You are on page 1of 3

DOUBLE FURRING 0.36 X 2.16 + 0.

07776 = 1
WALL ANGLE 0.26 X 2.16 + 0.05616 = 1
CARRYING CHANNEL 0.16 X 2.16 + 0.03456 = 1
W CLIP 1.44 X 2.16 + 0.31104 = 4
SUSPENSION CLIP 0.8 X 2.16 + 0.1728 = 2
STEEL ANGLE 0.8 X 2.16 + 0.1728 = 2
BLIND RIVETS 3 X 2.16 + 0.648 = 8
BOARDS 2.16 / 2.88 = 1

COST

DOUBLE FURRING 19mm x 50 mm x 5M 119.75 x 1 = 119.75


WALL ANGLE 10ft (3M) 37.75 x 1 = 37.75
CARRYING CHANNEL 12mm x 38 mm x 5M 134.75 x 1 = 134.75
W CLIP 4.75 x 4 = 19
SUSPENSION CLIP 14.75 x 2 = 29.5
STEEL ANGLE 7.75 x 2 = 15.5
BLIND RIVETS 1/8 x 1/2 (100 pcs) 94.75 x 1 = 94.75
BOARDS 1/2 4x8 780 x 1 = 780
total = 1231

wall partion

studs sapcing at 0.60m 9 x 139.75 = 1257.75 35mmx76mmx3M


tracks (top & bototm) 4 x 124.75 = 499 35mmx76mmx3M
rivets 1 x 94.75 = 94.75
boards 10 x 780 = 7800
total = 9651.5
AREA = 2.16
FACTOR2 = 0.07776
FACTOR3 = 0.05616
FACTOR4 = 0.03456
FACTOR5 = 0.31104
FACTOR6 = 0.1728
FACTOR7 = 0.1728
FACTOR8 = 0.648

board area 2.88 (4x8)


wall perimeter = 4.9 area 4.9 x
=
mmx76mmx3M 4.9 / 0.6 = 9 pcs
mmx76mmx3M 4.9 x 2 = 9.8 meter
9.8 / 3 = 4 pcs

rivet 9 x 8 = 72
boards 13.72 / 2.88 = 5 x2
= 10
2.8
13.72