200. How many hours does a fine aggregate tested for specific
gravity and absorption be soaked in water?
Ans : 15 to 19 hours
201. How to determine if the fine aggregate reaches the saturated
dry condition.
Ans : It is determined by the use of cone test for surface moisture.
If the molded shape of line aggregate slump slightly, it indicates
that it has reached surface dry condition.
202. What is the significance of testing reinforcement steel bars?
Ans : To determine the yield and tensile strength of the bar as well
as its elongation and is used to classify the bars into grade.
203. What is the significance of bending test for RSB?
Ans : To evaluate the ductile properties of RSB
204. What is required testing requirement for paints?
Ans : 1 can ( gal or pail/ 100 cans(gal or pail)
205. How many concrete cylinder sample is required for 300 pcs
RCCP
Ans : 12 sets
206. If the concrete cylinder is not available for a 300 pcs RCCP,
How many pipes shall be subjected to test?
Ans : 5 pcs
207. In placing concrete, the required temperature should be less
than _____
Ans : 29C
208. Rolling of bituminous mix shall be discontinued whenever it
begins to produce excessive _____or _____
Ans : pulverizing of the aggregates, displacement of the mixture.
209. Soft and unsuitable soils were encountered during the course of
subgrade preparation. If you were ME assigned to the project, what
is the most effective and cheaper method that you would recommend
to stabilize the soil prior to the construction of the subbase course.
Ans : Geotextile
210. During the application of the first half of the anticipated load a
______ rate of loading shall be permitted?
Ans : Higher
211. If there is a necessity to add water to the concrete mix in order
to increase its workability (provided concrete does not exceed
specified slump), how many minutes after the initial time of mixing
does adding water be permitted?
Ans : not exceeding 45 minutes and that water- cement ratio is not
exceeded.
212. What are two(2) types of bitumen that are commonly used in
the bituminous mixture?
Ans : TAR = is a viscous liquid obtained from the distillation of
coat or wood
PETROLEUM ASPHALT = are the products of the
distillation of crude oil.
213. What are the three (3) major petroleum asphalts?
Ans : Asphalt cement, cut-back asphalt, emulsified asphalt
214. What are the solvents of cut-back asphalts?
Ans : GASOLINE = for rapid curing type
KEROSINE = for medium curing type
DIESEL = for slow curing type
215. Emulsified asphalt are either _____ and _______
Ans : CATIONIC EMULSION = works better with wet aggregate
and in cold weather, it is
positively charge electron.
ANIONIC EMULSION = Adhers better to aggregate
which have positive charge. It is
a negative charge electron.
216. What is the Bituminous materials used in Item 310?
Ans : asphalt cement
217. What greatly affects the service of the asphalt?
Ans : grade and quantity of asphalt
218. The requisites in transporting sample of the laboratory is
______
Ans : Well packed in durable container to avoid damages in transit,
accompanied by a sample card filled up in detail and duly signed
by the ME.
219. The mineral filler which is the used in the bituminous mix is
passing sieve?
Ans : No.200
220. Cold mix asphalt is used in _____
Ans : pothole patching
221. VMA means
Ans : Voids in Mineral Aggregates
222. The compaction temperature in molding the bituminous
mixture specimen
Ans : 124C
223. The mixing temperature of bituminous mix is
Ans : 163C
224. The heating temperature of bituminous mix is
Ans : 121C 188C
225. A type of coring bit used in lock coring
Ans : diamond bit
226. It is dynamic test used in the field to obtain rapid empirical
results which can be used to estimate shear strength and bearing
capacity.
Ans : Standard Penetration Test
227. A tube sampler is the used in sampling disturbed sample.
Ans : Split spoon sampler
228. Used in sealing undisturbed sample
Ans : wax
229. A tube sampler is used in sampling undisturbed sample
Ans : Shelby tube
230. The maximum moisture content of CHB
Ans : 45%
231. The maximum absorption content of CHB
Ans : 240 kg/m
232. The heating temperature of aggregate range from
Ans : 177C -191C
233. The specific gravity of asphalt ranges from
Ans : 1.01 1.04
234. The allowable % variation in mass of deformed reinforcing
steel is
Ans : 6% maximum under nominal stress
235. The maximum allowable % phosphorous content of a
deformed and plain billet steel bar is
Ans : 0.06%
236. Tensile and yield strengths of steel bars?
Ans : Tensile strength Yield Point
Grade 40 483 Mpa 276 Mpa
Grade 60 621 Mpa 414 Mpa
Grade 75 689 Mpa 517 Mpa
237. Plasticity index is an indication of percent
Ans : clay content
238. The condition of the soil to be tested in the laboratory
compaction test is
Ans : Airdried condition
239. The method in the determination of density of soil in- place
Ans : Sand Cone Method
240. Air-dry sand used in the density apparatus is passing
Ans : Sieve No. 10 retained No. 200
241. In abrasion test, the abrasive charge shall consist of cast-iron
or steel spheres
Ans : Grading A 12 spheres
Grading B 11 spheres
Grading C 8 spheres
Grading D 6 spheres
242. In trucking mixing, the minimum number of revolutions after
all ingredient including water in the drum is
Ans : 100 rpm
243. A maximum time of ____ shall be permitted for wet mixing,
lay down and finishing when this method is used (Item206)
Ans : 2 hours
244. Traffic shall be prohibited from traveling at the speeds in
excess of ___ until the asphalt material has set
Ans : 40 kph
245. Mortar shall be used within ______ after its preparation
Ans : 90 minutes
246. In placing concrete for slab, using buggies, the correct method
that should be followed is
Ans : concrete should be dump into the face of the previously
placed concrete.
247. There is a failure of flexural strength in the pavement, if you
are the ME of your firm, what will you recommend?
Ans : conduct re-coring
248. When loads have been arriving at the spreader with the
material peaked or doomed up and a load suddenly appears in which
the material lies flat, it indicates
Ans : Excessive Asphalt
249. Where and when was the first use of Portland Cement?
Ans : BELTALONTAINE, OHIO (1893)
250. The curve in the logarithmic scale where the 25th blow is
projected in order to determine the liquid limit of the soil.
Ans : Flow curve
251. Percentage of wear represents the value of ______
Ans : Abrasion loss
252. In the design of concrete mix, what is the volume of water in
the concrete mix that produces a slump of 76.2 mm?
Ans : 24.7 liters
253. The standard fineness modulus of sand is about ______.
Ans : 2.75
254. The standard packaging weight of cement
Ans : 40 kg/bag
255. It is an impervious membrane applied to concrete pavement
before its initial setting that prevents rapid evaporation of water
from the mix
Ans : curing compound
256. The type of paint that is used for zone marking, traffic lane
and parking spaces which is rapid drying, resistant to abrasion and
weather condition an process improved visibility at night
Ans : reflectorized paint
257. An ingredient in the paint that gives reflection during night
time.
Ans : glass beads
258. The paint which is used in concrete or masonry units
Ans : Latex
259. The average loss in weight of three specimens in zinc coating
test
Ans : Single spot test
260. The type of paint that is used in wood surfaces. It is a special
type of paint made with varnish as the vehicle,
Ans : Enamel
261. good index is an empirical number ranging from 0 to 20 under
average condition of good drainage and adequate compaction. The
supporting value of a material as subgrade may be assumed as an
inverse ratio to its group index, that is a group index of zero indicates
Ans : good subgrade materials
262. It determines the target density which is constructed at the
beginning of the work on each course of material to be compacted.
Ans : Control strips
263. The instrument used in placing concrete in water in a
compacted mass in its final position.
Ans : tremie with 250mm
264. The maximum specific gravity of thermoplastic paint
Ans : 2.15
265. The softening point of a thermoplastic paint
Ans : 102.5C
266. The maximum drying time of thermoplastic paint.
Ans : 10 minutes
267. The rate of application of traffic paint.
Ans : 0.33 lit/m
268. The maximum drying time of traffic paint
Ans : 15-30 minutes
269. The minimum weight of sample for reflectorized paint
Ans : 10 kg
270. The apparatus used to measure the thickness or height of
compacted bituminous paving mixture.
Ans : vernier caliper
271. It is used in calculating the unit weight of the mixture of the
degree of compaction of the asphalt pavement.
Ans : Bulk specific gravity of compacted bituminous mixture using
saturated surface dry specimen.
272. The solvent in the extraction of bitumen.
Ans : gasoline
273. The percent of bitumen is computed based on
Ans : mass of dry aggregate
274. The method used to determine the grading of aggregate
extracted from bituminous mixture.
Ans : Mechanical analysis of extracted aggregates
275. A device used to determine the relative hardness of asphalt.
Ans : penetrometer
276. The measurement wherein the asphalt begins to melt.
Ans : Softening point
277. The Index of Retained Strength (IRS) is computed through the
formula
Ans : (wet stability/dry stability) x 100%
278. The temperature requirement in initial rolling for Item 310.
Ans : 200F to 225F
279. What is the color of asphalt when it is overcooked?
Ans : yellowish brown
280. How many gradation ranges for Hot Plant Mix bituminous
pavement are there in the blue book?
Ans : seven (7)
281. How many gradation ranges for Cold Plant Mix bituminous
pavement are there in the blue book?
Ans : two (2)
282. The cored sample of asphalt pavement is measured at
Ans : approximately quarter point
283. What is the plasticity index of mineral filler.
Ans : not greater than 4
284. The wearing away of pavement surface caused by dislodging
of aggregate particle.
Ans : raveling
285. The interconnected cracked forming a series of small blocks
resembling an alligators skin or chicken wire.
Ans : Alligator crack
286. If the Coarse aggregate are subjected to five cycles of sodium
sulfate soundness test, the weighted loss shall not exceed
Ans : 10 mass %
287. If the Fine aggregate are subjected to five cycles of sodium
sulfate soundness test, the weighted loss shall not exceed
Ans : 12 mass %
288. Additives used in concrete mixing.
Ans : Admixture
289. The test that determines the resistance of aggregates to
disintegration by saturated solutions of sodium sulfate, magnesium
sulfate.
Ans : Soundness test
290. The design of concrete mix specified in the blue book is based
on
Ans : Absolute Design Method
291. The initial setting time of Portland Cement is not less than
Ans : 45 minutes
292. The final setting time of Portland cement
Ans : 10 hours
293. The apparatus used to determine the fineness of Portland
cement by air permeability
Ans : Blaine Air Permeability Apparatus
294. A mixture of cement and water is
Ans : Cement paste
295. The apparatus used to determine the initial & final setting of
Portland cement in the laboratory.
Ans : Gilmore needle
296. The compressive strength of cement mortar sample in 7 days is
Ans ; 19.3 MPa
297. What is the appearance of the molded cement paste which fail
to meet the autoclave.
Ans : crumbled
298. The critical number of days of curing of concrete
Ans : 7 days
299. It is equality as important as testing, and the sampler shall sue
every precaution to obtain samples that will show the nature and
condition of the materials which they represent.
Ans : Sampling
300. A soil sample received from the field for subsequent tests by
reducing aggregations of particle into sizes which will pass certain
sieves.
Ans : disturbed sample
301. A procedure to recover relatively undisturbed soil samples
suitable laboratory test of structural properties.
Ans : thin-walled tube sampling
302. The representative who will witness the testing of material in
an accredited laboratory.
Ans : Government
303. The type of additive that is used to delay the setting of fresh
concrete.
Ans : retarder
304. The type of additive that is used to attain maximum
compressive strength of concrete
Ans : Accelerator
305. The best enemy of construction.
Ans : Water
306. The following are considered unsuitable materials :
Ans : Materials containing detrimental quantities of organic
materials such as grass, roots and sewage
Highly organic material soil such peak and muck
Soils with LL exceeding 80% and /or PL exceeding 55%
Soils with a natural moisture content exceeding 100%
Soils with very low natural density, 800 kg/m
Soils that cannot be properly compacted as determined by
the engineer
307. What is the spec. of mass% passing in sieve No.200, grading A
for aggregate base course?
Ans : 0 to 12%
308. The rate of application of special curing agent.
Ans : 4 liter per 14 sq.m
309. The method of measurement for determining the depth of
river channel.
Ans : Sounding
310. If the type of soil in Item 200 is non-plastic, what atterberg
limit test can be performed?
Ans : Liquid limit Test
311. The minimum penetration of the preservation into the surface
of timber is
Ans : 20 mm
312. The Engineer shall be noticed at least _____ before the
treating process of timber.
Ans : 10 days
313. All grout shall pass through a screen with a _____ maximum
clear opening.
Ans : 2 mm
314. The allowable height of fall in driving piles to avoid injury
using gravity hammer.
Ans : 2.5m 3.5m (concrete)
4.5m (timber)
315. This increases the shearing strength of aggregates of any size,
shape and gradation
Ans : Compaction
316. Bowl-shaped holes of various sizes in the pavement surface.
Ans : potholes
317. It is the activity of monitoring planned schedule against actual
and by speed task to make- up for past or future loss of time.
Ans : Delivery control
318. Admixture which can help incorporate a controlled amount of
air on the form moist in concrete during mixing without significantly
altering the setting or rate of characteristic of concrete.
Ans : air entraining admixture
319. Loose material is removed from all joints, cracks and areas
that have previously patched by asphalt by_____ with nominal ____
air pressure.
Ans : power sweeping and air blowing, 100psi
320. Super plasticizers can reduce the water content by __ and
increase the 24 hours strength by___?
Ans : 25% to 35%, 50% to 70%
321. Stabilization and under sealing are recommended if the mean
deflection is _____ or the differential deflection is _____
Ans : greater than 0.14 , greater than 0.002
374. The DPWH specs provide ____ tolerance for asphalt pavement
thickness
Ans : 5mm
375. Geosynthematic maybe used for
Ans : filtration or drainage, reinforcement, erosion control
376. Which of the is not included in determining moisture content?
Ans : a) beam balance
b) oven
c) moisture can
d) extruder
377. Steel bars are considered undersize if
Ans : Its nominal diameter as determined by caliper doesnt meet
the manufactured size
378. Sample of aggregate for base course when tested for quality
the requirements. Except grading. What will you recommend?
Ans : reprocess the materials by blending
379. Concrete curing refers to
Ans : procedure done to maximize concrete strength
380. What is the most interior type of soil as to its Engineering
Properties?
Ans : Organic
381. what is Quality?
Ans : the degree of excellence
382. What is control?
Ans : is to regulate
383. What is quality control?
Ans : it is conformance to requirement
384. What is assurance?
Ans : is the degree of certainly
385. What are the two kinds of control and activities?
Ans: Inspection and Testing
386. What is the minimum distance of the water table from
subgrade level?
Ans : 4-5 feet
387. What is the process of combining two or more soil in suitable
properties to produce good grading on gravel, sand, silt and clay?
Ans : Mechanical Stabilization
388. what is the common material employed in stabilizing the
moisture content of soil or liquid and hydroscope in nature? It is an
aid in the compaction process by slowing the rate of evaporation of
moisture from the soil.
Ans : Calcium chloride or rock salt
389. When do clay and granular soils become unsuitable?
Ans : Clay soil becomes unstable if moisture content increase,
granular material become unstable if it has dried
390. Why do liquid asphalt was introduced in road construction
aside from asphalt cement?
Ans : it was introduced in order to save heating costs and from
convenience in road-mixing or priming
391. The theory of concrete design mix is to
Ans : Optimize aggregate packing and optimize properties of
cement mortar.
392. To optimize the properties of the cement mortar, one has to
depend on
Ans : cement type, cement content and water content
393. What type of cement is the ordinary cement (OPC)?
Ans : Type I
394. What type of cement is the moderate Sulphate Resistant
Portland Cement (MSRPC)?
Ans : Type II
395. What type of cement is the Rapid Hardening Portland Cement
(RHPC)?
Ans : Type III
396. What type of cement is the Low Heat Portland Cement
(LHPC)?
Ans : Type IV
397. What type of cement is the High Sulphate Resistant Portland
Cement (HSRPC)?
Ans : Type V
398. What type of cement is the Portland Blast Furnace Slag
Cement (PBFSC)?
Ans : Type 10
424. What type of cracks will appear on concrete if it was not cured
immediately after final placement especially during the first seven
days?
Ans : Plastic Shrinkage cracks
425. What is the commonly used as curing media for fresh
concrete?
Ans : Liquid membrane forming
426. What is the work sequence on cylinder specimen?
Ans : Cylinder shall be prepared, cured and tested at the specified
date.
427. When to remove the false work of continuous structure?
Ans : when the 1th and 2nd adjoining span on each side have
reached the specified strength
428. It is generally either a soft soil composed largely of sill, clay,
organic deposit or loose sand having high void rather and usually not
high water content.
Ans : weak Subgrade
429. What is Twelve- inches Method Embankment?
Ans : the material shall be deposited and spread in layers not more
than 300mm in depth (12) measure, parallel to the finished grade
and extending to the full width of the embankment
430. What is rock embankment method?
Ans : the material shall be deposited on the fill and push over the
end of the fill by means of bulldozer. This method is only
applicable to fill 1.2m in depth. It shall not place with 600 mm of
the other grade.
431. What is the Hydraulic Fill Method Embankment?
Ans : the material shall be taken from borrow location and shall be
deposited so as to form the grade and cross section and shall be
thoroughly compacted.
432. What is the principal factor used in determining the thickness
of the pavement?
Ans : STRENGTH SUBGRADE (deterioration due to frustration
move also be considered)
433. What is placing and removing Surcharge Method
Embankment?
Ans : were unsuitable material is present under the embankment
corrected work consists of placing a surcharge constructed to the
full width of the road bed. This surcharge shall remain in place
until the embankment has stability or the required settlement.
434. What is Hydraulic Construction Method Embankment?
ANS : this involves the introduction of water into the embankment
to accelerate consideration.
435. Mixture of fine-grained aggregates, bituminous binder and
water for surface seating.
Ans : Slurry seal (bituminous slurry)
436. What is the formula for percentage of wear?
Ans : percentage of wear, % = (orig. wt. wt. retained @ sieve
#12) X 100 %
Original wt.
437. Free bitumen on the surface of the pavement which creates a
shiny, glass- like reflecting surface that usually becomes quite sticky
Ans : Bleeding
438. Occurring usually at the transverse cracks joint caused by
excessive expansion of the slabs during hot weather.
Ans : Crushing
439. The authorized hauling of materials in excess of the free haul
distance.
Ans : Overhaul
440. If slurry (wet) time is employed, what is the typical slurry
ratio?
Ans : 1 tonne time : 2 cubic meter of water
441. What is the amount of cement to be added to the soil
aggregates in Item 204?
Ans : 6-10 mass% of the dry soil
442. Who is the father of soil mechanics?
Ans : Dr. Karl Terzhagi
443. Type V cement is used for
Ans : When sulfate content of groundwater is very high
444. The Inventor of Portland Cement was
Ans : Joseph Aspdin
445. Portland Cement is composed of blended materials containing
Ans : Calcium, Alumina, Iron, and silica
446. The simple recipe of Portland Cement is
Ans : 2 parts of crushed limestone, 1 part claypulvorized shale, 1
pinch of Iron, then 1 pinch of gypsum added to clinker.
447. Pozzolan cement is composed of raw material; called
Ans : volcanic earth
448. The 75% compressive strength of Portland Cement is
composed of
Ans : C3S and C2S
449. The 25% setting time of Portland Cement is controlled by
Ans : C3A and C4AF
450. When water is added to Portland Cement, _______ process is
developed.
Ans : Hydration
451. When Portland Cement contains low C3A, it means
Ans : the setting time is larger
452. Surplus time [Ca(OH)2] in Portland Cement when mixed with
water takes care of the concretes
Ans : Alkalinity
453. Course aggregates can be taken from
Ans : crushed rock, slag and river gravel
454. The water required for concrete mix should be
Ans : Fresh Water
455. Sea water is deleterious to concrete mix unless on admixture is
added because it contains
Ans : chloride
456. The entrapped air in concrete is
Ans : Accidental and unwanted
457. The entrained air in concrete is
Ans : deliberate and desirable
458. We use aggregate in concrete as
Ans : filler materials in concrete
459. Aggregate are important in concrete because they strongly
influence:
Ans : the properties of concrete, its mix proportion and its
economy
460. Which of the following is not deleterious material to concrete?
Ans : a) calcium
b) chloride
c) coal
d) sulphate
461. Over sanded and under sanded mixture require more water to
be workable, but ______ making it so will only result to sacrifice in
Ans : Strength
462. Concrete in the area represented by the cores will be
considered adequate if the average strength of the cores is equal to or
at least ____of the specified strength fc and no single core is less than
___.
Ans : 85% of fc, 75% of fc
463. Fine aggregate shall be rejected when it fails in the _____ for
organic impurities
Ans : Colormatic test
464. Portland Cement may be/ shall be rejected if:
Ans : it has partially set, it contains lumps of cake cement and it
comes from a discarded or used bag
465. A measurement of the coarseness or fineness of aggregates
Ans : Fineness modulus
466. An excess water needed for absorption of coarse aggregates
Ans : Free water
467. What do you mean by SSD?
Ans : Saturated Surface Dry
468. A general term relating to the character of a mix with respect
to its fluidity
Ans : Consistency
469. More silt and clay content to fine aggregate is
Ans : Objectionable
470. Type A admixture is classified by ASTM C494 as
Ans : Water- reducing admixture
471. The unit pressure greater than which progressive settlement
occur leading to failure
Ans : bearing capacity
472. The recommended thickness of hot mixed asphalt overlay
Ans : 2
473. In the test to determine the moisture content of samples, the
beam balance should be sensitive up to.
Ans : 0.1 gram
474. If the sample can not be weighted within the prescribed time
after being removed from the oven within
Ans : 1 hour
475. Drying the material sample in the oven to constant weight at a
prescribe temperature, the drying time depends on the kind of soil
and size of the sample. A 25 gram sample of sandy material will be
dried about
Ans : 2 hours
476. Test conducted for building 3 storey and above
Ans : Boring test
477. A test to determine the moisture content of soil
Ans : calcium tri-chloride
478. The aggregate crushing value of strong aggregate is
Ans : Low
479. The kind of asphalt used in overlaying seated pavement
Ans : hot-mix asphalt
480. The minimum width of paved sidewalk
Ans : 1.5 meters
481. The limit of water- cement ratio of concrete
Ans : 0.50-0.60
482. A cement where compression is induced before the application
of working load so that tension under this load is reduced.
Ans : Pre-stressing
483. What laboratory test is used in determining the phosphorus
content of steel materials?
Ans : Phospho-molydate
484. What chemical property in the composition of steel material
that will cause brilleness or cold shortness when its content goes
beyond 0.05% to .10%
Ans : phosphorous
485. Base or Sub-base is exceed beyond each edge of proposed
concrete pavement
Ans : 0.60 m
486. If you want to adjust the slump and the air content, how you
do it?
Ans : + 10mm slump = + 2 kg/m from (water)
+ air entrapment = + 2 kg/m of average (water)
487. In non-entrained concrete, what is the range of air entrained?
Ans : 3% - 0.2% (small- bigger aggregate)
488. In air-entrained concrete, what is the range of air entrained?
Ans : 8% - 3% (small- bigger aggregate)
489. For the constant water cement ratio, what will happen if air
content involved?
Ans : The strength of concrete is reduce
490. What will happen if the lower the water-cement ratio and
maintaining other values of its ingredients?
Ans : it will acquire strength
491. What is the mixing time of concrete?
Ans : 1.5 m capacity mixer, T260 seconds
Above 1.5 m capacity mixer, T 290 seconds
492. When cement is in contact with moist aggregates, batch made
by mix will be disallowed beyond ____.
Ans : 1 hours
493. How many hours should an aggregate be washed and
stockpiled before batching starts?
Ans : 12 hours prior to batching shall be stockpiled or binned for
draining
494. When will truck mixing start?
Ans : mixing shall begin within 30 minutes upon cement has due
added 15 minutes when wet aggregate is used as 32C temperature
is present
495. Concrete delivered by agitation of truck mixer must be
discharged within 1 hour or 250 revolutions of the drum. why?
Ans : to avoid over mixing and initial setting of the concrete
496. In final computation of concrete in road to be paid, what is the
maximum size of pipe that is negligible in the volume computation?
Ans : pipes with of 4 or less