Professional Documents
Culture Documents
Month AP
No. Description Day TU Wed Thu
Date 19 20 21
1 CIVIL
Rigid
Finishing Office
Finishing Shelter Main Eq
Finishing Ruang Panel
Totem
Taman
Cat Pagar
4 Drain/Venting
Persiapan
Survey Ulang 1 1
Pembelian Material Consumable 1
Construction
Pemasangan Support
Pemasangan Pipa Vent dan Drain
6 Dewatering/Flushing
Dewatering HP Tubing Main Line
Air Instrument Line
8 PreCommissioning
SAFE Setting (Parallel E/I Schedule)
SAFE Setting (CNG Compressor Aligned dan Solo Run)
SAFE Ground Storage Leak Test
Individual Testing
CCTV
FACP System (Gas Detector, Smoke Detector, Heat Detector)
Pos System
Air Instrument System
HMI
Purging N2
9 Commissioning
Note :
22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
10 10 10 10
4 4 2 2 2 2 4 4 4 4 4
4 4 4 4 2 2
2 2 2 2 2 2 2
2 2 2 2 2 2
2 2 2 2 2 2 2 2 2 2 2 2 2
2 2 2 2 2 2 2 2 2 2 2 2 2
1 1 1 1
1 1 1
2 2
1 1 1 1 1 1
1 1 1 1 1
1 1 1 1 1
1 2 2 2 2 2
1 1 1 1 1
2 2 2 2
1 1 1
1 1 1
2 2 2 2
1 1 1 1
4 4 4
4 4 4 4
6 6 6 6 6
2 2
2
2
13 15 16 13 4 4 2 4 4 8 9 7 7 7 7 10 10 21 25 25 28 24 16 13 10 8
MAY
Wed Thu Fri Sat Sun Mon TU Wed Thu Fri Sat Sun Mon
18 19 20 21 22 23 24 25 26 27 28 29 30
4
1 1 1 1 1 1 1 1
2 2 2 2 2 2 2 2
2 2 2 2 2 2 2 2
2 2
2 2
2 2 2
2 2 2 2
10 10 10
8 9 7 9 9 7 7 5 5 10 10 10 0
Schedule Penyelesaian Daughter Station SPBG Serang Paket 5
Month APRIL
No. Description Day TU Wed Thu Fri Sat
Date 19 20 21 22 23
1 CIVIL
Rigid 10 10
Finishing Office
Finishing shelter dispenser
Totem
Taman
2 LP/HP
Persiapan
Survey Ulang
Pembelian Material Consumable
Construction
Pemasangan Support
Pemasangan Tubing
4 Drain/Venting
Persiapan
Survey Ulang
Pembelian Material Consumable
Construction
Pemasangan Support
Pemasangan Tubing
5 Hydro/Leak Test
LP/HP Tubing
Air Instrument Tubing
Drain Venting
6 Flushing
LP/HP Tubing
Air Instrument Tubing
Drain Venting
7 Electrical
Perapihan Kabel Kontrol
Perapihan Kabel Power
8 PreCommissioning
SAFE Setting (Parallel E/I Schedule)
Individual Testing
CCTV
FACP System
Pos System
Air Instrument System
HMI
9 Commissioning
Note :
1. PT. Zoomindo akan komit untuk menyediakan man power. Material dan peralatan sesuai target diatas
2. Anggaran untuk penyelesaian pekerjaan ini sekitar Rp. 5 Milyard dan tersedia secara liquid
3. Masalah Perijinan akan diselesaikan segera secara pararel
4. Commisioning ditargetkan tanggal 15 Mei 2016
24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
10 10 10 10 10 10
8 8 8 8 8 8 8
8 8 8 8 8 8
2 2 2 2 2
5 5 5 5 5 5 5 5 5
1 1
0.3 0.3
2 2 2 2
2 2 2 2
2 2
0.3 0.3
0.3 0.3
0.3 0.3
2 2 2 2
1 1 1
1 1 1
1
1
1
1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1
2 2 2 2
2 2 2 2
2 2 2 2 2 2 2 2 2 2
2 2 2 2 2 2 2 2
0.5 0.5 0.5
2 2 2 2
10 10
10 18 18 26 27 31 24 26 18 19 15 17 15 13 16 15 19 13 2.5 2 12 10
Month Apr-16
No. Description Day TU Wed Thu Fri Sat Sun Mon TU Wed Thu Fri Sat
Date 19 20 21 22 23 24 25 26 27 28 29 30
1 Pipeline 5 5 5 5 5 5
2 Pekerjaan sipil
Pagar, penimbunan tanah dan pengerasan jalan
Pagar 10 10 10 10 10 10 10 10
Penimbunan tanah dan pengerasan jalan 5 5
3 Pondasi main equipment
Pondasi equipment 10 10 10 10 10 10 10 10
Paving block
Pipe support 4 4
Platform 2 2 2
Pipe support area u-ditch 2 2 2 2 2 2
4 Pembuatan saluran air, pipa dan kabel
Saluran air keliling bangunan dan jalan keluar-masuk 5 5 5 5 5 5 5 5
Pengadaan dan pemasangan oil catcher dari bahan pe
Saluran untuk pipa, kabel listrik dan kabel data 3 3 3 3 3
Saluran untuk pipa dari storage ke dispenser 3 3 3 3 3
5 Rumah panel dan shelter
Rumah panel (trafo, panel peralatan, ups, instrument air compressor)
Shelter peralatan utama
Shelter untuk alat pemadam api beroda
6 Bangunan canopy dispenser
Struktur bangunan - ukuran 33.5 x 13,9 m - tinggi 6 m,
Pondasi bangunan 5
Arsitektur bangunan 1
Struktur bangunan
Arsitektur bangunan
Sanitary dan plumbing (air bersih & air kotor)
Furniture & peralatan kantor
Taman dan sumur resapan
Rambu-rambu dan safety sign
7 Pekerjaan mekanikal
Peralatan main equipment
Pemasangan gas scrubber
Pemasangan gas dryer
Pemasangan cng reciprocating compressor
Pemasangan cng ground storage
Pemasangan filling dispencer ngv
8 Pekerjaan piping
Pemasangan pipeline system
Pemasangan low pressure piping system
Pemasangan high pressure piping system
Pemasangan vent, drain & utility piping system
9 Pekerjaan elektrikal
Pemasangan sambungan daya, trafo, dan panel
Pemasangan lighting
Pemasangan lightning arrester & grounding system
Pemasangan rak kabel dan kabel tray
Pemasangan kabel power
10 Pekerjaan instrument
Custody metering
Check meter
Emergency shut down valve
Field instrument
Material, instalasi & accesories gas detector
Material, instalasi & accessories fire alarm system
Material, instalasi & accessories closed circuit television (cctv)
Utility
Point of sales (pos) system
Bulk material
Kabel
11 LP/HP
Persiapan
Survey Ulang
Pembelian Material Consumable
Construction
Pemasangan Support
Pemasangan Tubing
13 Drain/Venting
Persiapan
Survey Ulang
Pembelian Material Consumable
Construction
Pemasangan Support
Pemasangan Tubing
14 Hydro/Leak Test
LP/HP Tubing
Air Instrument Tubing
Drain Venting
15 Flushing
LP/HP Tubing
Air Instrument Tubing
Drain Venting
16 Electrical
Perapihan Kabel Kontrol
Perapihan Kabel Power
17 PreCommissioning
SAFE Setting (Parallel E/I Schedule)
Individual Testing
CCTV
FACP System
Pos System
Air Instrument System
HMI
18 Commissioning
Note :
1. PT. Zoomindo akan komit untuk menyediakan man power. Material dan peralatan sesuai target diatas
2. Anggaran untuk penyelesaian pekerjaan ini sekitar Rp.13 Milyard dan tersedia secara liquid
3. Masalah Perijinan akan diselesaikan segera secara pararel
4. Commisioning ditargetkan tanggal 27 Juni 2016
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9
5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
10
5 5 5 5
10 10
4 4 4 4 4 4 4
4 4 4 4 4 4
2 2 2 2
2 2
2 2 2 2 2
3 3 3
3 3 3
2 2 2 2 2 2 2 2
2 2 2 2 2 2 2 2 2 2
2 2 2 2 2 2 2 2 2 2
6 6 6 6 6 6 6 6 6 6 6 6 6
5 5 5 5 5 5
1 1 1 1 1 1 1 1 1
4 4 4 4 4 4 4 4 4 4 4
3 3 3 3 3 3 3 2 2 2 2
2 2 2 2 2 2 2 2 2
1 1 1 1 1 1 1 1 1 1 1
5 5 5 5 5 5 5
1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1
2 2 2 2 2 2 2
1 1 1 1 1 1
1 1 1 1 1 1 1
2 2 2 2 2 2 2 2
2 2 2 2 2 2 2 2
2 2 2 2 2 2 2 2 2 2
2 2 2 2 2 2 2 2 2 2
2 2 2 2 2 2 2 2
3 3 3 3 3 3 3
3 3 3 3 3 3
2 2 2 2 2 2 2 2
3 3 3 3 3 3 3 3
4 4 4 4 4 4 4 4
4 4 4 4 4 4 4 4 4 4
4 4 4 4 4 4 4 4 4
3 3 3 3 3 3 3 3
2 2 2 2 2 2 2
1 1 1 1 1 1 1
1 1 1 1
1 1 1 1
2 2 2
1 1
3 3
50 49 37 31 26 26 15 15 20 19 19 19 19 22 22 20 20 25 30 32 29 27 24 25 25 22 16 15 17 16 17 13 16 19 19 19 17 19 23 18
Rr. Listijo Retno W
Project Manager Paket 5 PT. Zoomindo Inti Perkasa
Jun-16
Fri Sat Sun Mon TU Wed Thu Fri Sat Sun Mon TU Wed Thu Fri Sat Sun Mon
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
4
3 3
2 2
1 1 1 1
1 1 1 1 1
1 1 1 1 1
2 2 2 2
1 1 1 1 1 1
3 3 3 3 3 3
0.5 0.5
0.5 0.5
2 2
2 2
0.5 0.5
0.5 0.5
1 1 1 1
1 1 1
1 1 1
1
1
1
1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1
4 4 4 4 4 4 4 4
2 2 2 2 2 2
2 2 2 2 2 2 2
2 2 2 2 2 2 2 2
2 2 2 2 2 2 2 2 2
10 10 10
18 14 13 15 14 10 10 14 15 16 15 13 11 13 6 10 10 10