Periodo de Tiempo

Partida Descripcin Unidad Cantidad P. Unitario Parcial Das 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45


1.00 OBRAS PRELIMINARES

1.01 TRAZO Y REPLANTEO

1.01.01 TRAZO Y REPLANTEO PRELIMINAR m2 252.00 S/. 2.00 S/. 504.00 2.00

2.00 MOVIMIENTO DE TIERRAS

2.01 EXCAVACION PARA CIMIENTOS m3 226.80 S/. 18.00 S/. 4,082.40 3.00

2.02 RELLENO CON MATERIAL PROPIO CON EQUIPO m3 37.80 S/. 45.00 S/. 1,701.00 2.00

2.03 ELIMINACION MATERIAL EXCEDENTE C/MAQUINARIA m3 245.70 S/. 17.00 S/. 4,176.90 3.00

3.00 CONCRETO SIMPLE

3.01 CIMIENTOS CORRIDOS

3.01.01 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% PG m3 176.40 S/. 270.00 S/. 47,628.00 14.00

4.01 SOBRECIMIENTO

4.01.01 CONCRETO 1:8+25% PM PARA SOBRECIMIENTOS e=0.15m m3 31.50 S/. 280.00 S/. 8,820.00 3.00

4.01.02 ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMIENTO m2 354.00 S/. 29.00 S/. 10,266.00 10.00

5.00 CONCRETO ARMADO

5.01 COLUMNAS

5.01.01 CONCRETO EN COLUMNAS f'c=210 kg/cm2 m3 30.94 S/. 415.00 S/. 12,840.10 3.00

5.01.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS m2 123.75 S/. 35.00 S/. 4,331.25 5.00

5.01.03 ACERO fy=4200 kg/cm2 GRADO 60 en COLUMNAS kg 3,006.60 S/. 5.00 S/. 15,033.00 5.00

6.00 MURO DE ALBAILERIA

6.01.01 MURO DE LADRILLO KK 18 HUECOS SOGA m2 1,176.00 S/. 50.00 S/. 58,800.00 20.00
Primera valorizacin Valorizacin Anterior Valorizacin Actual Total Acumulado
(1 al 15) (16 AL 30) (31 AL 45)
Partida Descripcin Unidad Cantidad P. Unitario Parcial Metrado Parcial % Metrado Parcial % Metrado Parcial % Metrado Parcial %

1.00 OBRAS PRELIMINARES


1.01 TRAZO Y REPLANTEO
1.01.01 TRAZO Y REPLANTEO PRELIMINAR m2 252.00 S/. 2.00 S/. 504.00 200.00 S/.400.00 79% 52.00 S/.104.00 21% 0.00 S/.0.00 0% 252.00 S/. 504.00 100%

2.00 MOVIMIENTO DE TIERRAS


2.01 EXCAVACION PARA CIMIENTOS m3 226.80 S/. 18.00 S/. 4,082.40 200.000 S/.3,600.00 88% 26.80 S/.482.40 12% 0.00 S/.0.00 0% 226.80 S/. 4,082.40 100%

2.02 RELLENO CON MATERIAL PROPIO CON EQUIPO m3 37.80 S/. 45.00 S/. 1,701.00 0.000 S/.0.00 0% 37.00 S/.1,665.00 98% 0.80 S/.36.00 2% 37.80 S/. 1,701.00 100%

2.03 ELIMINACION MATERIAL EXCEDENTE C/MAQUINARIA m3 245.70 S/. 17.00 S/. 4,176.90 200.000 S/.3,400.00 81% 45.70 S/.776.90 19% 0.00 S/.0.00 0% 245.70 S/. 4,176.90 100%

3.00 CONCRETO SIMPLE


3.01 CIMIENTOS CORRIDOS

3.01.01 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 3 m3 176.40 S/. 270.00 S/. 47,628.00 113.400 S/.30,618.00 64.29% 63.00 S/.17,010.00 36% S/.0.00 0% 176.40 S/. 47,628.00 100%

4.01 SOBRECIMIENTO
4.01.01 CONCRETO 1:8+25% PM PARA SOBRECIMIENTOS e=0.15m m3 31.50 S/. 280.00 S/. 8,820.00 0.000 S/.0.00 0% 25.00 S/.7,000.00 79% 6.50 S/.1,820.00 21% 31.50 S/. 8,820.00 100%

4.01.02 ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMI m2 354.00 S/. 29.00 S/. 10,266.00 0.000 S/.0.00 0% 300.00 S/.8,700.00 85% 54.00 S/.1,566.00 15% 354.00 S/. 10,266.00 100%

5.00 CONCRETO ARMADO


5.01 COLUMNAS

5.01.01 CONCRETO EN COLUMNAS f'c=210 kg/cm2 m3 30.94 S/. 415.00 S/. 12,840.10 0.000 S/.0.00 0% 0.00 S/.0.00 0% 30.94 S/. 12,840.10 100% 30.94 S/. 12,840.10 100%

5.01.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS m2 123.75 S/. 35.00 S/. 4,331.25 0.000 S/.0.00 0% 30.00 S/.1,050.00 24% 93.75 S/. 3,281.25 76% 123.75 S/. 4,331.25 100%

5.01.03 ACERO fy=4200 kg/cm2 GRADO 60 en COLUMNAS kg 3,006.60 S/. 5.00 S/. 15,033.00 2000.000 S/.10,000.00 67% 1006.60 S/.5,033.00 33% 0.00 S/.0.00 0% 3006.60 S/. 15,033.00 100%

6.00 MURO DE ALBAILERIA


6.01.01 MURO DE LADRILLO KK 18 HUECOS SOGA m2 1,176.00 S/. 50.00 S/. 58,800.00 0.000 S/.0.00 0% 400.00 S/.20,000.00 34% 776.50 S/. 38,825.00 66% 1176.50 S/. 58,825.00 100%

COSTO DIRECTO S/. 168,182.65 S/. 48,018.00 S/. 61,821.30 S/. 58,368.35 S/. 168,207.65

GASTOS GENERALES S/. 16,818.27 10% S/. 4,801.80 S/. 6,182.13 S/. 5,836.84 S/. 16,820.77

UTILIDAD S/. 12,613.70 7.50% S/. 3,601.35 S/. 4,636.60 S/. 4,377.63 S/. 12,615.57

SUB TOTAL S/. 197,614.61 S/. 56,421.15 S/. 72,640.03 S/. 68,582.81 S/. 197,643.99

IMPUESTO IGV (18.00%) S/. 35,570.63 18% S/. 10,155.81 S/. 13,075.20 S/. 12,344.91 S/. 35,575.92

TOTAL PRESUPUESTO S/. 233,185.24 S/. 66,576.96 S/. 85,715.23 S/. 80,927.72 S/. 233,219.91
Avances Reales

Partida Descripcin Unidad P. Unitario Metrado Metrado Metrado


(REAL) Val 1 Val 2 Val 3
1.00 OBRAS PRELIMINARES
1.01 TRAZO Y REPLANTEO
1.01.01 TRAZO Y REPLANTEO PRELIMINAR m2 S/. 1.80 200.00 52.00 0.00

2.00 MOVIMIENTO DE TIERRAS


2.01 EXCAVACION PARA CIMIENTOS m3 S/. 17.00 200.000 26.80 0.00

2.02 RELLENO CON MATERIAL PROPIO CON EQUIPO m3 S/. 48.00 0.000 37.00 0.80

2.03 ELIMINACION MATERIAL EXCEDENTE C/MAQUINARIA m3 S/. 18.00 200.000 45.70 0.00

3.00 CONCRETO SIMPLE


3.01 CIMIENTOS CORRIDOS

3.01.01 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 3 m3 S/. 270.00 113.400 63.00 0.00

4.01 SOBRECIMIENTO

4.01.01 CONCRETO 1:8+25% PM PARA SOBRECIMIENTOS e=0.15m m3 S/. 285.00 0.000 25.00 6.50

4.01.02 ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMIE m2 S/. 30.00 0.000 300.00 54.00

5.00 CONCRETO ARMADO

5.01 COLUMNAS

5.01.01 CONCRETO EN COLUMNAS f'c=210 kg/cm2 m3 S/. 420.00 0.000 0.00 30.94

5.01.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS m2 S/. 36.00 0.000 30.00 93.75

5.01.03 ACERO fy=4200 kg/cm2 GRADO 60 en COLUMNAS kg S/. 6.00 2000.000 1006.60 0.00

6.00 MURO DE ALBAILERIA

6.01.01 MURO DE LADRILLO KK 18 HUECOS SOGA m2 S/. 45.00 0.000 400.00 776.00