & Issue MDS for Propane Vaporizer- I/II(2000-EA-06A/09A) LPG 5*8 13d 31/Jul/2017 18/Aug/2017 05/Sep/2017 25/Sep/2017 24d Prepare & Issue MDS for Propane Vaporizer- I/II(2000-EA-06A/09A)
208 EM1252 MLTPL Review MDS for Propane Vaporizer- I/II(2000-EA-06A/09A) LPG 5*8 7d 18/Aug/2017 29/Aug/2017 25/Sep/2017 04/Oct/2017 24d MLTPL Review MDS for Propane Vaporizer- I/II(2000-EA-06A/09A)
209 EM1254 Finalize MDS for Propane Vaporizer- I/II(2000-EA-06A/09A) LPG 5*8 6d 29/Aug/2017 06/Sep/2017 04/Oct/2017 12/Oct/2017 24d Finalize MDS for Propane Vaporizer- I/II(2000-EA-06A/09A)
210 EM1334 Prepare & Issue MR for Propane Vaporizer- I/II LPG 5*8 5d 06/Sep/2017 13/Sep/2017 13/Oct/2017 19/Oct/2017 24d Prepare & Issue MR for Propane Vaporizer- I/II
211 Propane/Butane Flash Condenser LPG 5*8 31d 24/Jul/2017 06/Sep/2017 05/Sep/2017 19/Oct/2017 29d 06/Sep/2017, Propane/Butane Flash Condenser
212 EM1256 Prepare & Issue MDS for for Propane & Butane Flash Condenser(2000-EA-03/04) LPG 5*8 13d 24/Jul/2017 10/Aug/2017 05/Sep/2017 25/Sep/2017 29d Prepare & Issue MDS for for Propane & Butane Flash Condenser(2000-EA-03/04)
213 EM1258 MLTPL Review MDS for for Propane & Butane Flash Condenser(2000-EA-03/04) LPG 5*8 7d 10/Aug/2017 22/Aug/2017 25/Sep/2017 04/Oct/2017 29d MLTPL Review MDS for for Propane & Butane Flash Condenser(2000-EA-03/04)
214 EM1260 Finalize MDS for for Propane & Butane Flash Condenser(2000-EA-03/04) LPG 5*8 6d 22/Aug/2017 30/Aug/2017 04/Oct/2017 12/Oct/2017 29d Finalize MDS for for Propane & Butane Flash Condenser(2000-EA-03/04)
215 EM1330 Prepare & Issue MR for for Propane & Butane Flash Condenser LPG 5*8 5d 30/Aug/2017 06/Sep/2017 13/Oct/2017 19/Oct/2017 29d Prepare & Issue MR for for Propane & Butane Flash Condenser

Actual Level of Effort Remaining Work Milestone Page 5 of 30 TASK filter: All Activities
Actual Work Critical Remaining Work summary Oracle Corporation
Mundra LPG Pvt Ltd Classic Schedule Layout 12/Jun/2017 16:07
# Ac vity ID Ac vity Name Calendar Original Early Start Early Finish Late Start Late Finish Total 2017 2018
Float Apr M Jun Jul Aug Sep Oct N Dec Jan F M Apr M Jun Jul Aug Sep Oct N Dec
216 Suc on Separators LPG 5*8Dura31d
on 24/Jul/2017 06/Sep/2017 05/Sep/2017 19/Oct/2017 29d 06/Sep/2017, Suc on Separators
217 EM1262 Prepare & Issue MDS for Suc on Separator - I/II LPG 5*8 13d 24/Jul/2017 10/Aug/2017 05/Sep/2017 25/Sep/2017 29d Prepare & Issue MDS for Suc on Separator - I/II
218 EM1264 MLTPL Review MDS for Suc on Separator - I/II LPG 5*8 7d 10/Aug/2017 22/Aug/2017 25/Sep/2017 04/Oct/2017 29d MLTPL Review MDS for Suc on Separator - I/II
219 EM1266 Finalize MDS for Suc on Separator - I/II LPG 5*8 6d 22/Aug/2017 30/Aug/2017 04/Oct/2017 12/Oct/2017 29d Finalize MDS for Suc on Separator - I/II
220 EM1336 Prepare & Issue MR for Suc on Separator - I/II LPG 5*8 5d 30/Aug/2017 06/Sep/2017 13/Oct/2017 19/Oct/2017 29d Prepare & Issue MR for Suc on Separator - I/II
221 Propane & Butane BOG/Flash Condensate Receiver LPG 5*8 31d 24/Jul/2017 06/Sep/2017 15/Sep/2017 01/Nov/2017 37d 06/Sep/2017, Propane & Butane BOG/Flash Condensate Receiver
222 EM1268 Prepare & Issue MDS for Butane & Propane BOG / Flash Condensate Receiver LPG 5*8 13d 24/Jul/2017 10/Aug/2017 15/Sep/2017 05/Oct/2017 37d Prepare & Issue MDS for Butane & Propane BOG / Flash Condensate Receiver
223 EM1270 MLTPL Review MDS for Butane & Propane BOG / Flash Condensate Receiver LPG 5*8 7d 10/Aug/2017 22/Aug/2017 05/Oct/2017 16/Oct/2017 37d MLTPL Review MDS for Butane & Propane BOG / Flash Condensate Receiver
224 EM1272 Finalize MDS for Butane & Propane BOG / Flash Condensate Receiver LPG 5*8 6d 22/Aug/2017 30/Aug/2017 16/Oct/2017 24/Oct/2017 37d Finalize MDS for Butane & Propane BOG / Flash Condensate Receiver
225 EM1338 Prepare & Issue MR for Propane & Butane BOG / Flash Condensate Receiver LPG 5*8 5d 30/Aug/2017 06/Sep/2017 26/Oct/2017 01/Nov/2017 37d Prepare & Issue MR for Propane & Butane BOG / Flash Condensate Receiver
226 Steam Condensate Receiver LPG 5*8 31d 24/Jul/2017 06/Sep/2017 16/Aug/2017 29/Sep/2017 15d 06/Sep/2017, Steam Condensate Receiver
227 EM1274 Prepare & Issue MDS for Steam Condensate Receiver LPG 5*8 13d 24/Jul/2017 10/Aug/2017 16/Aug/2017 01/Sep/2017 15d Prepare & Issue MDS for Steam Condensate Receiver
228 EM1276 MLTPL Review MDS for Steam Condensate Receiver LPG 5*8 7d 10/Aug/2017 22/Aug/2017 01/Sep/2017 12/Sep/2017 15d MLTPL Review MDS for Steam Condensate Receiver
229 EM1278 Finalize MDS for Steam Condensate Receiver LPG 5*8 6d 22/Aug/2017 30/Aug/2017 12/Sep/2017 22/Sep/2017 15d Finalize MDS for Steam Condensate Receiver
230 EM1340 Prepare & Issue MR for Steam Condensate Receiver LPG 5*8 5d 30/Aug/2017 06/Sep/2017 25/Sep/2017 29/Sep/2017 15d Prepare & Issue MR for Steam Condensate Receiver
231 DM, FW, SW CondansateTanks LPG 5*8 22d 24/Jul/2017 24/Aug/2017 08/Aug/2017 07/Sep/2017 10d 24/Aug/2017, DM, FW, SW CondansateTanks
232 EM1280 Prepare & Issue MDS for FW, SW, DM Condansate Storage Tank LPG 5*8 5d 24/Jul/2017 28/Jul/2017 08/Aug/2017 14/Aug/2017 10d Prepare & Issue MDS for FW, SW, DM Condansate Storage Tank
233 EM1282 MLTPL Review MDS for FW, SW, DM Condansate Storage Tank LPG 5*8 7d 31/Jul/2017 09/Aug/2017 16/Aug/2017 24/Aug/2017 10d MLTPL Review MDS for FW, SW, DM Condansate Storage Tank
234 EM1284 Finalize MDS for FW, SW, DM Condansate Storage Tank LPG 5*8 5d 10/Aug/2017 17/Aug/2017 25/Aug/2017 31/Aug/2017 10d Finalize MDS for FW, SW, DM Condansate Storage Tank
235 EM1348 Prepare & Issue MR for FW, SW, DM Condansate Storage Tank LPG 5*8 5d 18/Aug/2017 24/Aug/2017 01/Sep/2017 07/Sep/2017 10d Prepare & Issue MR for FW, SW, DM Condansate Storage Tank
236 Rota ng Equipment LPG 5*8 31d 24/Jul/2017 06/Sep/2017 19/Jul/2017 20/Oct/2017 30d 06/Sep/2017, Rota ng Equipment
237 Steam Condensate Pump LPG 5*8 31d 24/Jul/2017 06/Sep/2017 19/Jul/2017 01/Sep/2017 -3d 06/Sep/2017, Steam Condensate Pump
238 EM1286 Prepare & Issue MDS for Steam Condensate Pumps LPG 5*8 13d 24/Jul/2017 10/Aug/2017 19/Jul/2017 04/Aug/2017 -3d Prepare & Issue MDS for Steam Condensate Pumps
239 EM1288 MLTPL Review MDS for Steam Condensate Pumps LPG 5*8 7d 10/Aug/2017 22/Aug/2017 04/Aug/2017 17/Aug/2017 -3d MLTPL Review MDS for Steam Condensate Pumps
240 EM1290 Finalize MDS for Steam Condensate Pumps LPG 5*8 6d 22/Aug/2017 30/Aug/2017 17/Aug/2017 25/Aug/2017 -3d Finalize MDS for Steam Condensate Pumps
241 EM1344 Prepare & Issue MR for Steam Condensate Pumps LPG 5*8 5d 30/Aug/2017 06/Sep/2017 28/Aug/2017 01/Sep/2017 -3d Prepare & Issue MR for Steam Condensate Pumps
242 Propane & Butane BOG/Flash Condensate Pumps LPG 5*8 31d 24/Jul/2017 06/Sep/2017 19/Jul/2017 01/Sep/2017 -3d 06/Sep/2017, Propane & Butane BOG/Flash Condensate Pumps
243 EM1292 Prepare & Issue MDS for Propane BOG/Flash Condensate Pumps LPG 5*8 13d 24/Jul/2017 10/Aug/2017 19/Jul/2017 04/Aug/2017 -3d Prepare & Issue MDS for Propane BOG/Flash Condensate Pumps
244 EM1294 MLTPL Review MDS for Butane BOG/Flash Condensate Pumps LPG 5*8 7d 10/Aug/2017 22/Aug/2017 04/Aug/2017 17/Aug/2017 -3d MLTPL Review MDS for Butane BOG/Flash Condensate Pumps
245 EM1296 Finalize MDS for Butane BOG/Flash Condensate Pumps LPG 5*8 6d 22/Aug/2017 30/Aug/2017 17/Aug/2017 25/Aug/2017 -3d Finalize MDS for Butane BOG/Flash Condensate Pumps
246 EM1342 Prepare & Issue MR for Propane & Butane BOG/Flash Condensate Pumps LPG 5*8 5d 30/Aug/2017 06/Sep/2017 28/Aug/2017 01/Sep/2017 -3d Prepare & Issue MR for Propane & Butane BOG/Flash Condensate Pumps
247 FW Pumps LPG 5*8 27d 24/Jul/2017 31/Aug/2017 12/Sep/2017 20/Oct/2017 34d 31/Aug/2017, FW Pumps
248 EM1298 Prepare & Issue MDS for Fire Water Main Pump LPG 5*8 5d 24/Jul/2017 28/Jul/2017 12/Sep/2017 18/Sep/2017 34d Prepare & Issue MDS for Fire Water Main Pump
249 EM1300 MLTPL Review MDS for Fire Water Main Pump LPG 5*8 7d 31/Jul/2017 09/Aug/2017 21/Sep/2017 29/Sep/2017 34d MLTPL Review MDS for Fire Water Main Pump
250 EM1302 Finalize MDS for Fire Water Main Pump LPG 5*8 5d 10/Aug/2017 17/Aug/2017 02/Oct/2017 06/Oct/2017 34d Finalize MDS for Fire Water Main Pump
251 EM1350 Prepare & Issue MR for Fire Water (Main + Jockey) Pump LPG 5*8 10d 18/Aug/2017 31/Aug/2017 09/Oct/2017 20/Oct/2017 34d Prepare & Issue MR for Fire Water (Main + Jockey) Pump
252 Jockey Pump LPG 5*8 17d 24/Jul/2017 17/Aug/2017 12/Sep/2017 06/Oct/2017 34d 17/Aug/2017, Jockey Pump
253 EM1304 Prepare & Issue MDS for Jockey Pump LPG 5*8 5d 24/Jul/2017 28/Jul/2017 12/Sep/2017 18/Sep/2017 34d Prepare & Issue MDS for Jockey Pump
254 EM1306 MLTPL Review MDS for Jockey Pump LPG 5*8 7d 31/Jul/2017 09/Aug/2017 21/Sep/2017 29/Sep/2017 34d MLTPL Review MDS for Jockey Pump
255 EM1308 Finalize MDS for Jockey Pump LPG 5*8 5d 10/Aug/2017 17/Aug/2017 02/Oct/2017 06/Oct/2017 34d Finalize MDS for Jockey Pump
256 Non API Pumps - CT, SW, ETP, OWS, Sewage etc LPG 5*8 10d 24/Jul/2017 04/Aug/2017 09/Oct/2017 20/Oct/2017 51d 04/Aug/2017, Non API Pumps - CT, SW, ETP, OWS, Sewage etc
257 EM1310 Prepare & Issue MDS for Non API Pumps - CT, SW, ETP, OWS, Sewage LPG 5*8 5d 24/Jul/2017 28/Jul/2017 09/Oct/2017 13/Oct/2017 51d Prepare & Issue MDS for Non API Pumps - CT, SW, ETP, OWS, Sewage
258 EM1354 Prepare & Issue MR for Non API Pumps - CT, SW, ETP, OWS, Sewage LPG 5*8 5d 31/Jul/2017 04/Aug/2017 16/Oct/2017 20/Oct/2017 51d Prepare & Issue MR for Non API Pumps - CT, SW, ETP, OWS, Sewage

Actual Level of Effort Remaining Work Milestone Page 6 of 30 TASK filter: All Activities
Actual Work Critical Remaining Work summary Oracle Corporation
Mundra LPG Pvt Ltd Classic Schedule Layout 12/Jun/2017 16:07
# Ac vity ID Ac vity Name Calendar Original Early Start Early Finish Late Start Late Finish Total 2017 2018
Float Apr M Jun Jul Aug Sep Oct N Dec Jan F M Apr M Jun Jul Aug Sep Oct N Dec
259 Packages LPG 5*8Dura40d
on 26/Jun/2017 22/Aug/2017 10/Aug/2017 13/Dec/2017 78d 22/Aug/2017, Packages
260 Loading/ Vapor Return Arms LPG 5*8 20d 24/Jul/2017 22/Aug/2017 10/Aug/2017 07/Sep/2017 12d 22/Aug/2017, Loading/ Vapor Return Arms
261 EM1312 Prepare & Issue MDS for Truck Loading & Vapor Return Arms LPG 5*8 10d 24/Jul/2017 04/Aug/2017 10/Aug/2017 24/Aug/2017 12d Prepare & Issue MDS for Truck Loading & Vapor Return Arms
262 EM1346 Prepare & Issue MR for Truck Loading & Vapor Return Arms LPG 5*8 10d 08/Aug/2017 22/Aug/2017 25/Aug/2017 07/Sep/2017 12d Prepare & Issue MR for Truck Loading & Vapor Return Arms
263 Cooling Tower Package LPG 5*8 30d 26/Jun/2017 04/Aug/2017 18/Sep/2017 20/Nov/2017 71d 04/Aug/2017, Cooling Tower Package
264 EM1314 Prepare & Issue MDS for CT Package LPG 5*8 5d 26/Jun/2017 30/Jun/2017 18/Sep/2017 26/Sep/2017 58d Prepare & Issue MDS for CT Package
265 EM1316 Prepare & Issue MDS for CT Side Stream Filters LPG 5*8 5d 24/Jul/2017 28/Jul/2017 07/Nov/2017 13/Nov/2017 71d Prepare & Issue MDS for CT Side Stream Filters
266 EM1318 Prepare & Issue MDS for CT Dosing Package LPG 5*8 5d 24/Jul/2017 28/Jul/2017 07/Nov/2017 13/Nov/2017 71d Prepare & Issue MDS for CT Dosing Package
267 EM1320 Prepare & Issue MDS for Clorina on Package LPG 5*8 5d 24/Jul/2017 28/Jul/2017 07/Nov/2017 13/Nov/2017 71d Prepare & Issue MDS for Clorina on Package
268 EM1352 Prepare & Issue MR for for CT Package LPG 5*8 5d 03/Jul/2017 07/Jul/2017 27/Sep/2017 03/Oct/2017 58d Prepare & Issue MR for for CT Package
269 EM1356 Prepare & Issue MR for CT Side Stream Filters LPG 5*8 5d 31/Jul/2017 04/Aug/2017 14/Nov/2017 20/Nov/2017 71d Prepare & Issue MR for CT Side Stream Filters
270 EM1358 Prepare & Issue MR for CT Dosing Package LPG 5*8 5d 31/Jul/2017 04/Aug/2017 14/Nov/2017 20/Nov/2017 71d Prepare & Issue MR for CT Dosing Package
271 EM1360 Prepare & Issue MR for CT Clorina on Package LPG 5*8 5d 31/Jul/2017 04/Aug/2017 14/Nov/2017 20/Nov/2017 71d Prepare & Issue MR for CT Clorina on Package
272 Weigh Bridge LPG 5*8 10d 24/Jul/2017 04/Aug/2017 18/Sep/2017 03/Oct/2017 38d 04/Aug/2017, Weigh Bridge
273 EM1322 Prepare & Issue MDS for Weight Bridge Package LPG 5*8 5d 24/Jul/2017 28/Jul/2017 18/Sep/2017 26/Sep/2017 38d Prepare & Issue MDS for Weight Bridge Package
274 EM1362 Prepare & Issue MR for Weightbridge Package LPG 5*8 5d 31/Jul/2017 04/Aug/2017 27/Sep/2017 03/Oct/2017 38d Prepare & Issue MR for Weightbridge Package
275 Mercaptan Dosing Package LPG 5*8 10d 24/Jul/2017 04/Aug/2017 18/Sep/2017 03/Oct/2017 38d 04/Aug/2017, Mercaptan Dosing Package
276 EM1324 Prepare & Issue MDS for Mercaptan Dosing Package LPG 5*8 5d 24/Jul/2017 28/Jul/2017 18/Sep/2017 26/Sep/2017 38d Prepare & Issue MDS for Mercaptan Dosing Package
277 EM1364 Prepare & Issue MR for Mercapan Dosing Package LPG 5*8 5d 31/Jul/2017 04/Aug/2017 27/Sep/2017 03/Oct/2017 38d Prepare & Issue MR for Mercapan Dosing Package
278 EOT & Hoist System LPG 5*8 18d 24/Jul/2017 18/Aug/2017 20/Nov/2017 13/Dec/2017 81d 18/Aug/2017, EOT & Hoist System
279 EM1326 Prepare & Issue MDS for EOT & Hoist System LPG 5*8 13d 24/Jul/2017 10/Aug/2017 20/Nov/2017 06/Dec/2017 81d Prepare & Issue MDS for EOT & Hoist System
280 EM1366 Prepare & Issue MR for EOT & HOIST System LPG 5*8 5d 10/Aug/2017 18/Aug/2017 07/Dec/2017 13/Dec/2017 81d Prepare & Issue MR for EOT & HOIST System
281 Piping LPG 5*8 225d 25/May/2017 13/Apr/2018 15/Jun/2017 06/Nov/2018 145d 13/Apr/2018, Piping
282 Commons LPG 5*8 225d 25/May/2017 13/Apr/2018 15/Jun/2017 06/Nov/2018 145d 13/Apr/2018, Commons
283 Overall LPG 5*8 225d 25/May/2017 13/Apr/2018 15/Jun/2017 06/Nov/2018 145d 13/Apr/2018, Overall
284 EL2000 Prepare & Issue Piping Design Basis LPG 5*8 15d 25/May/2017 14/Jun/2017 09/Aug/2018 30/Aug/2018 308d Prepare & Issue Piping Design Basis
285 EL2005 MLTPL Review Piping Design Basis LPG 5*8 7d 15/Jun/2017 23/Jun/2017 28/Sep/2018 09/Oct/2018 328d MLTPL Review Piping Design Basis
286 EL2010 Finalize Piping Design Basis LPG 5*8 20d 26/Jun/2017 21/Jul/2017 10/Oct/2018 06/Nov/2018 328d Finalize Piping Design Basis
287 EL2015 Prepare & Issue PMS, VMS LPG 5*8 10d 15/Jun/2017 28/Jun/2017 31/Aug/2018 13/Sep/2018 308d Prepare & Issue PMS, VMS
288 EL2020 MLTPL Review PMS, VMS LPG 5*8 7d 29/Jun/2017 07/Jul/2017 28/Sep/2018 09/Oct/2018 318d MLTPL Review PMS, VMS
289 EL2025 Finalize PMS, VMS LPG 5*8 20d 10/Jul/2017 04/Aug/2017 10/Oct/2018 06/Nov/2018 318d Finalize PMS, VMS
290 EL2030 Prepare & Issue Tech Specica on LPG 5*8 10d 29/Jun/2017 12/Jul/2017 14/Sep/2018 27/Sep/2018 308d Prepare & Issue Tech Specica on
291 EL2035 MLTPL Review Tech Specica on LPG 5*8 7d 13/Jul/2017 21/Jul/2017 28/Sep/2018 09/Oct/2018 308d MLTPL Review Tech Specica on
292 EL2040 Finalize Tech Specica on LPG 5*8 20d 24/Jul/2017 22/Aug/2017 10/Oct/2018 06/Nov/2018 308d Finalize Tech Specica on
293 EL2045 Prepare & Issue Specica on for Pain ng & Insula on LPG 5*8 10d 15/Jun/2017 28/Jun/2017 05/Oct/2018 18/Oct/2018 332d Prepare & Issue Specica on for Pain ng & Insula on
294 EL2050 MLTPL Review Specica on for Pain ng & Insula on LPG 5*8 7d 29/Jun/2017 07/Jul/2017 19/Oct/2018 29/Oct/2018 332d MLTPL Review Specica on for Pain ng & Insula on
295 EL2055 Finalize Specica on for Pain ng & Insula on LPG 5*8 6d 10/Jul/2017 17/Jul/2017 30/Oct/2018 06/Nov/2018 332d Finalize Specica on for Pain ng & Insula on
296 EL2060 Prepare & Issue Overall Plot Plan LPG 5*8 10d 26/Jun/2017 07/Jul/2017 08/Aug/2017 22/Aug/2017 30d Prepare & Issue Overall Plot Plan
297 EL2065 MLTPL Review Overall Plot Plan LPG 5*8 7d 10/Jul/2017 18/Jul/2017 23/Aug/2017 31/Aug/2017 30d MLTPL Review Overall Plot Plan
298 EL2070 Finalize Overall Plot Plan LPG 5*8 60d 19/Jul/2017 16/Oct/2017 01/Sep/2017 28/Nov/2017 30d Finalize Overall Plot Plan
299 EL2075 Prepare & Issue Equipment Layout - IFR/IFA LPG 5*8 10d 17/Jul/2017 28/Jul/2017 28/Aug/2017 08/Sep/2017 28d Prepare & Issue Equipment Layout - IFR/IFA
300 EL2080 MLTPL Review Equipment Layout LPG 5*8 7d 31/Jul/2017 09/Aug/2017 13/Sep/2017 25/Sep/2017 30d MLTPL Review Equipment Layout
301 EL2085 Finalize Equipment Layout LPG 5*8 45d 10/Aug/2017 16/Oct/2017 26/Sep/2017 28/Nov/2017 30d Finalize Equipment Layout

Actual Level of Effort Remaining Work Milestone Page 7 of 30 TASK filter: All Activities
Actual Work Critical Remaining Work summary Oracle Corporation
Mundra LPG Pvt Ltd Classic Schedule Layout 12/Jun/2017 16:07
# Ac vity ID Ac vity Name Calendar Original Early Start Early Finish Late Start Late Finish Total 2017 2018
Float Apr M Jun Jul Aug Sep Oct N Dec Jan F M Apr M Jun Jul Aug Sep Oct N Dec
302 EL2090 Modelling for 30% Model Review LPG 5*8Dura55d
on 15/Jun/2017 01/Sep/2017 15/Jun/2017 01/Sep/2017 0d Modelling for 30% Model Review
303 EL2095 30% Model Review by MLTPL LPG 5*8 5d 04/Sep/2017 08/Sep/2017 04/Sep/2017 08/Sep/2017 0d 30% Model Review by MLTPL
304 EL2100 Incorporate MLTPL Comments & Issue 30% - 3D Model LPG 5*8 10d 11/Sep/2017 26/Sep/2017 11/Sep/2017 26/Sep/2017 0d Incorporate MLTPL Comments & Issue 30% - 3D Model
305 EL2105 Prepare & Issue Cri cal Line List LPG 5*8 10d 27/Sep/2017 10/Oct/2017 27/Sep/2017 10/Oct/2017 0d Prepare & Issue Cri cal Line List
306 EL2110 MLTPL Review Cri cal Line List LPG 5*8 7d 11/Oct/2017 19/Oct/2017 07/Aug/2018 16/Aug/2018 211d MLTPL Review Cri cal Line List
307 EL2115 Finalize Cri cal Line List LPG 5*8 20d 20/Oct/2017 17/Nov/2017 17/Aug/2018 13/Sep/2018 211d Finalize Cri cal Line List
308 EL2120 Prepare & Issue Stress Analysis Report LPG 5*8 45d 11/Oct/2017 13/Dec/2017 11/Oct/2017 13/Dec/2017 0d Prepare & Issue Stress Analysis Report
309 EL2125 MLTPL Review Stress Analysis Report LPG 5*8 7d 14/Dec/2017 22/Dec/2017 22/Aug/2018 30/Aug/2018 176d MLTPL Review Stress Analysis Report
310 EL2130 Finalize Stress Analysis Report LPG 5*8 20d 25/Dec/2017 19/Jan/2018 31/Aug/2018 27/Sep/2018 176d Finalize Stress Analysis Report
311 EL2135 Modelling for 60% Model Review LPG 5*8 55d 11/Sep/2017 29/Nov/2017 26/Sep/2017 12/Dec/2017 9d Modelling for 60% Model Review
312 EL2140 MLTPL Review 60% - 3D Model LPG 5*8 5d 30/Nov/2017 06/Dec/2017 13/Dec/2017 19/Dec/2017 9d MLTPL Review 60% - 3D Model
313 EL2145 Incorporate MLTPL Comments & Issue 60% 3D Model LPG 5*8 10d 07/Dec/2017 20/Dec/2017 20/Dec/2017 02/Jan/2018 9d Incorporate MLTPL Comments & Issue 60% 3D Model
314 EL2150 Prepare & Issue Piping GAD LPG 5*8 20d 21/Dec/2017 17/Jan/2018 17/Aug/2018 13/Sep/2018 168d Prepare & Issue Piping GAD
315 EL2151 MLTLP Review Piping GADs LPG 5*8 7d 18/Jan/2018 29/Jan/2018 14/Sep/2018 24/Sep/2018 168d MLTLP Review Piping GADs
316 EL2152 Finalize Piping GADs LPG 5*8 30d 30/Jan/2018 12/Mar/2018 25/Sep/2018 06/Nov/2018 168d Finalize Piping GADs
317 EL2153 Prepare & Issue Piperack GAD LPG 5*8 20d 07/Dec/2017 03/Jan/2018 17/Aug/2018 13/Sep/2018 178d Prepare & Issue Piperack GAD
318 EL2154 MLTLP Review Piperack GADs LPG 5*8 7d 04/Jan/2018 12/Jan/2018 14/Sep/2018 24/Sep/2018 178d MLTLP Review Piperack GADs
319 EL2155 Finalize Piperack GADs LPG 5*8 30d 15/Jan/2018 26/Feb/2018 25/Sep/2018 06/Nov/2018 178d Finalize Piperack GADs
320 EL2170 Modelling for 90% Model Review LPG 5*8 45d 21/Dec/2017 22/Feb/2018 03/Jan/2018 07/Mar/2018 9d Modelling for 90% Model Review
321 EL2175 MLTPL Review 90% - 3D Model LPG 5*8 5d 23/Feb/2018 01/Mar/2018 08/Mar/2018 15/Mar/2018 9d MLTPL Review 90% - 3D Model
322 EL2180 Incorporate MLTPL Comments & Issue 90% 3D Model LPG 5*8 10d 02/Mar/2018 16/Mar/2018 16/Mar/2018 29/Mar/2018 9d Incorporate MLTPL Comments & Issue 90% 3D Model
323 EL2185 Prepare & Issue Piping ISO -IFI LPG 5*8 20d 19/Mar/2018 13/Apr/2018 25/Sep/2018 23/Oct/2018 135d Prepare & Issue Piping ISO -IFI
324 EL2200 Prepare & Issue DS Special Support Drawing LPG 5*8 20d 14/Dec/2017 10/Jan/2018 16/Feb/2018 16/Mar/2018 45d Prepare & Issue DS Special Support Drawing
325 EL2205 MLTPL Review DS Special Support Drawing LPG 5*8 7d 11/Jan/2018 19/Jan/2018 14/Sep/2018 24/Sep/2018 173d MLTPL Review DS Special Support Drawing
326 EL2210 Finalize DS Special Support Drawing LPG 5*8 30d 22/Jan/2018 05/Mar/2018 25/Sep/2018 06/Nov/2018 173d Finalize DS Special Support Drawing
327 EL2215 Prepare & Issue Flexbility Analysis Report LPG 5*8 10d 22/Jan/2018 05/Feb/2018 28/Sep/2018 12/Oct/2018 176d Prepare & Issue Flexbility Analysis Report
328 EL2220 MLTPL Review Flexbility Analysis Report LPG 5*8 7d 06/Feb/2018 14/Feb/2018 15/Oct/2018 23/Oct/2018 176d MLTPL Review Flexbility Analysis Report
329 EL2225 Finalize Flexbility Analysis Report LPG 5*8 10d 15/Feb/2018 28/Feb/2018 24/Oct/2018 06/Nov/2018 176d Finalize Flexbility Analysis Report
330 MR/MTO for Material Procurement LPG 5*8 178d 17/Jul/2017 30/Mar/2018 04/Sep/2017 31/May/2018 44d 30/Mar/2018, MR/MTO for Material Procurement
331 Overall LPG 5*8 178d 17/Jul/2017 30/Mar/2018 04/Sep/2017 31/May/2018 44d 30/Mar/2018, Overall
332 EL1450 Prepare & Issue MTO-1 LPG 5*8 15d 17/Jul/2017 04/Aug/2017 04/Sep/2017 26/Sep/2017 33d Prepare & Issue MTO-1
333 EL1452 Prepare & Issue MR for Pipes LPG 5*8 10d 08/Aug/2017 22/Aug/2017 27/Sep/2017 10/Oct/2017 33d Prepare & Issue MR for Pipes
334 EL1453 Prepare & Issue MR for Valves LPG 5*8 10d 23/Aug/2017 05/Sep/2017 11/Oct/2017 24/Oct/2017 33d Prepare & Issue MR for Valves
335 EL1454 Prepare & Issue MR for Fi ngs LPG 5*8 10d 06/Sep/2017 21/Sep/2017 26/Oct/2017 08/Nov/2017 33d Prepare & Issue MR for Fi ngs
336 EL1456 Prepare & Issue MR for Flanges LPG 5*8 10d 22/Sep/2017 05/Oct/2017 09/Nov/2017 22/Nov/2017 33d Prepare & Issue MR for Flanges
337 EL1460 Prepare & Issue MR for Fasteners, Gaskets etc LPG 5*8 10d 06/Oct/2017 19/Oct/2017 30/Mar/2018 12/Apr/2018 122d Prepare & Issue MR for Fasteners, Gaskets etc
338 EL1461 Prepare & Issue MR for Piping /Equipment Erec on Work LPG 5*8 20d 08/Aug/2017 05/Sep/2017 13/Dec/2017 09/Jan/2018 87d Prepare & Issue MR for Piping /Equipment Erec on Work
339 EL1462 Prepare & Issue MTO-2 LPG 5*8 10d 21/Dec/2017 03/Jan/2018 20/Apr/2018 03/May/2018 84d Prepare & Issue MTO-2
340 EL1464 Prepare & Issue MR for Special Support LPG 5*8 10d 11/Jan/2018 24/Jan/2018 19/Mar/2018 30/Mar/2018 45d Prepare & Issue MR for Special Support
341 EL1465 Prepare & Issue MR for Insula on/Pain ng Work LPG 5*8 20d 04/Jan/2018 01/Feb/2018 04/May/2018 31/May/2018 84d Prepare & Issue MR for Insula on/Pain ng Work
342 EL1466 Prepare & Issue MR for MTO-3 Items LPG 5*8 10d 19/Mar/2018 30/Mar/2018 30/Mar/2018 12/Apr/2018 9d Prepare & Issue MR for MTO-3 Items
343 Electrical LPG 5*8 186d 10/May/2017 01/Feb/2018 09/Oct/2017 06/Nov/2018 195d 01/Feb/2018, Electrical
344 Commons LPG 5*8 186d 10/May/2017 01/Feb/2018 20/Apr/2018 06/Nov/2018 195d 01/Feb/2018, Commons

Actual Level of Effort Remaining Work Milestone Page 8 of 30 TASK filter: All Activities
Actual Work Critical Remaining Work summary Oracle Corporation
Mundra LPG Pvt Ltd Classic Schedule Layout 12/Jun/2017 16:07
# Ac vity ID Ac vity Name Calendar Original Early Start Early Finish Late Start Late Finish Total 2017 2018
Float Apr M Jun Jul Aug Sep Oct N Dec Jan F M Apr M Jun Jul Aug Sep Oct N Dec
345 Overall LPG 5*8Dura186d
on 10/May/2017 01/Feb/2018 20/Apr/2018 06/Nov/2018 195d 01/Feb/2018, Overall
346 EE1468 Design Basis - Electrical LPG 5*8 10d 25/May/2017 07/Jun/2017 20/Apr/2018 03/May/2018 229d Design Basis - Electrical
347 EE1470 MLTPL Review Design Basis Electrical LPG 5*8 7d 08/Jun/2017 16/Jun/2017 19/Oct/2018 29/Oct/2018 347d MLTPL Review Design Basis Electrical
348 EE1472 Finalize Design Basis Electrical LPG 5*8 6d 19/Jun/2017 26/Jun/2017 30/Oct/2018 06/Nov/2018 347d Finalize Design Basis Electrical
349 EE1474 Prepare & Issue Load List LPG 5*8 10d 01/Jun/2017 14/Jun/2017 28/Aug/2018 10/Sep/2018 315d Prepare & Issue Load List
350 EE1476 MLTPL Review Load List LPG 5*8 7d 15/Jun/2017 23/Jun/2017 19/Oct/2018 29/Oct/2018 342d MLTPL Review Load List
351 EE1478 Finalize Load List LPG 5*8 6d 26/Jun/2017 03/Jul/2017 30/Oct/2018 06/Nov/2018 342d Finalize Load List
352 EE1480 Prepare & Issue Overall SLD LPG 5*8 10d 12/Jun/2017 23/Jun/2017 06/Sep/2018 19/Sep/2018 315d Prepare & Issue Overall SLD
353 EE1482 MLTPL Review Overall SLD LPG 5*8 7d 10/Jul/2017 18/Jul/2017 19/Oct/2018 29/Oct/2018 325d MLTPL Review Overall SLD
354 EE1484 Finalize Overall SLD LPG 5*8 6d 19/Jul/2017 26/Jul/2017 30/Oct/2018 06/Nov/2018 325d Finalize Overall SLD
355 EE1486 Prepare & Issue SLD for (33, 6.6 KV) LPG 5*8 10d 26/Jun/2017 07/Jul/2017 20/Sep/2018 04/Oct/2018 315d Prepare & Issue SLD for (33, 6.6 KV)
356 EE1488 Prepare & Issue SubSta on Layout LPG 5*8 10d 10/Jul/2017 21/Jul/2017 05/Oct/2018 18/Oct/2018 315d Prepare & Issue SubSta on Layout
357 EE1490 MLTPL Review SubSta on Layout LPG 5*8 7d 24/Jul/2017 01/Aug/2017 19/Oct/2018 29/Oct/2018 315d MLTPL Review SubSta on Layout
358 EE1492 Finalize SubSta on Layout LPG 5*8 6d 02/Aug/2017 10/Aug/2017 30/Oct/2018 06/Nov/2018 315d Finalize SubSta on Layout
359 EE1494 Prepare & Issue Transformer, UPS, Capacitor, DG & NGR Sizing LPG 5*8 60d 08/Jun/2017 01/Sep/2017 21/May/2018 10/Aug/2018 240d Prepare & Issue Transformer, UPS, Capacitor, DG & NGR Sizing
360 EE1496 MLTPL Review Transformer , UPS , Capacitor , DG & NGR Sizing LPG 5*8 7d 04/Sep/2017 12/Sep/2017 19/Oct/2018 29/Oct/2018 287d MLTPL Review Transformer , UPS , Capacitor , DG & NGR Sizing
361 EE1498 Finalize Transformer , UPS , Capacitor , DG & NGR Sizing LPG 5*8 6d 13/Sep/2017 22/Sep/2017 30/Oct/2018 06/Nov/2018 287d Finalize Transformer , UPS , Capacitor , DG & NGR Sizing
362 EE1500 Prepare & Issue Earthing Layouts LPG 5*8 30d 27/Sep/2017 08/Nov/2017 25/Sep/2018 06/Nov/2018 255d Prepare & Issue Earthing Layouts
363 EE1502 Prepare & Issue HT/LT Cable Sizing LPG 5*8 15d 04/Sep/2017 26/Sep/2017 13/Aug/2018 03/Sep/2018 240d Prepare & Issue HT/LT Cable Sizing
364 EE1504 MLTPL Review HT/LT Cable Sizing LPG 5*8 7d 27/Sep/2017 05/Oct/2017 19/Oct/2018 29/Oct/2018 272d MLTPL Review HT/LT Cable Sizing
365 EE1506 Finalize HT/LT Cable Sizing LPG 5*8 6d 06/Oct/2017 13/Oct/2017 30/Oct/2018 06/Nov/2018 272d Finalize HT/LT Cable Sizing
366 EE1508 Prepare & Issue Cable Schedule LPG 5*8 50d 18/Sep/2017 29/Nov/2017 28/Aug/2018 06/Nov/2018 240d Prepare & Issue Cable Schedule
367 EE1510 Prepare & Issue Ligh ng Calcula on LPG 5*8 60d 10/May/2017 01/Aug/2017 21/Jun/2018 13/Sep/2018 284d Prepare & Issue Ligh ng Calcula on
368 EE1512 MLTPL Review Ligh ng Calcula on LPG 5*8 7d 17/May/2017 25/May/2017 28/Jun/2018 06/Jul/2018 284d MLTPL Review Ligh ng Calcula on
369 EE1514 Finalize Ligh ng Calcula on LPG 5*8 60d 26/May/2017 21/Aug/2017 09/Jul/2018 01/Oct/2018 284d Finalize Ligh ng Calcula on
370 EE1516 Prepare & Issue Ligh ng Layouts IFI LPG 5*8 35d 14/Dec/2017 01/Feb/2018 18/Sep/2018 06/Nov/2018 195d Prepare & Issue Ligh ng Layouts IFI
371 EE1518 Prepare & Issue Cable Rou ng/Tray Layout IFI LPG 5*8 35d 14/Dec/2017 01/Feb/2018 18/Sep/2018 06/Nov/2018 195d Prepare & Issue Cable Rou ng/Tray Layout IFI
372 EE1520 Prepare & Issue Installa on Drawing - IFI LPG 5*8 20d 29/Aug/2017 27/Sep/2017 10/Oct/2018 06/Nov/2018 284d Prepare & Issue Installa on Drawing - IFI
373 EE1522 Prepare & Issue Interconnec on Diagram IFI LPG 5*8 20d 29/Aug/2017 27/Sep/2017 10/Oct/2018 06/Nov/2018 284d Prepare & Issue Interconnec on Diagram IFI
374 Fast track Packages LPG 5*8 10d 12/Jun/2017 23/Jun/2017 09/Oct/2017 20/Oct/2017 81d 23/Jun/2017, Fast track Packages
375 DG Set/ Emergency Power LPG 5*8 10d 12/Jun/2017 23/Jun/2017 09/Oct/2017 20/Oct/2017 81d 23/Jun/2017, DG Set/ Emergency Power
376 EE1524 Prepare & Issue AS for DG Set LPG 5*8 10d 12/Jun/2017 23/Jun/2017 09/Oct/2017 20/Oct/2017 81d Prepare & Issue AS for DG Set
377 Instrumenta on LPG 5*8 147d 12/Jun/2017 09/Jan/2018 31/May/2018 06/Nov/2018 211d 09/Jan/2018, Instrumenta on
378 Commons LPG 5*8 147d 12/Jun/2017 09/Jan/2018 31/May/2018 06/Nov/2018 211d 09/Jan/2018, Commons
379 Overall LPG 5*8 147d 12/Jun/2017 09/Jan/2018 31/May/2018 06/Nov/2018 211d 09/Jan/2018, Overall
380 EI1528 Prepare & Issue DS Instruments LPG 5*8 40d 24/Jul/2017 21/Sep/2017 23/Aug/2018 18/Oct/2018 275d Prepare & Issue DS Instruments
381 EI1530 MLTPL Review Instrument DS LPG 5*8 7d 22/Sep/2017 02/Oct/2017 19/Oct/2018 29/Oct/2018 275d MLTPL Review Instrument DS
382 EI1532 Finalize Instrument DS LPG 5*8 6d 03/Oct/2017 10/Oct/2017 30/Oct/2018 06/Nov/2018 275d Finalize Instrument DS
383 EI1534 Prepare & Issue Instrument Design Basis LPG 5*8 15d 12/Jun/2017 30/Jun/2017 07/Sep/2018 27/Sep/2018 316d Prepare & Issue Instrument Design Basis
384 EI1536 MLTPL Review Instrument Design Basis LPG 5*8 7d 03/Jul/2017 11/Jul/2017 22/Oct/2018 30/Oct/2018 331d MLTPL Review Instrument Design Basis
385 EI1538 Finalize Instrument Design Basis LPG 5*8 5d 12/Jul/2017 18/Jul/2017 31/Oct/2018 06/Nov/2018 331d Finalize Instrument Design Basis
386 EI1540 Prepare & Issue Instrument Index - IFI LPG 5*8 5d 03/Jul/2017 07/Jul/2017 28/Sep/2018 05/Oct/2018 316d Prepare & Issue Instrument Index - IFI
387 EI1542 Pressure & Issue I/O List LPG 5*8 10d 31/Jul/2017 14/Aug/2017 31/May/2018 13/Jun/2018 211d Pressure & Issue I/O List

Actual Level of Effort Remaining Work Milestone Page 9 of 30 TASK filter: All Activities
Actual Work Critical Remaining Work summary Oracle Corporation
Mundra LPG Pvt Ltd Classic Schedule Layout 12/Jun/2017 16:07
# Ac vity ID Ac vity Name Calendar Original Early Start Early Finish Late Start Late Finish Total 2017 2018
Float Apr M Jun Jul Aug Sep Oct N Dec Jan F M Apr M Jun Jul Aug Sep Oct N Dec
388 EI1544 MLTPL Review I/O List LPG 5*8Dura on
7d 16/Aug/2017 24/Aug/2017 22/Oct/2018 30/Oct/2018 301d MLTPL Review I/O List
389 EI1546 Finalize I/O List LPG 5*8 5d 25/Aug/2017 31/Aug/2017 31/Oct/2018 06/Nov/2018 301d Finalize I/O List
390 EI1548 Prepare & Issue Pneuma c & Process Hookup Diagram LPG 5*8 10d 31/Jul/2017 14/Aug/2017 31/May/2018 13/Jun/2018 211d Prepare & Issue Pneuma c & Process Hookup Diagram
391 EI1550 MLTPL Review Pneuma c & Process Hookup Diagram LPG 5*8 7d 16/Aug/2017 24/Aug/2017 22/Oct/2018 30/Oct/2018 301d MLTPL Review Pneuma c & Process Hookup Diagram
392 EI1552 Finalize Pneuma c & Process Hookup Diagram LPG 5*8 5d 25/Aug/2017 31/Aug/2017 31/Oct/2018 06/Nov/2018 301d Finalize Pneuma c & Process Hookup Diagram
393 EI1554 Prepare & Issue System Congura on Diagram LPG 5*8 30d 31/Jul/2017 12/Sep/2017 05/Jul/2018 16/Aug/2018 236d Prepare & Issue System Congura on Diagram
394 EI1556 MLTPL Review System Congura on Diagram LPG 5*8 7d 13/Sep/2017 25/Sep/2017 22/Oct/2018 30/Oct/2018 281d MLTPL Review System Congura on Diagram
395 EI1558 Finalize System Congura on Diagram LPG 5*8 5d 26/Sep/2017 02/Oct/2017 31/Oct/2018 06/Nov/2018 281d Finalize System Congura on Diagram
396 EI1560 Prepare & Issue Secica on Datasheets for DCS/ESD/FGS/CCTV/PAGA etc LPG 5*8 45d 13/Sep/2017 17/Nov/2017 17/Aug/2018 19/Oct/2018 236d Prepare & Issue Secica on Datasheets for DCS/ESD/FGS/CCTV/PAGA etc
397 EI1562 MLTPL Review Fire Alarm System Diagram LPG 5*8 7d 20/Nov/2017 28/Nov/2017 22/Oct/2018 30/Oct/2018 236d MLTPL Review Fire Alarm System Diagram
398 EI1564 Finalize Fire Alarm System Diagram LPG 5*8 5d 29/Nov/2017 05/Dec/2017 31/Oct/2018 06/Nov/2018 236d Finalize Fire Alarm System Diagram
399 EI1566 Prepare & Issue Cable Rou ng & Trays, Layouts for JB, F&G Detectors, Plant Buildings etc LPG 5*8 45d 20/Oct/2017 22/Dec/2017 17/Aug/2018 19/Oct/2018 211d Prepare & Issue Cable Rou ng & Trays, Layouts for JB, F&G Detectors, Plant Buildin
400 EI1568 MLTPL Review Cable Rou ng & Trays, Layouts for JB, F&G Detectors, Plant Buildings etc LPG 5*8 7d 25/Dec/2017 02/Jan/2018 22/Oct/2018 30/Oct/2018 211d MLTPL Review Cable Rou ng & Trays, Layouts for JB, F&G Detectors, Plant Buildi
401 EI1570 Fialize Cable Rou ng & Trays, Layouts for JB, F&G Detectors, Plant Buildings etc LPG 5*8 5d 03/Jan/2018 09/Jan/2018 31/Oct/2018 06/Nov/2018 211d Fialize Cable Rou ng & Trays, Layouts for JB, F&G Detectors, Plant Buildings etc
402 EI1572 Prepare & Issue JB, Cable, Drum Cu ng schedule etc LPG 5*8 45d 16/Aug/2017 19/Oct/2017 14/Jun/2018 16/Aug/2018 211d Prepare & Issue JB, Cable, Drum Cu ng schedule etc
403 EI1574 MLTPL Review JB, Cable, Drum Cu ng schedule etc LPG 5*8 7d 20/Oct/2017 31/Oct/2017 22/Oct/2018 30/Oct/2018 256d MLTPL Review JB, Cable, Drum Cu ng schedule etc
404 EI1576 Finalize JB, Cable, Drum Cu ng schedule etc LPG 5*8 5d 01/Nov/2017 07/Nov/2017 31/Oct/2018 06/Nov/2018 256d Finalize JB, Cable, Drum Cu ng schedule etc
405 EI1578 Prepare & Issue Control Narra ve, Block Diag. Funclogic Logics LPG 5*8 10d 10/Jul/2017 21/Jul/2017 08/Oct/2018 19/Oct/2018 316d Prepare & Issue Control Narra ve, Block Diag. Funclogic Logics
406 EI1580 MLTPL Review Control Narra ve, Block Diag. Funclogic Logics LPG 5*8 7d 24/Jul/2017 01/Aug/2017 22/Oct/2018 30/Oct/2018 316d MLTPL Review Control Narra ve, Block Diag. Funclogic Logics
407 EI1582 Finalize Control Narra ve, Block Diag. Funclogic Logics LPG 5*8 5d 02/Aug/2017 09/Aug/2017 31/Oct/2018 06/Nov/2018 316d Finalize Control Narra ve, Block Diag. Funclogic Logics
408 MR/MTO for Material Procurement LPG 5*8 20d 20/Oct/2017 17/Nov/2017 10/Oct/2018 06/Nov/2018 248d 17/Nov/2017, MR/MTO for Material Procurement
409 Overall LPG 5*8 20d 20/Oct/2017 17/Nov/2017 10/Oct/2018 06/Nov/2018 248d 17/Nov/2017, Overall
410 EI1584 Prepare & Issue PR for Instrumenta on work LPG 5*8 20d 20/Oct/2017 17/Nov/2017 10/Oct/2018 06/Nov/2018 248d Prepare & Issue PR for Instrumenta on work
411 Procurement LPG 5*8 348d 10/May/2017 19/Sep/2018 03/Jul/2017 06/Nov/2018 33d 19/Sep/2018, Procurement

412 Civil LPG 5*8 306d 10/May/2017 20/Jul/2018 03/Jul/2017 02/Aug/2018 9d 20/Jul/2018, Civil
413 Commons LPG 5*8 306d 10/May/2017 20/Jul/2018 03/Jul/2017 02/Aug/2018 9d 20/Jul/2018, Commons
414 Sub-Contracts LPG 5*8 306d 10/May/2017 20/Jul/2018 03/Jul/2017 02/Aug/2018 9d 20/Jul/2018, Sub-Contracts
415 PC2000 Issue Tender to Award TOPO and Geo-Technical Surveys LPG 5*8 15d 24/May/2017 13/Jun/2017 03/Jul/2017 21/Jul/2017 28d Issue Tender to Award TOPO and Geo-Technical Surveys
416 PC2005 Prepare & Issue Tender for Enabling Works LPG 5*8 5d 13/Jul/2017 19/Jul/2017 26/Mar/2018 30/Mar/2018 175d Prepare & Issue Tender for Enabling Works
417 PC2007 Receive Bids Tender for Enabling Works LPG 5*8 10d 20/Jul/2017 02/Aug/2017 02/Apr/2018 13/Apr/2018 175d Receive Bids Tender for Enabling Works
418 PC2010 Techno-Commercial Evalua on Tender for Enabling Works LPG 5*8 10d 03/Aug/2017 18/Aug/2017 16/Apr/2018 27/Apr/2018 175d Techno-Commercial Evalua on Tender for Enabling Works
419 PC2012 Award Tender for Enabling Works LPG 5*8 5d 21/Aug/2017 25/Aug/2017 30/Apr/2018 04/May/2018 175d Award Tender for Enabling Works
420 PC2025 Prepare & Issue Tender for Piling Work LPG 5*8 5d 04/Aug/2017 11/Aug/2017 15/Sep/2017 25/Sep/2017 28d Prepare & Issue Tender for Piling Work
421 PC2026 Receive Bids Tender for Piling Work LPG 5*8 10d 14/Aug/2017 28/Aug/2017 26/Sep/2017 09/Oct/2017 28d Receive Bids Tender for Piling Work
422 PC2027 Techno-Commercial Evalua on Tender for Piling Work LPG 5*8 10d 29/Aug/2017 11/Sep/2017 10/Oct/2017 23/Oct/2017 28d Techno-Commercial Evalua on Tender for Piling Work
423 PC2028 Award Tender for Piling Work LPG 5*8 5d 12/Sep/2017 18/Sep/2017 24/Oct/2017 31/Oct/2017 28d Award Tender for Piling Work
424 PC2035 Prepare & Issue Tender for Civil Work 1 (All Buildings) LPG 5*8 5d 27/Sep/2017 03/Oct/2017 03/Oct/2017 09/Oct/2017 4d Prepare & Issue Tender for Civil Work 1 (All Buildings)
425 PC2036 Receive Bids Tender for Civil Work 1 (All Buildings) LPG 5*8 15d 04/Oct/2017 24/Oct/2017 10/Oct/2017 31/Oct/2017 4d Receive Bids Tender for Civil Work 1 (All Buildings)
426 PC2037 Techno-Commercial Evalua on Tender for Civil Work 1 (All Buildings) LPG 5*8 15d 26/Oct/2017 15/Nov/2017 01/Nov/2017 21/Nov/2017 4d Techno-Commercial Evalua on Tender for Civil Work 1 (All Buildings)
427 PC2038 Award Tender for Civil Work 1 (All Buildings) LPG 5*8 5d 16/Nov/2017 22/Nov/2017 22/Nov/2017 28/Nov/2017 4d Award Tender for Civil Work 1 (All Buildings)
428 PC2040 Prepare & Issue Tender for Civil Work 2 (Roads, Founda ons, Drainages, U/G and A/G Services
LPG 5*8
etc) 5d 06/Nov/2017 10/Nov/2017 20/Dec/2017 26/Dec/2017 32d Prepare & Issue Tender for Civil Work 2 (Roads, Founda ons, Drainages, U/G and A/G Ser
429 PC2041 Receive Bids Tender for Civil Work 2 (Roads, Founda ons, Drainages, U/G and A/G ServicesLPG
etc)5*8 10d 13/Nov/2017 24/Nov/2017 27/Dec/2017 09/Jan/2018 32d Receive Bids Tender for Civil Work 2 (Roads, Founda ons, Drainages, U/G and A/G Serv
430 PC2042 Techno-Commercial Evalua on Tender for Civil Work 2 (Roads, Founda ons, Drainages, U/G
LPG
and
5*8
A/G Services
10d 27/Nov/2017
etc) 08/Dec/2017 10/Jan/2018 23/Jan/2018 32d Techno-Commercial Evalua on Tender for Civil Work 2 (Roads, Founda ons, Drainag

Actual Level of Effort Remaining Work Milestone Page 10 of 30 TASK filter: All Activities
Actual Work Critical Remaining Work summary Oracle Corporation
Mundra LPG Pvt Ltd Classic Schedule Layout 12/Jun/2017 16:07
# Ac vity ID Ac vity Name Calendar Original Early Start Early Finish Late Start Late Finish Total 2017 2018
Float Apr M Jun Jul Aug Sep Oct N Dec Jan F M Apr M Jun Jul Aug Sep Oct N Dec
431 PC2043 Award Tender for Civil Work 2 (Roads, Founda ons, Drainages, U/G and A/G Services etc) LPG 5*8Dura on
5d 11/Dec/2017 15/Dec/2017 24/Jan/2018 31/Jan/2018 32d Award Tender for Civil Work 2 (Roads, Founda ons, Drainages, U/G and A/G Service
432 PC2045 Prepare & Issue Tender for Civil/Strl Work 3 (Steel Strl for Complete Plant with Piperack, Compressor/Pump
LPG 5*8 5dhouse,
30/Oct/2017
Flare) 03/Nov/2017 20/Dec/2017 26/Dec/2017 37d Prepare & Issue Tender for Civil/Strl Work 3 (Steel Strl for Complete Plant with Piperack, Com
433 PC2046 Receive Bids Tender for Civil/Strl Work 3 (Steel Strl for Complete Plant with Piperack, Compressor/Pump
LPG 5*8 house,
10d 06/Nov/2017
Flare) 17/Nov/2017 27/Dec/2017 09/Jan/2018 37d Receive Bids Tender for Civil/Strl Work 3 (Steel Strl for Complete Plant with Piperack, Com
434 PC2047 Techno-Commercial Evalua on Tender for Civil/Strl Work 3 (Steel Strl for Complete Plant with
LPGPiperack,
5*8 Compressor/Pump
10d 20/Nov/2017 01/Dec/2017 10/Jan/2018 23/Jan/2018 37d Techno-Commercial Evalua on Tender for Civil/Strl Work 3 (Steel Strl for Complete Plan
435 PC2048 Award Tender for Structural Work (Steel Strl for Complete Plant with Piperack, Compressor/Pump
LPG 5*8house,5d
Flare)
04/Dec/2017 08/Dec/2017 24/Jan/2018 31/Jan/2018 37d Award Tender for Structural Work (Steel Strl for Complete Plant with Piperack, Comp
436 PC2050 Prepare & Issue Tender for Piping /Mechanical Work LPG 5*8 5d 30/Oct/2017 03/Nov/2017 10/Jan/2018 16/Jan/2018 52d Prepare & Issue Tender for Piping /Mechanical Work
437 PC2051 Receive Bids Tender for Piping /Mechanical Work LPG 5*8 15d 06/Nov/2017 24/Nov/2017 17/Jan/2018 07/Feb/2018 52d Receive Bids Tender for Piping /Mechanical Work
438 PC2052 Techno-Commercial Evalua on Tender for Piping /Mechanical Work LPG 5*8 15d 27/Nov/2017 15/Dec/2017 08/Feb/2018 28/Feb/2018 52d Techno-Commercial Evalua on Tender for Piping /Mechanical Work
439 PC2053 Award Tender for Piping /Equipment Erec on Work LPG 5*8 5d 18/Dec/2017 22/Dec/2017 01/Mar/2018 07/Mar/2018 52d Award Tender for Piping /Equipment Erec on Work
440 PC2055 Prepare & Issue Tender for Electrical Work LPG 5*8 5d 08/Jun/2017 14/Jun/2017 04/May/2018 10/May/2018 229d Prepare & Issue Tender for Electrical Work
441 PC2056 Receive Bids Tender for Electrical Work LPG 5*8 15d 15/Jun/2017 05/Jul/2017 11/May/2018 31/May/2018 229d Receive Bids Tender for Electrical Work
442 PC2057 Techno-Commercial Evalua on Tender for Electrical Work LPG 5*8 15d 06/Jul/2017 26/Jul/2017 01/Jun/2018 21/Jun/2018 229d Techno-Commercial Evalua on Tender for Electrical Work
443 PC2058 Award Tender for Electrical Work LPG 5*8 10d 27/Jul/2017 10/Aug/2017 22/Jun/2018 05/Jul/2018 229d Award Tender for Electrical Work
444 PC2060 Prepare & Issue Tender for Instrumenta on work LPG 5*8 5d 10/May/2017 16/May/2017 01/Jun/2018 07/Jun/2018 270d Prepare & Issue Tender for Instrumenta on work
445 PC2061 Receive Bids Tender for Instrumenta on work LPG 5*8 15d 17/May/2017 06/Jun/2017 08/Jun/2018 28/Jun/2018 270d Receive Bids Tender for Instrumenta on work
446 PC2062 Techno-Commercial Evalua on Tender for Instrumenta on work LPG 5*8 15d 07/Jun/2017 27/Jun/2017 29/Jun/2018 19/Jul/2018 270d Techno-Commercial Evalua on Tender for Instrumenta on work
447 PC2063 Award Tender for Instrumenta on work LPG 5*8 10d 28/Jun/2017 11/Jul/2017 20/Jul/2018 02/Aug/2018 270d Award Tender for Instrumenta on work
448 PC2065 Prepare & Issue Tender for Insula on/Pain ng Work LPG 5*8 5d 21/May/2018 25/May/2018 01/Jun/2018 07/Jun/2018 9d Prepare & Issue Tender for Insula on/Pain ng Work
449 PC2066 Receive Bids Tender for Insula on/Pain ng Work LPG 5*8 10d 28/May/2018 08/Jun/2018 08/Jun/2018 21/Jun/2018 9d Receive Bids Tender for Insula on/Pain ng Work
450 PC2068 Techno-Commercial Evalua on Tender for Insula on/Pain ng Work LPG 5*8 15d 11/Jun/2018 29/Jun/2018 22/Jun/2018 12/Jul/2018 9d Techno-Commercial Evalua on Tender for Insula
451 PC2069 Award Tender for Insula on/Pain ng Work LPG 5*8 15d 02/Jul/2018 20/Jul/2018 13/Jul/2018 02/Aug/2018 9d Award Tender for Insula on/Pain ng Work
452 PC2119 Prepare & Issue Tender for Jack up Barge LPG 5*8 5d 10/May/2017 16/May/2017 01/Jun/2018 07/Jun/2018 270d Prepare & Issue Tender for Jack up Barge
453 PC2120 Receive Bids Tender for Jack up Barge LPG 5*8 15d 17/May/2017 06/Jun/2017 08/Jun/2018 28/Jun/2018 270d Receive Bids Tender for Jack up Barge
454 PC2165 Techno-Commercial Evalua on Tender for Jack up Barge LPG 5*8 15d 07/Jun/2017 27/Jun/2017 29/Jun/2018 19/Jul/2018 270d Techno-Commercial Evalua on Tender for Jack up Barge
455 PC2220 Award Tender for Jack up Barge LPG 5*8 10d 28/Jun/2017 11/Jul/2017 20/Jul/2018 02/Aug/2018 270d Award Tender for Jack up Barge
456 Mechanical LPG 5*8 314d 07/Jun/2017 30/Aug/2018 27/Jul/2017 23/Oct/2018 37d 30/Aug/2018, Mechanical
457 Fas rack Packages LPG 5*8 270d 07/Jun/2017 28/Jun/2018 27/Jul/2017 12/Oct/2018 74d 28/Jun/2018, Fas rack Packages
458 Marine Loading/Unloading Arms LPG 5*8 255d 28/Jun/2017 28/Jun/2018 27/Jul/2017 27/Jul/2018 21d 28/Jun/2018, Marine Loading/Unloading Arms
459 PM1000 MLTPL Review/Approval of AS LPG 5*8 7d 03/Jul/2017 11/Jul/2017 01/Aug/2017 10/Aug/2017 21d MLTPL Review/Approval of AS
460 PM1002 Prepare CBE & Nego ate LPG 5*8 10d 28/Jun/2017 11/Jul/2017 27/Jul/2017 10/Aug/2017 21d Prepare CBE & Nego ate
461 PM1004 Prepare & Issue LOI LPG 5*8 5d 12/Jul/2017 18/Jul/2017 11/Aug/2017 18/Aug/2017 21d Prepare & Issue LOI
462 PM1006 Prepare & Issue PR LPG 5*8 5d 19/Jul/2017 25/Jul/2017 31/Aug/2017 06/Sep/2017 29d Prepare & Issue PR
463 PM1008 Prepare & Issue PO LPG 5*8 5d 19/Jul/2017 25/Jul/2017 21/Aug/2017 25/Aug/2017 21d Prepare & Issue PO
464 PM1010 MLTPL Review/Approval of PR LPG 5*8 7d 26/Jul/2017 03/Aug/2017 07/Sep/2017 15/Sep/2017 29d MLTPL Review/Approval of PR
465 PM1012 Receive VDR LPG 5*8 15d 26/Jul/2017 17/Aug/2017 28/Aug/2017 15/Sep/2017 21d Receive VDR
466 PM1014 Approval of VDR LPG 5*8 15d 10/Aug/2017 31/Aug/2017 11/Sep/2017 03/Oct/2017 21d Approval of VDR
467 PM1016 Manufacturing LPG 5*8 175d 18/Aug/2017 26/Apr/2018 18/Sep/2017 25/May/2018 21d Manufacturing
468 PM1018 FAT LPG 5*8 5d 27/Apr/2018 03/May/2018 28/May/2018 01/Jun/2018 21d FAT
469 PM1020 Packaging & Dispatch - Ex Works LPG 5*8 10d 04/May/2018 17/May/2018 04/Jun/2018 15/Jun/2018 21d Packaging & Dispatch - Ex Works
470 PM1022 Delivery at Site LPG 5*8 30d 18/May/2018 28/Jun/2018 18/Jun/2018 27/Jul/2018 21d Delivery at Site
471 BOG Compressor LPG 5*8 230d 28/Jun/2017 24/May/2018 04/Oct/2017 27/Aug/2018 66d 24/May/2018, BOG Compressor
472 PM1198 MLTPL Review/Approval of AS LPG 5*8 7d 03/Jul/2017 11/Jul/2017 09/Oct/2017 17/Oct/2017 66d MLTPL Review/Approval of AS
473 PM1200 Prepare CBE & Nego ate LPG 5*8 10d 28/Jun/2017 11/Jul/2017 04/Oct/2017 17/Oct/2017 66d Prepare CBE & Nego ate

Actual Level of Effort Remaining Work Milestone Page 11 of 30 TASK filter: All Activities
Actual Work Critical Remaining Work summary Oracle Corporation
Mundra LPG Pvt Ltd Classic Schedule Layout 12/Jun/2017 16:07
# Ac vity ID Ac vity Name Calendar Original Early Start Early Finish Late Start Late Finish Total 2017 2018
Float Apr M Jun Jul Aug Sep Oct N Dec Jan F M Apr M Jun Jul Aug Sep Oct N Dec
474 PM1202 Prepare & Issue LOI LPG 5*8Dura on
5d 12/Jul/2017 18/Jul/2017 18/Oct/2017 24/Oct/2017 66d Prepare & Issue LOI
475 PM1204 Prepare & Issue PR LPG 5*8 10d 19/Jul/2017 01/Aug/2017 07/Nov/2017 20/Nov/2017 74d Prepare & Issue PR
476 PM1206 Prepare & Issue PO LPG 5*8 10d 19/Jul/2017 01/Aug/2017 26/Oct/2017 08/Nov/2017 66d Prepare & Issue PO
477 PM1208 MLTPL Review/Approval of PR LPG 5*8 7d 02/Aug/2017 11/Aug/2017 21/Nov/2017 29/Nov/2017 74d MLTPL Review/Approval of PR
478 PM1210 Receive VDR 1 LPG 5*8 15d 02/Aug/2017 24/Aug/2017 09/Nov/2017 29/Nov/2017 66d Receive VDR 1
479 PM1212 Approval of VDR LPG 5*8 20d 18/Aug/2017 14/Sep/2017 23/Nov/2017 20/Dec/2017 66d Approval of VDR
480 PM1214 Manufacturing LPG 5*8 165d 25/Aug/2017 19/Apr/2018 30/Nov/2017 20/Jul/2018 66d Manufacturing
481 PM1216 FAT LPG 5*8 5d 20/Apr/2018 26/Apr/2018 23/Jul/2018 27/Jul/2018 66d FAT
482 PM1218 Packaging & Dispach - Ex Works LPG 5*8 10d 27/Apr/2018 10/May/2018 30/Jul/2018 10/Aug/2018 66d Packaging & Dispach - Ex Works
483 PM1220 Delivery at Site LPG 5*8 10d 11/May/2018 24/May/2018 13/Aug/2018 27/Aug/2018 66d Delivery at Site
484 PM1222 Receive VDR 2 LPG 5*8 15d 02/Aug/2017 24/Aug/2017 09/Nov/2017 29/Nov/2017 66d Receive VDR 2
485 PM1224 Approval of VDR LPG 5*8 20d 18/Aug/2017 14/Sep/2017 23/Nov/2017 20/Dec/2017 66d Approval of VDR
486 PM1226 Manufacturing LPG 5*8 165d 25/Aug/2017 19/Apr/2018 30/Nov/2017 20/Jul/2018 66d Manufacturing
487 PM1228 FAT LPG 5*8 5d 20/Apr/2018 26/Apr/2018 23/Jul/2018 27/Jul/2018 66d FAT
488 PM1230 Packaging & Dispach - Ex Works LPG 5*8 10d 27/Apr/2018 10/May/2018 30/Jul/2018 10/Aug/2018 66d Packaging & Dispach - Ex Works
489 PM1240 Delivery at Site LPG 5*8 10d 11/May/2018 24/May/2018 13/Aug/2018 27/Aug/2018 66d Delivery at Site
490 Flash Gas Compressor LPG 5*8 230d 28/Jun/2017 24/May/2018 04/Oct/2017 27/Aug/2018 66d 24/May/2018, Flash Gas Compressor
491 PM1246 MLTPL Review/Approval of AS LPG 5*8 7d 03/Jul/2017 11/Jul/2017 09/Oct/2017 17/Oct/2017 66d MLTPL Review/Approval of AS
492 PM1248 Prepare CBE & Nego ate LPG 5*8 10d 28/Jun/2017 11/Jul/2017 04/Oct/2017 17/Oct/2017 66d Prepare CBE & Nego ate
493 PM1250 Prepare & Issue LOI LPG 5*8 5d 12/Jul/2017 18/Jul/2017 18/Oct/2017 24/Oct/2017 66d Prepare & Issue LOI
494 PM1252 Prepare & Issue PR LPG 5*8 10d 19/Jul/2017 01/Aug/2017 07/Nov/2017 20/Nov/2017 74d Prepare & Issue PR
495 PM1254 Prepare & Issue PO LPG 5*8 10d 19/Jul/2017 01/Aug/2017 26/Oct/2017 08/Nov/2017 66d Prepare & Issue PO
496 PM1256 MLTPL Review/Approval of PR LPG 5*8 7d 02/Aug/2017 11/Aug/2017 21/Nov/2017 29/Nov/2017 74d MLTPL Review/Approval of PR
497 PM1258 Receive VDR LPG 5*8 15d 02/Aug/2017 24/Aug/2017 09/Nov/2017 29/Nov/2017 66d Receive VDR
498 PM1260 Approval of VDR LPG 5*8 20d 18/Aug/2017 14/Sep/2017 23/Nov/2017 20/Dec/2017 66d Approval of VDR
499 PM1262 Manufacturing LPG 5*8 165d 25/Aug/2017 19/Apr/2018 30/Nov/2017 20/Jul/2018 66d Manufacturing
500 PM1264 FAT LPG 5*8 5d 20/Apr/2018 26/Apr/2018 23/Jul/2018 27/Jul/2018 66d FAT
501 PM1266 Packaging & Dispach - Ex Works LPG 5*8 10d 27/Apr/2018 10/May/2018 30/Jul/2018 10/Aug/2018 66d Packaging & Dispach - Ex Works
502 PM1268 Delivery at Site LPG 5*8 10d 11/May/2018 24/May/2018 13/Aug/2018 27/Aug/2018 66d Delivery at Site
503 PM1270 Receive VDR LPG 5*8 15d 02/Aug/2017 24/Aug/2017 09/Nov/2017 29/Nov/2017 66d Receive VDR
504 PM1272 Approval of VDR LPG 5*8 20d 18/Aug/2017 14/Sep/2017 23/Nov/2017 20/Dec/2017 66d Approval of VDR
505 PM1274 Manufacturing LPG 5*8 165d 25/Aug/2017 19/Apr/2018 30/Nov/2017 20/Jul/2018 66d Manufacturing
506 PM1276 FAT LPG 5*8 5d 20/Apr/2018 26/Apr/2018 23/Jul/2018 27/Jul/2018 66d FAT
507 PM1278 Packaging & Dispach - Ex Works LPG 5*8 10d 27/Apr/2018 10/May/2018 30/Jul/2018 10/Aug/2018 66d Packaging & Dispach - Ex Works
508 PM1280 Delivery at Site LPG 5*8 10d 11/May/2018 24/May/2018 13/Aug/2018 27/Aug/2018 66d Delivery at Site
509 Propane & Butane Transfer Pumps LPG 5*8 230d 28/Jun/2017 24/May/2018 06/Oct/2017 29/Aug/2018 68d 24/May/2018, Propane & Butane Transfer Pumps
510 PM1282 MLTPL Review/Approval of AS LPG 5*8 7d 03/Jul/2017 11/Jul/2017 11/Oct/2017 19/Oct/2017 68d MLTPL Review/Approval of AS
511 PM1284 Prepare CBE & Nego ate LPG 5*8 10d 28/Jun/2017 11/Jul/2017 06/Oct/2017 19/Oct/2017 68d Prepare CBE & Nego ate
512 PM1286 Prepare & Issue LOI LPG 5*8 5d 12/Jul/2017 18/Jul/2017 20/Oct/2017 27/Oct/2017 68d Prepare & Issue LOI
513 PM1288 Prepare & Issue PR LPG 5*8 10d 19/Jul/2017 01/Aug/2017 30/Nov/2017 13/Dec/2017 91d Prepare & Issue PR
514 PM1290 Prepare & Issue PO / LC LPG 5*8 10d 19/Jul/2017 01/Aug/2017 30/Oct/2017 10/Nov/2017 68d Prepare & Issue PO / LC
515 PM1292 MLTPL Review/Approval of PR LPG 5*8 7d 02/Aug/2017 11/Aug/2017 14/Dec/2017 22/Dec/2017 91d MLTPL Review/Approval of PR
516 PM1293 Receive VDR 1 LPG 5*8 30d 02/Aug/2017 14/Sep/2017 13/Nov/2017 22/Dec/2017 68d Receive VDR 1

Actual Level of Effort Remaining Work Milestone Page 12 of 30 TASK filter: All Activities
Actual Work Critical Remaining Work summary Oracle Corporation
Mundra LPG Pvt Ltd Classic Schedule Layout 12/Jun/2017 16:07
# Ac vity ID Ac vity Name Calendar Original Early Start Early Finish Late Start Late Finish Total 2017 2018
Float Apr M Jun Jul Aug Sep Oct N Dec Jan F M Apr M Jun Jul Aug Sep Oct N Dec
517 PM1294 Approval of VDR 1 LPG 5*8Dura30d
on 18/Aug/2017 02/Oct/2017 27/Nov/2017 05/Jan/2018 68d Approval of VDR 1
518 PM1295 Manufacturing 1 LPG 5*8 120d 25/Aug/2017 14/Feb/2018 04/Dec/2017 22/May/2018 68d Manufacturing 1
519 PM1296 FAT 1 LPG 5*8 5d 15/Feb/2018 21/Feb/2018 23/May/2018 29/May/2018 68d FAT 1
520 PM1297 Packaging & Dispach - FOC 1 LPG 5*8 10d 22/Feb/2018 07/Mar/2018 30/May/2018 12/Jun/2018 68d Packaging & Dispach - FOC 1
521 PM1298 Shipping & Coustom Clearance 1 LPG 5*8 45d 08/Mar/2018 10/May/2018 13/Jun/2018 14/Aug/2018 68d Shipping & Coustom Clearance 1
522 PM1299 Delivery at Site 1 LPG 5*8 10d 11/May/2018 24/May/2018 16/Aug/2018 29/Aug/2018 68d Delivery at Site 1
523 PM1300 Receive VDR LPG 5*8 15d 02/Aug/2017 24/Aug/2017 15/Jan/2018 05/Feb/2018 113d Receive VDR
524 PM1301 Approval of VDR LPG 5*8 20d 18/Aug/2017 14/Sep/2017 30/Jan/2018 26/Feb/2018 113d Approval of VDR
525 PM1302 Manufacturing LPG 5*8 120d 25/Aug/2017 14/Feb/2018 06/Feb/2018 24/Jul/2018 113d Manufacturing
526 PM1303 FAT LPG 5*8 5d 15/Feb/2018 21/Feb/2018 25/Jul/2018 31/Jul/2018 113d FAT
527 PM1304 Packaging & Dispach - Ex Works LPG 5*8 10d 22/Feb/2018 07/Mar/2018 01/Aug/2018 14/Aug/2018 113d Packaging & Dispach - Ex Works
528 PM1305 Delivery at Site LPG 5*8 10d 08/Mar/2018 22/Mar/2018 16/Aug/2018 29/Aug/2018 113d Delivery at Site
529 DM Water Package LPG 5*8 145d 30/Jun/2017 25/Jan/2018 22/Jan/2018 14/Aug/2018 141d 25/Jan/2018, DM Water Package
530 PM1024 MLTPL Review/Approval of AS LPG 5*8 7d 05/Jul/2017 13/Jul/2017 25/Jan/2018 05/Feb/2018 141d MLTPL Review/Approval of AS
531 PM1026 Prepare CBE & Nego ate LPG 5*8 10d 30/Jun/2017 13/Jul/2017 22/Jan/2018 05/Feb/2018 141d Prepare CBE & Nego ate
532 PM1028 Prepare & Issue LOI LPG 5*8 5d 14/Jul/2017 20/Jul/2017 06/Feb/2018 12/Feb/2018 141d Prepare & Issue LOI
533 PM1030 Prepare & Issue PR LPG 5*8 10d 21/Jul/2017 03/Aug/2017 23/Feb/2018 08/Mar/2018 149d Prepare & Issue PR
534 PM1032 Prepare & Issue PO LPG 5*8 10d 21/Jul/2017 03/Aug/2017 13/Feb/2018 26/Feb/2018 141d Prepare & Issue PO
535 PM1034 MLTPL Review/Approval of PR LPG 5*8 7d 04/Aug/2017 16/Aug/2017 09/Mar/2018 20/Mar/2018 149d MLTPL Review/Approval of PR
536 PM1036 Receive VDR LPG 5*8 15d 04/Aug/2017 28/Aug/2017 27/Feb/2018 20/Mar/2018 141d Receive VDR
537 PM1038 Approval of VDR LPG 5*8 20d 22/Aug/2017 18/Sep/2017 14/Mar/2018 10/Apr/2018 141d Approval of VDR
538 PM1040 Manufacturing LPG 5*8 80d 29/Aug/2017 21/Dec/2017 21/Mar/2018 10/Jul/2018 141d Manufacturing
539 PM1042 FAT LPG 5*8 5d 22/Dec/2017 28/Dec/2017 11/Jul/2018 17/Jul/2018 141d FAT
540 PM1044 Packaging & Dispach - Ex Works LPG 5*8 10d 29/Dec/2017 11/Jan/2018 18/Jul/2018 31/Jul/2018 141d Packaging & Dispach - Ex Works
541 PM1046 Delivery at Site LPG 5*8 10d 12/Jan/2018 25/Jan/2018 01/Aug/2018 14/Aug/2018 141d Delivery at Site
542 FW Water Package LPG 5*8 225d 30/Jun/2017 21/May/2018 28/Nov/2017 12/Oct/2018 102d 21/May/2018, FW Water Package
543 PM1048 MLTPL Review/Approval of AS LPG 5*8 7d 05/Jul/2017 13/Jul/2017 01/Dec/2017 11/Dec/2017 102d MLTPL Review/Approval of AS
544 PM1050 Prepare CBE & Nego ate LPG 5*8 10d 30/Jun/2017 13/Jul/2017 28/Nov/2017 11/Dec/2017 102d Prepare CBE & Nego ate
545 PM1052 Prepare & Issue LOI LPG 5*8 5d 14/Jul/2017 20/Jul/2017 12/Dec/2017 18/Dec/2017 102d Prepare & Issue LOI
546 PM1054 Prepare & Issue PR LPG 5*8 10d 21/Jul/2017 03/Aug/2017 29/Dec/2017 11/Jan/2018 110d Prepare & Issue PR
547 PM1056 Prepare & Issue PO LPG 5*8 10d 21/Jul/2017 03/Aug/2017 19/Dec/2017 01/Jan/2018 102d Prepare & Issue PO
548 PM1058 MLTPL Review/Approval of PR LPG 5*8 7d 04/Aug/2017 16/Aug/2017 12/Jan/2018 22/Jan/2018 110d MLTPL Review/Approval of PR
549 PM1060 Receive VDR LPG 5*8 15d 04/Aug/2017 28/Aug/2017 02/Jan/2018 22/Jan/2018 102d Receive VDR
550 PM1062 Approval of VDR LPG 5*8 20d 22/Aug/2017 18/Sep/2017 16/Jan/2018 13/Feb/2018 102d Approval of VDR
551 PM1064 Manufacturing LPG 5*8 160d 29/Aug/2017 16/Apr/2018 23/Jan/2018 06/Sep/2018 102d Manufacturing
552 PM1066 FAT LPG 5*8 5d 17/Apr/2018 23/Apr/2018 07/Sep/2018 13/Sep/2018 102d FAT
553 PM1068 Packaging & Dispach - Ex Works LPG 5*8 10d 24/Apr/2018 07/May/2018 14/Sep/2018 27/Sep/2018 102d Packaging & Dispach - Ex Works
554 PM1070 Delivery at Site LPG 5*8 10d 08/May/2018 21/May/2018 28/Sep/2018 12/Oct/2018 102d Delivery at Site
555 Liq Nitrogen Package LPG 5*8 195d 29/Jun/2017 06/Apr/2018 01/Nov/2017 02/Aug/2018 84d 06/Apr/2018, Liq Nitrogen Package
556 PM1120 MLTPL Review/Approval of AS LPG 5*8 7d 04/Jul/2017 12/Jul/2017 06/Nov/2017 14/Nov/2017 84d MLTPL Review/Approval of AS
557 PM1122 Prepare CBE & Nego ate LPG 5*8 10d 29/Jun/2017 12/Jul/2017 01/Nov/2017 14/Nov/2017 84d Prepare CBE & Nego ate
558 PM1124 Prepare & Issue LOI LPG 5*8 5d 13/Jul/2017 19/Jul/2017 15/Nov/2017 21/Nov/2017 84d Prepare & Issue LOI
559 PM1126 Prepare & Issue PR LPG 5*8 10d 20/Jul/2017 02/Aug/2017 04/Dec/2017 15/Dec/2017 92d Prepare & Issue PR

Actual Level of Effort Remaining Work Milestone Page 13 of 30 TASK filter: All Activities
Actual Work Critical Remaining Work summary Oracle Corporation
Mundra LPG Pvt Ltd Classic Schedule Layout 12/Jun/2017 16:07
# Ac vity ID Ac vity Name Calendar Original Early Start Early Finish Late Start Late Finish Total 2017 2018
Float Apr M Jun Jul Aug Sep Oct N Dec Jan F M Apr M Jun Jul Aug Sep Oct N Dec
560 PM1128 Prepare & Issue PO LPG 5*8Dura10d
on 20/Jul/2017 02/Aug/2017 22/Nov/2017 05/Dec/2017 84d Prepare & Issue PO
561 PM1130 MLTPL Review/Approval of PR LPG 5*8 7d 03/Aug/2017 14/Aug/2017 18/Dec/2017 26/Dec/2017 92d MLTPL Review/Approval of PR
562 PM1132 Receive VDR LPG 5*8 15d 03/Aug/2017 25/Aug/2017 06/Dec/2017 26/Dec/2017 84d Receive VDR
563 PM1134 Approval of VDR LPG 5*8 20d 21/Aug/2017 15/Sep/2017 20/Dec/2017 16/Jan/2018 84d Approval of VDR
564 PM1136 Manufacturing LPG 5*8 130d 28/Aug/2017 01/Mar/2018 27/Dec/2017 28/Jun/2018 84d Manufacturing
565 PM1138 FAT LPG 5*8 5d 02/Mar/2018 08/Mar/2018 29/Jun/2018 05/Jul/2018 84d FAT
566 PM1140 Packaging & Dispach - Ex Works LPG 5*8 10d 09/Mar/2018 23/Mar/2018 06/Jul/2018 19/Jul/2018 84d Packaging & Dispach - Ex Works
567 PM1142 Delivery at Site LPG 5*8 10d 26/Mar/2018 06/Apr/2018 20/Jul/2018 02/Aug/2018 84d Delivery at Site
568 Boiler Package LPG 5*8 225d 29/Jun/2017 18/May/2018 15/Sep/2017 02/Aug/2018 54d 18/May/2018, Boiler Package
569 PM1072 MLTPL Review/Approval of TBE LPG 5*8 7d 04/Jul/2017 12/Jul/2017 22/Sep/2017 02/Oct/2017 54d MLTPL Review/Approval of TBE
570 PM1074 Prepare CBE & Nego ate LPG 5*8 10d 29/Jun/2017 12/Jul/2017 15/Sep/2017 02/Oct/2017 54d Prepare CBE & Nego ate
571 PM1076 Prepare & Issue LOI LPG 5*8 5d 13/Jul/2017 19/Jul/2017 03/Oct/2017 09/Oct/2017 54d Prepare & Issue LOI
572 PM1078 Prepare & Issue PR LPG 5*8 10d 20/Jul/2017 02/Aug/2017 20/Oct/2017 03/Nov/2017 62d Prepare & Issue PR
573 PM1080 Prepare & Issue PO LPG 5*8 10d 20/Jul/2017 02/Aug/2017 10/Oct/2017 23/Oct/2017 54d Prepare & Issue PO
574 PM1082 MLTPL Review/Approval of PR LPG 5*8 7d 03/Aug/2017 14/Aug/2017 06/Nov/2017 14/Nov/2017 62d MLTPL Review/Approval of PR
575 PM1084 Receive VDR LPG 5*8 15d 03/Aug/2017 25/Aug/2017 24/Oct/2017 14/Nov/2017 54d Receive VDR
576 PM1086 Approval of VDR LPG 5*8 20d 21/Aug/2017 15/Sep/2017 08/Nov/2017 05/Dec/2017 54d Approval of VDR
577 PM1088 Manufacturing LPG 5*8 160d 28/Aug/2017 13/Apr/2018 15/Nov/2017 28/Jun/2018 54d Manufacturing
578 PM1090 FAT LPG 5*8 5d 16/Apr/2018 20/Apr/2018 29/Jun/2018 05/Jul/2018 54d FAT
579 PM1092 Packaging & Dispach - Ex Works LPG 5*8 10d 23/Apr/2018 04/May/2018 06/Jul/2018 19/Jul/2018 54d Packaging & Dispach - Ex Works
580 PM1094 Delivery at Site LPG 5*8 10d 07/May/2018 18/May/2018 20/Jul/2018 02/Aug/2018 54d Delivery at Site
581 Flare Package LPG 5*8 235d 30/Jun/2017 04/Jun/2018 01/Sep/2017 02/Aug/2018 43d 04/Jun/2018, Flare Package
582 PM1174 MLTPL Review/Approval of AS LPG 5*8 7d 05/Jul/2017 13/Jul/2017 06/Sep/2017 14/Sep/2017 43d MLTPL Review/Approval of AS
583 PM1176 Prepare CBE & Nego ate LPG 5*8 10d 30/Jun/2017 13/Jul/2017 01/Sep/2017 14/Sep/2017 43d Prepare CBE & Nego ate
584 PM1178 Prepare & Issue LOI LPG 5*8 5d 14/Jul/2017 20/Jul/2017 15/Sep/2017 25/Sep/2017 43d Prepare & Issue LOI
585 PM1180 Prepare & Issue PR LPG 5*8 10d 21/Jul/2017 03/Aug/2017 06/Oct/2017 19/Oct/2017 51d Prepare & Issue PR
586 PM1182 Prepare & Issue PO LPG 5*8 10d 21/Jul/2017 03/Aug/2017 26/Sep/2017 09/Oct/2017 43d Prepare & Issue PO
587 PM1184 MLTPL Review/Approval of PR LPG 5*8 7d 04/Aug/2017 16/Aug/2017 20/Oct/2017 31/Oct/2017 51d MLTPL Review/Approval of PR
588 PM1186 Receive VDR LPG 5*8 15d 04/Aug/2017 28/Aug/2017 10/Oct/2017 31/Oct/2017 43d Receive VDR
589 PM1188 Approval of VDR LPG 5*8 20d 22/Aug/2017 18/Sep/2017 24/Oct/2017 21/Nov/2017 43d Approval of VDR
590 PM1190 Manufacturing LPG 5*8 170d 29/Aug/2017 30/Apr/2018 01/Nov/2017 28/Jun/2018 43d Manufacturing
591 PM1192 FAT LPG 5*8 5d 01/May/2018 07/May/2018 29/Jun/2018 05/Jul/2018 43d FAT
592 PM1194 Packaging & Dispach - Ex Works LPG 5*8 10d 08/May/2018 21/May/2018 06/Jul/2018 19/Jul/2018 43d Packaging & Dispach - Ex Works
593 PM1196 Delivery at Site LPG 5*8 10d 22/May/2018 04/Jun/2018 20/Jul/2018 02/Aug/2018 43d Delivery at Site
594 Air Compressor Package LPG 5*8 185d 28/Jun/2017 22/Mar/2018 07/Dec/2017 27/Aug/2018 111d 22/Mar/2018, Air Compressor Package
595 PM1096 MLTPL Review/Approval of AS LPG 5*8 7d 03/Jul/2017 11/Jul/2017 12/Dec/2017 20/Dec/2017 111d MLTPL Review/Approval of AS
596 PM1098 Prepare CBE & Nego ate LPG 5*8 10d 28/Jun/2017 11/Jul/2017 07/Dec/2017 20/Dec/2017 111d Prepare CBE & Nego ate
597 PM1100 Prepare & Issue LOI LPG 5*8 5d 12/Jul/2017 18/Jul/2017 21/Dec/2017 27/Dec/2017 111d Prepare & Issue LOI
598 PM1102 Prepare & Issue PR LPG 5*8 10d 19/Jul/2017 01/Aug/2017 09/Jan/2018 22/Jan/2018 119d Prepare & Issue PR
599 PM1104 Prepare & Issue PO LPG 5*8 10d 19/Jul/2017 01/Aug/2017 28/Dec/2017 10/Jan/2018 111d Prepare & Issue PO
600 PM1106 MLTPL Review/Approval of PR LPG 5*8 7d 02/Aug/2017 11/Aug/2017 23/Jan/2018 01/Feb/2018 119d MLTPL Review/Approval of PR
601 PM1108 Receive VDR LPG 5*8 15d 02/Aug/2017 24/Aug/2017 11/Jan/2018 01/Feb/2018 111d Receive VDR
602 PM1110 Approval of VDR LPG 5*8 20d 18/Aug/2017 14/Sep/2017 25/Jan/2018 22/Feb/2018 111d Approval of VDR

Actual Level of Effort Remaining Work Milestone Page 14 of 30 TASK filter: All Activities
Actual Work Critical Remaining Work summary Oracle Corporation
Mundra LPG Pvt Ltd Classic Schedule Layout 12/Jun/2017 16:07
# Ac vity ID Ac vity Name Calendar Original Early Start Early Finish Late Start Late Finish Total 2017 2018
Float Apr M Jun Jul Aug Sep Oct N Dec Jan F M Apr M Jun Jul Aug Sep Oct N Dec
603 PM1112 Manufacturing LPG 5*8Dura120d
on 25/Aug/2017 14/Feb/2018 02/Feb/2018 20/Jul/2018 111d Manufacturing
604 PM1114 FAT LPG 5*8 5d 15/Feb/2018 21/Feb/2018 23/Jul/2018 27/Jul/2018 111d FAT
605 PM1116 Packaging & Dispach - Ex Works LPG 5*8 10d 22/Feb/2018 07/Mar/2018 30/Jul/2018 10/Aug/2018 111d Packaging & Dispach - Ex Works
606 PM1118 Delivery at Site LPG 5*8 10d 08/Mar/2018 22/Mar/2018 13/Aug/2018 27/Aug/2018 111d Delivery at Site
607 DG Set LPG 5*8 230d 07/Jun/2017 03/May/2018 04/Oct/2017 27/Aug/2018 81d 03/May/2018, DG Set
608 PM1144 MLTPL Review/Approval of MR LPG 5*8 7d 26/Jun/2017 04/Jul/2017 23/Oct/2017 01/Nov/2017 81d MLTPL Review/Approval of MR
609 PM1146 Receive Bids LPG 5*8 20d 07/Jun/2017 04/Jul/2017 04/Oct/2017 01/Nov/2017 81d Receive Bids
610 PM1148 Prepare & Issue TBE LPG 5*8 20d 05/Jul/2017 01/Aug/2017 02/Nov/2017 29/Nov/2017 81d Prepare & Issue TBE
611 PM1150 MLTPL Review/Approval of TBE LPG 5*8 7d 02/Aug/2017 11/Aug/2017 05/Dec/2017 13/Dec/2017 84d MLTPL Review/Approval of TBE
612 PM1152 Prepare CBE & Nego ate LPG 5*8 10d 02/Aug/2017 17/Aug/2017 30/Nov/2017 13/Dec/2017 81d Prepare CBE & Nego ate
613 PM1154 Prepare & Issue LOI LPG 5*8 5d 18/Aug/2017 24/Aug/2017 14/Dec/2017 20/Dec/2017 81d Prepare & Issue LOI
614 PM1156 Prepare & Issue PR LPG 5*8 10d 25/Aug/2017 07/Sep/2017 02/Jan/2018 15/Jan/2018 89d Prepare & Issue PR
615 PM1158 Prepare & Issue PO LPG 5*8 10d 25/Aug/2017 07/Sep/2017 21/Dec/2017 03/Jan/2018 81d Prepare & Issue PO
616 PM1160 MLTPL Review/Approval of PR LPG 5*8 7d 08/Sep/2017 18/Sep/2017 16/Jan/2018 24/Jan/2018 89d MLTPL Review/Approval of PR
617 PM1162 Receive VDR LPG 5*8 15d 08/Sep/2017 02/Oct/2017 04/Jan/2018 24/Jan/2018 81d Receive VDR
618 PM1164 Approval of VDR LPG 5*8 20d 26/Sep/2017 23/Oct/2017 18/Jan/2018 15/Feb/2018 81d Approval of VDR
619 PM1166 Manufacturing LPG 5*8 125d 03/Oct/2017 29/Mar/2018 25/Jan/2018 20/Jul/2018 81d Manufacturing
620 PM1168 FAT LPG 5*8 5d 30/Mar/2018 05/Apr/2018 23/Jul/2018 27/Jul/2018 81d FAT
621 PM1170 Packaging & Dispach - Ex Works LPG 5*8 10d 06/Apr/2018 19/Apr/2018 30/Jul/2018 10/Aug/2018 81d Packaging & Dispach - Ex Works
622 PM1172 Delivery at Site LPG 5*8 10d 20/Apr/2018 03/May/2018 13/Aug/2018 27/Aug/2018 81d Delivery at Site
623 Heat Exchangers LPG 5*8 215d 06/Sep/2017 11/Jul/2018 20/Oct/2017 14/Aug/2018 24d 11/Jul/2018, Heat Exchangers
624 Propane/Butane Heater LPG 5*8 77d 06/Sep/2017 27/Dec/2017 20/Oct/2017 19/Feb/2018 37d 27/Dec/2017, Propane/Butane Heater
625 PM1306 Prepare & Issue of Enquiry LPG 5*8 5d 06/Sep/2017 13/Sep/2017 20/Oct/2017 27/Oct/2017 29d Prepare & Issue of Enquiry
626 PM1308 MLTPL Review/Approval of MR LPG 5*8 7d 06/Sep/2017 15/Sep/2017 16/Nov/2017 24/Nov/2017 47d MLTPL Review/Approval of MR
627 PM1310 Receive Bids LPG 5*8 20d 13/Sep/2017 13/Oct/2017 30/Oct/2017 24/Nov/2017 29d Receive Bids
628 PM1312 Prepare & Issue TBE LPG 5*8 20d 13/Oct/2017 13/Nov/2017 27/Nov/2017 22/Dec/2017 29d Prepare & Issue TBE
629 PM1314 MLTPL Review/Approval of TBE LPG 5*8 7d 13/Nov/2017 22/Nov/2017 28/Dec/2017 05/Jan/2018 32d MLTPL Review/Approval of TBE
630 PM1316 Prepare CBE & Nego ate LPG 5*8 10d 13/Nov/2017 27/Nov/2017 25/Dec/2017 05/Jan/2018 29d Prepare CBE & Nego ate
631 PM1318 Prepare & Issue LOI LPG 5*8 5d 27/Nov/2017 04/Dec/2017 08/Jan/2018 12/Jan/2018 29d Prepare & Issue LOI
632 PM1320 Prepare & Issue PR LPG 5*8 10d 04/Dec/2017 18/Dec/2017 25/Jan/2018 08/Feb/2018 37d Prepare & Issue PR
633 PM1322 Prepare & Issue PO LPG 5*8 10d 04/Dec/2017 18/Dec/2017 15/Jan/2018 29/Jan/2018 29d Prepare & Issue PO
634 PM1324 MLTPL Review/Approval of PR LPG 5*8 7d 18/Dec/2017 27/Dec/2017 09/Feb/2018 19/Feb/2018 37d MLTPL Review/Approval of PR
635 Propane Heater I LPG 5*8 140d 18/Dec/2017 04/Jul/2018 30/Jan/2018 14/Aug/2018 29d 04/Jul/2018, Propane Heater I
636 PM1326 Receive VDR LPG 5*8 15d 18/Dec/2017 08/Jan/2018 30/Jan/2018 19/Feb/2018 29d Receive VDR
637 PM1328 Approval of VDR LPG 5*8 20d 01/Jan/2018 30/Jan/2018 13/Feb/2018 12/Mar/2018 29d Approval of VDR
638 PM1330 Manufacturing LPG 5*8 100d 08/Jan/2018 30/May/2018 20/Feb/2018 10/Jul/2018 29d Manufacturing
639 PM1332 FAT LPG 5*8 5d 30/May/2018 06/Jun/2018 11/Jul/2018 17/Jul/2018 29d FAT
640 PM1334 Packaging & Dispach - Ex Works LPG 5*8 10d 06/Jun/2018 20/Jun/2018 18/Jul/2018 31/Jul/2018 29d Packaging & Dispach - Ex Works
641 PM1336 Delivery at Site LPG 5*8 10d 20/Jun/2018 04/Jul/2018 01/Aug/2018 14/Aug/2018 29d Delivery at Site
642 Propane Heater II LPG 5*8 140d 18/Dec/2017 04/Jul/2018 30/Jan/2018 14/Aug/2018 29d 04/Jul/2018, Propane Heater II
643 PM1338 Receive VDR LPG 5*8 15d 18/Dec/2017 08/Jan/2018 30/Jan/2018 19/Feb/2018 29d Receive VDR
644 PM1340 Approval of VDR LPG 5*8 20d 01/Jan/2018 30/Jan/2018 13/Feb/2018 12/Mar/2018 29d Approval of VDR
645 PM1342 Manufacturing LPG 5*8 100d 08/Jan/2018 30/May/2018 20/Feb/2018 10/Jul/2018 29d Manufacturing

Actual Level of Effort Remaining Work Milestone Page 15 of 30 TASK filter: All Activities
Actual Work Critical Remaining Work summary Oracle Corporation
Mundra LPG Pvt Ltd Classic Schedule Layout 12/Jun/2017 16:07
# Ac vity ID Ac vity Name Calendar Original Early Start Early Finish Late Start Late Finish Total 2017 2018
Float Apr M Jun Jul Aug Sep Oct N Dec Jan F M Apr M Jun Jul Aug Sep Oct N Dec
646 PM1344 FAT LPG 5*8Dura on
5d 30/May/2018 06/Jun/2018 11/Jul/2018 17/Jul/2018 29d FAT
647 PM1346 Packaging & Dispach - Ex Works LPG 5*8 10d 06/Jun/2018 20/Jun/2018 18/Jul/2018 31/Jul/2018 29d Packaging & Dispach - Ex Works
648 PM1348 Delivery at Site LPG 5*8 10d 20/Jun/2018 04/Jul/2018 01/Aug/2018 14/Aug/2018 29d Delivery at Site
649 Butane Heater I LPG 5*8 140d 18/Dec/2017 04/Jul/2018 30/Jan/2018 14/Aug/2018 29d 04/Jul/2018, Butane Heater I
650 PM1350 Receive VDR LPG 5*8 15d 18/Dec/2017 08/Jan/2018 30/Jan/2018 19/Feb/2018 29d Receive VDR
651 PM1352 Approval of VDR LPG 5*8 20d 01/Jan/2018 30/Jan/2018 13/Feb/2018 12/Mar/2018 29d Approval of VDR
652 PM1354 Manufacturing LPG 5*8 100d 08/Jan/2018 30/May/2018 20/Feb/2018 10/Jul/2018 29d Manufacturing
653 PM1356 FAT LPG 5*8 5d 30/May/2018 06/Jun/2018 11/Jul/2018 17/Jul/2018 29d FAT
654 PM1358 Packaging & Dispach - Ex Works LPG 5*8 10d 06/Jun/2018 20/Jun/2018 18/Jul/2018 31/Jul/2018 29d Packaging & Dispach - Ex Works
655 PM1360 Delivery at Site LPG 5*8 10d 20/Jun/2018 04/Jul/2018 01/Aug/2018 14/Aug/2018 29d Delivery at Site
656 Butane Heater II LPG 5*8 140d 18/Dec/2017 04/Jul/2018 30/Jan/2018 14/Aug/2018 29d 04/Jul/2018, Butane Heater II
657 PM1362 Receive VDR LPG 5*8 15d 18/Dec/2017 08/Jan/2018 30/Jan/2018 19/Feb/2018 29d Receive VDR
658 PM1364 Approval of VDR LPG 5*8 20d 01/Jan/2018 30/Jan/2018 13/Feb/2018 12/Mar/2018 29d Approval of VDR
659 PM1366 Manufacturing LPG 5*8 100d 08/Jan/2018 30/May/2018 20/Feb/2018 10/Jul/2018 29d Manufacturing
660 PM1368 FAT LPG 5*8 5d 30/May/2018 06/Jun/2018 11/Jul/2018 17/Jul/2018 29d FAT
661 PM1370 Packaging & Dispach - Ex Works LPG 5*8 10d 06/Jun/2018 20/Jun/2018 18/Jul/2018 31/Jul/2018 29d Packaging & Dispach - Ex Works
662 PM1372 Delivery at Site LPG 5*8 10d 20/Jun/2018 04/Jul/2018 01/Aug/2018 14/Aug/2018 29d Delivery at Site
663 Propane Vaporizer LPG 5*8 77d 13/Sep/2017 03/Jan/2018 20/Oct/2017 19/Feb/2018 32d 03/Jan/2018, Propane Vaporizer
664 PM1374 Prepare & Issue of Enquiry LPG 5*8 5d 13/Sep/2017 22/Sep/2017 20/Oct/2017 27/Oct/2017 24d Prepare & Issue of Enquiry
665 PM1376 MLTPL Review/Approval of MR LPG 5*8 7d 13/Sep/2017 26/Sep/2017 16/Nov/2017 24/Nov/2017 42d MLTPL Review/Approval of MR
666 PM1378 Receive Bids LPG 5*8 20d 22/Sep/2017 20/Oct/2017 30/Oct/2017 24/Nov/2017 24d Receive Bids
667 PM1380 Prepare & Issue TBE LPG 5*8 20d 20/Oct/2017 20/Nov/2017 27/Nov/2017 22/Dec/2017 24d Prepare & Issue TBE
668 PM1382 MLTPL Review/Approval of TBE LPG 5*8 7d 20/Nov/2017 29/Nov/2017 28/Dec/2017 05/Jan/2018 27d MLTPL Review/Approval of TBE
669 PM1384 Prepare CBE & Nego ate LPG 5*8 10d 20/Nov/2017 04/Dec/2017 25/Dec/2017 05/Jan/2018 24d Prepare CBE & Nego ate
670 PM1386 Prepare & Issue LOI LPG 5*8 5d 04/Dec/2017 11/Dec/2017 08/Jan/2018 12/Jan/2018 24d Prepare & Issue LOI
671 PM1388 Prepare & Issue PR LPG 5*8 10d 11/Dec/2017 25/Dec/2017 25/Jan/2018 08/Feb/2018 32d Prepare & Issue PR
672 PM1390 Prepare & Issue PO LPG 5*8 10d 11/Dec/2017 25/Dec/2017 15/Jan/2018 29/Jan/2018 24d Prepare & Issue PO
673 PM1392 MLTPL Review/Approval of PR LPG 5*8 7d 25/Dec/2017 03/Jan/2018 09/Feb/2018 19/Feb/2018 32d MLTPL Review/Approval of PR
674 Propane Vaporizer I LPG 5*8 140d 25/Dec/2017 11/Jul/2018 30/Jan/2018 14/Aug/2018 24d 11/Jul/2018, Propane Vaporizer I
675 PM1394 Receive VDR LPG 5*8 15d 25/Dec/2017 15/Jan/2018 30/Jan/2018 19/Feb/2018 24d Receive VDR
676 PM1396 Approval of VDR LPG 5*8 20d 08/Jan/2018 06/Feb/2018 13/Feb/2018 12/Mar/2018 24d Approval of VDR
677 PM1398 Manufacturing LPG 5*8 100d 15/Jan/2018 06/Jun/2018 20/Feb/2018 10/Jul/2018 24d Manufacturing
678 PM1400 FAT LPG 5*8 5d 06/Jun/2018 13/Jun/2018 11/Jul/2018 17/Jul/2018 24d FAT
679 PM1402 Packaging & Dispach - Ex Works LPG 5*8 10d 13/Jun/2018 27/Jun/2018 18/Jul/2018 31/Jul/2018 24d Packaging & Dispach - Ex Works
680 PM1404 Delivery at Site LPG 5*8 10d 27/Jun/2018 11/Jul/2018 01/Aug/2018 14/Aug/2018 24d Delivery at Site
681 Propane Vaporizer II LPG 5*8 140d 25/Dec/2017 11/Jul/2018 30/Jan/2018 14/Aug/2018 24d 11/Jul/2018, Propane Vaporizer II
682 PM1406 Receive VDR LPG 5*8 15d 25/Dec/2017 15/Jan/2018 30/Jan/2018 19/Feb/2018 24d Receive VDR
683 PM1408 Approval of VDR LPG 5*8 20d 08/Jan/2018 06/Feb/2018 13/Feb/2018 12/Mar/2018 24d Approval of VDR
684 PM1410 Manufacturing LPG 5*8 100d 15/Jan/2018 06/Jun/2018 20/Feb/2018 10/Jul/2018 24d Manufacturing
685 PM1412 FAT LPG 5*8 5d 06/Jun/2018 13/Jun/2018 11/Jul/2018 17/Jul/2018 24d FAT
686 PM1414 Packaging & Dispach - Ex Works LPG 5*8 10d 13/Jun/2018 27/Jun/2018 18/Jul/2018 31/Jul/2018 24d Packaging & Dispach - Ex Works
687 PM1416 Delivery at Site LPG 5*8 10d 27/Jun/2018 11/Jul/2018 01/Aug/2018 14/Aug/2018 24d Delivery at Site
688 Propane/Butane Flash Condenser LPG 5*8 77d 06/Sep/2017 27/Dec/2017 20/Oct/2017 19/Feb/2018 37d 27/Dec/2017, Propane/Butane Flash Condenser

Actual Level of Effort Remaining Work Milestone Page 16 of 30 TASK filter: All Activities
Actual Work Critical Remaining Work summary Oracle Corporation
Mundra LPG Pvt Ltd Classic Schedule Layout 12/Jun/2017 16:07
# Ac vity ID Ac vity Name Calendar Original Early Start Early Finish Late Start Late Finish Total 2017 2018
Float Apr M Jun Jul Aug Sep Oct N Dec Jan F M Apr M Jun Jul Aug Sep Oct N Dec
689 PM1418 Prepare & Issue of Enquiry LPG 5*8Dura on
5d 06/Sep/2017 13/Sep/2017 20/Oct/2017 27/Oct/2017 29d Prepare & Issue of Enquiry
690 PM1420 MLTPL Review/Approval of MR LPG 5*8 7d 06/Sep/2017 15/Sep/2017 16/Nov/2017 24/Nov/2017 47d MLTPL Review/Approval of MR
691 PM1422 Receive Bids LPG 5*8 20d 13/Sep/2017 13/Oct/2017 30/Oct/2017 24/Nov/2017 29d Receive Bids
692 PM1424 Prepare & Issue TBE LPG 5*8 20d 13/Oct/2017 13/Nov/2017 27/Nov/2017 22/Dec/2017 29d Prepare & Issue TBE
693 PM1426 MLTPL Review/Approval of TBE LPG 5*8 7d 13/Nov/2017 22/Nov/2017 28/Dec/2017 05/Jan/2018 32d MLTPL Review/Approval of TBE
694 PM1428 Prepare CBE & Nego ate LPG 5*8 10d 13/Nov/2017 27/Nov/2017 25/Dec/2017 05/Jan/2018 29d Prepare CBE & Nego ate
695 PM1430 Prepare & Issue LOI LPG 5*8 5d 27/Nov/2017 04/Dec/2017 08/Jan/2018 12/Jan/2018 29d Prepare & Issue LOI
696 PM1432 Prepare & Issue PR LPG 5*8 10d 04/Dec/2017 18/Dec/2017 25/Jan/2018 08/Feb/2018 37d Prepare & Issue PR
697 PM1434 Prepare & Issue PO LPG 5*8 10d 04/Dec/2017 18/Dec/2017 15/Jan/2018 29/Jan/2018 29d Prepare & Issue PO
698 PM1436 MLTPL Review/Approval of PR LPG 5*8 7d 18/Dec/2017 27/Dec/2017 09/Feb/2018 19/Feb/2018 37d MLTPL Review/Approval of PR
699 Propane Flash Condenser LPG 5*8 140d 18/Dec/2017 04/Jul/2018 30/Jan/2018 14/Aug/2018 29d 04/Jul/2018, Propane Flash Condenser
700 PM1438 Receive VDR LPG 5*8 15d 18/Dec/2017 08/Jan/2018 30/Jan/2018 19/Feb/2018 29d Receive VDR
701 PM1440 Approval of VDR LPG 5*8 20d 01/Jan/2018 30/Jan/2018 13/Feb/2018 12/Mar/2018 29d Approval of VDR
702 PM1442 Manufacturing LPG 5*8 100d 08/Jan/2018 30/May/2018 20/Feb/2018 10/Jul/2018 29d Manufacturing
703 PM1444 FAT LPG 5*8 5d 30/May/2018 06/Jun/2018 11/Jul/2018 17/Jul/2018 29d FAT
704 PM1446 Packaging & Dispach - Ex Works LPG 5*8 10d 06/Jun/2018 20/Jun/2018 18/Jul/2018 31/Jul/2018 29d Packaging & Dispach - Ex Works
705 PM1448 Delivery at Site LPG 5*8 10d 20/Jun/2018 04/Jul/2018 01/Aug/2018 14/Aug/2018 29d Delivery at Site
706 Butane Flash Condenser LPG 5*8 140d 18/Dec/2017 04/Jul/2018 30/Jan/2018 14/Aug/2018 29d 04/Jul/2018, Butane Flash Condenser
707 PM1450 Receive VDR LPG 5*8 15d 18/Dec/2017 08/Jan/2018 30/Jan/2018 19/Feb/2018 29d Receive VDR
708 PM1452 Approval of VDR LPG 5*8 20d 01/Jan/2018 30/Jan/2018 13/Feb/2018 12/Mar/2018 29d Approval of VDR
709 PM1454 Manufacturing LPG 5*8 100d 08/Jan/2018 30/May/2018 20/Feb/2018 10/Jul/2018 29d Manufacturing
710 PM1456 FAT LPG 5*8 5d 30/May/2018 06/Jun/2018 11/Jul/2018 17/Jul/2018 29d FAT
711 PM1458 Packaging & Dispach - Ex Works LPG 5*8 10d 06/Jun/2018 20/Jun/2018 18/Jul/2018 31/Jul/2018 29d Packaging & Dispach - Ex Works
712 PM1460 Delivery at Site LPG 5*8 10d 20/Jun/2018 04/Jul/2018 01/Aug/2018 14/Aug/2018 29d Delivery at Site
713 Vessels LPG 5*8 210d 06/Sep/2017 04/Jul/2018 20/Oct/2017 27/Aug/2018 37d 04/Jul/2018, Vessels
714 Suc on Separators LPG 5*8 77d 06/Sep/2017 27/Dec/2017 20/Oct/2017 19/Feb/2018 37d 27/Dec/2017, Suc on Separators
715 PM1462 Prepare & Issue of Enquiry LPG 5*8 5d 06/Sep/2017 13/Sep/2017 20/Oct/2017 27/Oct/2017 29d Prepare & Issue of Enquiry
716 PM1464 MLTPL Review/Approval of MR LPG 5*8 7d 06/Sep/2017 15/Sep/2017 16/Nov/2017 24/Nov/2017 47d MLTPL Review/Approval of MR
717 PM1466 Receive Bids LPG 5*8 20d 13/Sep/2017 13/Oct/2017 30/Oct/2017 24/Nov/2017 29d Receive Bids
718 PM1468 Prepare & Issue TBE LPG 5*8 20d 13/Oct/2017 13/Nov/2017 27/Nov/2017 22/Dec/2017 29d Prepare & Issue TBE
719 PM1470 MLTPL Review/Approval of TBE LPG 5*8 7d 13/Nov/2017 22/Nov/2017 28/Dec/2017 05/Jan/2018 32d MLTPL Review/Approval of TBE
720 PM1472 Prepare CBE & Nego ate LPG 5*8 10d 13/Nov/2017 27/Nov/2017 25/Dec/2017 05/Jan/2018 29d Prepare CBE & Nego ate
721 PM1474 Prepare & Issue LOI LPG 5*8 5d 27/Nov/2017 04/Dec/2017 08/Jan/2018 12/Jan/2018 29d Prepare & Issue LOI
722 PM1476 Prepare & Issue PR LPG 5*8 10d 04/Dec/2017 18/Dec/2017 25/Jan/2018 08/Feb/2018 37d Prepare & Issue PR
723 PM1478 Prepare & Issue PO LPG 5*8 10d 04/Dec/2017 18/Dec/2017 15/Jan/2018 29/Jan/2018 29d Prepare & Issue PO
724 PM1480 MLTPL Review/Approval of PR LPG 5*8 7d 18/Dec/2017 27/Dec/2017 09/Feb/2018 19/Feb/2018 37d MLTPL Review/Approval of PR
725 Suc on Separator I LPG 5*8 140d 18/Dec/2017 04/Jul/2018 30/Jan/2018 14/Aug/2018 29d 04/Jul/2018, Suc on Separator I
726 PM1482 Receive VDR LPG 5*8 15d 18/Dec/2017 08/Jan/2018 30/Jan/2018 19/Feb/2018 29d Receive VDR
727 PM1484 Approval of VDR LPG 5*8 20d 01/Jan/2018 30/Jan/2018 13/Feb/2018 12/Mar/2018 29d Approval of VDR
728 PM1486 Manufacturing LPG 5*8 100d 08/Jan/2018 30/May/2018 20/Feb/2018 10/Jul/2018 29d Manufacturing
729 PM1488 FAT LPG 5*8 5d 30/May/2018 06/Jun/2018 11/Jul/2018 17/Jul/2018 29d FAT
730 PM1490 Packaging & Dispach - Ex Works LPG 5*8 10d 06/Jun/2018 20/Jun/2018 18/Jul/2018 31/Jul/2018 29d Packaging & Dispach - Ex Works
731 PM1492 Delivery at Site LPG 5*8 10d 20/Jun/2018 04/Jul/2018 01/Aug/2018 14/Aug/2018 29d Delivery at Site

Actual Level of Effort Remaining Work Milestone Page 17 of 30 TASK filter: All Activities
Actual Work Critical Remaining Work summary Oracle Corporation
Mundra LPG Pvt Ltd Classic Schedule Layout 12/Jun/2017 16:07
# Ac vity ID Ac vity Name Calendar Original Early Start Early Finish Late Start Late Finish Total 2017 2018
Float Apr M Jun Jul Aug Sep Oct N Dec Jan F M Apr M Jun Jul Aug Sep Oct N Dec
732 Suc on Separator II LPG 5*8Dura140d
on 18/Dec/2017 04/Jul/2018 30/Jan/2018 14/Aug/2018 29d 04/Jul/2018, Suc on Separator II
733 PM1494 Receive VDR LPG 5*8 15d 18/Dec/2017 08/Jan/2018 30/Jan/2018 19/Feb/2018 29d Receive VDR
734 PM1496 Approval of VDR LPG 5*8 20d 01/Jan/2018 30/Jan/2018 13/Feb/2018 12/Mar/2018 29d Approval of VDR
735 PM1498 Manufacturing LPG 5*8 100d 08/Jan/2018 30/May/2018 20/Feb/2018 10/Jul/2018 29d Manufacturing
736 PM1500 FAT LPG 5*8 5d 30/May/2018 06/Jun/2018 11/Jul/2018 17/Jul/2018 29d FAT
737 PM1502 Packaging & Dispach - Ex Works LPG 5*8 10d 06/Jun/2018 20/Jun/2018 18/Jul/2018 31/Jul/2018 29d Packaging & Dispach - Ex Works
738 PM1504 Delivery at Site LPG 5*8 10d 20/Jun/2018 04/Jul/2018 01/Aug/2018 14/Aug/2018 29d Delivery at Site
739 Propane & Butane BOG/Flash Condensate Receiver LPG 5*8 77d 06/Sep/2017 27/Dec/2017 02/Nov/2017 01/Mar/2018 45d 27/Dec/2017, Propane & Butane BOG/Flash Condensate Receiver
740 PM1506 Prepare & Issue of Enquiry LPG 5*8 5d 06/Sep/2017 13/Sep/2017 02/Nov/2017 08/Nov/2017 37d Prepare & Issue of Enquiry
741 PM1508 MLTPL Review/Approval of MR LPG 5*8 7d 06/Sep/2017 15/Sep/2017 28/Nov/2017 06/Dec/2017 55d MLTPL Review/Approval of MR
742 PM1510 Receive Bids LPG 5*8 20d 13/Sep/2017 13/Oct/2017 09/Nov/2017 06/Dec/2017 37d Receive Bids
743 PM1512 Prepare & Issue TBE LPG 5*8 20d 13/Oct/2017 13/Nov/2017 07/Dec/2017 03/Jan/2018 37d Prepare & Issue TBE
744 PM1514 MLTPL Review/Approval of TBE LPG 5*8 7d 13/Nov/2017 22/Nov/2017 09/Jan/2018 17/Jan/2018 40d MLTPL Review/Approval of TBE
745 PM1516 Prepare CBE & Nego ate LPG 5*8 10d 13/Nov/2017 27/Nov/2017 04/Jan/2018 17/Jan/2018 37d Prepare CBE & Nego ate
746 PM1518 Prepare & Issue LOI LPG 5*8 5d 27/Nov/2017 04/Dec/2017 18/Jan/2018 24/Jan/2018 37d Prepare & Issue LOI
747 PM1520 Prepare & Issue PR LPG 5*8 10d 04/Dec/2017 18/Dec/2017 07/Feb/2018 20/Feb/2018 45d Prepare & Issue PR
748 PM1522 Prepare & Issue PO LPG 5*8 10d 04/Dec/2017 18/Dec/2017 25/Jan/2018 08/Feb/2018 37d Prepare & Issue PO
749 PM1524 MLTPL Review/Approval of PR LPG 5*8 7d 18/Dec/2017 27/Dec/2017 21/Feb/2018 01/Mar/2018 45d MLTPL Review/Approval of PR
750 Propane BOG/Flash Condensate Receiver LPG 5*8 140d 18/Dec/2017 04/Jul/2018 09/Feb/2018 27/Aug/2018 37d 04/Jul/2018, Propane BOG/Flash Condensate Re
751 PM1526 Receive VDR LPG 5*8 15d 18/Dec/2017 08/Jan/2018 09/Feb/2018 01/Mar/2018 37d Receive VDR
752 PM1528 Approval of VDR LPG 5*8 20d 01/Jan/2018 30/Jan/2018 23/Feb/2018 23/Mar/2018 37d Approval of VDR
753 PM1530 Manufacturing LPG 5*8 100d 08/Jan/2018 30/May/2018 02/Mar/2018 20/Jul/2018 37d Manufacturing
754 PM1532 FAT LPG 5*8 5d 30/May/2018 06/Jun/2018 23/Jul/2018 27/Jul/2018 37d FAT
755 PM1534 Packaging & Dispach - Ex Works LPG 5*8 10d 06/Jun/2018 20/Jun/2018 30/Jul/2018 10/Aug/2018 37d Packaging & Dispach - Ex Works
756 PM1536 Delivery at Site LPG 5*8 10d 20/Jun/2018 04/Jul/2018 13/Aug/2018 27/Aug/2018 37d Delivery at Site
757 Butane BOG/Flash Condensate Receiver LPG 5*8 140d 18/Dec/2017 04/Jul/2018 09/Feb/2018 27/Aug/2018 37d 04/Jul/2018, Butane BOG/Flash Condensate Rec
758 PM1538 Receive VDR LPG 5*8 15d 18/Dec/2017 08/Jan/2018 09/Feb/2018 01/Mar/2018 37d Receive VDR
759 PM1540 Approval of VDR LPG 5*8 20d 01/Jan/2018 30/Jan/2018 23/Feb/2018 23/Mar/2018 37d Approval of VDR
760 PM1542 Manufacturing LPG 5*8 100d 08/Jan/2018 30/May/2018 02/Mar/2018 20/Jul/2018 37d Manufacturing
761 PM1544 FAT LPG 5*8 5d 30/May/2018 06/Jun/2018 23/Jul/2018 27/Jul/2018 37d FAT
762 PM1546 Packaging & Dispach - Ex Works LPG 5*8 10d 06/Jun/2018 20/Jun/2018 30/Jul/2018 10/Aug/2018 37d Packaging & Dispach - Ex Works
763 PM1548 Delivery at Site LPG 5*8 10d 20/Jun/2018 04/Jul/2018 13/Aug/2018 27/Aug/2018 37d Delivery at Site
764 Steam Condensate Receiver LPG 5*8 210d 06/Sep/2017 04/Jul/2018 02/Nov/2017 27/Aug/2018 37d 04/Jul/2018, Steam Condensate Receiver
765 PM1550 Prepare & Issue of Enquiry LPG 5*8 5d 06/Sep/2017 13/Sep/2017 02/Nov/2017 08/Nov/2017 37d Prepare & Issue of Enquiry
766 PM1552 MLTPL Review/Approval of MR LPG 5*8 7d 06/Sep/2017 15/Sep/2017 28/Nov/2017 06/Dec/2017 55d MLTPL Review/Approval of MR
767 PM1554 Receive Bids LPG 5*8 20d 13/Sep/2017 13/Oct/2017 09/Nov/2017 06/Dec/2017 37d Receive Bids
768 PM1556 Prepare & Issue TBE LPG 5*8 20d 13/Oct/2017 13/Nov/2017 07/Dec/2017 03/Jan/2018 37d Prepare & Issue TBE
769 PM1558 MLTPL Review/Approval of TBE LPG 5*8 7d 13/Nov/2017 22/Nov/2017 09/Jan/2018 17/Jan/2018 40d MLTPL Review/Approval of TBE
770 PM1560 Prepare CBE & Nego ate LPG 5*8 10d 13/Nov/2017 27/Nov/2017 04/Jan/2018 17/Jan/2018 37d Prepare CBE & Nego ate
771 PM1562 Prepare & Issue LOI LPG 5*8 5d 27/Nov/2017 04/Dec/2017 18/Jan/2018 24/Jan/2018 37d Prepare & Issue LOI
772 PM1564 Prepare & Issue PR LPG 5*8 10d 04/Dec/2017 18/Dec/2017 07/Feb/2018 20/Feb/2018 45d Prepare & Issue PR
773 PM1566 Prepare & Issue PO LPG 5*8 10d 04/Dec/2017 18/Dec/2017 25/Jan/2018 08/Feb/2018 37d Prepare & Issue PO
774 PM1568 MLTPL Review/Approval of PR LPG 5*8 7d 18/Dec/2017 27/Dec/2017 21/Feb/2018 01/Mar/2018 45d MLTPL Review/Approval of PR

Actual Level of Effort Remaining Work Milestone Page 18 of 30 TASK filter: All Activities
Actual Work Critical Remaining Work summary Oracle Corporation
Mundra LPG Pvt Ltd Classic Schedule Layout 12/Jun/2017 16:07
# Ac vity ID Ac vity Name Calendar Original Early Start Early Finish Late Start Late Finish Total 2017 2018
Float Apr M Jun Jul Aug Sep Oct N Dec Jan F M Apr M Jun Jul Aug Sep Oct N Dec
775 PM1570 Receive VDR LPG 5*8Dura15d
on 18/Dec/2017 08/Jan/2018 09/Feb/2018 01/Mar/2018 37d Receive VDR
776 PM1572 Approval of VDR LPG 5*8 20d 01/Jan/2018 30/Jan/2018 23/Feb/2018 23/Mar/2018 37d Approval of VDR
777 PM1574 Manufacturing LPG 5*8 100d 08/Jan/2018 30/May/2018 02/Mar/2018 20/Jul/2018 37d Manufacturing
778 PM1576 FAT LPG 5*8 5d 30/May/2018 06/Jun/2018 23/Jul/2018 27/Jul/2018 37d FAT
779 PM1578 Packaging & Dispach - Ex Works LPG 5*8 10d 06/Jun/2018 20/Jun/2018 30/Jul/2018 10/Aug/2018 37d Packaging & Dispach - Ex Works
780 PM1580 Delivery at Site LPG 5*8 10d 20/Jun/2018 04/Jul/2018 13/Aug/2018 27/Aug/2018 37d Delivery at Site
781 Storage Tanks LPG 5*8 230d 25/Aug/2017 19/Jul/2018 08/Sep/2017 12/Oct/2018 59d 19/Jul/2018, Storage Tanks
782 DM Water Tank LPG 5*8 230d 25/Aug/2017 19/Jul/2018 08/Sep/2017 02/Aug/2018 10d 19/Jul/2018, DM Water Tank
783 PM1582 Prepare & Issue of Enquiry LPG 5*8 5d 25/Aug/2017 31/Aug/2017 08/Sep/2017 14/Sep/2017 10d Prepare & Issue of Enquiry
784 PM1584 MLTPL Review/Approval of MR LPG 5*8 7d 25/Aug/2017 04/Sep/2017 06/Oct/2017 16/Oct/2017 28d MLTPL Review/Approval of MR
785 PM1586 Receive Bids LPG 5*8 20d 01/Sep/2017 02/Oct/2017 15/Sep/2017 16/Oct/2017 10d Receive Bids
786 PM1588 Prepare & Issue TBE LPG 5*8 20d 03/Oct/2017 31/Oct/2017 17/Oct/2017 14/Nov/2017 10d Prepare & Issue TBE
787 PM1590 MLTPL Review/Approval of TBE LPG 5*8 7d 01/Nov/2017 09/Nov/2017 20/Nov/2017 28/Nov/2017 13d MLTPL Review/Approval of TBE
788 PM1592 Prepare CBE & Nego ate LPG 5*8 10d 01/Nov/2017 14/Nov/2017 15/Nov/2017 28/Nov/2017 10d Prepare CBE & Nego ate
789 PM1594 Prepare & Issue LOI LPG 5*8 5d 15/Nov/2017 21/Nov/2017 29/Nov/2017 05/Dec/2017 10d Prepare & Issue LOI
790 PM1596 Prepare & Issue PR LPG 5*8 10d 22/Nov/2017 05/Dec/2017 18/Dec/2017 29/Dec/2017 18d Prepare & Issue PR
791 PM1598 Prepare & Issue PO LPG 5*8 10d 22/Nov/2017 05/Dec/2017 06/Dec/2017 19/Dec/2017 10d Prepare & Issue PO
792 PM1600 MLTPL Review/Approval of PR LPG 5*8 7d 06/Dec/2017 14/Dec/2017 01/Jan/2018 09/Jan/2018 18d MLTPL Review/Approval of PR
793 PM1602 Receive VDR LPG 5*8 15d 06/Dec/2017 26/Dec/2017 20/Dec/2017 09/Jan/2018 10d Receive VDR
794 PM1604 Approval of VDR LPG 5*8 20d 20/Dec/2017 16/Jan/2018 03/Jan/2018 31/Jan/2018 10d Approval of VDR
795 PM1606 Manufacturing LPG 5*8 120d 27/Dec/2017 14/Jun/2018 10/Jan/2018 28/Jun/2018 10d Manufacturing
796 PM1608 FAT LPG 5*8 5d 15/Jun/2018 21/Jun/2018 29/Jun/2018 05/Jul/2018 10d FAT
797 PM1610 Packaging & Dispach - Ex Works LPG 5*8 10d 22/Jun/2018 05/Jul/2018 06/Jul/2018 19/Jul/2018 10d Packaging & Dispach - Ex Works
798 PM1612 Delivery at Site LPG 5*8 10d 06/Jul/2018 19/Jul/2018 20/Jul/2018 02/Aug/2018 10d Delivery at Site
799 DM, FW, SW CondansateTanks LPG 5*8 230d 25/Aug/2017 19/Jul/2018 21/Nov/2017 12/Oct/2018 59d 19/Jul/2018, DM, FW, SW CondansateTanks
800 PM1646 Prepare & Issue of Enquiry LPG 5*8 5d 25/Aug/2017 31/Aug/2017 21/Nov/2017 27/Nov/2017 59d Prepare & Issue of Enquiry
801 PM1648 MLTPL Review/Approval of MR LPG 5*8 7d 25/Aug/2017 04/Sep/2017 15/Dec/2017 25/Dec/2017 77d MLTPL Review/Approval of MR
802 PM1650 Receive Bids LPG 5*8 20d 01/Sep/2017 02/Oct/2017 28/Nov/2017 25/Dec/2017 59d Receive Bids
803 PM1652 Prepare & Issue TBE LPG 5*8 20d 03/Oct/2017 31/Oct/2017 26/Dec/2017 22/Jan/2018 59d Prepare & Issue TBE
804 PM1654 MLTPL Review/Approval of TBE LPG 5*8 7d 01/Nov/2017 09/Nov/2017 29/Jan/2018 06/Feb/2018 62d MLTPL Review/Approval of TBE
805 PM1656 Prepare CBE & Nego ate LPG 5*8 10d 01/Nov/2017 14/Nov/2017 23/Jan/2018 06/Feb/2018 59d Prepare CBE & Nego ate
806 PM1658 Prepare & Issue LOI LPG 5*8 5d 15/Nov/2017 21/Nov/2017 07/Feb/2018 13/Feb/2018 59d Prepare & Issue LOI
807 PM1660 Prepare & Issue PR LPG 5*8 10d 22/Nov/2017 05/Dec/2017 26/Feb/2018 09/Mar/2018 67d Prepare & Issue PR
808 PM1662 Prepare & Issue PO LPG 5*8 10d 22/Nov/2017 05/Dec/2017 14/Feb/2018 27/Feb/2018 59d Prepare & Issue PO
809 PM1664 MLTPL Review/Approval of PR LPG 5*8 7d 06/Dec/2017 14/Dec/2017 12/Mar/2018 21/Mar/2018 67d MLTPL Review/Approval of PR
810 PM1666 Receive VDR LPG 5*8 15d 06/Dec/2017 26/Dec/2017 28/Feb/2018 21/Mar/2018 59d Receive VDR
811 PM1668 Approval of VDR LPG 5*8 20d 20/Dec/2017 16/Jan/2018 15/Mar/2018 11/Apr/2018 59d Approval of VDR
812 PM1670 Manufacturing LPG 5*8 120d 27/Dec/2017 14/Jun/2018 22/Mar/2018 06/Sep/2018 59d Manufacturing
813 PM1672 FAT LPG 5*8 5d 15/Jun/2018 21/Jun/2018 07/Sep/2018 13/Sep/2018 59d FAT
814 PM1674 Packaging & Dispach - Ex Works LPG 5*8 10d 22/Jun/2018 05/Jul/2018 14/Sep/2018 27/Sep/2018 59d Packaging & Dispach - Ex Works
815 PM1676 Delivery at Site LPG 5*8 10d 06/Jul/2018 19/Jul/2018 28/Sep/2018 12/Oct/2018 59d Delivery at Site
816 SW Water Tank LPG 5*8 230d 25/Aug/2017 19/Jul/2018 21/Nov/2017 12/Oct/2018 59d 19/Jul/2018, SW Water Tank
817 PM1614 Prepare & Issue of Enquiry LPG 5*8 5d 25/Aug/2017 31/Aug/2017 21/Nov/2017 27/Nov/2017 59d Prepare & Issue of Enquiry

Actual Level of Effort Remaining Work Milestone Page 19 of 30 TASK filter: All Activities
Actual Work Critical Remaining Work summary Oracle Corporation
Mundra LPG Pvt Ltd Classic Schedule Layout 12/Jun/2017 16:07
# Ac vity ID Ac vity Name Calendar Original Early Start Early Finish Late Start Late Finish Total 2017 2018
Float Apr M Jun Jul Aug Sep Oct N Dec Jan F M Apr M Jun Jul Aug Sep Oct N Dec
818 PM1616 MLTPL Review/Approval of MR LPG 5*8Dura on
7d 25/Aug/2017 04/Sep/2017 15/Dec/2017 25/Dec/2017 77d MLTPL Review/Approval of MR
819 PM1618 Receive Bids LPG 5*8 20d 01/Sep/2017 02/Oct/2017 28/Nov/2017 25/Dec/2017 59d Receive Bids
820 PM1620 Prepare & Issue TBE LPG 5*8 20d 03/Oct/2017 31/Oct/2017 26/Dec/2017 22/Jan/2018 59d Prepare & Issue TBE
821 PM1622 MLTPL Review/Approval of TBE LPG 5*8 7d 01/Nov/2017 09/Nov/2017 29/Jan/2018 06/Feb/2018 62d MLTPL Review/Approval of TBE
822 PM1624 Prepare CBE & Nego ate LPG 5*8 10d 01/Nov/2017 14/Nov/2017 23/Jan/2018 06/Feb/2018 59d Prepare CBE & Nego ate
823 PM1626 Prepare & Issue LOI LPG 5*8 5d 15/Nov/2017 21/Nov/2017 07/Feb/2018 13/Feb/2018 59d Prepare & Issue LOI
824 PM1628 Prepare & Issue PR LPG 5*8 10d 22/Nov/2017 05/Dec/2017 26/Feb/2018 09/Mar/2018 67d Prepare & Issue PR
825 PM1630 Prepare & Issue PO LPG 5*8 10d 22/Nov/2017 05/Dec/2017 14/Feb/2018 27/Feb/2018 59d Prepare & Issue PO
826 PM1632 MLTPL Review/Approval of PR LPG 5*8 7d 06/Dec/2017 14/Dec/2017 12/Mar/2018 21/Mar/2018 67d MLTPL Review/Approval of PR
827 PM1634 Receive VDR LPG 5*8 15d 06/Dec/2017 26/Dec/2017 28/Feb/2018 21/Mar/2018 59d Receive VDR
828 PM1636 Approval of VDR LPG 5*8 20d 20/Dec/2017 16/Jan/2018 15/Mar/2018 11/Apr/2018 59d Approval of VDR
829 PM1638 Manufacturing LPG 5*8 120d 27/Dec/2017 14/Jun/2018 22/Mar/2018 06/Sep/2018 59d Manufacturing
830 PM1640 FAT LPG 5*8 5d 15/Jun/2018 21/Jun/2018 07/Sep/2018 13/Sep/2018 59d FAT
831 PM1642 Packaging & Dispach - Ex Works LPG 5*8 10d 22/Jun/2018 05/Jul/2018 14/Sep/2018 27/Sep/2018 59d Packaging & Dispach - Ex Works
832 PM1644 Delivery at Site LPG 5*8 10d 06/Jul/2018 19/Jul/2018 28/Sep/2018 12/Oct/2018 59d Delivery at Site
833 Pumps (API, Non API) LPG 5*8 271d 08/Aug/2017 30/Aug/2018 04/Sep/2017 12/Oct/2018 30d 30/Aug/2018, Pumps (API, Non API)
834 Steam Condensate Pump LPG 5*8 250d 06/Sep/2017 30/Aug/2018 04/Sep/2017 27/Aug/2018 -3d 30/Aug/2018, Steam Condensate Pum
835 PM1678 Prepare & Issue of Enquiry LPG 5*8 5d 06/Sep/2017 13/Sep/2017 04/Sep/2017 08/Sep/2017 -3d Prepare & Issue of Enquiry
836 PM1680 MLTPL Review/Approval of MR LPG 5*8 7d 06/Sep/2017 15/Sep/2017 02/Oct/2017 10/Oct/2017 15d MLTPL Review/Approval of MR
837 PM1682 Receive Bids LPG 5*8 20d 13/Sep/2017 13/Oct/2017 11/Sep/2017 10/Oct/2017 -3d Receive Bids
838 PM1684 Prepare & Issue TBE LPG 5*8 20d 13/Oct/2017 13/Nov/2017 11/Oct/2017 08/Nov/2017 -3d Prepare & Issue TBE
839 PM1686 MLTPL Review/Approval of TBE LPG 5*8 7d 13/Nov/2017 22/Nov/2017 14/Nov/2017 22/Nov/2017 0d MLTPL Review/Approval of TBE
840 PM1688 Prepare CBE & Nego ate LPG 5*8 10d 13/Nov/2017 27/Nov/2017 09/Nov/2017 22/Nov/2017 -3d Prepare CBE & Nego ate
841 PM1690 Prepare & Issue LOI LPG 5*8 5d 27/Nov/2017 04/Dec/2017 23/Nov/2017 29/Nov/2017 -3d Prepare & Issue LOI
842 PM1692 Prepare & Issue PR LPG 5*8 10d 04/Dec/2017 18/Dec/2017 12/Dec/2017 25/Dec/2017 5d Prepare & Issue PR
843 PM1694 Prepare & Issue PO LPG 5*8 10d 04/Dec/2017 18/Dec/2017 30/Nov/2017 13/Dec/2017 -3d Prepare & Issue PO
844 PM1696 MLTPL Review/Approval of PR LPG 5*8 7d 18/Dec/2017 27/Dec/2017 26/Dec/2017 03/Jan/2018 5d MLTPL Review/Approval of PR
845 PM1698 Receive VDR LPG 5*8 15d 18/Dec/2017 08/Jan/2018 14/Dec/2017 03/Jan/2018 -3d Receive VDR
846 PM1700 Approval of VDR LPG 5*8 20d 01/Jan/2018 30/Jan/2018 28/Dec/2017 24/Jan/2018 -3d Approval of VDR
847 PM1702 Manufacturing LPG 5*8 140d 08/Jan/2018 25/Jul/2018 04/Jan/2018 20/Jul/2018 -3d Manufacturing
848 PM1704 FAT LPG 5*8 5d 25/Jul/2018 01/Aug/2018 23/Jul/2018 27/Jul/2018 -3d FAT
849 PM1706 Packaging & Dispach - Ex Works LPG 5*8 10d 01/Aug/2018 16/Aug/2018 30/Jul/2018 10/Aug/2018 -3d Packaging & Dispach - Ex Works
850 PM1708 Delivery at Site LPG 5*8 10d 16/Aug/2018 30/Aug/2018 13/Aug/2018 27/Aug/2018 -3d Delivery at Site
851 Propane & Butane BOG/Flash Condensate Pumps LPG 5*8 77d 06/Sep/2017 27/Dec/2017 04/Sep/2017 03/Jan/2018 5d 27/Dec/2017, Propane & Butane BOG/Flash Condensate Pumps
852 PM1710 Prepare & Issue of Enquiry LPG 5*8 5d 06/Sep/2017 13/Sep/2017 04/Sep/2017 08/Sep/2017 -3d Prepare & Issue of Enquiry
853 PM1712 MLTPL Review/Approval of MR LPG 5*8 7d 06/Sep/2017 15/Sep/2017 02/Oct/2017 10/Oct/2017 15d MLTPL Review/Approval of MR
854 PM1714 Receive Bids LPG 5*8 20d 13/Sep/2017 13/Oct/2017 11/Sep/2017 10/Oct/2017 -3d Receive Bids
855 PM1716 Prepare & Issue TBE LPG 5*8 20d 13/Oct/2017 13/Nov/2017 11/Oct/2017 08/Nov/2017 -3d Prepare & Issue TBE
856 PM1718 MLTPL Review/Approval of TBE LPG 5*8 7d 13/Nov/2017 22/Nov/2017 14/Nov/2017 22/Nov/2017 0d MLTPL Review/Approval of TBE
857 PM1720 Prepare CBE & Nego ate LPG 5*8 10d 13/Nov/2017 27/Nov/2017 09/Nov/2017 22/Nov/2017 -3d Prepare CBE & Nego ate
858 PM1722 Prepare & Issue LOI LPG 5*8 5d 27/Nov/2017 04/Dec/2017 23/Nov/2017 29/Nov/2017 -3d Prepare & Issue LOI
859 PM1724 Prepare & Issue PR LPG 5*8 10d 04/Dec/2017 18/Dec/2017 12/Dec/2017 25/Dec/2017 5d Prepare & Issue PR
860 PM1726 Prepare & Issue PO LPG 5*8 10d 04/Dec/2017 18/Dec/2017 30/Nov/2017 13/Dec/2017 -3d Prepare & Issue PO

Actual Level of Effort Remaining Work Milestone Page 20 of 30 TASK filter: All Activities
Actual Work Critical Remaining Work summary Oracle Corporation
Mundra LPG Pvt Ltd Classic Schedule Layout 12/Jun/2017 16:07
# Ac vity ID Ac vity Name Calendar Original Early Start Early Finish Late Start Late Finish Total 2017 2018
Float Apr M Jun Jul Aug Sep Oct N Dec Jan F M Apr M Jun Jul Aug Sep Oct N Dec
861 PM1728 MLTPL Review/Approval of PR LPG 5*8Dura on
7d 18/Dec/2017 27/Dec/2017 26/Dec/2017 03/Jan/2018 5d MLTPL Review/Approval of PR
862 Propane BOG/Flash Condensate Pumps LPG 5*8 180d 18/Dec/2017 30/Aug/2018 14/Dec/2017 27/Aug/2018 -3d 30/Aug/2018, Propane BOG/Flash Con
863 PM1730 Receive VDR LPG 5*8 15d 18/Dec/2017 08/Jan/2018 14/Dec/2017 03/Jan/2018 -3d Receive VDR
864 PM1732 Approval of VDR LPG 5*8 20d 01/Jan/2018 30/Jan/2018 28/Dec/2017 24/Jan/2018 -3d Approval of VDR
865 PM1734 Manufacturing LPG 5*8 140d 08/Jan/2018 25/Jul/2018 04/Jan/2018 20/Jul/2018 -3d Manufacturing
866 PM1736 FAT LPG 5*8 5d 25/Jul/2018 01/Aug/2018 23/Jul/2018 27/Jul/2018 -3d FAT
867 PM1738 Packaging & Dispach - Ex Works LPG 5*8 10d 01/Aug/2018 16/Aug/2018 30/Jul/2018 10/Aug/2018 -3d Packaging & Dispach - Ex Works
868 PM1740 Delivery at Site LPG 5*8 10d 16/Aug/2018 30/Aug/2018 13/Aug/2018 27/Aug/2018 -3d Delivery at Site
869 Butane BOG/Flash Condensate Pumps LPG 5*8 180d 18/Dec/2017 30/Aug/2018 14/Dec/2017 27/Aug/2018 -3d 30/Aug/2018, Butane BOG/Flash Cond
870 PM1742 Receive VDR LPG 5*8 15d 18/Dec/2017 08/Jan/2018 14/Dec/2017 03/Jan/2018 -3d Receive VDR
871 PM1744 Approval of VDR LPG 5*8 20d 01/Jan/2018 30/Jan/2018 28/Dec/2017 24/Jan/2018 -3d Approval of VDR
872 PM1746 Manufacturing LPG 5*8 140d 08/Jan/2018 25/Jul/2018 04/Jan/2018 20/Jul/2018 -3d Manufacturing
873 PM1748 FAT LPG 5*8 5d 25/Jul/2018 01/Aug/2018 23/Jul/2018 27/Jul/2018 -3d FAT
874 PM1750 Packaging & Dispach - Ex Works LPG 5*8 10d 01/Aug/2018 16/Aug/2018 30/Jul/2018 10/Aug/2018 -3d Packaging & Dispach - Ex Works
875 PM1752 Delivery at Site LPG 5*8 10d 16/Aug/2018 30/Aug/2018 13/Aug/2018 27/Aug/2018 -3d Delivery at Site
876 FW Pumps LPG 5*8 250d 01/Sep/2017 24/Aug/2018 23/Oct/2017 12/Oct/2018 34d 24/Aug/2018, FW Pumps
877 PM1754 Prepare & Issue of Enquiry LPG 5*8 5d 01/Sep/2017 07/Sep/2017 23/Oct/2017 30/Oct/2017 34d Prepare & Issue of Enquiry
878 PM1756 MLTPL Review/Approval of MR LPG 5*8 7d 01/Sep/2017 11/Sep/2017 17/Nov/2017 27/Nov/2017 52d MLTPL Review/Approval of MR
879 PM1758 Receive Bids LPG 5*8 20d 08/Sep/2017 09/Oct/2017 31/Oct/2017 27/Nov/2017 34d Receive Bids
880 PM1760 Prepare & Issue TBE LPG 5*8 20d 10/Oct/2017 07/Nov/2017 28/Nov/2017 25/Dec/2017 34d Prepare & Issue TBE
881 PM1762 MLTPL Review/Approval of TBE LPG 5*8 7d 08/Nov/2017 16/Nov/2017 29/Dec/2017 08/Jan/2018 37d MLTPL Review/Approval of TBE
882 PM1764 Prepare CBE & Nego ate LPG 5*8 10d 08/Nov/2017 21/Nov/2017 26/Dec/2017 08/Jan/2018 34d Prepare CBE & Nego ate
883 PM1766 Prepare & Issue LOI LPG 5*8 5d 22/Nov/2017 28/Nov/2017 09/Jan/2018 15/Jan/2018 34d Prepare & Issue LOI
884 PM1768 Prepare & Issue PR LPG 5*8 10d 29/Nov/2017 12/Dec/2017 29/Jan/2018 09/Feb/2018 42d Prepare & Issue PR
885 PM1770 Prepare & Issue PO LPG 5*8 10d 29/Nov/2017 12/Dec/2017 16/Jan/2018 30/Jan/2018 34d Prepare & Issue PO
886 PM1772 MLTPL Review/Approval of PR LPG 5*8 7d 13/Dec/2017 21/Dec/2017 12/Feb/2018 20/Feb/2018 42d MLTPL Review/Approval of PR
887 PM1774 Receive VDR LPG 5*8 15d 13/Dec/2017 02/Jan/2018 31/Jan/2018 20/Feb/2018 34d Receive VDR
888 PM1776 Approval of VDR LPG 5*8 20d 27/Dec/2017 23/Jan/2018 14/Feb/2018 14/Mar/2018 34d Approval of VDR
889 PM1778 Manufacturing LPG 5*8 140d 03/Jan/2018 19/Jul/2018 21/Feb/2018 06/Sep/2018 34d Manufacturing
890 PM1780 FAT LPG 5*8 5d 20/Jul/2018 26/Jul/2018 07/Sep/2018 13/Sep/2018 34d FAT
891 PM1782 Packaging & Dispach - Ex Works LPG 5*8 10d 27/Jul/2018 09/Aug/2018 14/Sep/2018 27/Sep/2018 34d Packaging & Dispach - Ex Works
892 PM1784 Delivery at Site LPG 5*8 10d 10/Aug/2018 24/Aug/2018 28/Sep/2018 12/Oct/2018 34d Delivery at Site
893 Jockey Pump LPG 5*8 160d 13/Dec/2017 26/Jul/2018 28/Feb/2018 12/Oct/2018 54d 26/Jul/2018, Jockey Pump
894 PM1786 Receive VDR LPG 5*8 15d 13/Dec/2017 02/Jan/2018 28/Feb/2018 21/Mar/2018 54d Receive VDR
895 PM1788 Approval of VDR LPG 5*8 20d 27/Dec/2017 23/Jan/2018 15/Mar/2018 11/Apr/2018 54d Approval of VDR
896 PM1790 Manufacturing LPG 5*8 120d 03/Jan/2018 21/Jun/2018 22/Mar/2018 06/Sep/2018 54d Manufacturing
897 PM1792 FAT LPG 5*8 5d 22/Jun/2018 28/Jun/2018 07/Sep/2018 13/Sep/2018 54d FAT
898 PM1794 Packaging & Dispach - Ex Works LPG 5*8 10d 29/Jun/2018 12/Jul/2018 14/Sep/2018 27/Sep/2018 54d Packaging & Dispach - Ex Works
899 PM1796 Delivery at Site LPG 5*8 10d 13/Jul/2018 26/Jul/2018 28/Sep/2018 12/Oct/2018 54d Delivery at Site
900 Non API Pumps - CT, SW, ETP, OWS, Sewage etc LPG 5*8 250d 08/Aug/2017 31/Jul/2018 23/Oct/2017 12/Oct/2018 51d 31/Jul/2018, Non API Pumps - CT, SW, ETP, O
901 PM1798 Prepare & Issue of Enquiry LPG 5*8 5d 08/Aug/2017 14/Aug/2017 23/Oct/2017 30/Oct/2017 51d Prepare & Issue of Enquiry
902 PM1800 MLTPL Review/Approval of MR LPG 5*8 7d 08/Aug/2017 17/Aug/2017 17/Nov/2017 27/Nov/2017 69d MLTPL Review/Approval of MR
903 PM1802 Receive Bids LPG 5*8 20d 16/Aug/2017 12/Sep/2017 31/Oct/2017 27/Nov/2017 51d Receive Bids

Actual Level of Effort Remaining Work Milestone Page 21 of 30 TASK filter: All Activities
Actual Work Critical Remaining Work summary Oracle Corporation
Mundra LPG Pvt Ltd Classic Schedule Layout 12/Jun/2017 16:07
# Ac vity ID Ac vity Name Calendar Original Early Start Early Finish Late Start Late Finish Total 2017 2018
Float Apr M Jun Jul Aug Sep Oct N Dec Jan F M Apr M Jun Jul Aug Sep Oct N Dec
904 PM1804 Prepare & Issue TBE LPG 5*8Dura20d
on 13/Sep/2017 12/Oct/2017 28/Nov/2017 25/Dec/2017 51d Prepare & Issue TBE
905 PM1806 MLTPL Review/Approval of TBE LPG 5*8 7d 13/Oct/2017 23/Oct/2017 29/Dec/2017 08/Jan/2018 54d MLTPL Review/Approval of TBE
906 PM1808 Prepare CBE & Nego ate LPG 5*8 10d 13/Oct/2017 27/Oct/2017 26/Dec/2017 08/Jan/2018 51d Prepare CBE & Nego ate
907 PM1810 Prepare & Issue LOI LPG 5*8 5d 30/Oct/2017 03/Nov/2017 09/Jan/2018 15/Jan/2018 51d Prepare & Issue LOI
908 PM1812 Prepare & Issue PR LPG 5*8 10d 06/Nov/2017 17/Nov/2017 29/Jan/2018 09/Feb/2018 59d Prepare & Issue PR
909 PM1814 Prepare & Issue PO LPG 5*8 10d 06/Nov/2017 17/Nov/2017 16/Jan/2018 30/Jan/2018 51d Prepare & Issue PO
910 PM1816 MLTPL Review/Approval of PR LPG 5*8 7d 20/Nov/2017 28/Nov/2017 12/Feb/2018 20/Feb/2018 59d MLTPL Review/Approval of PR
911 PM1818 Receive VDR LPG 5*8 15d 20/Nov/2017 08/Dec/2017 31/Jan/2018 20/Feb/2018 51d Receive VDR
912 PM1820 Approval of VDR LPG 5*8 20d 04/Dec/2017 29/Dec/2017 14/Feb/2018 14/Mar/2018 51d Approval of VDR
913 PM1822 Manufacturing LPG 5*8 140d 11/Dec/2017 26/Jun/2018 21/Feb/2018 06/Sep/2018 51d Manufacturing
914 PM1824 FAT LPG 5*8 5d 27/Jun/2018 03/Jul/2018 07/Sep/2018 13/Sep/2018 51d FAT
915 PM1826 Packaging & Dispach - Ex Works LPG 5*8 10d 04/Jul/2018 17/Jul/2018 14/Sep/2018 27/Sep/2018 51d Packaging & Dispach - Ex Works
916 PM1828 Delivery at Site LPG 5*8 10d 18/Jul/2018 31/Jul/2018 28/Sep/2018 12/Oct/2018 51d Delivery at Site
917 Sta c Equipment LPG 5*8 284d 10/Jul/2017 21/Aug/2018 08/Sep/2017 23/Oct/2018 44d 21/Aug/2018, Sta c Equipment
918 Sta c Blender(s) LPG 5*8 77d 26/Sep/2017 11/Jan/2018 28/Nov/2017 16/Mar/2018 44d 11/Jan/2018, Sta c Blender(s)
919 PM2054 Prepare & Issue of Enquiry LPG 5*8 5d 26/Sep/2017 02/Oct/2017 28/Nov/2017 04/Dec/2017 44d Prepare & Issue of Enquiry
920 PM2056 MLTPL Review/Approval of MR LPG 5*8 7d 26/Sep/2017 04/Oct/2017 22/Dec/2017 01/Jan/2018 62d MLTPL Review/Approval of MR
921 PM2058 Receive Bids LPG 5*8 20d 03/Oct/2017 31/Oct/2017 05/Dec/2017 01/Jan/2018 44d Receive Bids
922 PM2060 Prepare & Issue TBE LPG 5*8 20d 01/Nov/2017 28/Nov/2017 02/Jan/2018 30/Jan/2018 44d Prepare & Issue TBE
923 PM2062 MLTPL Review/Approval of TBE LPG 5*8 7d 29/Nov/2017 07/Dec/2017 31/Jan/2018 08/Feb/2018 44d MLTPL Review/Approval of TBE
924 PM2064 Prepare CBE & Nego ate LPG 5*8 10d 29/Nov/2017 12/Dec/2017 31/Jan/2018 13/Feb/2018 44d Prepare CBE & Nego ate
925 PM2066 Prepare & Issue LOI LPG 5*8 5d 13/Dec/2017 19/Dec/2017 14/Feb/2018 20/Feb/2018 44d Prepare & Issue LOI
926 PM2068 Prepare & Issue PR LPG 5*8 10d 20/Dec/2017 02/Jan/2018 21/Feb/2018 06/Mar/2018 44d Prepare & Issue PR
927 PM2070 Prepare & Issue PO LPG 5*8 10d 20/Dec/2017 02/Jan/2018 23/Feb/2018 08/Mar/2018 46d Prepare & Issue PO
928 PM2072 MLTPL Review/Approval of PR LPG 5*8 7d 03/Jan/2018 11/Jan/2018 07/Mar/2018 16/Mar/2018 44d MLTPL Review/Approval of PR
929 Sta c Blender I LPG 5*8 160d 05/Jan/2018 21/Aug/2018 09/Mar/2018 23/Oct/2018 44d 21/Aug/2018, Sta c Blender I
930 PM2074 Receive VDR LPG 5*8 15d 05/Jan/2018 25/Jan/2018 09/Mar/2018 30/Mar/2018 44d Receive VDR
931 PM2076 Approval of VDR LPG 5*8 20d 19/Jan/2018 16/Feb/2018 26/Mar/2018 20/Apr/2018 44d Approval of VDR
932 PM2078 Manufacturing LPG 5*8 120d 29/Jan/2018 16/Jul/2018 02/Apr/2018 17/Sep/2018 44d Manufacturing
933 PM2080 FAT LPG 5*8 5d 17/Jul/2018 23/Jul/2018 18/Sep/2018 24/Sep/2018 44d FAT
934 PM2082 Packaging & Dispach - Ex Works LPG 5*8 10d 24/Jul/2018 06/Aug/2018 25/Sep/2018 09/Oct/2018 44d Packaging & Dispach - Ex Works
935 PM2084 Delivery at Site LPG 5*8 10d 07/Aug/2018 21/Aug/2018 10/Oct/2018 23/Oct/2018 44d Delivery at Site
936 Sta c Blender II LPG 5*8 160d 05/Jan/2018 21/Aug/2018 09/Mar/2018 23/Oct/2018 44d 21/Aug/2018, Sta c Blender II
937 PM2086 Receive VDR LPG 5*8 15d 05/Jan/2018 25/Jan/2018 09/Mar/2018 30/Mar/2018 44d Receive VDR
938 PM2088 Approval of VDR LPG 5*8 20d 19/Jan/2018 16/Feb/2018 26/Mar/2018 20/Apr/2018 44d Approval of VDR
939 PM2090 Manufacturing LPG 5*8 120d 29/Jan/2018 16/Jul/2018 02/Apr/2018 17/Sep/2018 44d Manufacturing
940 PM2092 FAT LPG 5*8 5d 17/Jul/2018 23/Jul/2018 18/Sep/2018 24/Sep/2018 44d FAT
941 PM2094 Packaging & Dispach - Ex Works LPG 5*8 10d 24/Jul/2018 06/Aug/2018 25/Sep/2018 09/Oct/2018 44d Packaging & Dispach - Ex Works
942 PM2096 Delivery at Site LPG 5*8 10d 07/Aug/2018 21/Aug/2018 10/Oct/2018 23/Oct/2018 44d Delivery at Site
943 Sta c Blender III LPG 5*8 160d 05/Jan/2018 21/Aug/2018 09/Mar/2018 23/Oct/2018 44d 21/Aug/2018, Sta c Blender III
944 PM2098 Receive VDR LPG 5*8 15d 05/Jan/2018 25/Jan/2018 09/Mar/2018 30/Mar/2018 44d Receive VDR
945 PM2100 Approval of VDR LPG 5*8 20d 19/Jan/2018 16/Feb/2018 26/Mar/2018 20/Apr/2018 44d Approval of VDR
946 PM2102 Manufacturing LPG 5*8 120d 29/Jan/2018 16/Jul/2018 02/Apr/2018 17/Sep/2018 44d Manufacturing

Actual Level of Effort Remaining Work Milestone Page 22 of 30 TASK filter: All Activities
Actual Work Critical Remaining Work summary Oracle Corporation
Mundra LPG Pvt Ltd Classic Schedule Layout 12/Jun/2017 16:07
# Ac vity ID Ac vity Name Calendar Original Early Start Early Finish Late Start Late Finish Total 2017 2018
Float Apr M Jun Jul Aug Sep Oct N Dec Jan F M Apr M Jun Jul Aug Sep Oct N Dec
947 PM2104 FAT LPG 5*8Dura on
5d 17/Jul/2018 23/Jul/2018 18/Sep/2018 24/Sep/2018 44d FAT
948 PM2106 Packaging & Dispach - Ex Works LPG 5*8 10d 24/Jul/2018 06/Aug/2018 25/Sep/2018 09/Oct/2018 44d Packaging & Dispach - Ex Works
949 PM2108 Delivery at Site LPG 5*8 10d 07/Aug/2018 21/Aug/2018 10/Oct/2018 23/Oct/2018 44d Delivery at Site
950 Sta c Blender IV LPG 5*8 160d 05/Jan/2018 21/Aug/2018 09/Mar/2018 23/Oct/2018 44d 21/Aug/2018, Sta c Blender IV
951 PM2110 Receive VDR LPG 5*8 15d 05/Jan/2018 25/Jan/2018 09/Mar/2018 30/Mar/2018 44d Receive VDR
952 PM2112 Approval of VDR LPG 5*8 20d 19/Jan/2018 16/Feb/2018 26/Mar/2018 20/Apr/2018 44d Approval of VDR
953 PM2114 Manufacturing LPG 5*8 120d 29/Jan/2018 16/Jul/2018 02/Apr/2018 17/Sep/2018 44d Manufacturing
954 PM2116 FAT LPG 5*8 5d 17/Jul/2018 23/Jul/2018 18/Sep/2018 24/Sep/2018 44d FAT
955 PM2118 Packaging & Dispach - Ex Works LPG 5*8 10d 24/Jul/2018 06/Aug/2018 25/Sep/2018 09/Oct/2018 44d Packaging & Dispach - Ex Works
956 PM2120 Delivery at Site LPG 5*8 10d 07/Aug/2018 21/Aug/2018 10/Oct/2018 23/Oct/2018 44d Delivery at Site
957 Loading/ Vapor Return Arms LPG 5*8 230d 23/Aug/2017 17/Jul/2018 08/Sep/2017 02/Aug/2018 12d 17/Jul/2018, Loading/ Vapor Return Arms
958 PM1926 Prepare & Issue of Enquiry LPG 5*8 5d 23/Aug/2017 29/Aug/2017 08/Sep/2017 14/Sep/2017 12d Prepare & Issue of Enquiry
959 PM1928 MLTPL Review/Approval of MR LPG 5*8 7d 23/Aug/2017 31/Aug/2017 06/Oct/2017 16/Oct/2017 30d MLTPL Review/Approval of MR
960 PM1930 Receive Bids LPG 5*8 20d 30/Aug/2017 28/Sep/2017 15/Sep/2017 16/Oct/2017 12d Receive Bids
961 PM1932 Prepare & Issue TBE LPG 5*8 20d 29/Sep/2017 27/Oct/2017 17/Oct/2017 14/Nov/2017 12d Prepare & Issue TBE
962 PM1934 MLTPL Review/Approval of TBE LPG 5*8 7d 30/Oct/2017 07/Nov/2017 20/Nov/2017 28/Nov/2017 15d MLTPL Review/Approval of TBE
963 PM1936 Prepare CBE & Nego ate LPG 5*8 10d 30/Oct/2017 10/Nov/2017 15/Nov/2017 28/Nov/2017 12d Prepare CBE & Nego ate
964 PM1938 Prepare & Issue LOI LPG 5*8 5d 13/Nov/2017 17/Nov/2017 29/Nov/2017 05/Dec/2017 12d Prepare & Issue LOI
965 PM1940 Prepare & Issue PR LPG 5*8 10d 20/Nov/2017 01/Dec/2017 18/Dec/2017 29/Dec/2017 20d Prepare & Issue PR
966 PM1942 Prepare & Issue PO LPG 5*8 10d 20/Nov/2017 01/Dec/2017 06/Dec/2017 19/Dec/2017 12d Prepare & Issue PO
967 PM1944 MLTPL Review/Approval of PR LPG 5*8 7d 04/Dec/2017 12/Dec/2017 01/Jan/2018 09/Jan/2018 20d MLTPL Review/Approval of PR
968 PM1946 Receive VDR LPG 5*8 15d 04/Dec/2017 22/Dec/2017 20/Dec/2017 09/Jan/2018 12d Receive VDR
969 PM1948 Approval of VDR LPG 5*8 20d 18/Dec/2017 12/Jan/2018 03/Jan/2018 31/Jan/2018 12d Approval of VDR
970 PM1950 Manufacturing LPG 5*8 120d 25/Dec/2017 12/Jun/2018 10/Jan/2018 28/Jun/2018 12d Manufacturing
971 PM1952 FAT LPG 5*8 5d 13/Jun/2018 19/Jun/2018 29/Jun/2018 05/Jul/2018 12d FAT
972 PM1954 Packaging & Dispach - Ex Works LPG 5*8 10d 20/Jun/2018 03/Jul/2018 06/Jul/2018 19/Jul/2018 12d Packaging & Dispach - Ex Works
973 PM1956 Delivery at Site LPG 5*8 10d 04/Jul/2018 17/Jul/2018 20/Jul/2018 02/Aug/2018 12d Delivery at Site
974 Cooling Tower Package LPG 5*8 230d 10/Jul/2017 05/Jun/2018 04/Oct/2017 27/Aug/2018 58d 05/Jun/2018, Cooling Tower Package
975 PM1958 Prepare & Issue of Enquiry LPG 5*8 5d 10/Jul/2017 14/Jul/2017 04/Oct/2017 10/Oct/2017 58d Prepare & Issue of Enquiry
976 PM1960 MLTPL Review/Approval of MR LPG 5*8 7d 10/Jul/2017 18/Jul/2017 31/Oct/2017 08/Nov/2017 76d MLTPL Review/Approval of MR
977 PM1962 Receive Bids LPG 5*8 20d 17/Jul/2017 14/Aug/2017 11/Oct/2017 08/Nov/2017 58d Receive Bids
978 PM1964 Prepare & Issue TBE LPG 5*8 20d 16/Aug/2017 12/Sep/2017 09/Nov/2017 06/Dec/2017 58d Prepare & Issue TBE
979 PM1966 MLTPL Review/Approval of TBE LPG 5*8 7d 13/Sep/2017 25/Sep/2017 12/Dec/2017 20/Dec/2017 61d MLTPL Review/Approval of TBE
980 PM1968 Prepare CBE & Nego ate LPG 5*8 10d 13/Sep/2017 28/Sep/2017 07/Dec/2017 20/Dec/2017 58d Prepare CBE & Nego ate
981 PM1970 Prepare & Issue LOI LPG 5*8 5d 29/Sep/2017 05/Oct/2017 21/Dec/2017 27/Dec/2017 58d Prepare & Issue LOI
982 PM1972 Prepare & Issue PR LPG 5*8 10d 06/Oct/2017 19/Oct/2017 09/Jan/2018 22/Jan/2018 66d Prepare & Issue PR
983 PM1974 Prepare & Issue PO LPG 5*8 10d 06/Oct/2017 19/Oct/2017 28/Dec/2017 10/Jan/2018 58d Prepare & Issue PO
984 PM1976 MLTPL Review/Approval of PR LPG 5*8 7d 20/Oct/2017 31/Oct/2017 23/Jan/2018 01/Feb/2018 66d MLTPL Review/Approval of PR
985 PM1978 Receive VDR LPG 5*8 15d 20/Oct/2017 10/Nov/2017 11/Jan/2018 01/Feb/2018 58d Receive VDR
986 PM1980 Approval of VDR LPG 5*8 20d 06/Nov/2017 01/Dec/2017 25/Jan/2018 22/Feb/2018 58d Approval of VDR
987 PM1982 Manufacturing LPG 5*8 120d 13/Nov/2017 01/May/2018 02/Feb/2018 20/Jul/2018 58d Manufacturing
988 PM1984 FAT LPG 5*8 5d 02/May/2018 08/May/2018 23/Jul/2018 27/Jul/2018 58d FAT
989 PM1986 Packaging & Dispach - Ex Works LPG 5*8 10d 09/May/2018 22/May/2018 30/Jul/2018 10/Aug/2018 58d Packaging & Dispach - Ex Works

Actual Level of Effort Remaining Work Milestone Page 23 of 30 TASK filter: All Activities
Actual Work Critical Remaining Work summary Oracle Corporation
Mundra LPG Pvt Ltd Classic Schedule Layout 12/Jun/2017 16:07
# Ac vity ID Ac vity Name Calendar Original Early Start Early Finish Late Start Late Finish Total 2017 2018
Float Apr M Jun Jul Aug Sep Oct N Dec Jan F M Apr M Jun Jul Aug Sep Oct N Dec
990 PM1988 Delivery at Site LPG 5*8Dura10d
on 23/May/2018 05/Jun/2018 13/Aug/2018 27/Aug/2018 58d Delivery at Site
991 CT Side Stream Filters LPG 5*8 230d 08/Aug/2017 03/Jul/2018 21/Nov/2017 12/Oct/2018 71d 03/Jul/2018, CT Side Stream Filters
992 PM1830 Prepare & Issue of Enquiry LPG 5*8 5d 08/Aug/2017 14/Aug/2017 21/Nov/2017 27/Nov/2017 71d Prepare & Issue of Enquiry
993 PM1832 MLTPL Review/Approval of MR LPG 5*8 7d 08/Aug/2017 17/Aug/2017 15/Dec/2017 25/Dec/2017 89d MLTPL Review/Approval of MR
994 PM1834 Receive Bids LPG 5*8 20d 16/Aug/2017 12/Sep/2017 28/Nov/2017 25/Dec/2017 71d Receive Bids
995 PM1836 Prepare & Issue TBE LPG 5*8 20d 13/Sep/2017 12/Oct/2017 26/Dec/2017 22/Jan/2018 71d Prepare & Issue TBE
996 PM1838 MLTPL Review/Approval of TBE LPG 5*8 7d 13/Oct/2017 23/Oct/2017 29/Jan/2018 06/Feb/2018 74d MLTPL Review/Approval of TBE
997 PM1840 Prepare CBE & Nego ate LPG 5*8 10d 13/Oct/2017 27/Oct/2017 23/Jan/2018 06/Feb/2018 71d Prepare CBE & Nego ate
998 PM1842 Prepare & Issue LOI LPG 5*8 5d 30/Oct/2017 03/Nov/2017 07/Feb/2018 13/Feb/2018 71d Prepare & Issue LOI
999 PM1844 Prepare & Issue PR LPG 5*8 10d 06/Nov/2017 17/Nov/2017 26/Feb/2018 09/Mar/2018 79d Prepare & Issue PR
1000 PM1846 Prepare & Issue PO LPG 5*8 10d 06/Nov/2017 17/Nov/2017 14/Feb/2018 27/Feb/2018 71d Prepare & Issue PO
1001 PM1848 MLTPL Review/Approval of PR LPG 5*8 7d 20/Nov/2017 28/Nov/2017 12/Mar/2018 21/Mar/2018 79d MLTPL Review/Approval of PR
1002 PM1850 Receive VDR LPG 5*8 15d 20/Nov/2017 08/Dec/2017 28/Feb/2018 21/Mar/2018 71d Receive VDR
1003 PM1852 Approval of VDR LPG 5*8 20d 04/Dec/2017 29/Dec/2017 15/Mar/2018 11/Apr/2018 71d Approval of VDR
1004 PM1854 Manufacturing LPG 5*8 120d 11/Dec/2017 29/May/2018 22/Mar/2018 06/Sep/2018 71d Manufacturing
1005 PM1856 FAT LPG 5*8 5d 30/May/2018 05/Jun/2018 07/Sep/2018 13/Sep/2018 71d FAT
1006 PM1858 Packaging & Dispach - Ex Works LPG 5*8 10d 06/Jun/2018 19/Jun/2018 14/Sep/2018 27/Sep/2018 71d Packaging & Dispach - Ex Works
1007 PM1860 Delivery at Site LPG 5*8 10d 20/Jun/2018 03/Jul/2018 28/Sep/2018 12/Oct/2018 71d Delivery at Site
1008 CT Dosing Package LPG 5*8 230d 08/Aug/2017 03/Jul/2018 21/Nov/2017 12/Oct/2018 71d 03/Jul/2018, CT Dosing Package
1009 PM1862 Prepare & Issue of Enquiry LPG 5*8 5d 08/Aug/2017 14/Aug/2017 21/Nov/2017 27/Nov/2017 71d Prepare & Issue of Enquiry
1010 PM1864 MLTPL Review/Approval of MR LPG 5*8 7d 08/Aug/2017 17/Aug/2017 15/Dec/2017 25/Dec/2017 89d MLTPL Review/Approval of MR
1011 PM1866 Receive Bids LPG 5*8 20d 16/Aug/2017 12/Sep/2017 28/Nov/2017 25/Dec/2017 71d Receive Bids
1012 PM1868 Prepare & Issue TBE LPG 5*8 20d 13/Sep/2017 12/Oct/2017 26/Dec/2017 22/Jan/2018 71d Prepare & Issue TBE
1013 PM1870 MLTPL Review/Approval of TBE LPG 5*8 7d 13/Oct/2017 23/Oct/2017 29/Jan/2018 06/Feb/2018 74d MLTPL Review/Approval of TBE
1014 PM1872 Prepare CBE & Nego ate LPG 5*8 10d 13/Oct/2017 27/Oct/2017 23/Jan/2018 06/Feb/2018 71d Prepare CBE & Nego ate
1015 PM1874 Prepare & Issue LOI LPG 5*8 5d 30/Oct/2017 03/Nov/2017 07/Feb/2018 13/Feb/2018 71d Prepare & Issue LOI
1016 PM1876 Prepare & Issue PR LPG 5*8 10d 06/Nov/2017 17/Nov/2017 26/Feb/2018 09/Mar/2018 79d Prepare & Issue PR
1017 PM1878 Prepare & Issue PO LPG 5*8 10d 06/Nov/2017 17/Nov/2017 14/Feb/2018 27/Feb/2018 71d Prepare & Issue PO
1018 PM1880 MLTPL Review/Approval of PR LPG 5*8 7d 20/Nov/2017 28/Nov/2017 12/Mar/2018 21/Mar/2018 79d MLTPL Review/Approval of PR
1019 PM1882 Receive VDR LPG 5*8 15d 20/Nov/2017 08/Dec/2017 28/Feb/2018 21/Mar/2018 71d Receive VDR
1020 PM1884 Approval of VDR LPG 5*8 20d 04/Dec/2017 29/Dec/2017 15/Mar/2018 11/Apr/2018 71d Approval of VDR
1021 PM1886 Manufacturing LPG 5*8 120d 11/Dec/2017 29/May/2018 22/Mar/2018 06/Sep/2018 71d Manufacturing
1022 PM1888 FAT LPG 5*8 5d 30/May/2018 05/Jun/2018 07/Sep/2018 13/Sep/2018 71d FAT
1023 PM1890 Packaging & Dispach - Ex Works LPG 5*8 10d 06/Jun/2018 19/Jun/2018 14/Sep/2018 27/Sep/2018 71d Packaging & Dispach - Ex Works
1024 PM1892 Delivery at Site LPG 5*8 10d 20/Jun/2018 03/Jul/2018 28/Sep/2018 12/Oct/2018 71d Delivery at Site
1025 CT Clorina on Package LPG 5*8 230d 08/Aug/2017 03/Jul/2018 21/Nov/2017 12/Oct/2018 71d 03/Jul/2018, CT Clorina on Package
1026 PM1894 Prepare & Issue of Enquiry LPG 5*8 5d 08/Aug/2017 14/Aug/2017 21/Nov/2017 27/Nov/2017 71d Prepare & Issue of Enquiry
1027 PM1896 MLTPL Review/Approval of MR LPG 5*8 7d 08/Aug/2017 17/Aug/2017 15/Dec/2017 25/Dec/2017 89d MLTPL Review/Approval of MR
1028 PM1898 Receive Bids LPG 5*8 20d 16/Aug/2017 12/Sep/2017 28/Nov/2017 25/Dec/2017 71d Receive Bids
1029 PM1900 Prepare & Issue TBE LPG 5*8 20d 13/Sep/2017 12/Oct/2017 26/Dec/2017 22/Jan/2018 71d Prepare & Issue TBE
1030 PM1902 MLTPL Review/Approval of TBE LPG 5*8 7d 13/Oct/2017 23/Oct/2017 29/Jan/2018 06/Feb/2018 74d MLTPL Review/Approval of TBE
1031 PM1904 Prepare CBE & Nego ate LPG 5*8 10d 13/Oct/2017 27/Oct/2017 23/Jan/2018 06/Feb/2018 71d Prepare CBE & Nego ate
1032 PM1906 Prepare & Issue LOI LPG 5*8 5d 30/Oct/2017 03/Nov/2017 07/Feb/2018 13/Feb/2018 71d Prepare & Issue LOI

Actual Level of Effort Remaining Work Milestone Page 24 of 30 TASK filter: All Activities
Actual Work Critical Remaining Work summary Oracle Corporation
Mundra LPG Pvt Ltd Classic Schedule Layout 12/Jun/2017 16:07
# Ac vity ID Ac vity Name Calendar Original Early Start Early Finish Late Start Late Finish Total 2017 2018
Float Apr M Jun Jul Aug Sep Oct N Dec Jan F M Apr M Jun Jul Aug Sep Oct N Dec
1033 PM1908 Prepare & Issue PR LPG 5*8Dura10d
on 06/Nov/2017 17/Nov/2017 26/Feb/2018 09/Mar/2018 79d Prepare & Issue PR
1034 PM1910 Prepare & Issue PO LPG 5*8 10d 06/Nov/2017 17/Nov/2017 14/Feb/2018 27/Feb/2018 71d Prepare & Issue PO
1035 PM1912 MLTPL Review/Approval of PR LPG 5*8 7d 20/Nov/2017 28/Nov/2017 12/Mar/2018 21/Mar/2018 79d MLTPL Review/Approval of PR
1036 PM1914 Receive VDR LPG 5*8 15d 20/Nov/2017 08/Dec/2017 28/Feb/2018 21/Mar/2018 71d Receive VDR
1037 PM1916 Approval of VDR LPG 5*8 20d 04/Dec/2017 29/Dec/2017 15/Mar/2018 11/Apr/2018 71d Approval of VDR
1038 PM1918 Manufacturing LPG 5*8 120d 11/Dec/2017 29/May/2018 22/Mar/2018 06/Sep/2018 71d Manufacturing
1039 PM1920 FAT LPG 5*8 5d 30/May/2018 05/Jun/2018 07/Sep/2018 13/Sep/2018 71d FAT
1040 PM1922 Packaging & Dispach - Ex Works LPG 5*8 10d 06/Jun/2018 19/Jun/2018 14/Sep/2018 27/Sep/2018 71d Packaging & Dispach - Ex Works
1041 PM1924 Delivery at Site LPG 5*8 10d 20/Jun/2018 03/Jul/2018 28/Sep/2018 12/Oct/2018 71d Delivery at Site
1042 Weigh Bridge LPG 5*8 230d 08/Aug/2017 03/Jul/2018 04/Oct/2017 27/Aug/2018 38d 03/Jul/2018, Weigh Bridge
1043 PM1990 Prepare & Issue of Enquiry LPG 5*8 5d 08/Aug/2017 14/Aug/2017 04/Oct/2017 10/Oct/2017 38d Prepare & Issue of Enquiry
1044 PM1992 MLTPL Review/Approval of MR LPG 5*8 7d 08/Aug/2017 17/Aug/2017 31/Oct/2017 08/Nov/2017 56d MLTPL Review/Approval of MR
1045 PM1994 Receive Bids LPG 5*8 20d 16/Aug/2017 12/Sep/2017 11/Oct/2017 08/Nov/2017 38d Receive Bids
1046 PM1996 Prepare & Issue TBE LPG 5*8 20d 13/Sep/2017 12/Oct/2017 09/Nov/2017 06/Dec/2017 38d Prepare & Issue TBE
1047 PM1998 MLTPL Review/Approval of TBE LPG 5*8 7d 13/Oct/2017 23/Oct/2017 12/Dec/2017 20/Dec/2017 41d MLTPL Review/Approval of TBE
1048 PM2000 Prepare CBE & Nego ate LPG 5*8 10d 13/Oct/2017 27/Oct/2017 07/Dec/2017 20/Dec/2017 38d Prepare CBE & Nego ate
1049 PM2002 Prepare & Issue LOI LPG 5*8 5d 30/Oct/2017 03/Nov/2017 21/Dec/2017 27/Dec/2017 38d Prepare & Issue LOI
1050 PM2004 Prepare & Issue PR LPG 5*8 10d 06/Nov/2017 17/Nov/2017 09/Jan/2018 22/Jan/2018 46d Prepare & Issue PR
1051 PM2006 Prepare & Issue PO LPG 5*8 10d 06/Nov/2017 17/Nov/2017 28/Dec/2017 10/Jan/2018 38d Prepare & Issue PO
1052 PM2008 MLTPL Review/Approval of PR LPG 5*8 7d 20/Nov/2017 28/Nov/2017 23/Jan/2018 01/Feb/2018 46d MLTPL Review/Approval of PR
1053 PM2010 Receive VDR LPG 5*8 15d 20/Nov/2017 08/Dec/2017 11/Jan/2018 01/Feb/2018 38d Receive VDR
1054 PM2012 Approval of VDR LPG 5*8 20d 04/Dec/2017 29/Dec/2017 25/Jan/2018 22/Feb/2018 38d Approval of VDR
1055 PM2014 Manufacturing LPG 5*8 120d 11/Dec/2017 29/May/2018 02/Feb/2018 20/Jul/2018 38d Manufacturing
1056 PM2016 FAT LPG 5*8 5d 30/May/2018 05/Jun/2018 23/Jul/2018 27/Jul/2018 38d FAT
1057 PM2018 Packaging & Dispach - Ex Works LPG 5*8 10d 06/Jun/2018 19/Jun/2018 30/Jul/2018 10/Aug/2018 38d Packaging & Dispach - Ex Works
1058 PM2020 Delivery at Site LPG 5*8 10d 20/Jun/2018 03/Jul/2018 13/Aug/2018 27/Aug/2018 38d Delivery at Site
1059 Mercaptan Dosing Package LPG 5*8 230d 08/Aug/2017 03/Jul/2018 04/Oct/2017 27/Aug/2018 38d 03/Jul/2018, Mercaptan Dosing Package
1060 PM2022 Prepare & Issue of Enquiry LPG 5*8 5d 08/Aug/2017 14/Aug/2017 04/Oct/2017 10/Oct/2017 38d Prepare & Issue of Enquiry
1061 PM2024 MLTPL Review/Approval of MR LPG 5*8 7d 08/Aug/2017 17/Aug/2017 31/Oct/2017 08/Nov/2017 56d MLTPL Review/Approval of MR
1062 PM2026 Receive Bids LPG 5*8 20d 16/Aug/2017 12/Sep/2017 11/Oct/2017 08/Nov/2017 38d Receive Bids
1063 PM2028 Prepare & Issue TBE LPG 5*8 20d 13/Sep/2017 12/Oct/2017 09/Nov/2017 06/Dec/2017 38d Prepare & Issue TBE
1064 PM2030 MLTPL Review/Approval of TBE LPG 5*8 7d 13/Oct/2017 23/Oct/2017 12/Dec/2017 20/Dec/2017 41d MLTPL Review/Approval of TBE
1065 PM2032 Prepare CBE & Nego ate LPG 5*8 10d 13/Oct/2017 27/Oct/2017 07/Dec/2017 20/Dec/2017 38d Prepare CBE & Nego ate
1066 PM2034 Prepare & Issue LOI LPG 5*8 5d 30/Oct/2017 03/Nov/2017 21/Dec/2017 27/Dec/2017 38d Prepare & Issue LOI
1067 PM2036 Prepare & Issue PR LPG 5*8 10d 06/Nov/2017 17/Nov/2017 09/Jan/2018 22/Jan/2018 46d Prepare & Issue PR
1068 PM2038 Prepare & Issue PO LPG 5*8 10d 06/Nov/2017 17/Nov/2017 28/Dec/2017 10/Jan/2018 38d Prepare & Issue PO
1069 PM2040 MLTPL Review/Approval of PR LPG 5*8 7d 20/Nov/2017 28/Nov/2017 23/Jan/2018 01/Feb/2018 46d MLTPL Review/Approval of PR
1070 PM2042 Receive VDR LPG 5*8 15d 20/Nov/2017 08/Dec/2017 11/Jan/2018 01/Feb/2018 38d Receive VDR
1071 PM2044 Approval of VDR LPG 5*8 20d 04/Dec/2017 29/Dec/2017 25/Jan/2018 22/Feb/2018 38d Approval of VDR
1072 PM2046 Manufacturing LPG 5*8 120d 11/Dec/2017 29/May/2018 02/Feb/2018 20/Jul/2018 38d Manufacturing
1073 PM2048 FAT LPG 5*8 5d 30/May/2018 05/Jun/2018 23/Jul/2018 27/Jul/2018 38d FAT
1074 PM2050 Packaging & Dispach - Ex Works LPG 5*8 10d 06/Jun/2018 19/Jun/2018 30/Jul/2018 10/Aug/2018 38d Packaging & Dispach - Ex Works
1075 PM2052 Delivery at Site LPG 5*8 10d 20/Jun/2018 03/Jul/2018 13/Aug/2018 27/Aug/2018 38d Delivery at Site

Actual Level of Effort Remaining Work Milestone Page 25 of 30 TASK filter: All Activities
Actual Work Critical Remaining Work summary Oracle Corporation
Mundra LPG Pvt Ltd Classic Schedule Layout 12/Jun/2017 16:07
# Ac vity ID Ac vity Name Calendar Original Early Start Early Finish Late Start Late Finish Total 2017 2018
Float Apr M Jun Jul Aug Sep Oct N Dec Jan F M Apr M Jun Jul Aug Sep Oct N Dec
1076 Piping LPG 5*8Dura278d
on 18/Aug/2017 19/Sep/2018 09/Nov/2017 06/Nov/2018 33d 19/Sep/2018, Piping
1077 Commons LPG 5*8 278d 18/Aug/2017 19/Sep/2018 09/Nov/2017 06/Nov/2018 33d 19/Sep/2018, Commons
1078 EOT & Hoist System LPG 5*8 230d 18/Aug/2017 13/Jul/2018 14/Dec/2017 06/Nov/2018 81d 13/Jul/2018, EOT & Hoist System
1079 PL2120 Prepare & Issue of Enquiry LPG 5*8 5d 18/Aug/2017 25/Aug/2017 14/Dec/2017 20/Dec/2017 81d Prepare & Issue of Enquiry
1080 PL2122 MLTPL Review/Approval of MR LPG 5*8 7d 18/Aug/2017 29/Aug/2017 09/Jan/2018 17/Jan/2018 99d MLTPL Review/Approval of MR
1081 PL2124 Receive Bids LPG 5*8 20d 25/Aug/2017 26/Sep/2017 21/Dec/2017 17/Jan/2018 81d Receive Bids
1082 PL2126 Prepare & Issue TBE LPG 5*8 20d 26/Sep/2017 24/Oct/2017 18/Jan/2018 15/Feb/2018 81d Prepare & Issue TBE
1083 PL2128 MLTPL Review/Approval of TBE LPG 5*8 7d 24/Oct/2017 03/Nov/2017 21/Feb/2018 01/Mar/2018 84d MLTPL Review/Approval of TBE
1084 PL2130 Prepare CBE & Nego ate LPG 5*8 10d 24/Oct/2017 08/Nov/2017 16/Feb/2018 01/Mar/2018 81d Prepare CBE & Nego ate
1085 PL2132 Prepare & Issue LOI LPG 5*8 5d 08/Nov/2017 15/Nov/2017 02/Mar/2018 08/Mar/2018 81d Prepare & Issue LOI
1086 PL2134 Prepare & Issue PR LPG 5*8 10d 15/Nov/2017 29/Nov/2017 22/Mar/2018 04/Apr/2018 89d Prepare & Issue PR
1087 PL2136 Prepare & Issue PO LPG 5*8 10d 15/Nov/2017 29/Nov/2017 09/Mar/2018 23/Mar/2018 81d Prepare & Issue PO
1088 PL2138 MLTPL Review/Approval of PR LPG 5*8 7d 29/Nov/2017 08/Dec/2017 05/Apr/2018 13/Apr/2018 89d MLTPL Review/Approval of PR
1089 PL2140 Receive VDR LPG 5*8 15d 29/Nov/2017 20/Dec/2017 26/Mar/2018 13/Apr/2018 81d Receive VDR
1090 PL2142 Approval of VDR LPG 5*8 20d 13/Dec/2017 10/Jan/2018 09/Apr/2018 04/May/2018 81d Approval of VDR
1091 PL2144 Manufacturing LPG 5*8 120d 20/Dec/2017 08/Jun/2018 16/Apr/2018 01/Oct/2018 81d Manufacturing
1092 PL2146 FAT LPG 5*8 5d 08/Jun/2018 15/Jun/2018 03/Oct/2018 09/Oct/2018 81d FAT
1093 PL2148 Packaging & Dispach - Ex Works LPG 5*8 10d 15/Jun/2018 29/Jun/2018 10/Oct/2018 23/Oct/2018 81d Packaging & Dispach - Ex Works
1094 PL2150 Delivery at Site LPG 5*8 10d 29/Jun/2018 13/Jul/2018 24/Oct/2018 06/Nov/2018 81d Delivery at Site
1095 Pipe(CS/LTCS/AS+SS) LPG 5*8 245d 23/Aug/2017 07/Aug/2018 23/Nov/2017 06/Nov/2018 63d 07/Aug/2018, Pipe(CS/LTCS/AS+SS)
1096 PL2200 Prepare & Issue of Enquiry LPG 5*8 5d 23/Aug/2017 29/Aug/2017 23/Nov/2017 29/Nov/2017 63d Prepare & Issue of Enquiry
1097 PL2202 Receive Bids LPG 5*8 15d 30/Aug/2017 21/Sep/2017 30/Nov/2017 20/Dec/2017 63d Receive Bids
1098 PL2204 Techno Commercial Evalua on LPG 5*8 10d 22/Sep/2017 05/Oct/2017 21/Dec/2017 03/Jan/2018 63d Techno Commercial Evalua on
1099 PL2206 Prepare & Issue LOI LPG 5*8 5d 06/Oct/2017 12/Oct/2017 04/Jan/2018 10/Jan/2018 63d Prepare & Issue LOI
1100 PL2208 Prepare & Issue PR LPG 5*8 10d 13/Oct/2017 27/Oct/2017 11/Jan/2018 24/Jan/2018 63d Prepare & Issue PR
1101 PL2210 Prepare & Issue PO LPG 5*8 10d 30/Oct/2017 10/Nov/2017 25/Jan/2018 08/Feb/2018 63d Prepare & Issue PO
1102 PL2212 Manufacturing - Part Delivery LPG 5*8 100d 13/Nov/2017 03/Apr/2018 09/Feb/2018 29/Jun/2018 63d Manufacturing - Part Delivery
1103 PL2214 Full Delivery at Site LPG 5*8 90d 04/Apr/2018 07/Aug/2018 02/Jul/2018 06/Nov/2018 63d Full Delivery at Site
1104 Valve(Bu ery,Plug,Ball) LPG 5*8 255d 06/Sep/2017 05/Sep/2018 09/Nov/2017 06/Nov/2018 43d 05/Sep/2018, Valve(Bu ery,Plug,Bal
1105 PL2152 Prepare & Issue of Enquiry LPG 5*8 5d 06/Sep/2017 12/Sep/2017 09/Nov/2017 15/Nov/2017 43d Prepare & Issue of Enquiry
1106 PL2154 Receive Bids LPG 5*8 15d 13/Sep/2017 05/Oct/2017 16/Nov/2017 06/Dec/2017 43d Receive Bids
1107 PL2156 Techno Commercial Evalua on LPG 5*8 10d 06/Oct/2017 19/Oct/2017 07/Dec/2017 20/Dec/2017 43d Techno Commercial Evalua on
1108 PL2158 Prepare & Issue LOI LPG 5*8 5d 20/Oct/2017 27/Oct/2017 21/Dec/2017 27/Dec/2017 43d Prepare & Issue LOI
1109 PL2160 Prepare & Issue PR LPG 5*8 10d 30/Oct/2017 10/Nov/2017 28/Dec/2017 10/Jan/2018 43d Prepare & Issue PR
1110 PL2162 Prepare & Issue PO LPG 5*8 10d 13/Nov/2017 24/Nov/2017 11/Jan/2018 24/Jan/2018 43d Prepare & Issue PO
1111 PL2164 Manufacturing - Part Delivery LPG 5*8 110d 27/Nov/2017 01/May/2018 25/Jan/2018 29/Jun/2018 43d Manufacturing - Part Delivery
1112 PL2166 Full Delivery at Site LPG 5*8 90d 02/May/2018 05/Sep/2018 02/Jul/2018 06/Nov/2018 43d Full Delivery at Site
1113 Fi ngs(CS/LTCS/AS+SS) LPG 5*8 245d 22/Sep/2017 05/Sep/2018 23/Nov/2017 06/Nov/2018 43d 05/Sep/2018, Fi ngs(CS/LTCS/AS+SS)
1114 PL2168 Prepare & Issue of Enquiry LPG 5*8 5d 22/Sep/2017 28/Sep/2017 23/Nov/2017 29/Nov/2017 43d Prepare & Issue of Enquiry
1115 PL2170 Receive Bids LPG 5*8 15d 29/Sep/2017 19/Oct/2017 30/Nov/2017 20/Dec/2017 43d Receive Bids
1116 PL2172 Techno Commercial Evalua on LPG 5*8 10d 20/Oct/2017 03/Nov/2017 21/Dec/2017 03/Jan/2018 43d Techno Commercial Evalua on
1117 PL2174 Prepare & Issue LOI LPG 5*8 5d 06/Nov/2017 10/Nov/2017 04/Jan/2018 10/Jan/2018 43d Prepare & Issue LOI
1118 PL2176 Prepare & Issue PR LPG 5*8 10d 13/Nov/2017 24/Nov/2017 11/Jan/2018 24/Jan/2018 43d Prepare & Issue PR

Actual Level of Effort Remaining Work Milestone Page 26 of 30 TASK filter: All Activities
Actual Work Critical Remaining Work summary Oracle Corporation
Mundra LPG Pvt Ltd Classic Schedule Layout 12/Jun/2017 16:07
# Ac vity ID Ac vity Name Calendar Original Early Start Early Finish Late Start Late Finish Total 2017 2018
Float Apr M Jun Jul Aug Sep Oct N Dec Jan F M Apr M Jun Jul Aug Sep Oct N Dec
1119 PL2178 Prepare & Issue PO LPG 5*8Dura10d
on 27/Nov/2017 08/Dec/2017 25/Jan/2018 08/Feb/2018 43d Prepare & Issue PO
1120 PL2180 Manufacturing - Part Delivery LPG 5*8 100d 11/Dec/2017 01/May/2018 09/Feb/2018 29/Jun/2018 43d Manufacturing - Part Delivery
1121 PL2182 Full Delivery at Site LPG 5*8 90d 02/May/2018 05/Sep/2018 02/Jul/2018 06/Nov/2018 43d Full Delivery at Site
1122 Flange(CS/LTCS/AS+SS) LPG 5*8 245d 06/Oct/2017 19/Sep/2018 23/Nov/2017 06/Nov/2018 33d 19/Sep/2018, Flange(CS/LTCS/AS+S
1123 PL2184 Prepare & Issue of Enquiry LPG 5*8 5d 06/Oct/2017 12/Oct/2017 23/Nov/2017 29/Nov/2017 33d Prepare & Issue of Enquiry
1124 PL2186 Receive Bids LPG 5*8 15d 13/Oct/2017 03/Nov/2017 30/Nov/2017 20/Dec/2017 33d Receive Bids
1125 PL2188 Techno Commercial Evalua on LPG 5*8 10d 06/Nov/2017 17/Nov/2017 21/Dec/2017 03/Jan/2018 33d Techno Commercial Evalua on
1126 PL2190 Prepare & Issue LOI LPG 5*8 5d 20/Nov/2017 24/Nov/2017 04/Jan/2018 10/Jan/2018 33d Prepare & Issue LOI
1127 PL2192 Prepare & Issue PR LPG 5*8 10d 27/Nov/2017 08/Dec/2017 11/Jan/2018 24/Jan/2018 33d Prepare & Issue PR
1128 PL2194 Prepare & Issue PO LPG 5*8 10d 11/Dec/2017 22/Dec/2017 25/Jan/2018 08/Feb/2018 33d Prepare & Issue PO
1129 PL2196 Manufacturing - Part Delivery LPG 5*8 100d 25/Dec/2017 15/May/2018 09/Feb/2018 29/Jun/2018 33d Manufacturing - Part Delivery
1130 PL2198 Full Delivery at Site LPG 5*8 90d 16/May/2018 19/Sep/2018 02/Jul/2018 06/Nov/2018 33d Full Delivery at Site
1131 Special Items(Strainers,Hanger,Steam Traps, Bellows,Safety Showerss,Hose Coupling) LPG 5*8 155d 25/Jan/2018 03/Sep/2018 02/Apr/2018 06/Nov/2018 45d 03/Sep/2018, Special Items(Strainers,
1132 PL2216 Prepare & Issue of Enquiry LPG 5*8 5d 25/Jan/2018 01/Feb/2018 02/Apr/2018 06/Apr/2018 45d Prepare & Issue of Enquiry
1133 PL2218 Receive Bids LPG 5*8 15d 02/Feb/2018 22/Feb/2018 09/Apr/2018 27/Apr/2018 45d Receive Bids
1134 PL2220 Techno Commercial Evalua on LPG 5*8 10d 23/Feb/2018 08/Mar/2018 30/Apr/2018 11/May/2018 45d Techno Commercial Evalua on
1135 PL2222 Prepare & Issue LOI LPG 5*8 5d 09/Mar/2018 16/Mar/2018 14/May/2018 18/May/2018 45d Prepare & Issue LOI
1136 PL2224 Prepare & Issue PR LPG 5*8 10d 19/Mar/2018 30/Mar/2018 21/May/2018 01/Jun/2018 45d Prepare & Issue PR
1137 PL2226 Prepare & Issue PO LPG 5*8 10d 02/Apr/2018 13/Apr/2018 04/Jun/2018 15/Jun/2018 45d Prepare & Issue PO
1138 PL2228 Manufacturing - Part Delivery LPG 5*8 60d 16/Apr/2018 06/Jul/2018 18/Jun/2018 10/Sep/2018 45d Manufacturing - Part Delivery
1139 PL2230 Full Delivery at Site LPG 5*8 40d 09/Jul/2018 03/Sep/2018 11/Sep/2018 06/Nov/2018 45d Full Delivery at Site
1140 Fasteners,Gaskets,Pipe Support,Insula on , Pain ng LPG 5*8 115d 02/Apr/2018 10/Sep/2018 13/Apr/2018 06/Nov/2018 40d 10/Sep/2018, Fasteners,Gaskets,Pip
1141 PL2232 Prepare & Issue of Enquiry LPG 5*8 5d 02/Apr/2018 06/Apr/2018 13/Apr/2018 19/Apr/2018 9d Prepare & Issue of Enquiry
1142 PL2234 Receive Bids LPG 5*8 15d 09/Apr/2018 27/Apr/2018 20/Apr/2018 10/May/2018 9d Receive Bids
1143 PL2236 Techno Commercial Evalua on LPG 5*8 10d 30/Apr/2018 11/May/2018 11/May/2018 24/May/2018 9d Techno Commercial Evalua on
1144 PL2238 Prepare & Issue LOI LPG 5*8 5d 14/May/2018 18/May/2018 25/May/2018 31/May/2018 9d Prepare & Issue LOI
1145 PL2240 Prepare & Issue PR LPG 5*8 10d 21/May/2018 01/Jun/2018 16/Jul/2018 27/Jul/2018 40d Prepare & Issue PR
1146 PL2242 Prepare & Issue PO LPG 5*8 10d 04/Jun/2018 15/Jun/2018 30/Jul/2018 10/Aug/2018 40d Prepare & Issue PO
1147 PL2244 Manufacturing - Part Delivery LPG 5*8 40d 18/Jun/2018 10/Aug/2018 13/Aug/2018 09/Oct/2018 40d Manufacturing - Part Delivery
1148 PL2246 Full Delivery at Site LPG 5*8 20d 13/Aug/2018 10/Sep/2018 10/Oct/2018 06/Nov/2018 40d Full Delivery at Site
1149 Construction LPG 6*10 431d 13/Jun/2017 12/Nov/2018 24/Jul/2017 06/Nov/2018 -3d 12/Nov/2018, Construc o

1150 Civil & Structural LPG 6*10 417d 13/Jun/2017 24/Oct/2018 24/Jul/2017 06/Nov/2018 11d 24/Oct/2018, Civil & Structura
1151 Je y and Piperack LPG 6*10 125d 08/Dec/2017 07/May/2018 25/May/2018 19/Oct/2018 140d 07/May/2018, Je y and Piperack
1152 Overall LPG 6*10 125d 08/Dec/2017 07/May/2018 25/May/2018 19/Oct/2018 140d 07/May/2018, Overall
1153 CS1000 Structural Strengthing of Conveyor Gallary LPG 6*10 65d 08/Dec/2017 24/Feb/2018 25/May/2018 08/Aug/2018 140d Structural Strengthing of Conveyor Gallary
1154 CS1002 Control Room Modica on LPG 6*10 65d 02/Jan/2018 21/Mar/2018 18/Jun/2018 01/Sep/2018 140d Control Room Modica on
1155 CS1004 Fireproong Work - Je y & Piperack Area LPG 6*10 65d 25/Jan/2018 13/Apr/2018 11/Jul/2018 25/Sep/2018 140d Fireproong Work - Je y & Piperack Area
1156 CS1006 Installa on of Control Room Equipments LPG 6*10 65d 19/Feb/2018 07/May/2018 03/Aug/2018 19/Oct/2018 140d Installa on of Control Room Equipments
1157 Plant Buildings LPG 6*10 253d 22/Nov/2017 18/Sep/2018 29/Nov/2017 25/Sep/2018 5d 18/Sep/2018, Plant Buildings
1158 SubSta on, Control Room & Lab, First Aid Buildings LPG 6*10 253d 22/Nov/2017 18/Sep/2018 29/Nov/2017 25/Sep/2018 5d 18/Sep/2018, SubSta on, Control R
1159 CS1008 Excava on LPG 6*10 78d 22/Nov/2017 23/Feb/2018 29/Nov/2017 02/Mar/2018 5d Excava on
1160 CS1010 Founda on Works LPG 6*10 102d 15/Dec/2017 17/Apr/2018 22/Dec/2017 24/Apr/2018 5d Founda on Works
1161 CS1012 Super Structure Works LPG 6*10 132d 20/Jan/2018 26/Jun/2018 29/Jan/2018 03/Jul/2018 5d Super Structure Works

Actual Level of Effort Remaining Work Milestone Page 27 of 30 TASK filter: All Activities
Actual Work Critical Remaining Work summary Oracle Corporation
Mundra LPG Pvt Ltd Classic Schedule Layout 12/Jun/2017 16:07
# Ac vity ID Ac vity Name Calendar Original Early Start Early Finish Late Start Late Finish Total 2017 2018
Float Apr M Jun Jul Aug Sep Oct N Dec Jan F M Apr M Jun Jul Aug Sep Oct N Dec
1162 CS1014 Brick Work LPG 6*10 Dura102d
on 16/Mar/2018 13/Jul/2018 23/Mar/2018 20/Jul/2018 5d Brick Work
1163 CS1016 Plastering Work LPG 6*10 102d 20/Apr/2018 18/Aug/2018 27/Apr/2018 25/Aug/2018 5d Plastering Work
1164 CS1018 Flooring Work LPG 6*10 78d 25/May/2018 25/Aug/2018 01/Jun/2018 01/Sep/2018 5d Flooring Work
1165 CS1020 Finishing Work LPG 6*10 78d 18/Jun/2018 18/Sep/2018 25/Jun/2018 25/Sep/2018 5d Finishing Work
1166 Commons LPG 6*10 417d 13/Jun/2017 24/Oct/2018 24/Jul/2017 06/Nov/2018 11d 24/Oct/2018, Commons
1167 Founda on for Equipment & Shed Structure LPG 6*10 417d 13/Jun/2017 24/Oct/2018 24/Jul/2017 06/Nov/2018 11d 24/Oct/2018, Founda on for
1168 CC1022 Soil tes ng, Topo & Geo-Tech Surveys LPG 6*10 20d 13/Jun/2017 06/Jul/2017 24/Jul/2017 18/Aug/2017 34d Soil tes ng, Topo & Geo-Tech Surveys
1169 CC1026 Boundary Wall, Site Oce, Security Gate House, Parking, Temp Store, Approach Road, Micro
LPG 6*10
grading etc.
156d 25/Aug/2017 01/Mar/2018 07/May/2018 06/Nov/2018 211d Boundary Wall, Site Oce, Security Gate House, Parking, Temp Store,
1170 CC1028 Piling Work LPG 6*10 78d 19/Sep/2017 21/Dec/2017 01/Nov/2017 02/Feb/2018 34d Piling Work
1171 CC1030 Structural Works (Piperack, Pla orms, Piping Supports & Sheds) LPG 6*10 132d 08/Dec/2017 15/May/2018 31/Jan/2018 05/Jul/2018 44d Structural Works (Piperack, Pla orms, Piping Supports &
1172 CC1031 UG Civil Works Draigage, Road, Pavings, Cable/Pipe Trenched, Pits LPG 6*10 156d 15/Dec/2017 19/Jun/2018 01/Feb/2018 02/Aug/2018 38d UG Civil Works Draigage, Road, Pavings, Cable/Pipe
1173 CC1032 Founda ons Work - U lity/Osites LPG 6*10 102d 09/Jan/2018 10/May/2018 24/Feb/2018 23/Jun/2018 38d Founda ons Work - U lity/Osites
1174 CC1034 Founda on Work - HC Area LPG 6*10 102d 02/Feb/2018 02/Jun/2018 21/Jun/2018 19/Oct/2018 117d Founda on Work - HC Area
1175 CC1036 Equipment Installa on Work - U lity/Osites LPG 6*10 102d 27/Jan/2018 28/May/2018 09/Jul/2018 06/Nov/2018 137d Equipment Installa on Work - U lity/Osites
1176 CC1037 Equipment Installa on Work - Process Vessels/HE/Pumps/Arms LPG 6*10 102d 20/Feb/2018 20/Jun/2018 09/Jul/2018 06/Nov/2018 117d Equipment Installa on Work - Process Vessels/HE/
1177 CC1040 U lity Area Piping Work LPG 6*10 156d 07/Mar/2018 07/Sep/2018 02/Apr/2018 01/Oct/2018 20d U lity Area Piping Work
1178 CC1042 Plant Piping Work LPG 6*10 156d 07/Mar/2018 07/Sep/2018 07/Mar/2018 07/Sep/2018 0d Plant Piping Work
1179 CC1044 Insula on/Pain ng Work LPG 6*10 80d 20/Jul/2018 24/Oct/2018 03/Aug/2018 06/Nov/2018 11d Insula on/Pain ng Work
1180 CC1046 Electrical Installa ons Works LPG 6*10 104d 10/Aug/2017 14/Dec/2017 06/Jul/2018 06/Nov/2018 275d Electrical Installa ons Works
1181 CC1048 Instrument Installa ons Works LPG 6*10 80d 11/Jul/2017 16/Oct/2017 03/Aug/2018 06/Nov/2018 324d Instrument Installa ons Works
1182 Mechanical & Piping LPG 6*10 243d 25/Jan/2018 12/Nov/2018 28/Jul/2018 06/Nov/2018 -3d 12/Nov/2018, Mechanica
1183 Ui lity & Support LPG 6*10 228d 25/Jan/2018 23/Oct/2018 03/Aug/2018 06/Nov/2018 12d 23/Oct/2018, Ui lity & Suppo
1184 DM Water Plant LPG 6*10 228d 25/Jan/2018 23/Oct/2018 03/Aug/2018 06/Nov/2018 12d 23/Oct/2018, DM Water Plan
1185 CM1110 Installa on of DM Water Package LPG 6*10 70d 25/Jan/2018 19/Apr/2018 16/Aug/2018 06/Nov/2018 170d Installa on of DM Water Package
1186 CM1112 Installa on of DM Water Tank LPG 6*10 80d 19/Jul/2018 23/Oct/2018 03/Aug/2018 06/Nov/2018 12d Installa on of DM Water Tan
1187 FW Water Plant LPG 6*10 101d 22/May/2018 17/Sep/2018 15/Oct/2018 06/Nov/2018 42d 17/Sep/2018, FW Water Plant
1188 CM1116 Installa on of FW Water Package LPG 6*10 20d 22/May/2018 13/Jun/2018 15/Oct/2018 06/Nov/2018 123d Installa on of FW Water Package
1189 CM1118 Installa on of FW Water Pump LPG 6*10 20d 24/Aug/2018 17/Sep/2018 15/Oct/2018 06/Nov/2018 42d Installa on of FW Water Pump
1190 CM1120 Installa on of FW Water Jockey Pump LPG 6*10 20d 26/Jul/2018 20/Aug/2018 15/Oct/2018 06/Nov/2018 66d Installa on of FW Water Jockey Pump
1191 CM1122 Installa on of FW Water Tank LPG 6*10 20d 19/Jul/2018 11/Aug/2018 15/Oct/2018 06/Nov/2018 72d Installa on of FW Water Tank
1192 Cooling Tower Package LPG 6*10 68d 05/Jun/2018 24/Aug/2018 28/Aug/2018 06/Nov/2018 62d 24/Aug/2018, Cooling Tower Package
1193 CM1124 Installa on of Cooling Tower Package LPG 6*10 60d 05/Jun/2018 14/Aug/2018 28/Aug/2018 06/Nov/2018 70d Installa on of Cooling Tower Package
1194 CM1126 Installa on of CT Pumps LPG 6*10 20d 31/Jul/2018 24/Aug/2018 15/Oct/2018 06/Nov/2018 62d Installa on of CT Pumps
1195 CM1128 Installa on of CT Side Stream Filter LPG 6*10 20d 03/Jul/2018 26/Jul/2018 15/Oct/2018 06/Nov/2018 86d Installa on of CT Side Stream Filter
1196 CM1130 Install on of CT Dosing Package LPG 6*10 20d 03/Jul/2018 26/Jul/2018 15/Oct/2018 06/Nov/2018 86d Install on of CT Dosing Package
1197 CM1132 Installa on of CT Clorina on Package LPG 6*10 20d 03/Jul/2018 26/Jul/2018 15/Oct/2018 06/Nov/2018 86d Installa on of CT Clorina on Package
1198 SW Water LPG 6*10 20d 19/Jul/2018 11/Aug/2018 15/Oct/2018 06/Nov/2018 72d 11/Aug/2018, SW Water
1199 CM1114 Installa on of SW Tank LPG 6*10 20d 19/Jul/2018 11/Aug/2018 15/Oct/2018 06/Nov/2018 72d Installa on of SW Tank
1200 Liq Nitrogen Package LPG 6*10 80d 06/Apr/2018 09/Jul/2018 03/Aug/2018 06/Nov/2018 101d 09/Jul/2018, Liq Nitrogen Package
1201 CM1138 Installa on of Nitrogen Storage System LPG 6*10 80d 06/Apr/2018 09/Jul/2018 03/Aug/2018 06/Nov/2018 101d Installa on of Nitrogen Storage System
1202 Boiler Package LPG 6*10 80d 18/May/2018 21/Aug/2018 03/Aug/2018 06/Nov/2018 65d 21/Aug/2018, Boiler Package
1203 CM1134 Installa on of Boiler Package and Auxilaries LPG 6*10 80d 18/May/2018 21/Aug/2018 03/Aug/2018 06/Nov/2018 65d Installa on of Boiler Package and Auxilar
1204 Flare Package LPG 6*10 80d 05/Jun/2018 06/Sep/2018 03/Aug/2018 06/Nov/2018 51d 06/Sep/2018, Flare Package
1205 CM1142 Installa on of Flare Package LPG 6*10 80d 05/Jun/2018 06/Sep/2018 03/Aug/2018 06/Nov/2018 51d Installa on of Flare Package
1206 Plant & Instrument Air Package LPG 6*10 60d 22/Mar/2018 31/May/2018 28/Aug/2018 06/Nov/2018 134d 31/May/2018, Plant & Instrument Air Package
1207 CM1136 Install on of Plant Air/Instument Air Package LPG 6*10 60d 22/Mar/2018 31/May/2018 28/Aug/2018 06/Nov/2018 134d Install on of Plant Air/Instument Air Package

Actual Level of Effort Remaining Work Milestone Page 28 of 30 TASK filter: All Activities
Actual Work Critical Remaining Work summary Oracle Corporation
Mundra LPG Pvt Ltd Classic Schedule Layout 12/Jun/2017 16:07
# Ac vity ID Ac vity Name Calendar Original Early Start Early Finish Late Start Late Finish Total 2017 2018
Float Apr M Jun Jul Aug Sep Oct N Dec Jan F M Apr M Jun Jul Aug Sep Oct N Dec
1208 DG Set/ Emergency Power LPG 6*10 Dura60d
on 03/May/2018 12/Jul/2018 28/Aug/2018 06/Nov/2018 98d 12/Jul/2018, DG Set/ Emergency Power
1209 CM1140 Installa on of DG Set LPG 6*10 60d 03/May/2018 12/Jul/2018 28/Aug/2018 06/Nov/2018 98d Installa on of DG Set
1210 Weigh Bridge LPG 6*10 60d 03/Jul/2018 12/Sep/2018 28/Aug/2018 06/Nov/2018 46d 12/Sep/2018, Weigh Bridge
1211 CM1144 Instala on of Weight Bridge LPG 6*10 60d 03/Jul/2018 12/Sep/2018 28/Aug/2018 06/Nov/2018 46d Instala on of Weight Bridge
1212 Mercaptan Dosing Package LPG 6*10 60d 03/Jul/2018 12/Sep/2018 28/Aug/2018 06/Nov/2018 46d 12/Sep/2018, Mercaptan Dosing Pac
1213 CM1146 Installa on of Mercaptan Dosing System LPG 6*10 60d 03/Jul/2018 12/Sep/2018 28/Aug/2018 06/Nov/2018 46d Installa on of Mercaptan Dosing Sys
1214 Process Equipments LPG 6*10 197d 22/Mar/2018 12/Nov/2018 28/Jul/2018 06/Nov/2018 -3d 12/Nov/2018, Process Eq
1215 Marine Loading/Unloading Arms LPG 6*10 85d 28/Jun/2018 08/Oct/2018 28/Jul/2018 06/Nov/2018 25d 08/Oct/2018, Marine Loading/U
1216 CM1058 Installa on of Marine Unloading/Loading Arms LPG 6*10 85d 28/Jun/2018 08/Oct/2018 28/Jul/2018 06/Nov/2018 25d Installa on of Marine Unloading
1217 Tank & BOG Area LPG 6*10 114d 22/Mar/2018 02/Aug/2018 28/Aug/2018 06/Nov/2018 80d 02/Aug/2018, Tank & BOG Area
1218 CM1054 Installa on of Flash Gas Compressor I LPG 6*10 60d 24/May/2018 02/Aug/2018 28/Aug/2018 06/Nov/2018 80d Installa on of Flash Gas Compressor I
1219 CM1056 Installa on of Flash Gas Compressor II LPG 6*10 60d 24/May/2018 02/Aug/2018 28/Aug/2018 06/Nov/2018 80d Installa on of Flash Gas Compressor II
1220 CM1060 Installa on of BOG Gas Compressor I LPG 6*10 60d 24/May/2018 02/Aug/2018 28/Aug/2018 06/Nov/2018 80d Installa on of BOG Gas Compressor I
1221 CM1062 Installa on of BOG Gas Compressor II LPG 6*10 60d 24/May/2018 02/Aug/2018 28/Aug/2018 06/Nov/2018 80d Installa on of BOG Gas Compressor II
1222 CM1064 Handover to Package C Contractor LPG 6*10 10d 24/May/2018 05/Jun/2018 30/Aug/2018 10/Sep/2018 82d Handover to Package C Contractor
1223 CM1066 Handover to Package C Contractor LPG 6*10 10d 22/Mar/2018 03/Apr/2018 30/Aug/2018 10/Sep/2018 136d Handover to Package C Contractor
1224 Sta c Blender(s) LPG 6*10 12d 21/Aug/2018 04/Sep/2018 24/Oct/2018 06/Nov/2018 53d 04/Sep/2018, Sta c Blender(s)
1225 CM1068 Installa on of Sta c Blender I LPG 6*10 12d 21/Aug/2018 04/Sep/2018 24/Oct/2018 06/Nov/2018 53d Installa on of Sta c Blender I
1226 CM1070 Installa on of Sta c Blender II LPG 6*10 12d 21/Aug/2018 04/Sep/2018 24/Oct/2018 06/Nov/2018 53d Installa on of Sta c Blender II
1227 CM1072 Installa on of Sta c Blender III LPG 6*10 12d 21/Aug/2018 04/Sep/2018 24/Oct/2018 06/Nov/2018 53d Installa on of Sta c Blender III
1228 CM1074 Installa on of Sta c Blender IV LPG 6*10 12d 21/Aug/2018 04/Sep/2018 24/Oct/2018 06/Nov/2018 53d Installa on of Sta c Blender IV
1229 Heat Exchangers LPG 6*10 76d 04/Jul/2018 03/Oct/2018 16/Aug/2018 06/Nov/2018 29d 03/Oct/2018, Heat Exchangers
1230 CM1076 Installa on of Propane Heater I LPG 6*10 70d 04/Jul/2018 25/Sep/2018 16/Aug/2018 06/Nov/2018 35d Installa on of Propane Heater I
1231 CM1078 Installa on of Butane Heater I LPG 6*10 70d 04/Jul/2018 25/Sep/2018 16/Aug/2018 06/Nov/2018 35d Installa on of Butane Heater I
1232 CM1080 Installa on of Propane Heater II LPG 6*10 70d 04/Jul/2018 25/Sep/2018 16/Aug/2018 06/Nov/2018 35d Installa on of Propane Heater II
1233 CM1082 Installa on of Butane Heater II LPG 6*10 70d 04/Jul/2018 25/Sep/2018 16/Aug/2018 06/Nov/2018 35d Installa on of Butane Heater II
1234 CM1084 Installa on of Propane Vaporizer I LPG 6*10 70d 11/Jul/2018 03/Oct/2018 16/Aug/2018 06/Nov/2018 29d Installa on of Propane Vaporizer
1235 CM1086 Installa on of Propane Vaporizer II LPG 6*10 70d 11/Jul/2018 03/Oct/2018 16/Aug/2018 06/Nov/2018 29d Installa on of Propane Vaporizer
1236 CM1088 Installa on of Propane BOG/Flash Condenser LPG 6*10 70d 04/Jul/2018 25/Sep/2018 16/Aug/2018 06/Nov/2018 35d Installa on of Propane BOG/Flash
1237 CM1090 Installa on of Butane BOG/Flash Condenser LPG 6*10 70d 04/Jul/2018 25/Sep/2018 16/Aug/2018 06/Nov/2018 35d Installa on of Butane BOG/Flash C
1238 CM1092 Installa on of Suc on Separator I LPG 6*10 70d 04/Jul/2018 25/Sep/2018 16/Aug/2018 06/Nov/2018 35d Installa on of Suc on Separator I
1239 CM1094 Installa on of Suc on Separator II LPG 6*10 70d 04/Jul/2018 25/Sep/2018 16/Aug/2018 06/Nov/2018 35d Installa on of Suc on Separator II
1240 Pressure Vessels LPG 6*10 60d 04/Jul/2018 13/Sep/2018 28/Aug/2018 06/Nov/2018 45d 13/Sep/2018, Pressure Vessels
1241 CM1096 Installa on of Propane BOG/Flash Condensate Receiver LPG 6*10 60d 04/Jul/2018 13/Sep/2018 28/Aug/2018 06/Nov/2018 45d Installa on of Propane BOG/Flash Co
1242 CM1098 Installa on of Butane BOG/Flash Condensate Receiver LPG 6*10 60d 04/Jul/2018 13/Sep/2018 28/Aug/2018 06/Nov/2018 45d Installa on of Butane BOG/Flash Con
1243 CM1100 Installa on of Steam Condensate Receiver LPG 6*10 60d 04/Jul/2018 13/Sep/2018 28/Aug/2018 06/Nov/2018 45d Installa on of Steam Condensate Re
1244 Pumps LPG 6*10 60d 30/Aug/2018 12/Nov/2018 28/Aug/2018 06/Nov/2018 -3d 12/Nov/2018, Pumps
1245 CM1102 Installa on of Propane BOG/Flash Condensate Pumps LPG 6*10 60d 30/Aug/2018 12/Nov/2018 28/Aug/2018 06/Nov/2018 -3d Installa on of Propane BO
1246 CM1104 Installa on of Butane BOG/Flash Condensate Pumps LPG 6*10 60d 30/Aug/2018 12/Nov/2018 28/Aug/2018 06/Nov/2018 -3d Installa on of Butane BOG
1247 CM1106 Installa on of Steam Condensate Pump LPG 6*10 60d 30/Aug/2018 12/Nov/2018 28/Aug/2018 06/Nov/2018 -3d Installa on of Steam Cond
1248 Truck Loading Gantries LPG 6*10 80d 17/Jul/2018 20/Oct/2018 03/Aug/2018 06/Nov/2018 14d 20/Oct/2018, Truck Loading G
1249 CM1108 Installa on of Loading/Vapor Return Arms LPG 6*10 80d 17/Jul/2018 20/Oct/2018 03/Aug/2018 06/Nov/2018 14d Installa on of Loading/Vapor R
1250 Pre-Commissoning & Commissoning 381d 10/May/2017 06/Nov/2018 07/Sep/2018 06/Nov/2018 0d 06/Nov/2018, Pre-Commis

1251 General Ac vi es & Milestones 381d 10/May/2017 06/Nov/2018 07/Sep/2018 06/Nov/2018 0d 06/Nov/2018, General Ac
1252 Commons 381d 10/May/2017 06/Nov/2018 07/Sep/2018 06/Nov/2018 0d 06/Nov/2018, Commons
1253 Overall 381d 10/May/2017 06/Nov/2018 07/Sep/2018 06/Nov/2018 0d 06/Nov/2018, Overall

Actual Level of Effort Remaining Work Milestone Page 29 of 30 TASK filter: All Activities
Actual Work Critical Remaining Work summary Oracle Corporation
Mundra LPG Pvt Ltd Classic Schedule Layout 12/Jun/2017 16:07
# Ac vity ID Ac vity Name Calendar Original Early Start Early Finish Late Start Late Finish Total 2017 2018
Float Apr M Jun Jul Aug Sep Oct N Dec Jan F M Apr M Jun Jul Aug Sep Oct N Dec
1254 C5572 Loop Tes ng LPG 6*10 Dura30d
on 07/Sep/2018 13/Oct/2018 03/Oct/2018 06/Nov/2018 20d Loop Tes ng
1255 C5574 Punchlis ng & Handover Civil Buildings to MLTPL LPG 5*8 30d 19/Sep/2018 31/Oct/2018 25/Sep/2018 06/Nov/2018 4d Punchlis ng & Handover Civ
1256 C5575 Site Cleaning & Restora on LPG 6*10 15d 07/May/2018 24/May/2018 20/Oct/2018 06/Nov/2018 140d Site Cleaning & Restora on
1257 C5584 Closing Punch List A/B LPG 6*10 30d 07/Sep/2018 13/Oct/2018 07/Sep/2018 13/Oct/2018 0d Closing Punch List A/B
1258 C5585 Prepare & Issue Punch List - C LPG 6*10 20d 13/Oct/2018 06/Nov/2018 13/Oct/2018 06/Nov/2018 0d Prepare & Issue Punch List
1259 C5594 Interconnec on with Package C & F LPG 6*10 28d 10/May/2017 10/Jun/2017 04/Oct/2018 06/Nov/2018 430d Interconnec on with Package C & F