FACTOR DE SALARIO REAL

365.25-70.17= 295.08 DIAS

SALARIO MAYOR AL MINIMO

382.25+ (.2328775x365.25)/295.08= 1.58


IMPUESTO DE LA VIVIENDA 0.05
IMPUESTO A LA EDUCACION 0.01

TOTAL= 1.64%

SALARIO MINIMO

382.25+(.2841375x365.25)/295.08= 1.64
IMPUESTO DE LA VIVIENDA 0.05
IMPUESTO A LA EDUCACION 0.01

TOTAL= 1.70%
LISTA DE SALARIOS

PESOS SALARIO
PROFESIONALES DIARIOS FSR REAL

PEON 73.04 1.7 124.168


OFICIAL ALBAIL 106.49 1.64 174.6436
OPERADOR DE MAQUINARIA 107.97 1.64 177.0708
CARPINTERO DE OBRA NEGRA 106.49 1.64 174.6436
CARPINTERO FABRICACION 104.41 1.64 171.2324
COLOCADOR DE AZULEJOS 106.49 1.64 174.6436
YESERO 98.52 1.64 161.5728
CHOFER DE CAMION 108.94 1.64 178.6616
CHOFER OPERADOR 100.97 1.64 165.5908
OFICIAL HERRERO 102.58 1.64 168.2312
PINTOR DE CASAS 101.8 1.64 166.952
PLOMERO 89.06 1.64 146.0584
CABO 120.83 1.64 198.1612
CUADRILLAS

CUAD INTEGRANTES ACTIVIDAD COSTO

C#1 PEON ACARREO DE MATERIAL $124.17


1/10 CABO PEGADO DE LADRILLO $19.81
$143.98
C#2 7 PEONES $869.17
7/10 CABO FABRICACION DE CONCRETOS $138.71
$1,007.88
C#3 1 OFICIAL DE ALBAILERIA VACIADOS $174.64
4 PEONES $496.68
$671.32
C#4 1 OFICIL DE ALBAILERIA CIMENTACIONES $174.64
1 PEON $124.17
$298.81
C#5 1 OFICIAL DE CARPINTERIA OBRA N CIMBRADO $174.64
1 PEON $124.17
$298.81
C#6 I OFICIAL FIERRERO CORTADO Y DOBLADO DE $174.64
1 PEON VARILLAS $124.17
$298.81
C#7 1 COLOCADOR DE AZULEJOS VITROPISOS $174.64
1 PEON ACABADOS $124.17
$298.81
C#9 1 OFICIAL HERRERO FABRICACION DE PUERTAS $168.23
1 PEON Y PROTECCIONES $124.17
$292.40
C#111 OFICIAL YESERO RECUBRIMIENTO EN YESO, $161.57
1 PEON TIROLES $124.17
$285.74
C#121 OFICIAL CARPINTERO FABRICACION DE PUERTAS $171.23
1 PEON Y MUEBLES $124.17
$295.40
C#131 OFICIAL PINTOR PINTAR $166.95
1 PEON $124.17
$291.12
B) PRESTACIONES

VACACIONES 8 DIAS
PRIMA VACACIONAL 2 DIAS

SUBTOTAL= 22 DIAS
365.25
TOTAL= 387.25 / 365.25 =
1.06
NOMINA 792,000
X 1.06

IMSS

792,000 - 243,600= 548,400 243,600 X .0875=


X .2328875= 21,315
127,762.08

NOMINA 839,520
IMSS 127,762.08
IMSS PERSONAL DIRECTO 21,315

NOMINA FINAL = 988,597.08


/ 18,000,000
PORCENTAJE 5.49%
CONCEPTO: TRAZO Y NIVELACION DE TERRENO A TRAVES DE MEDIO
MANUALES

UNIDAD: M2

MATERIAL UNIDADCANTIDADPRECIO IMPORTE

MADERA DE PINO # 3 PT 0.17 18.00 3.06

HILO ROLLO 0.03 129.00 4.00

CALHIDRA TON 0.00 2480.00 0.99

MANO DE OBRA C4 R/J= 40 M2 0.03 298.81 7.47

COSTO DIRECTO= 15.52

10% COSTO INDIRECTO= 1.55

SUBTOTAL= 17.07

10 % UTILIDAD = 1.71

SUBTOTAL= 18.78
3% IMPREVISTOS= 0.56

TOTAL= 19.34
CONCEPTO: LIMPIEZA DE TERRENO A TRAVES DE MEDIOS MANUALES.

UNIDAD: M2

MATERIAL UNIDADCANTIDADPRECIO IMPORTE

MANO DE OBRA C1 R/J= 40 M2 J 0.03 143.98 3.60

HERRAMIENTAS %

COSTO DIRECTO= 3.60

10% COSTO INDIRECTO= 0.36

SUBTOTAL= 3.96

10 % UTILIDAD = 0.40

SUBTOTAL= 4.36
3% IMPREVISTOS= 0.13

TOTAL= 4.49
CONCEPTO: EXCAVACION A MANO EN MATERIAL TIPO B DE O.OO A 1.00 M DE
PROFUNDIDAD SECCION OBLIGADA, INCLUYE AFINE DE TALUDES Y FONDO

UNIDAD: M3

MATERIAL UNIDADCANTIDADPRECIO IMPORTE

MANO DE OBRA C1 R/J= 4. 167M3 J 0.23 143.98 33.12

HERRAMIENTAS % 0.03

COSTO DIRECTO= 33.12

10% COSTO INDIRECTO= 3.31

SUBTOTAL= 36.43

10 % UTILIDAD = 3.64

SUBTOTAL= 40.07
3% IMPREVISTOS= 1.20

TOTAL= 41.27

CONCEPTO: PLANTILLA PARA RECIBIR MAMPOSTERIA A BASE DE CONCRETO


CON UNA RESISTENCIA DE FC=100KG/CM2 CON UN ESPESOR DE 10 CMS.

UNIDAD: M3

MATERIAL UNIDADCANTIDADPRECIO IMPORTE

CONCRETO F'C=100 KG/CM2 M3 0.011 1078.48 11.86328

MANO DE OBRA C3 J 0.167 671.32 112.11044

VIBRADOR M3 0.025 2.5 0.0625

REVOLVEDORA M3 0.025 8.05 0.20125

COSTO DIRECTO= 108.4638303

COSTO INDIRECTO= 10.846

subtotal 119.3098303
UTILIDAD 10 %= 11.93
subtotal 131.2398303
IMPREVISTOS 3% 3.937194909

TOTAL= 135.177025209

CONCEPTO: CIMIENTO DE MAMPOSTERIA A BASE DE PIEDRA BRAZA LIMPIA SIN


LABRAR ASENTADA CON MORTERO CEMENTO ARENA 1:4 CON UNA SECCION
TRAPEZOIDAL B=.8 M b=.30 M H=.9M

UNIDAD: M3

MATERIAL UNIDADCANTIDADPRECIO IMPORTE

PIEDRA( 50% DE VACIOS) M3 1.5 168.1 252.15

MORTERO (30% VACIOS)+10% DESP.M3 0.33 1655.45 546.2985

MANO DE OBRA C#1 R/J=2.00 M3 J 0.5 143.98 71.99

HERRAMIENTAS % 0.03 71.99 2.1597

COSTO DIRECTO= 872.5982

COSTO INDIRECTO= 87.26


subtotal 959.8582

UTILIDAD 10 %= 95.98582

IMPREVISTOS 3% 2.8795746

TOTAL= 1058.7235946
CONCEPTO:ANCLAJE DE CASTILLO A MAMPOSTERIA DE 30 X 70 X 70 CMS DE
CONCRETO FC=150 KG/CM2 ARMADO CON 4 VARILLAS DEL NO. 3 Y ESTRIBOS
DEL NO 2 A CADA 20 CMS. INCLUYE: ARMADO, CIMBRADO,
VACIADO,DESCIMBRADO Y CURADO.

UNIDAD: PIEZA

MATERIAL UNIDADCANTIDADPRECIO IMPORTE

CIMBRA CON MADERA DE PINO #3 M2 1.5 18 27

ACERO #3 KG 1.55 13.25 20.5375

ACERO #2 KG 0.6 13.25 7.95

CONCRETO F'C=150 KG/CM2 T.M.A


38MM+10% DESP. M3 0.08 1347.38 107.7904

MANO DE OBRA C4 R/J= 10 PZ J 0.1 298.81 29.881

HERRAMIENTAS % 0.03 29.881 0.89643

VIBRADOR DE CONCRETO M3 0.08 2.5 0.2

COSTO DIRECTO= 194.25533

COSTO INDIRECTO= 21.640043762

UTILIDAD 10 %= 21.5895373762
IMPREVISTOS 3% 7.1245473341

TOTAL= 244.6094584723

CADENA DE CONCRETO DE 14X 15 CMS, CON FC=150 KG/ CM2 ARMADO CON 4
VARILLAS DEL NO. 3 Y ESTRIBOS DEL NO. 2 A CADA 25 CMS.

UNIDAD: M3

MATERIAL UNIDADCANTIDADPRECIO IMPORTE

CIMBRA CON MADERA DE PINO #3 M2 0.28 180.60 50.57

ACERO #3 KG 2.26 16.20 36.68

ACERO #2 KG 0.73 16.20 11.76

CONCRETO F'C=150 KG/CM2 T.M.A


38MM+10% DESP. M3 0.02 1347.37 28.29

MANO DE OBRA C1 R/J= 18.02 M3 J 0.06 143.98 7.92

HERRAMIENTAS % 0.03 7.92 0.24

VIBRADOR DE CONCRETO M3 0.02 2.50 0.05

COSTO DIRECTO= 135.51

11.14% COSTO INDIRECTO= 15.10

SUBTOTAL= 150.61

10 % UTILIDAD = 15.06
SUBTOTAL= 165.67
3% IMPREVISTOS= 4.97

TOTAL= 170.64

CONCEPTO: MURO A BASE DE TABIQUE ROJO RECOCIDO ASENTADO CON


MORTERO CEMENTO-ARENA 1:3 A UNA ALTURA DE 2.10 M

UNIDAD: M3

MATERIAL UNIDADCANTIDADPRECIO IMPORTE

MORTERO M3 0.03 1655.50 49.67

TABIQUE MILLAR 0.06 1800.00 111.60

AGUA M3 0.08 6.73 0.54

MANO DE OBRA C#4 R/J= 10M2 J 0.10 298.81 29.88

HERRAMIENTAS % 0.03 29.88 0.90

COSTO DIRECTO= 142.92

11.14% COSTO INDIRECTO= 15.92

SUBTOTAL= 158.84
10 % UTILIDAD = 15.88

SUBTOTAL= 174.72
3% IMPREVISTOS= 5.24

TOTAL= 179.96

CASTILLO DE CONCRETO DE 14 X 14 CMS, CON FC= 150 KG/CM2 ARMADO CON


4 VARILLAS DEL NO 3 Y ESTRIBOS DEL NO. 2 A CADA 20 CMS.

UNIDAD: M3

MATERIAL UNIDADCANTIDADPRECIO IMPORTE

CIMBRA CON MADERA DE PINO #3 M2 0.42 140.60 59.05

ACERO #3 KG 2.26 16.20 36.68

ACERO #2 KG 0.70 16.20 11.34

CONCRETO F'C=150 KG/CM2 T.M.A


38MM+10% DESP. M3 0.02 1347.37 26.95

MANO DE OBRA C1 R/J= 14.32 M3 J 0.07 143.98 9.65

HERRAMIENTAS % 0.03 9.65 0.29

VIBRADOR DE CONCRETO M3 0.02 2.50 0.05

COSTO DIRECTO= 144.00

11.14% COSTO INDIRECTO= 16.04


SUBTOTAL= 160.04

10 % UTILIDAD = 16.00

SUBTOTAL= 176.05
3% IMPREVISTOS= 5.28

TOTAL= 181.33

CONCEPTO: CONCRETO FC= 250 KG/CM2 EN LOSAS con un espesor de 8 cm,


ELABORADO EN OBRA CON MAQUINA REVOLVEDORA. INCLUYE: CIMBRADO,
ARMADO, COLADO, DESCIMBRADO Y RIEGO DURANTE 7 DIAS. PRUEBAS DE
LABORATORIO 3 CILINDROS POR COLADO.
UNIDAD: M2

MATERIAL UNIDADCANTIDADPRECIO IMPORTE

CONCRETO f'c= 150 kg/ cm2 M3 1.65 1347.37 2223.16


0.00
ACERO 3 kg 6.70 16.20 108.54
0.00
0.00
CIMBRA APARENTE EN LOSA M2 1.00 273.56 273.56
0.00

MANO DE OBRA C3 R/J= 20 m3 J 0.05 671.32 33.57

HERRAMIENTAS % 0.03 33.57 1.01

VIBRADOR M3 0.08 2.50 0.20


COSTO DIRECTO= 2639.83

11.14% COSTO INDIRECTO= 294.08

SUBTOTAL= 2933.91
10 % UTILIDAD = 293.39

SUBTOTAL= 3227.30
3% IMPREVISTOS= 96.82

TOTAL= 3324.12

CONCEPTO: FIRMES DE CONCRETO, DE 8 CM DE ESPESOR, CONCRETO DE


F`C= 100KG/CM2. CON ACABADO COMUN PARA COLOCAR VITROPISO.
UNIDAD: M2

MATERIAL UNIDADCANTIDADPRECIO IMPORTE

CONCRETO M3 0.08 1347.37 107.79

MANO DE OBRA C4 R/J= 8.13 M2 J 0.12 298.81 36.75

HERRAMIENTAS % 0.03 36.75 1.10

VIBRADOR M3 0.08 2.50 0.20

MANO DE OBRA C1 R/J= 6.95 M3 J 0.14 143.98 20.59

COMPACTADORA M3 0.07 3.40 0.24

COSTO DIRECTO= 166.67

11.14% COSTO INDIRECTO= 18.57


SUBTOTAL= 185.24

10 % UTILIDAD = 18.52

SUBTOTAL= 203.76
3% IMPREVISTOS= 6.11

TOTAL= 209.88
Concepto: Elaboracion de un m3 de concreto cemento - grava - arena -
agua, proporcion 1: 3: 4. f'c= 98 kg/cm2. Incluye: materiales, desperdicio,
mano de obra y herramientas. Unidad: m3
Precio
Materiales Unidad Cantidad Unitario Importe
Cemento + 3% de desp Tonelada 0.269 2700 726.3
grava 1 1/2" + 3% de m3 0.712 180 128.16
Arena + 3% de desperm3 0.532 286.7 152.5244
Agua + 30% de desperm3 0.286 6.79 1.94194
Mano de obra C#2 J 0.067 1007.88 67.52796
Herramienta % 0.03 67.52796 2.0258388

TOTAL= 1078.48014
Concepto: Mortero cemento - arena cernida - agua, proporcion 1
: 4. Incluye: materiales, desperdicio, mano de obra y
herramientas. Unidad: m3
Precio
Materiales Unidad Cantidad Unitario Importe
cemento + 3%Tonelada 0.4532 3080 1395.856
Arena cernidam3 1.133 137.5 155.7875
Agua + 30% dm3 0.3614 6.79 2.453906
Mano de obraJ 0.67 143.98 96.4666
Mano de obraJ 0.555 143.98 79.9089
Herramienta % 0.03 176.3755 5.291265

TOTAL= 1655.85527

arena - agua, proporcion 1: 2.5 : 2.5. f'c= 156 kg/cm2. Incluye:


materiales, desperdicio, mano de obra y herramientas.
Unidad: m3
Precio
Materiales Unidad Cantidad Unitario Importe
Cemento + 3% Tonelada 0.361 3080 1111.88
grava 3/4" + m3 0.596 137.5 81.95
Arena + 3% dm3 0.596 137.5 81.95
Agua + 30% dm3 0.301 6.79 2.04379
Mano de obraJ 0.067 1007.88 67.52796
Herramienta % 0.03 67.52796 2.0258388

TOTAL= 1347.37759

arena - agua, proporcion 1: 2.5 : 2.5. f'c= 156 kg/cm2. Incluye:


materiales, desperdicio, mano de obra y herramientas.
Unidad: m3
Precio
Materiales Unidad Cantidad Unitario Importe
Cemento + 3% Tonelada 0.361 3080 1111.88
grava 3/4" + m3 0.596 137.5 81.95
Arena + 3% dm3 0.596 137.5 81.95
Agua + 30% dm3 0.301 6.79 2.04379
Mano de obraJ 0.067 1007.8 67.5226
Herramienta % 0.03 67.5226 2.025678

TOTAL= 1347.37207
Etapa Trabajo Descripcion Mat. Y Equipo Cant/Vol/Un Tiempo P. Unitar Monto $
Limpieza de terreno a travz de medios
Limpieza manuales incluyendo retiro del producto 327.75 1 Da $ 4.49 $ 1,471.60
hasta 10 m fuera de la obra m
Trazo y nivelacin del terreno de construc-Escuadras, nivel de manguera,
Trazo y cin realizando ejes en muros estableci- niveleta, cal, hilo, estacas, 327,75 m 2 Dias $ 19.34 $ 6,338.69
endo datos auxiliares dentro y fuera de la clavos, pintura.
Trab. Preliminares Nivelacin
obra.
Excavacin en terreno superficial para Retroexcavadora
alojar/recibir la cimentacin de mampos-
Excavacin tera, con una seccin de 0.90 m de ancho 155.933 2 Dias $ 41.27 $ 6,435.35
y 0.95 m de profundidad, incluyendo afi- m
nes de taludes
Plantilla de concreto pobre hecho en obraMortero, llana, vibrador,
con una resistencia F' C= 100 kg/cm cuchara 7.13 2 Dias $ 135.18 $ 963.83
Plantilla
Y 0.05 m de espesor, con un T.M.A 38 mm. m
incluyendo colado, vibrado y curado
Cimentacin de mampostera a base de Piedra braza, cuchara, mortero,
piedra brasa, limpia, sin labrar, asentada
Cimentacin con mortero, cemento, arena 1:4 con una 41.466 $1,058.72 $ 43,900.88
Cimentacin
seccin trapezoidal (B=0.80 m)(b=0.30m)
con H=0.90 m.
Anclaje de castillo 0.80 x 0.80 x 0.90 m
de concreto f'c= 150 kg/cm2 armado con
anclajes 4 varillas del #3 y estibos de #2 a cada 20 71 pzaz 344.61
cms, incluye: armado, cimbrado y descim-
brado y curado.
dala Cadena de concreto de 14x14
desplante f'c= 150 kg/cm2 armado con 4 varillas #3, 145.38 170.64
estribos #2 a cada 20 cm
Muro de tabique rojo recocido de 7x17x28
muros
planta baja cm de espesor con mortero-cemento- 249 179.96
arena 1:6. a una altura de 2.10 m
Cadena de concreto de 14x14
dala
cerramiento f'c= 150 kg/cm2 armado con 4 varillas #3, 145.38 170.64
estribos #2 a cada 20 cm
muros de Muro de tabique rojo recocido de 7x17x28
enrace cm de espesor con mortero-cemento- 60.88 179.96
arena 1:6. a una altura de 0.45 m

Firme de concreto de 8 cm de espesor,


firme concreto de f'c= 100 kg/cm2 con 207.72 209.88
acabado regreado para colocar vitropiso

concreto f'c=250 kg/cm2 en losas del pri-


losa mer nivel, elaborado en obra con maquina 181.7 3324.12
revolvedora, incluye: cimbrado, armado,
colado y descimbrado (espesor 15 cm)
Castillos de concreto de 14x14 cm
castillos f'c= 150 kg/cm2 armado con 4 varillas #3, 72 181.33
estribos #2 a cada 20 cm