RESUMEN DE VALORIZACION MENSUAL

VALORIZACIN N 02 - DICIEMBRE DEL 2011

OBRA : "MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE AGUA POTABLE Y ALCANTARILLADO DE LA CIUDAD DE RIOJA"
CONTRATO : CONTRATO Nro. 009 - 2011 - GRSM - PEAM - 01.00
ENTIDAD : GOBIERNO REGIONAL DE SAN MARTIN
MONTO DE OBRA : S/. 38,087,743.33
CONTRATISTA : CONSORCIO ALIANZA
SUPERVISION : CONSORCIO SUPERVISOR RIOJA
PLAZO DE EJECUCION : 540 DIAS CALENDARIO

VALORIZACION VALORIZACION
VALORIZACION
DESCRIPCION ACUMULADA ACUMULADA
ACTUAL
ANTERIOR ACTUAL

I.- VALORIZACION Y REAJUSTE S/. 415,331.88 S/. 280,371.00 S/. 695,702.88

Monto valorizado en el presente mes : S/. 403,030.65 S/. 280,371.00 S/. 683,401.65
. Valorizacin del Mes S/. 403,030.65 S/. 280,371.00 S/. 683,401.65

Reajuste de las valorizaciones : S/. 12,301.23 S/. 12,301.23


. Reajuste de la valorizacin No. 02 S/. 12,301.23 S/. 12,301.23

II.- AMORTIZACIONES, DEDUCCIONES Y OTROS S/. 234,821.67 S/. 56,074.20 S/. 290,895.87

Amortizaciones : S/. 234,821.67 S/. 56,074.20 S/. 290,895.87


. Del Adelanto en Efectivo S/. 80,606.13 S/. 56,074.20 S/. 136,680.33
. Del Adelanto de Materiales S/. 154,215.54 S/. - S/. 154,215.54

Deduccion del reajuste que no corresponde : S/. - S/. -


. Por Adelanto en Efectivo S/. - S/. -
. Por Adelanto de Materiales S/. -

Otros : S/. - S/. - S/. -


. Retencion por Retraso en la Obra S/. - S/. - S/. -
. Multas S/. - S/. - S/. -

III.- MONTO LIQUIDO A PAGAR ( I - II ) S/. 180,510.21 S/. 224,296.80 S/. 404,807.01

IV.- I.G.V. EXONERADO DEL PAGO S/. - S/. - S/. -

V.- MONTO EN EFECTIVO A CANCELAR AL CONTRATISTA S/. 180,510.21 S/. 224,296.80 S/. 404,807.01
VALORIZACION DE OBRA N 02
CORRESPONDIENTE AL MES DE DICIEMBRE DEL 2,011 (DEL 01/12/11 AL 31/12/11)

OBRA : "MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE AGUA POTABLE Y ALCANTARILLADO DE LA CIUDAD DE RIOJA"
CONTRATO : CONTRATO Nro. 009 - 2011 - GRSM - PEAM - 01.00
ENTIDAD : GOBIERNO REGIONAL DE SAN MARTIN
MONTO DE OBRA : S/. 38,087,743.33
CONTRATISTA : CONSORCIO ALIANZA FECHA DE INICIO : 13/11/2011
SUPERVISION : CONSORCIO SUPERVISOR RIOJA FECHA DE TERMINO : 05/05/2013
PLAZO DE EJECUCION : 540 DIAS CALENDARIO

RESUMEN DE AVANCE DE OBRA


Costo Valorizacin Acumulada Valorizacin Acumulada
Valorizacin del mes Saldo por Valorizar
Item Descripcin Parcial Anterior Actual
% Avance Monto (S/.) % Avance Monto (S/.) % Avance Monto (S/.) % Avance Monto (S/.)

MEJ. Y AMPL. DEL SISTEMA DE AGUA POTABLE Y


01
ALCANTARILLADO DE LA CIUDAD DE RIOJA
38,087,743.33 0.74% 280,371.00 1.06% 403,030.65 1.80% 683,401.65 98.20% 37,404,341.68

TOTAL 38,087,743.33 280,371.00 403,030.65 683,401.65 37,404,341.69


VALORIZACION DE OBRA N 02
CORRESPONDIENTE AL MES DE DICIEMBRE DEL 2,011 (DEL 01/12/11 AL 31/12/11)

OBRA : "MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE AGUA POTABLE Y ALCANTARILLADO DE LA CIUDAD DE RIOJA"
CONTRATO : CONTRATO Nro. 009 - 2011 - GRSM - PEAM - 01.00
ENTIDAD : GOBIERNO REGIONAL DE SAN MARTIN
MONTO DE OBRA : S/. 38,087,743.33
CONTRATISTA : CONSORCIO ALIANZA FECHA DE INICIO : 13/11/2011
SUPERVISION : CONSORCIO SUPERVISOR RIOJA FECHA DE TERMINO : 05/05/2013
PLAZO DE EJECUCIO : 540 DIAS CALENDARIO

CONTROL GENERAL DE AVANCE DE PROYECTO

MONTO PROGRAMADO MONTO REAL % AVANCE PROGRAMADO % AVANCE REAL SITUACION DE SITUACION DE
N PERIODO
PARCIAL ACUMULADO PARCIAL ACUMULADO PARCIAL ACUMULADO PARCIAL ACUMULADO OBRA POR MES OBRA TOTAL

1 Nov-11 57,307.34 57,307.34 280,371.00 280,371.00 0.15% 0.15% 0.74% 0.74% ADELANTADA ADELANTADA
2 Dec-11 209,603.07 266,910.41 403,030.65 683,401.65 0.55% 0.70% 1.06% 1.80% ADELANTADA ADELANTADA
3 Jan-12 400,029.87 666,940.28 1.05% 1.75%
4 Feb-12 381,041.52 1,047,981.80 1.00% 2.75%
5 Mar-12 476,229.46 1,524,211.26 1.25% 4.00%
6 Apr-12 571,407.34 2,095,618.60 1.50% 5.50%
7 May-12 1,332,890.61 3,428,509.21 3.50% 9.00%
8 Jun-12 1,904,489.57 5,332,998.78 5.00% 14.00%
9 Jul-12 3,046,975.03 8,379,973.81 8.00% 22.00%
10 Aug-12 3,427,889.43 11,807,863.24 9.00% 31.00%
11 Sep-12 4,189,681.03 15,997,544.27 11.00% 42.00%
12 Oct-12 5,332,224.40 21,329,768.67 14.00% 56.00%
13 Nov-12 4,189,588.97 25,519,357.64 11.00% 67.00%
14 Dec-12 3,428,029.13 28,947,386.77 9.00% 76.00%
15 Jan-13 3,046,925.02 31,994,311.79 8.00% 84.00%
16 Feb-13 2,475,672.90 34,469,984.69 6.50% 90.50%
17 Mar-13 1,904,575.06 36,374,559.75 5.00% 95.50%
18 Apr-13 1,355,828.27 37,730,388.02 3.56% 99.06%
19 May-13 357,355.31 38,087,743.33 0.94% 100.00%

38,087,743.33 683,401.65 100.00% 1.80% ADELANTADA


VALORIZACION DE OBRA N 02
CORRESPONDIENTE AL MES DE DICIEMBRE DEL 2,011 (DEL 01/12/11 AL 31/12/11)

OBRA : "MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE AGUA POTABLE Y ALCANTARILLADO DE LA CIUDAD DE RIOJA"
CONTRATO : CONTRATO Nro. 009 - 2011 - GRSM - PEAM - 01.00
ENTIDAD : GOBIERNO REGIONAL DE SAN MARTIN
MONTO DE OBRA : S/. 38,087,743.33
CONTRATISTA : CONSORCIO ALIANZA FECHA DE INICIO : 13/11/2011
SUPERVISION : CONSORCIO SUPERVISOR RIOJA FECHA DE TERMINO : 05/05/2013
PLAZO DE EJECUCION : 540 DIAS CALENDARIO

CURVA S DE AVANCE DE OBRA

100.00% 99.06% 100.00%


95.50%
90.00% 90.50%

84.00%
80.00%
76.00%

70.00%
67.00%

60.00%
56.00%

50.00%

42.00%
40.00%

30.00% 31.00%

AVANCE ACUMU. PROGRAMADO


22.00%
20.00%
AVANCE ACUMU. EJECUTADO
14.00%
10.00% 9.00%
1.80% 4.00% 5.50%
0.74% 2.75%
0.70% 1.75%
0.00% 0.00% 0.15%
Inicio 40848 40878 40909 40940 40969 41000 41030 41061 41091 41122 41153 41183 41214 41244 41275 41306 41334 41365 41395

Inicio Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13

TOTAL PROGRAMADO S/IGV 57,307.34 209,603.07 400,029.87 381,041.52 476,229.46 571,407.34 1,332,890.61 1,904,489.57 3,046,975.03 3,427,889.43 4,189,681.03 5,332,224.40 4,189,588.97 3,428,029.13 3,046,925.02 2,475,672.90 1,904,575.06 1,355,828.27 357,355.31
AVAN. MENS. PROGRAMADO 0.15% 0.55% 1.05% 1.00% 1.25% 1.50% 3.50% 5.00% 8.00% 9.00% 11.00% 14.00% 11.00% 9.00% 8.00% 6.50% 5.00% 3.56% 0.94%
AVAN. ACUM. PROG. 0.00% 0.15% 0.70% 1.75% 2.75% 4.00% 5.50% 9.00% 14.00% 22.00% 31.00% 42.00% 56.00% 67.00% 76.00% 84.00% 90.50% 95.50% 99.06% 100.00%

TOTAL VALORIZADO S/IGV 280,371.00 403,030.65


AVANCE MENSUAL VALORIZ. 0.74% 1.06%
AVANCE ACUM. VAL. 0.00% 0.74% 1.80%
VALORIZACION DE OBRA N 02
CORRESPONDIENTE AL MES DE DICIEMBRE DEL 2,011 (DEL 01/12/11 AL 31/12/11)

OBRA : "MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE AGUA POTABLE Y ALCANTARILLADO DE LA CIUDAD DE RIOJA"
CONTRATO : CONTRATO Nro. 009 - 2011 - GRSM - PEAM - 01.00
ENTIDAD : GOBIERNO REGIONAL DE SAN MARTIN
MONTO DE OBRA : S/. 38,087,743.33
CONTRATISTA : CONSORCIO ALIANZA
SUPERVISION : CONSORCIO SUPERVISOR RIOJA FECHA DE INICIO
PLAZO DE EJECUCION : 540 DIAS CALENDARIO FECHA DE TERMINO

RESUMEN DE SUB PRESUPUESTOS

ITEM DESCRIPCION PARCIALES

MEJ. Y AMPL. DEL SISTEMA DE AGUA POTABLE Y ALCANTARILLADO DE LA CIUDAD DE RIOJA

01 OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES PARA TODA LA OBRA 76,039.20

02 CAPTACION PROYECTADA RIO NEGRO CAP-01 0.00

03 LINEA DE IMPULSION PROYECTADA LI-01 17,842.68

04 LINEA DE CONDUCCION PROYECTADA RIO NEGRO LC-01 0.00

05 MEJORAMIENTO DE RESERVORIO EXISTENTE RAE-01 VOL=1,000M3 0.00

06 RESERVORIO APOYADO PROYECTADO RIO NEGRO RAP-01 VOL=1,200M3 0.00

07 CISTERNA PROYECTADA RIO NEGRO CIP-01 VOL=500m3 0.00

08 LINEA DE ADUCCION EXISTENTE LA-01 0.00

09 REDES DE DISTRIBUCION 72,378.42

10 CONEXIONES DOMICILIARIAS DE AGUA POTABLE 0.00

11 MICROMEDICION 0.00

12 REDES DE ALCANTARILLADO 172,420.92

13 CONEXIONES DOMICILIARIAS DE ALCANTARILLADO 0.00

14 EMISORES 0.00

15 CAMARA DE BOMBEO DE DESAGUE PROYECTADA CBD-01 0.00

16 PLANTA DE TRATAMIENTO DE AGUAS RESIDUALES 0.00

17 MITIGACION DE IMPACTO AMBIENTAL 0.00

18 MEDIA TENSION - BOMBEO DE AGUA POTABLE 0.00

19 MEDIA TENSION - CAMARA DE BOMBEO DE DESAGES 0.00

COSTO DIRECTO 338,681.22


GASTOS GENERALES (16.60%) 56,221.08
UTILIDAD (2.40%) 8,128.35
TOTAL 403,030.65
L 31/12/11)

CIUDAD DE RIOJA"

A DE INICIO : 13/11/2011
A DE TERMINO : 05/05/2013
AMORTIZACIN Y DEDUCCIN DEL ADELANTO DE MATERIALES N 01

OBRA : "MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE AGUA POTABLE Y ALCANTARILLADO DE LA CIUDAD DE RIOJA"
CONTRATO : CONTRATO Nro. 009 - 2011 - GRSM - PEAM - 01.00
ENTIDAD : GOBIERNO REGIONAL DE SAN MARTIN
MONTO DE OBRA : S/. 38,087,743.33
CONTRATISTA : CONSORCIO ALIANZA FECHA DE INICI : 13/11/2011
SUPERVISION : CONSORCIO SUPERVISOR RIOJA FECHA DE TER : 05/05/2013
PLAZO DE EJECUCION : 540 DIAS CALENDARIO

IU 71 7,283,875.69 Incidencia 0.262


Material TUBERA DE HIERRO FUNDIDO % 8.779%
Adelanto N 01 434,986.65 Io 515.66
Fecha Pago Dic. 2011 Ia 510.12
Monto Deflatado 439,710.69

ADELANTO Incidencia Io Ia Reajuste Monto Monto Adelanto


Valorizacin N IU A Deduccin Amortizacin
N Coef . % Mar-11 Nov-11 Mes Ir Valorizado Adelanto Utilizado
01 Nov.2011 71 0.262 8.779% 515.66 510.12 Nov.2011 510.12 280,371.00 439,710.69
01 Dic.2011 71 0.262 8.779% 515.66 510.12 Dic.2011 510.12 403,030.65 439,710.69 9,270.10 9,270.10 - 9,170.51

Sub total 0.00 9,170.51

IU 72 Incidencia 0.262
Material TUBERA DE PVC % 91.221%
Adelanto N 01 4,607,347.73 Io 342.38
Fecha Pago Dic. 2011 Ia 348.06
Monto Deflatado 4,532,160.31

ADELANTO Incidencia Io Ia Reajuste Monto Saldo Monto


Valorizacin N IU A Deduccin Amortizacin
N Coef . % Mar-11 Nov-11 Mes Ir Valorizado Adelanto Adelanto
01 Nov.2011 71 0.262 91.221% 342.38 348.06 Nov.2011 348.06 280,371.00 4,532,160.31
01 Dic.2011 71 0.262 91.221% 342.38 348.06 Dic.2011 348.06 403,030.65 4,532,160.31 96,323.93 96,323.93 - 97,921.92

Sub total 0.00 97,921.92

IU 30 Incidencia 0.062
Material DLAR % 32.258%
Adelanto N 01 383,745.84 Io 358.42
Fecha Pago Dic. 2011 Ia 356.94
Monto Deflatado 385,336.99

ADELANTO Incidencia Io Ia Reajuste Monto Saldo Monto


Valorizacin N IU A Deduccin Amortizacin
N Coef . % Mar-11 Nov-11 Mes Ir Valorizado Adelanto Adelanto
01 Nov.2011 71 0.062 32.258% 358.42 356.94 Nov.2011 356.94 280,371.00 385,336.99
01 Dic.2011 71 0.062 32.258% 358.42 356.94 Dic.2011 356.94 403,030.65 385,336.99 8,060.60 8,060.60 - 8,027.32

Sub total 0.00 8,027.32


AMORTIZACIN Y DEDUCCIN DEL ADELANTO DE MATERIALES N 01

OBRA : "MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE AGUA POTABLE Y ALCANTARILLADO DE LA CIUDAD DE RIOJA"
CONTRATO : CONTRATO Nro. 009 - 2011 - GRSM - PEAM - 01.00
ENTIDAD : GOBIERNO REGIONAL DE SAN MARTIN
MONTO DE OBRA : S/. 38,087,743.33
CONTRATISTA : CONSORCIO ALIANZA FECHA DE INICI : 13/11/2011
SUPERVISION : CONSORCIO SUPERVISOR RIOJA FECHA DE TER : 05/05/2013
PLAZO DE EJECUCION : 540 DIAS CALENDARIO

IU 21 Incidencia 0.098
Material CEMENTO PORTLAND TIPO I % 37.755%
Adelanto N 01 704,621.35 Io 415.90
Fecha Pago Dic. 2011 Ia 415.90
Monto Deflatado 704,621.35

ADELANTO Incidencia Io Ia Reajuste Monto Saldo Monto


Valorizacin N IU Coef . % A Deduccin Amortizacin
N Mar-11 Nov-11 Mes Ir Valorizado Adelanto Adelanto
01 Nov.2011 71 0.098 37.755% 415.90 415.90 Nov.2011 415.90 280,371.00 704,621.35
01 Dic.2011 71 0.098 37.755% 415.90 415.90 Dic.2011 415.90 403,030.65 704,621.35 14,912.09 14,912.09 - 14,912.09

Sub total 0.00 14,912.09

IU 03 Incidencia 0.098
Material ACERO DE CONSTRUCCION CORRUGADO % 31.633%
Adelanto N 01 543,151.41 Io 580.80
Fecha Pago Dic. 2011 Ia 529.27
Monto Deflatado 596,032.91

ADELANTO Incidencia Io Ia Reajuste Monto Saldo Monto


Valorizacin N IU A Deduccin Amortizacin
N Coef . % Mar-11 Nov-11 Mes Ir Valorizado Adelanto Adelanto
01 Nov.2011 71 0.098 31.633% 580.80 529.27 Nov.2011 529.27 280,371.00 596,032.91
01 Dic.2011 71 0.098 31.633% 580.80 529.27 Dic.2011 529.27 403,030.65 596,032.91 12,494.09 12,494.09 - 11,385.58

Sub total 0.00 11,385.58

IU 04 Incidencia 0.098
Material AGREGADO FINO % 30.612%
Adelanto N 01 610,022.71 Io 438.47
Fecha Pago Dic. 2011 Ia 464.12
Monto Deflatado 576,309.27

ADELANTO Incidencia Io Ia Reajuste Monto Saldo Monto


Valorizacin N IU A Deduccin Amortizacin
N Coef . % Mar-11 Nov-11 Mes Ir Valorizado Adelanto Adelanto
01 Nov.2011 71 0.098 30.612% 438.47 464.12 Nov.2011 464.12 280,371.00 576,309.27
01 Dic.2011 71 0.098 30.612% 438.47 464.12 Dic.2011 464.12 403,030.65 576,309.27 12,090.82 12,090.82 - 12,798.12

Sub total 0.00 12,798.12


RESUMEN ADELANTO DE MATERIALES N 01
AMORTIZACIN Y DEDUCCIN DEL ADELANTO DE MATERIALES N 01

OBRA : "MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE AGUA POTABLE Y ALCANTARILLADO DE LA CIUDAD DE RIOJA"
CONTRATO : CONTRATO Nro. 009 - 2011 - GRSM - PEAM - 01.00
ENTIDAD : GOBIERNO REGIONAL DE SAN MARTIN
MONTO DE OBRA : S/. 38,087,743.33
CONTRATISTA : CONSORCIO ALIANZA FECHA DE INICI : 13/11/2011
SUPERVISION : CONSORCIO SUPERVISOR RIOJA FECHA DE TER : 05/05/2013
PLAZO DE EJECUCION : 540 DIAS CALENDARIO

FOR Deduccin Amortizacin

01 - 154,215.54

SUB TOTAL - 154,215.54

CUADRO RESUMEN
DESCRIPCIN DEDUCCIN AMORTIZACIN

MONTO ACUMULADO ACTUAL - 154,215.54


MONTO ACUMULADO ANTERIOR 0.00 0.00
MONTO DEL MES - 154,215.54
VALORIZACION DE OBRA N 02
CORRESPONDIENTE AL MES DE DICIEMBRE DEL 2,011 (DEL 01/12/11 AL 31/12/11)

OBRA : "MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE AGUA POTABLE Y ALCANTARILLADO DE LA CIUDAD DE RIOJA"
CONTRATO : CONTRATO Nro. 009 - 2011 - GRSM - PEAM - 01.00
ENTIDAD : GOBIERNO REGIONAL DE SAN MARTIN
MONTO DE OBRA : S/. 38,087,743.33
CONTRATISTA : CONSORCIO ALIANZA
SUPERVISION : CONSORCIO SUPERVISOR RIOJA
PLAZO DE EJECUCIO : 540 DIAS CALENDARIO

MONTO CONTRACTUAL S/. 38,087,743.33


ADELANTO A OTORGAR S/. 7,617,548.66
FECHA DE ADELANTO Nov-11
% RELACION DEL ADELANTO 20.00%

CUADRO DE AMORTIZACION DEL ADELANTO EN EFECTIVO

AMORTIZACION
VALORIZAC.
ADELANTO OTORGADO
VALORIZACION MES AMORTIZACION SALDO POR AMORTIZ.
( Noviembre del 2011 )
( Sin / IGV ).
Amort=VB * 20.000% (SIN I.G.V)

ADELANTO DIRECTO AL (20.00 %)


7,617,548.66 VALOR. N 01 noviembre-11 S/. 280,371.00 S/. 56,074.20 S/. 7,561,474.46
VALOR. N 02 diciembre-11 S/. 403,030.65 S/. 80,606.13 S/. 7,480,868.33
VALOR. N 03 enero-12 S/. - S/. 7,480,868.33
VALOR. N 04 febrero-12 S/. - S/. 7,480,868.33

TOTAL S/. 136,680.33 S/. 7,480,868.33

AMORTIZACIN ACUMULADO ACTUAL S/. 136,680.33


AMORTIZACIN ACUMULADA ANTERIOR S/. 56,074.20
AMORTIZACIN DEL MES S/. 80,606.13
VALORIZACION DE OBRA N 02
CORRESPONDIENTE AL MES DE DICIEMBRE DEL 2,011 (DEL 01/12/11 AL 31/12/11)

CONTRATO : CONTRATO Nro. 009 - 2011 - GRSM - PEAM - 01.00 CONTRATISTA : CONSORCIO ALIANZA
OBRA : "MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE AGUA POTABLE Y ALCANTARILLADO DE LA CIUDAD DE RIOJA" SUPERVISION : CONSORCIO SUPERVISOR RIOJA
ENTIDAD : GOBIERNO REGIONAL DE SAN MARTIN PLAZO DE EJEC. : 540 DIAS CALENDARIO
MONTO DE OBRA : S/. 38,087,743.33 PRECIOS : Marzo 2011

CALCULO DE K ADELANTO DIRECTO AL 20.00% MES DE NOVIEMBRE DEL 2011

K1 = 0.230*(Jr / Jo) + 0.262*(TTr / TTo) + 0.137*(Mr / Mo) + 0.062*(FDr / FDo) + 0.098*(CAAr / CAAo) + 0.211*(GGUr / GGUo)

INCIDENCIA Nov-11
SIMBOLO IU DESCRIPCIN COEFICIENTE
ESPECFICA Ir - Nov 11 COEFIC.

J 47 MANO DE OBRA 0.230 100.000% 448.29 0.241

71 TUBERIA DE FIERRO FUNDIDO 8.779% 510.12


0.262 0.265
TT 72 TUBERIA DE PVC 91.221% 348.06

M 48 MAQUINARIA Y EQUIPO NACIONAL 0.137 100.000% 329.40 0.136

30 DLAR 32.258% 356.94


0.062 0.063
FD 32 FLETE TERRESTRE 67.742% 431.91

CAA 21 CEMENTO PORTALAND TIPO I 37.755% 415.90


0.098
03 ACERO DE CONSTRUCCION CORRUGADO 31.633% 529.27 0.096
04 AGREGADO FINO 30.612% 464.12

GGU 39 INDICE GENERAL DE PRECIO AL CONSUMIDOR 0.211 100.000% 370.47 0.217

COEFICIENTE DE REAJUSTE K - Nov 1.018


VALORIZACION DE OBRA N 02
CORRESPONDIENTE AL MES DE DICIEMBRE DEL 2,011 (DEL 01/12/11 AL 31/12/11)

CONTRATO : CONTRATO Nro. 009 - 2011 - GRSM - PEAM - 01.00 CONTRATISTA : CONSORCIO ALIANZA
OBRA : "MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE AGUA POTABLE Y ALCANTARILLADO DE LA CIUDAD DE RIOJA" SUPERVISION : CONSORCIO SUPERVISOR RIOJA
ENTIDAD : GOBIERNO REGIONAL DE SAN MARTIN PLAZO DE EJEC. : 540 DIAS CALENDARIO
MONTO DE OBRA : S/. 38,087,743.33 PRECIOS : Marzo 2011

CALCULO DEL K DE REAJUSTE

K1 = 0.230*(Jr / Jo) + 0.262*(TTr / TTo) + 0.137*(Mr / Mo) + 0.062*(FDr / FDo) + 0.098*(CAAr / CAAo) + 0.211*(GGUr / GGUo)

INCIDENCIA BASE Nov-11


SIMBOLO IU DESCRIPCIN COEFICIENTE
ESPECFICA Io - Mar 11 COEFIC. Ir - Nov 11 COEFIC.

J 47 MANO DE OBRA 0.230 100.000% 427.68 0.230 448.29 0.241

71 TUBERIA DE FIERRO FUNDIDO 8.779% 515.66 510.12


0.262 0.262 0.265
TT 72 TUBERIA DE PVC 91.221% 342.38 348.06

M 48 MAQUINARIA Y EQUIPO NACIONAL 0.137 100.000% 332.16 0.137 329.40 0.136

30 DLAR 32.258% 358.42 356.94


0.062 0.062 0.063
FD 32 FLETE TERRESTRE 67.742% 423.94 431.91

CAA 21 CEMENTO PORTALAND TIPO I 37.755% 415.90 415.90


0.098
03 ACERO DE CONSTRUCCION CORRUGADO 31.633% 580.80 0.098 529.27 0.096
04 AGREGADO FINO 30.612% 438.47 464.12

GGU 39 INDICE GENERAL DE PRECIO AL CONSUMIDOR 0.211 100.000% 359.92 0.211 370.47 0.217

COEFICIENTE DE REAJUSTE K - Mar 1.000 K - Nov 1.018


VALORIZACION DE OBRA N 02
CORRESPONDIENTE AL MES DE DICIEMBRE DEL 2,011 (DEL 01/12/11 AL 31/12/11)

CONTRATO : CONTRATO Nro. 009 - 2011 - GRSM - PEAM - 01.00 CONTRATISTA : CONSORCIO ALIANZA
OBRA : "MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE AGUA POTABLE Y ALCANTARILLADO DE LA CIUDAD DE RIOJA" SUPERVISION : CONSORCIO SUPERVISOR RIOJA
ENTIDAD : GOBIERNO REGIONAL DE SAN MARTIN PLAZO DE EJEC. : 540 DIAS CALENDARIO
MONTO DE OBRA : S/. 38,087,743.33 PRECIOS : Marzo 2011

CLCULO DE REINTEGRO
Monto Mensual Monto Acumulado Mes de Reajuste
Val Kr
Real Programado Real Programado Reajuste Real Programado Reconocido

November-11 S/. 280,371.00 S/. 57,307.34 S/. 280,371.00 S/. 57,307.34 Nov-11 1.018 S/. 5,046.68 S/. 1,031.53 S/. 5,046.68
December-11 S/. 403,030.65 S/. 209,603.07 S/. 683,401.65 S/. 266,910.41 Nov-11 1.018 S/. 7,254.55 S/. 3,772.86 S/. 7,254.55
January-12 S/. 400,029.87 S/. 666,940.28 S/. - S/. -
February-12 S/. 381,041.52 S/. 1,047,981.80 S/. - S/. -
March-12 S/. 476,229.46 S/. 1,524,211.26 S/. - S/. -
April-12 S/. 571,407.34 S/. 2,095,618.60 S/. - S/. -
May-12 S/. 1,332,890.61 S/. 3,428,509.21 S/. - S/. -
June-12 S/. 1,904,489.57 S/. 5,332,998.78 S/. - S/. -
July-12 S/. 3,046,975.03 S/. 8,379,973.81 S/. - S/. -
August-12 S/. 3,427,889.43 S/. 11,807,863.24 S/. - S/. -
September-12 S/. 4,189,681.03 S/. 15,997,544.27 S/. - S/. -
October-12 S/. 5,332,224.40 S/. 21,329,768.67 S/. - S/. -
November-12 S/. 4,189,588.97 S/. 25,519,357.64 S/. - S/. -
December-12 S/. 3,428,029.13 S/. 6,856,538.34 S/. - S/. -
January-13 S/. 3,046,925.02 S/. 9,903,463.36 S/. - S/. -
February-13 S/. 2,475,672.90 S/. 12,379,136.26 S/. - S/. -
March-13 S/. 1,904,575.06 S/. 14,283,711.32 S/. - S/. -
April-13 S/. 1,355,828.27 S/. 2,880,039.53 S/. - S/. -
May-13 S/. 357,355.31 S/. 2,452,973.91 S/. - S/. -

TOTAL S/. 683,401.65 S/. 38,087,743.33 S/. 12,301.23 S/. 4,804.39 S/. 12,301.23

RESUMEN

Descripcion Total
Reajuste Total 12,301.23
Reajuste pagado hasta el mes Anterior 0.00
Reajuste Reconocido 12,301.23
REAJUSTE DEL MES 12,301.23
VALORIZACION DE OBRA N 02
CORRESPONDIENTE AL MES DE DICIEMBRE DEL 2,011 (DEL 01/12/11 AL 31/12/11)

CONTRATO : CONTRATO Nro. 009 - 2011 - GRSM - PEAM - 01.00 CONTRATISTA : CONSORCIO ALIANZA
OBRA : "MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE AGUA POTABLE Y ALCANTARILLADO DE LA CIUDAD DE RIOJA" SUPERVISION : CONSORCIO SUPERVISOR RIOJA
ENTIDAD : GOBIERNO REGIONAL DE SAN MARTIN PLAZO DE EJEC. : 540 DIAS CALENDARIO
MONTO DE OBRA : S/. 38,087,743.33 Sin IGV Nuevos Soles PRECIOS : Marzo 2011

(K) COEF. DE REAJUSTE DE LA VALORIZACIN MES ADELANTO NOVIEMBRE DEL 2011


(Ka) COEF. DE REAJUSTE DEL MES EN QUE SE OTORG EL A.D. ADELANTO DIRECTO AL 20.00%

DEDUCCION = AMORTIZACION x (K-Ka)/Ka

CUADRO DE DEDUCCION DEL REINTEGRO QUE NO CORRESPONDE POR ADELANTO EN EFECTIVO N 01

PROGRAMADO EJECUTADO
VALORIZACION AMORTIZACION ADELANTO VALORIZACION AMORTIZACION ADELANTO
MES VAL No PROGRAMADA DEL DIRECTO DEDUCCION EJECUTADA DEL DIRECTO DEDUCCION
ADELANTO POR FORMULA Kr Ka PROGRAMADA ADELANTO POR FORMULA Kr Ka EFECTIVA
(V) (A) (C) (V) (A) (C)

November-11 01 S/. 57,307.34 S/. 11,461.47 S/. 7,617,548.66 1.018 1.018 S/. - S/. 280,371.00 S/. 56,074.20 S/. 7,617,548.66 1.018 1.018 S/. -
December-11 02 S/. 209,603.07 S/. 41,920.61 1.018 S/. 403,030.65 S/. 80,606.13 1.018 1.018 S/. -
January-12 03 S/. 400,029.87 S/. 80,005.97 1.018 S/. - 1.018
February-12 04 S/. 381,041.52 S/. 76,208.30 1.018 S/. - 1.018
March-12 05 S/. 476,229.46 S/. 95,245.89 1.018 S/. - 1.018
April-12 06 S/. 571,407.34 S/. 114,281.47 1.018 S/. - 1.018
May-12 07 S/. 1,332,890.61 S/. 266,578.12 1.018 S/. - 1.018
June-12 08 S/. 1,904,489.57 S/. 380,897.91 1.018 S/. - 1.018
July-12 09 S/. 3,046,975.03 S/. 609,395.01 1.018 S/. - 1.018
August-12 10 S/. 3,427,889.43 S/. 685,577.89 1.018 S/. - 1.018
September-12 11 S/. 4,189,681.03 S/. 837,936.21 1.018 S/. - 1.018
October-12 12 S/. 5,332,224.40 S/. 1,066,444.88 1.018 S/. - 1.018
November-12 13 S/. 4,189,588.97 S/. 837,917.79 1.018 S/. - 1.018
December-12 14 S/. 3,428,029.13 S/. 685,605.83 1.018 S/. - 1.018
January-13 15 S/. 3,046,925.02 S/. 609,385.00 1.018 S/. - 1.018
February-13 16 S/. 2,475,672.90 S/. 495,134.58 1.018 S/. - 1.018
March-13 17 S/. 1,904,575.06 S/. 380,915.01 1.018 S/. - 1.018
April-13 18 S/. 1,355,828.27 S/. 271,165.65 1.018 S/. - 1.018
May-13 19 S/. 357,355.31 S/. 71,471.06 1.018 S/. - 1.018 S/. -
S/. -

TOTALES S/. 38,087,743.33 S/. 7,617,548.66 S/. - S/. 683,401.65 S/. 136,680.33 S/. 0.00
OBRA : MEJORAMIENTO Y AMPLIACIN DEL SISTEMA DE AGUA POTABLE Y ALCANTARILLADO DE LA CIUDAD DE RIOJA, PROVINCIA DE RIOJA - SAN MARTIN
CONTRATO : CONTRATO
: GOBIERNO
Nro.
REGIONAL
009 - 2011DE
- GRSM
SAN MARTIN
- PEAM - 01.00
ENTIDAD : GOBIERNO REGIONAL DE SAN MARTIN
CONTRATISTA : CONSORCIO ALIANZA
SUPERVISION

VALORIZACION DE OBRA N 02
CORRESPONDIENTE AL MES DE DICIEMBRE DEL 2,011 (DEL 01/12/11 AL 31/12/11)

Presupuesto : S/. 38087743.33 Nuevos Soles, Exonerado del IGV

PRESUPUESTO ACUMULADO ANTERIOR PRESENTE VALORIZACION ACUMULADO ACTUAL SALDO POR VALORIZAR
Item Descripcin Und. P. U. Parcial Parcial Parcial Parcial Parcial
Metrado % Metrado % Metrado % Metrado % Metrado %
S/. S/. S/. S/. S/. S/.

01 OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES PARA TODA LA OBRA 981,899.00 3.07% 122,873.64 0.38% 76,039.20 0.24% 198,912.83 0.62% Err:502 Err:502
01.01 OBRAS PROVISIONALES
01.01.01 CAMPAMENTO PROVISIONAL DE OBRA GLB 1.00 6,300.00 6,300.00 100.00% 0.90 5,670.00 90.00% 0.00 0.00% 0.90 5,670.00 90.00% Err:502 Err:502 Err:502
01.01.02 CASETA ADICIONAL P/GUARDIANIA Y/O DEPOSITO UND 1.00 10,000.00 10,000.00 100.00% 1.00 10,000.00 100.00% 0.00 0.00% 1.00 10,000.00 100.00% Err:502 Err:502 Err:502
01.01.03 CARTEL DE IDENTIFICACION DE OBRA UND 1.00 1,517.07 1,517.07 100.00% 1.00 1,517.07 100.00% 0.00 0.00% 1.00 1,517.07 100.00% Err:502 Err:502 Err:502
01.02 TRABAJOS PRELIMINARES
01.02.01 MOVILIZACION DE EQUIPO GLB 1.00 92,783.68 92,783.68 100.00% 0.20 18,556.74 20.00% 0.35 32,474.29 35.00% 0.55 51,031.02 55.00% Err:502 Err:502 Err:502
01.02.02 TRANSPORTE DE MATERIALES DESDE LIMA A OBRA GLB 1.00 871,298.25 871,298.25 100.00% 0.10 87,129.83 10.00% 0.05 43,564.91 5.00% 0.15 130,694.74 15.00% Err:502 Err:502 Err:502
03 LINEA DE IMPULSION PROYECTADA LI-01 61,279.00 0.19% 0.00 0.00% 17,842.68 0.06% 17,842.68 0.06% Err:502 Err:502
03.03 SUMINISTRO E INSTALACION DE TUBERIAS PVC-UF ISO 4422
03.03.01 TUBERIA PVC-UF NTP ISO 4422 C-7.5 DN 350 incluye anillo + 2% de desperdicios. M 306.00 110.14 33,702.84 100.00% 0.00 0.00% 162.00 17,842.68 53.00% 162.00 17,842.68 53.00% Err:502 Err:502 Err:502
03.03.02 INSTALACION DE TUB. PVC-UF P/AGUA POTABLE DN 315 - 350 M 306.00 5.41 1,655.46 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
09 REDES DE DISTRIBUCION 3,493,845.00 10.92% 0.00 0.00% 72,378.42 0.23% 72,378.42 0.23% Err:502 Err:502
09.01 RENOVACION DE REDES DE DISTRIBUCION
09.01.03 SUMINISTRO E INSTALACION DE TUBERIAS PVC-UF ISO 4422
09.01.03.01 TUBERIA PVC-UF NTP ISO 4422 C-7.5 DN 63 incluye anillo + 2% de desperdicios. M 50.65 3.68 186.39 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
09.01.03.02 TUBERIA PVC-UF NTP ISO 4422 C-7.5 DN 90 incluye anillo + 2% de desperdicios. M 2,536.95 7.48 18,976.39 100.00% 0.00 0.00% 2,226.00 16,650.48 88.00% 2,226.00 16,650.48 88.00% Err:502 Err:502 Err:502
09.01.03.03 TUBERIA PVC-UF NTP ISO 4422 C-7.5 DN 110 incluye anillo + 2% de desperdicios. M 14,243.50 11.02 156,963.37 100.00% 0.00 0.00% 2,490.00 27,439.80 17.00% 2,490.00 27,439.80 17.00% Err:502 Err:502 Err:502
09.01.03.04 TUBERIA PVC-UF NTP ISO 4422 C-7.5 DN 160 incluye anillo + 2% de desperdicios. M 2,959.45 22.98 68,008.16 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
09.01.03.05 TUBERIA PVC-UF NTP ISO 4422 C-7.5 DN 200 incluye anillo + 2% de desperdicios. M 1,160.30 35.99 41,759.20 100.00% 0.00 0.00% 786.00 28,288.14 68.00% 786.00 28,288.14 68.00% Err:502 Err:502 Err:502
09.01.03.06 TUBERIA PVC-UF NTP ISO 4422 C-7.5 DN 250 incluye anillo + 2% de desperdicios. M 726.62 56.17 40,814.25 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
09.01.03.07 TUBERIA PVC-UF NTP ISO 4422 C-7.5 DN 315 incluye anillo + 2% de desperdicios. M 1,277.15 86.50 110,473.48 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
09.01.03.08 INSTALACION DE TUB. PVC-UF P/AGUA POTABLE DN 63 - 90 M 2,587.60 0.43 1,112.67 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
09.01.03.09 INSTALACION DE TUB. PVC-UF P/AGUA POTABLE DN 110 - 160 M 17,202.95 0.90 15,482.66 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
09.01.03.10 INSTALACION DE TUB. PVC-UF P/AGUA POTABLE DN 200 - 250 M 1,886.92 2.52 4,755.04 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
09.01.03.11 INSTALACION DE TUB. PVC-UF P/AGUA POTABLE DN 315 - 350 M 1,277.15 5.41 6,909.38 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
12 REDES DE ALCANTARILLADO 7,648,665.00 23.90% 112,732.24 0.35% 172,420.92 0.54% 285,153.16 0.89% Err:502 Err:502
12.01 REDES DE ALCANTARILLADO - PROYECTADAS
12.01.01 TRABAJOS PRELIMINARES
12.01.01.01 TRAZO Y REPLANTEO INICIALES DEL PROYECTO M 50,313.09 1.49 74,966.50 100.00% 21,635.06 32,236.24 43.00% 18,544.35 27,631.08 37.00% 40,179.41 59,867.32 80.00% Err:502 Err:502 Err:502
12.01.01.02 PROTECCION DE CONEXIONES DOMICILIARIAS DE AGUA POTABLE UND 120.00 13.02 1,562.40 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
TRAZO Y REPLANTEO FINALES DE OBRA
12.01.01.03 M 50,313.09 1.07 53,835.01 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
12.01.02 MOVIMIENTO DE TIERRAS
12.01.02.01 EXCAV. ZANJA (MAQ.) P/TUB. T-NORMAL DN 200 - 250 de 0.60m a 1.00m PROF. M 221.06 7.27 1,607.11 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
12.01.02.02 EXCAV. ZANJA (MAQ.) P/TUB. T-NORMAL DN 200 - 250 de 1.00m a 1.50m PROF. M 21,116.33 12.13 256,141.08 100.00% 0.00 0.00% 219.24 2,659.38 1.00% 219.24 2,659.38 1.00% Err:502 Err:502 Err:502
12.01.02.03 EXCAV. ZANJA (MAQ.) P/TUB. T-NORMAL DN 200 - 250 de 1.51m a 2.00m PROF. M 8,670.25 14.55 126,152.14 100.00% 0.00 0.00% 58.12 845.65 1.00% 58.12 845.65 1.00% Err:502 Err:502 Err:502
12.01.02.04 EXCAV. ZANJA (MAQ.) P/TUB. T-NORMAL DN 200 - 250 de 2.01m a 2.50m PROF. M 5,584.81 18.19 101,587.69 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
12.01.02.05 EXCAV. ZANJA (MAQ.) P/TUB. T-NORMAL DN 200 - 250 de 2.51m a 3.00m PROF. M 2,428.67 24.27 58,943.82 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
12.01.02.06 EXCAV. ZANJA (MAQ.) P/TUB. T-NORMAL DN 200 - 250 de 3.01m a 3.50m PROF. M 2,577.98 25.06 64,604.18 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
12.01.02.07 EXCAV. ZANJA (MAQ.) P/TUB. T-NORMAL DN 200 - 250 de 3.51m a 4.00m PROF. M 2,108.27 38.76 81,716.55 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
12.01.02.08 EXCAV. ZANJA (MAQ.) P/TUB. T-NORMAL DN 200 - 250 de 4.01m a 5.00m PROF. M 2,133.81 53.28 113,689.40 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
12.01.02.09 EXCAV. ZANJA (MAQ.) P/TUB. T-NORMAL DN 315 - 350 de 1.51m a 2.00m PROF. M 286.95 14.55 4,175.12 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
12.01.02.10 EXCAV. ZANJA (MAQ.) P/TUB. T-NORMAL DN 315 - 350 de 2.01m a 2.50m PROF. M 451.95 18.19 8,220.97 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
12.01.02.11 EXCAV. ZANJA (MAQ.) P/TUB. T-NORMAL DN 315 - 350 de 2.51m a 3.00m PROF. M 490.93 24.27 11,914.87 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
12.01.02.12 EXCAV. ZANJA (MAQ.) P/TUB. T-NORMAL DN 315 - 350 de 3.01m a 3.50m PROF. M 350.30 25.06 8,778.52 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
12.01.02.13 EXCAV. ZANJA (MAQ.) P/TUB. T-NORMAL DN 315 - 350 de 3.51m a 4.00m PROF. M 674.43 38.76 26,140.91 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
12.01.02.14 EXCAV. ZANJA (MAQ.) P/TUB. T-NORMAL DN 315 - 350 de 4.01m a 5.00m PROF. M 1,162.66 53.28 61,946.52 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
12.01.02.15 EXCAV. ZANJA (MAQ.) P/TUB. T-NORMAL DN 315 - 350 de 5.01m a 6.00m PROF. M 704.49 76.12 53,625.78 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
REFINE Y NIVELACION DE ZANJA T-NORMAL P/TUB. DN 200 - 250 PARA TODA
12.01.02.16 M 44,481.38 1.32 58,715.42 100.00% 0.00 0.00% 277.36 366.12 1.00% 277.36 366.12 1.00% Err:502 Err:502 Err:502
PROF.
REFINE Y NIVELACION DE ZANJA T-NORMAL P/TUB. DN 315 - 350 PARA TODA
12.01.02.17 M 4,121.71 1.60 6,594.74 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
PROF.
12.01.02.18 PREPARACION DE CAMA DE APOYO P/TUB. DN 200 - 250 PARA TODA PROF. M 44,841.38 3.89 174,432.97 100.00% 0.00 0.00% 277.36 1,078.93 1.00% 277.36 1,078.93 1.00% Err:502 Err:502 Err:502
12.01.02.19 PREPARACION DE CAMA DE APOYO P/TUB. DN 315 - 350 PARA TODA PROF. M 4,121.71 4.00 16,486.84 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
RELLENO COMP. ZANJA (PULSO) P/TUB. T-NORMAL DN 200 - 250 de 0.60m a 1.00m
12.01.02.20 M 221.26 11.72 2,593.17 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
PROF.
RELLENO COMP. ZANJA (PULSO) P/TUB. T-NORMAL DN 200 - 250 de 1.01m a 1.50m
12.01.02.21 M 21,116.33 13.67 288,660.23 100.00% 0.00 0.00% 219.24 2,997.01 1.00% 219.24 2,997.01 1.00% Err:502 Err:502 Err:502
PROF.
RELLENO COMP. ZANJA (PULSO) P/TUB. T-NORMAL DN 200 - 250 de 1.51m a 2.00m
12.01.02.22 M 8,670.25 19.89 172,451.27 100.00% 0.00 0.00% 58.12 1,156.01 1.00% 58.12 1,156.01 1.00% Err:502 Err:502 Err:502
PROF
RELLENO COMP. ZANJA (PULSO) P/TUB. T-NORMAL DN 200 - 250 de 2.01m a 2.50m
12.01.02.23 M 5,584.81 23.14 129,232.50 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
PROF.
RELLENO COMP. ZANJA (PULSO) P/TUB. T-NORMAL DN 200 - 250 de 2.51m a 3.00m
12.01.02.24 M 2,428.67 27.58 66,982.72 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
PROF.
RELLENO COMP. ZANJA (PULSO) P/TUB. T-NORMAL DN 200 - 250 de 3.01m a 3.50m
12.01.02.25 M 2,577.98 37.81 97,473.42 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
PROF.
15
OBRA : MEJORAMIENTO Y AMPLIACIN DEL SISTEMA DE AGUA POTABLE Y ALCANTARILLADO DE LA CIUDAD DE RIOJA, PROVINCIA DE RIOJA - SAN MARTIN
CONTRATO : CONTRATO
: GOBIERNO
Nro.
REGIONAL
009 - 2011DE
- GRSM
SAN MARTIN
- PEAM - 01.00
ENTIDAD : GOBIERNO REGIONAL DE SAN MARTIN
CONTRATISTA : CONSORCIO ALIANZA
SUPERVISION

VALORIZACION DE OBRA N 02
CORRESPONDIENTE AL MES DE DICIEMBRE DEL 2,011 (DEL 01/12/11 AL 31/12/11)

Presupuesto : S/. 38087743.33 Nuevos Soles, Exonerado del IGV

PRESUPUESTO ACUMULADO ANTERIOR PRESENTE VALORIZACION ACUMULADO ACTUAL SALDO POR VALORIZAR
Item Descripcin Und. P. U. Parcial Parcial Parcial Parcial Parcial
Metrado % Metrado % Metrado % Metrado % Metrado %
S/. S/. S/. S/. S/. S/.
RELLENO COMP. ZANJA (PULSO) P/TUB. T-NORMAL DN 200 - 250 de 3.51m a 4.00m
12.01.02.26 M 2,108.27 56.47 119,054.01 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
PROF.
RELLENO COMP. ZANJA (PULSO) P/TUB. T-NORMAL DN 200 - 250 de 4.01m a 5.00m
12.01.02.27 M 2,133.81 79.88 170,448.74 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
PROF.
RELLENO COMP. ZANJA (PULSO) P/TUB. T-NORMAL DN 315 - 350 de 1.51m a 2.00m
12.01.02.28 M 286.95 18.71 5,368.83 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
PROF.
RELLENO COMP. ZANJA (PULSO) P/TUB. T-NORMAL DN 315 - 350 de 2.01m a 2.50m
12.01.02.29 M 451.95 23.14 10,458.12 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
PROF.
RELLENO COMP. ZANJA (PULSO) P/TUB. T-NORMAL DN 315 - 350 de 2.51m a 3.00m
12.01.02.30 M 490.93 27.58 13,539.85 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
PROF.
RELLENO COMP. ZANJA (PULSO) P/TUB. T-NORMAL DN 315 - 350 de 3.01m a 3.50m
12.01.02.31 M 350.30 37.81 13,244.84 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
PROF.
RELLENO COMP. ZANJA (PULSO) P/TUB. T-NORMAL DN 315 - 350 de 3.51m a 4.00m
12.01.02.32 M3 674.43 56.47 38,085.06 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
PROF.
RELLENO COMP. ZANJA (PULSO) P/TUB. T-NORMAL DN 315 - 350 de 4.01m a 5.00m
12.01.02.33 M 1,162.66 79.88 92,873.28 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
PROF.
RELLENO COMP. ZANJA (PULSO) P/TUB. T-NORMAL DN 315 - 350 de 5.01m a 6.00m
12.01.02.34 M 704.49 105.10 74,041.90 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
PROF.
12.01.02.35 ELIMINACION DE MATERIAL EXCEDENTE M3K 8,160.94 17.86 145,754.39 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
12.01.03 SUMINISTRO E INSTALACION DE TUBERIAS PVC-UF ISO 4435
12.01.03.01 TUBERIA PVC-UF NTP ISO 4435 S-25 DN 200 incluye anillo + 2% de desperdicios. M 37,668.98 19.99 753,002.91 100.00% 1,800.00 35,982.00 5.00% 0.00 0.00% 1,800.00 35,982.00 5.00% Err:502 Err:502 Err:502
12.01.03.02 TUBERIA PVC-UF NTP ISO 4435 S-20 DN 200 incluye anillo + 2% de desperdicios. M 6,165.47 24.73 152,472.07 100.00% 1,800.00 44,514.00 29.00% 0.00 0.00% 1,800.00 44,514.00 29.00% Err:502 Err:502 Err:502
12.01.03.03 TUBERIA PVC-UF NTP ISO 4435 S-25 DN 250 incluye anillo + 2% de desperdicios. M 562.64 31.38 17,655.64 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
12.01.03.04 TUBERIA PVC-UF NTP ISO 4435 S-20 DN 250 incluye anillo + 2% de desperdicios. M 692.39 39.07 27,051.68 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
12.01.03.05 TUBERIA PVC-UF NTP ISO 4435 S-25 DN 315 incluye anillo + 2% de desperdicios. M 411.41 48.93 20,130.29 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
12.01.03.06 TUBERIA PVC-UF NTP ISO 4435 S-20 DN 315 incluye anillo + 2% de desperdicios. M 414.17 59.81 24,771.51 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
12.01.03.07 TUBERIA PVC-UF NTP ISO 4435 S-25 DN 355 incluye anillo + 2% de desperdicios. M 825.02 62.37 51,456.50 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
12.01.03.08 TUBERIA PVC-UF NTP ISO 4435 S-20 DN 355 incluye anillo + 2% de desperdicios. M 1,785.22 76.26 136,140.88 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
12.01.03.09 TUBERIA PVC-UF NTP ISO 4435 S-16.7 DN 355 incluye anillo + 2% de desperdicios. M 707.79 70.56 49,941.66 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
12.01.03.10 INSTALACION DE TUB. PVC-UF P/DESAGUE DN 200 - 250 M 45,089.48 2.40 108,214.75 100.00% 0.00 0.00% 277.36 665.66 1.00% 277.36 665.66 1.00% Err:502 Err:502 Err:502
12.01.03.11 INSTALACION DE TUB. PVC-UF P/DESAGUE DN 315 - 350 M 4,143.61 3.30 13,673.91 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
12.01.04 BUZONES Y BUZONETAS
12.01.04.01 EXCAV. ZANJA (PULSO) P/BUZON D=1.20 EN T-NORMAL DE 0.60m a 1.00m PROF M3 7.26 22.39 162.55 100.00% 0.00 0.00% 2.04 45.68 28.00% 2.04 45.68 28.00% Err:502 Err:502 Err:502
12.01.04.02 EXCAV. ZANJA (PULSO) P/BUZON D=1.20 EN T-NORMAL DE 1.01m a 2.00m PROF M3 1,525.31 25.19 38,422.56 100.00% 0.00 0.00% 194.67 4,903.74 13.00% 194.67 4,903.74 13.00% Err:502 Err:502 Err:502
12.01.04.03 EXCAV. ZANJA (PULSO) P/BUZON D=1.20 EN T-NORMAL DE 2.01m a 3.00m PROF M3 834.15 33.59 28,019.10 100.00% 0.00 0.00% 95.43 3,205.49 11.00% 95.43 3,205.49 11.00% Err:502 Err:502 Err:502
12.01.04.04 EXCAV. ZANJA (PULSO) P/BUZON D=1.50 EN T-NORMAL DE 3.01m a 4.00m PROF M3 1,055.58 40.30 42,539.87 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
12.01.04.05 EXCAV. ZANJA (PULSO) P/BUZON D=1.50 EN T-NORMAL DE 4.01m a 5.00m PROF M3 876.51 50.39 44,167.34 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
12.01.04.06 EXCAV. ZANJA (PULSO) P/BUZON D=1.50 EN T-NORMAL DE 5.01m a 6.00m PROF M3 190.07 67.19 12,770.80 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
12.01.04.07 CONSTRUCCION DE BUZON TIPO I Di=1.20, H=0.60m - 1.00m UND 4.00 1,319.93 5,279.72 100.00% 0.00 0.00% 1.00 1,319.93 25.00% 1.00 1,319.93 25.00% Err:502 Err:502 Err:502
12.01.04.08 CONSTRUCCION DE BUZON TIPO I Di=1.20, H=1.01m - 1.50m UND 322.00 1,639.51 527,922.22 100.00% 0.00 0.00% 29.00 47,545.79 9.00% 29.00 47,545.79 9.00% Err:502 Err:502 Err:502
12.01.04.09 CONSTRUCCION DE BUZON TIPO I Di=1.20, H=1.51m - 2.00m UND 126.00 1,927.26 242,834.76 100.00% 0.00 0.00% 23.00 44,326.98 18.00% 23.00 44,326.98 18.00% Err:502 Err:502 Err:502
12.01.04.10 CONSTRUCCION DE BUZON TIPO I Di=1.20, H=2.01m - 2.50m UND 85.00 2,129.71 181,025.35 100.00% 0.00 0.00% 9.00 19,167.39 11.00% 9.00 19,167.39 11.00% Err:502 Err:502 Err:502
12.01.04.11 CONSTRUCCION DE BUZON TIPO I Di=1.20, H=2.51m - 3.00m UND 62.00 2,417.68 149,896.16 100.00% 0.00 0.00% 6.00 14,506.08 10.00% 6.00 14,506.08 10.00% Err:502 Err:502 Err:502
12.01.04.12 CONSTRUCCION DE BUZON TIPO II Di=1.50, H=3.01m - 3.50m UND 41.00 4,652.85 190,766.85 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
12.01.04.13 CONSTRUCCION DE BUZON TIPO II Di=1.50, H=3.51m - 4.00m UND 55.00 5,104.06 280,723.30 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
12.01.04.14 CONSTRUCCION DE BUZON TIPO II Di=1.50, H=4.01m - 5.00m UND 52.00 5,851.84 304,295.68 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
12.01.04.15 CONSTRUCCION DE BUZON TIPO II Di=1.50, H=5.01m - 6.00m UND 11.00 6,636.04 72,996.44 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
DISPOSITIVO DE CAIDA EN INTERIOR DE BUZON L=1.50m DN200
12.01.04.16 UND 33.00 688.76 22,729.08 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
DISPOSITIVO DE CAIDA EN INTERIOR DE BUZON L=2.00 m DN200
12.01.04.17 UND 17.00 703.34 11,956.78 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
DISPOSITIVO DE CAIDA EN INTERIOR DE BUZON L=2.50 m DN200
12.01.04.18 UND 14.00 716.17 10,026.38 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
DISPOSITIVO DE CAIDA EN INTERIOR DE BUZON L=3.00 m DN200
12.01.04.19 UND 7.00 729.88 5,109.16 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
DISPOSITIVO DE CAIDA EN INTERIOR DE BUZON L=3.50 m DN200
12.01.04.20 UND 3.00 752.37 2,257.11 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502
12.01.04.21 ELIMINACION DE MATERIAL EXCEDENTE M3K 5,386.65 17.86 96,205.57 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% Err:502 Err:502 Err:502

TOTAL COSTO DIRECTO ### ### S/. 338,681.22 S/. 574,287.09 Err:502
GASTOS GENERALES 16.60% S/. 5,313,080.16 S/. 39,110.58 S/. 56,221.08 S/. 95,331.66 Err:502
UTILIDAD 2.40% S/. 768,156.17 S/. 5,654.54 S/. 8,128.35 S/. 13,782.89 Err:502
SUB-TOTAL ### ### S/. 403,030.65 S/. 683,401.64 Err:502
IMPUESTO GENERAL A LAS VENTAS (EXONERADO) 0.00% S/. - S/. - S/. - S/. - Err:502
TOTAL PRESUPUESTO S/. 38,087,743.33 100.00% S/. 280,371.00 0.74% S/. 403,030.65 1.06% S/. 683,401.64 1.80% Err:502 Err:502