You are on page 1of 7

PROCEDURE FOR INSTALLING REFRACTORY LINING

AT RK2 KILN OUTLET

Objective:
To describe the process of installing refractory at kiln outlet section

Domain of application:
Production Department Rotary Kilns
Document date: August 2016

Emergency numbers:
Shift Coordinator +254 720 627 023
CCR ext. 3233

Revisions and approvals:

Review Author Reviewer Approval Revised Paragraphs /


Notes
Name/Date Function Name/Date Function Name/Date Function
comments

Page 1 of 7 printed on 11/1/2017


PROCEDURE FOR INSTALLING REFRACTORY LINING
AT RK2 KILN OUTLET

Contents:
OBJECTIVE: ................................................................................................................................................................. 1
CONTENTS: .................................................................................................................................................................... 2
OBJECTIVE: ................................................................................................................................................................. 2
1. INTRODUCTION ................................................................................................................................................. 3
1.1. EQUIPMENT & TOOLS REQUIRED ...................................................................................................................... 3
1.2. PERSONNEL REQUIRED ..................................................................................................................................... 3
1.3. MATERIALS REQUIRED ..................................................................................................................................... 3
2. SAFETY ................................................................................................................................................................. 4
2.1. SAFETY DOCUMENTS ........................................................................................................................................ 4
2.2. PPE REQUIREMENTS......................................................................................................................................... 4
2.3. SAFETY ASPECTS .............................................................................................................................................. 4
3. INSTALLATION OF ANCHORS ....................................................................................................................... 5
3.1. MATERIAL SELECTION ...................................................................................................................................... 5
3.2. WELDING PREPARATION................................................................................................................................... 5
3.3. WELDING OF ANCHORS .................................................................................................................................... 5
3.4. ANCHOR DENSITY ............................................................................................................................................ 5
4. CASTING ............................................................................................................................................................... 6
4.1. SHUTTERING ..................................................................................................................................................... 6
4.2. EXPANSION ....................................................................................................................................................... 6
4.3. MIXING ............................................................................................................................................................. 6
4.4. BALL-HAND TEST ............................................................................................................................................ 6
4.5. POURING ........................................................................................................................................................... 7

Specific Definitions:

Distribution list:
Production Manager
Production Superintendent
Production Coach
Refractory Champion
Process/Production Engineer - CIP

Objective:
To describe process of installing refractory lining at kiln outlet section

Page 2 of 7 printed on 11/1/2017


PROCEDURE FOR INSTALLING REFRACTORY LINING
AT RK2 KILN OUTLET

1. Introduction
The kiln outlet section is subjected to significant thermal and mechanical stresses. In MOM RK2, the kiln
outlet is lined using monolithic castable from the nose ring segments up to the retainer. The castable length
is 1.1m.

1.1. Equipment & Tools Required


Cement mixing machine
Buckets
Shovels
Pneumatic vibrator
Hammers
Fork lift
Welding Machine

1.2. Personnel Required


Refractory Supervisor (1 No.)
Refractory Masons (2 No.)
Carpenters (2 No.)
Helpers (5 No.)
Welder (1 No.)

1.3. Materials Required


Prescribed low cement castable
Prescribed Steel/Ceramic Anchors
Clean portable water for mixing
Expansion joint material (Ceramic blanket)
Shuttering timber
Nails
Binding wire
Prescribed Welding rods

Page 3 of 7 printed on 11/1/2017


PROCEDURE FOR INSTALLING REFRACTORY LINING
AT RK2 KILN OUTLET

2. Safety
2.1. Safety Documents
1. Job Safety Analysis form
2. Permit to Work
3. Confined Space Entry Permit
4. LOTOTO Checklist
5. Hot Work Permit
6. Emergency Response Plan

2.2. PPE Requirements

2.3. Safety Aspects


1. Safe access platform into kiln
2. Adequate lighting (24V)
3. Disposal of used castable cement bags
4. Availability of emergency eye wash

Page 4 of 7 printed on 11/1/2017


PROCEDURE FOR INSTALLING REFRACTORY LINING
AT RK2 KILN OUTLET

3. Installation of Anchors
3.1. Material Selection
Anchors used are floating Omega type of anchors AISI 310, 10mm diameter.
The omega support diameter should be 2mm larger than the anchor diameter.
The anchors must have the same mechanical properties as the castable intended for use
The welding rods used must be compatible with the kiln shell (mild steel) and anchors (heat
resistant stainless steel).

3.2. Welding Preparation


The surface for welding anchors must be cleaned to prevent contamination of the welded joints.
Pre-heating of the surface and welding rods to about >80 degC is recommended. Supplier
instructions should be considered.

3.3. Welding of Anchors


The anchors are tack welded onto the Omega support base.
The support base is continuously welded onto the kiln shell.

3.4. Anchor Density


The correct anchor density is important for adequately supporting the castable onto the kiln shell.
Desired anchor density is a spacing of 200mm by 200mm placed at right angle to each other.
The number of anchor is thus a minimum of 12 anchors per segment.

Page 5 of 7 printed on 11/1/2017


PROCEDURE FOR INSTALLING REFRACTORY LINING
AT RK2 KILN OUTLET

4. Casting
The casting is done by working clockwise as the kiln moves in an anti-clockwise sense.

4.1. Shuttering
Shuttering is made by use of plywood to secure the poured castable mix in a box
The box dimension should follow the width of the nose ring segments.
Thus each box is 300mm wide by 600mm long.

4.2. Expansion
6mm expansion fiber (ceramic fiber or mansonite board rated 1600 degC) is placed on the edges
of each box.

4.3. Mixing
The castable is mixed in a motorized rotary cement mixer.
WARNING! Water content of the mixture is important since too much water adversely affects the
castable porosity and cold crushing strength. Follow the manufacturers instruction.
Place 5 to 6 bags in the mixer and rotate for about 1 minute.
Add about 80% of the required water content and mix for about 2 minutes.
Stop the mixer and let it rest for about a minute and test for consistency using ball-hand test.
If necessary, add the remaining 20% of the water, mix then repeat the ball-hand test

4.4. Ball-Hand Test


Collect a handful of the mixed castable and roll to form a ball.
Correct consistency is attained when the ball is formed and remains in firm shape and does not
disintegrated when tossed up and down.
If correct water content, no water should seep out when squeezed.

Page 6 of 7 printed on 11/1/2017


PROCEDURE FOR INSTALLING REFRACTORY LINING
AT RK2 KILN OUTLET

4.5. Pouring (Rotocasting Method)


Pouring of castable is started from 8 o clock position so as to settle well in the shutter box and
prevent concentric segregation
The castable mix is poured into the box and compacted by pneumatic vibration.
Compaction is done over the whole volume to remove all air inclusions.

Vibration should not exceed 5 minutes on each area to avoid segregation of particles. When
complete, the surface of the refractory should appear shiny.
Carefully withdraw the vibrating needle to prevent formation of an air bubble
Pierce a steam escape hole using a steel needle and leave to set for 30 45 minutes

4.6. Curing
Every casted segment must be left to cure for 30 to 45 minutes
Rotation of the tube can be done only when the surface is firm

4.7. Drying
At the kiln outlet, drying is done by the main burner during warming
Rapid increase of surface temperature from flame radiation can be controlled by covering the nose
ring area with 3 mm mineral fiber blankets.

Page 7 of 7 printed on 11/1/2017

You might also like