BP PROFESSIONAL & REVIEW CENTERS Project Start Date: 01-Feb-16

Project Finish Date: 06-May-17


PPSS Sample Project Data Date: 01-Feb-16;
WORKING SCHEDULE AS OF 01 FEB. 2016 Print Date: 29-Jan-16
Activity ID Activity Name Dur Start Finish Calendar 2016 2017
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May un
-
PPSS S
Sample Project 361 01-Feb-16 06-May-17
6 06-M

ENGINEERING & PROCUREMENT SUBMITTA


ENGIN 80 07-Feb-16 09-May-16 6-day Workweek w/o O.T.
16 09-May-16, ENGINEERING & PROCUREMENT SUBMITTALS
ENGINEERING (DRAWINGS)
ENGINE 80 07-Feb-16 09-May-16 6-day Workweek w/o O.T.
16 09-May-16, ENGINEERING (DRAWINGS)
400 Structural Shop Drawings 70 07-Feb-16 27-Apr-16 6-day Workweek w/o O.T.
410 Mechanical Shop Drawings 70 07-Feb-16 27-Apr-16 6-day Workweek w/o O.T.
420 Electrical Shop Drawings 70 07-Feb-16 27-Apr-16 6-day Workweek w/o O.T.
430 Architectural Shop Drawings 70 07-Feb-16 27-Apr-16 6-day Workweek w/o O.T.
440 Site Shop Drawings 70 07-Feb-16 27-Apr-16 6-day Workweek w/o O.T.
450 Finish Submittals 0 09-May-16 6-day Workweek w/o O.T. 09-May-16

PROCUREMENT (AR/STR)
PROCU 80 07-Feb-16 09-May-16 6-day Workweek w/o O.T.
16 09-May-16, PROCUREMENT (AR/STR)
100 Start Submittal 0 07-Feb-16 6-day Workweek w/o O.T.
110 Architectural & Structural Materials 80 07-Feb-16 09-May-16 6-day Workweek w/o O.T.
PROCUREMENT (MECH)
PROCU 80 07-Feb-16 09-May-16 6-day Workweek w/o O.T.
16 09-May-16, PROCUREMENT (MECH)
200 Mechanical Material 80 07-Feb-16 09-May-16 6-day Workweek w/o O.T.
PROCUREMENT (ELEC)
PROCU 80 07-Feb-16 09-May-16 6-day Workweek w/o O.T.
16 09-May-16, PROCUREMENT (ELEC)
300 Electrical Material 80 07-Feb-16 09-May-16 6-day Workweek w/o O.T.

CONSTRUCTION
CONS 375 01-Feb-16 29-Apr-17 6-day Workweek with O.T.
6 29-Ap
BUILDING
BUILDIN 375 01-Feb-16 29-Apr-17 6-day Workweek with O.T.
6 29-Ap
GENER
GENERAL REQUIREMENTS 7 01-Feb-16 09-Feb-16 6-day Workweek with O.T.
6 09-Feb-16, GENERAL REQUIREMENTS
1000 Project Start 0 01-Feb-16 6-day Workweek with O.T.
1010 Mobilization/Grading/Leveling 7 01-Feb-16 09-Feb-16 6-day Workweek with O.T.
SITEWO
SITEWORKS 84 09-Feb-16 17-May-16 6-day Workweek with O.T.
16 17-May-16, SITEWORKS
2000 Excavation/Termite Control 15 09-Feb-16 27-Feb-16 6-day Workweek with O.T.
2010 BF up to Bot. of Grade Beams 8 10-Apr-16 19-Apr-16 6-day Workweek with O.T.
2020 BF up to Bot. of Grade Slab 8 08-May-16 17-May-16 6-day Workweek with O.T.
SUBST
SUBSTRUCTURE 81 27-Feb-16 31-May-16 6-day Workweek with O.T.
eb-16 31-May-16, SUBSTRUCTURE
3000 Lean Concrete 4 27-Feb-16 02-Mar-16 6-day Workweek with O.T.
3010 FRP Footings 16 02-Mar-16 21-Mar-16 6-day Workweek with O.T.
3020 FRP Column Necks 17 21-Mar-16 10-Apr-16 6-day Workweek with O.T.
3030 FRP SafeDep & Cash Vault 17 21-Mar-16 10-Apr-16 6-day Workweek with O.T.
3040 FRP Grade Beams 16 19-Apr-16 08-May-16 6-day Workweek with O.T.
3050 FRP Grade Slabs 12 17-May-16 31-May-16 6-day Workweek with O.T.

Summary Remaining Work Date Revision Checked Approved


Project : PRIMA 1 - PPSS Sample Project
01-Feb-16 Issued for Approval BPA MPLACE
Milestone Actual Work Layout Name : SAMPLE CALENDAR LAYOUT
Critical Remaining Work Project Baseline Bar TASK filter: All Activities
Page 1 / 4
Activity ID Activity Name Dur Start Finish Calendar 2016 2017
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May un
-
SUPER
SUPERSTRUCTURE 61 31-May-16 25-Aug-16 6-day Workweek with O.T.
31-May-16 25-Aug-16, SUPERSTRUCTURE
3060 FRP GF Columns 17 31-May-16 30-Jun-16 6-day Workweek with O.T.
3070 FRP SD/CV Walls & Top Slab 17 31-May-16 30-Jun-16 6-day Workweek with O.T.
3080 FRP Roof Slab 32 30-Jun-16 11-Aug-16 6-day Workweek with O.T.
3090 Concrete Pads Roof Deck 7 11-Aug-16 20-Aug-16 6-day Workweek with O.T.
3100 Concrete Steps Ground Floor 5 20-Aug-16 25-Aug-16 6-day Workweek with O.T.
3110 Finish Structural Works 0 25-Aug-16 6-day Workweek with O.T. 25-Aug-16
MASON
MASONRY 32 25-Aug-16 02-Oct-16 6-day Workweek with O.T.
25-Aug-16 02-Oct-16, MASONRY
4000 Internal Block Works 32 25-Aug-16 02-Oct-16 6-day Workweek with O.T.
METALS 153 02-Oct-16 29-Mar-17 6-day Workweek with O.T.
02-Oct-16 29-Mar-17,
5000 Roof Cantilever 20 02-Oct-16 25-Oct-16 6-day Workweek with O.T.
5010 Hand Rails & Door Mats 10 18-Mar-17 29-Mar-17 6-day Workweek with O.T.
WOODS & PLASTIC 15 03-Jan-17 21-Jan-17 6-day Workweek with O.T.
03-Jan-17 21-Jan-17, WOODS & P
6000 Teller Counter 15 03-Jan-17 21-Jan-17 6-day Workweek with O.T.
THERM
THERMAL & MOISTURE PROTECTION 178 27-Feb-16 06-Oct-16 6-day Workweek with O.T.
eb-16 06-Oct-16, THERMAL & MOISTURE PROT
7000 Vapor Barrier / Damproofing 50 27-Feb-16 25-Apr-16 6-day Workweek with O.T.
7010 Light Foam / Membrane 7 25-Aug-16 03-Sep-16 6-day Workweek with O.T.
7020 Insulation Board & Geotextile Membrane 3 03-Sep-16 06-Sep-16 6-day Workweek with O.T.
7030 Terrazo Tiles Roof Deck 4 06-Sep-16 11-Sep-16 6-day Workweek with O.T.
7040 Waterproofing Toilet 4 02-Oct-16 06-Oct-16 6-day Workweek with O.T.
DOORS & WINDOWS 30 28-Dec-16 01-Feb-17 6-day Workweek with O.T.
28-Dec-16 01-Feb-17, DOORS &
8000 Doors & Windows 30 28-Dec-16 01-Feb-17 6-day Workweek with O.T.
FLOOR FINISHES 80 02-Oct-16 03-Jan-17 6-day Workweek with O.T.
02-Oct-16 03-Jan-17, FLOOR FINISH
9000 Concrete Screed 5 31-Oct-16 06-Nov-16 6-day Workweek with O.T.
9010 Sweet Gold Granite 25 29-Nov-16 28-Dec-16 6-day Workweek with O.T.
9020 Crema Marfil Marble Flooring 25 29-Nov-16 28-Dec-16 6-day Workweek with O.T.
9030 Ceramic Tile Toilet 25 29-Nov-16 28-Dec-16 6-day Workweek with O.T.
9040 Carpet Tiles 15 11-Dec-16 28-Dec-16 6-day Workweek with O.T.
9050 Skirting 5 28-Dec-16 03-Jan-17 6-day Workweek with O.T.
9060 Plaster for Parapet 15 02-Oct-16 19-Oct-16 6-day Workweek with O.T.
WALL FFINISHES 179 02-Oct-16 29-Apr-17 6-day Workweek with O.T.
02-Oct-16 29-Ap
9070 Plaster Internal/External Walls 25 02-Oct-16 31-Oct-16 6-day Workweek with O.T.
9080 Ceramic Wall Tiles 15 31-Oct-16 17-Nov-16 6-day Workweek with O.T.
9090 Crema Marfil Wall Cladding 25 31-Oct-16 29-Nov-16 6-day Workweek with O.T.
9100 Wooden Panels 25 28-Dec-16 26-Jan-17 6-day Workweek with O.T.
9110 Preliminary Paint 25 28-Dec-16 26-Jan-17 6-day Workweek with O.T.
9120 Alucomat External Cladding 26 28-Dec-16 28-Jan-17 6-day Workweek with O.T.
9130 Alpolic Internal/ATM Cladding 25 28-Jan-17 26-Feb-17 6-day Workweek with O.T.

Summary Remaining Work Date Revision Checked Approved


Project : PRIMA 1 - PPSS Sample Project
01-Feb-16 Issued for Approval BPA MPLACE
Milestone Actual Work Layout Name : SAMPLE CALENDAR LAYOUT
Critical Remaining Work Project Baseline Bar TASK filter: All Activities
Page 2 / 4
Activity ID Activity Name Dur Start Finish Calendar 2016 2017
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May un
-
9140 Stainless (30/80cm) Cladding 15 26-Feb-17 15-Mar-17 6-day Workweek with O.T.
9150 Poster, Internal Signage 10 15-Mar-17 27-Mar-17 6-day Workweek with O.T.
9160 Aluminum Light Cove 25 27-Mar-17 25-Apr-17 6-day Workweek with O.T.
9170 Flex Light Box 3 25-Apr-17 29-Apr-17 6-day Workweek with O.T.
9180 Painting 20 28-Jan-17 20-Feb-17 6-day Workweek with O.T.
9190 Glass Cladding Work 25 20-Feb-17 21-Mar-17 6-day Workweek with O.T.
9200 Bulk Head 15 21-Mar-17 08-Apr-17 6-day Workweek with O.T.
CEILING FINISHES 63 03-Jan-17 18-Mar-17 6-day Workweek with O.T.
03-Jan-17 18-Mar-17, CE
9210 Cement Plaster 7 03-Jan-17 11-Jan-17 6-day Workweek with O.T.
9220 Alum Cladding Roof Eaves 25 03-Jan-17 01-Feb-17 6-day Workweek with O.T.
9230 Gypsum Board & Diffusers 25 01-Feb-17 02-Mar-17 6-day Workweek with O.T.
9240 Paint Ceiling(Prep & First Coat) 8 02-Mar-17 12-Mar-17 6-day Workweek with O.T.
9250 Paint Ceiling Final Coat 5 12-Mar-17 18-Mar-17 6-day Workweek with O.T.
SPECIA
SPECIALTIES 20 15-Mar-17 08-Apr-17 6-day Workweek with O.T.
15-Mar-17 08-Apr-17
10000 Glass Partitons 12 15-Mar-17 29-Mar-17 6-day Workweek with O.T.
10010 Mirrors & Toilet Accessories 8 29-Mar-17 08-Apr-17 6-day Workweek with O.T.
EQUIPM
EQUIPMENTS 6 08-Apr-17 15-Apr-17 6-day Workweek with O.T.
08-Apr-17 15-Apr-1
11000 Cabinets 6 08-Apr-17 15-Apr-17 6-day Workweek with O.T.
MECHA
MECHANICAL 276 19-Apr-16 22-Mar-17 6-day Workweek with O.T.
19-Apr-16 22-Mar-17, M
15000 Plumbing Sanitary 1 7 19-Apr-16 27-Apr-16 6-day Workweek with O.T.
15010 Plumbing Sanitary 2 5 14-Jul-16 20-Jul-16 6-day Workweek with O.T.
15020 Plumbing Water Supply/Heater 8 04-Sep-16 13-Sep-16 6-day Workweek with O.T.
15030 Sanitary Fixtures, Roof Drain 10 04-Sep-16 15-Sep-16 6-day Workweek with O.T.
15040 Air Distribution System 10 04-Sep-16 15-Sep-16 6-day Workweek with O.T.
15050 FCU, ACCU, PACU 20 24-Sep-16 17-Oct-16 6-day Workweek with O.T.
15060 Fiber Glass Water Tank 8 17-Oct-16 26-Oct-16 6-day Workweek with O.T.
15070 Grills & Diffusers 7 02-Mar-17 11-Mar-17 6-day Workweek with O.T.
15080 Fire Protection System 10 11-Mar-17 22-Mar-17 6-day Workweek with O.T.
ELECTR
ELECTRICAL 202 31-May-16 06-Feb-17 6-day Workweek with O.T.
31-May-16 06-Feb-17, ELECTRI
16000 Grounding, Conduits 15 31-May-16 26-Jun-16 6-day Workweek with O.T.
16010 Lighting Points Conduiting, Wiring 10 04-Sep-16 15-Sep-16 6-day Workweek with O.T.
16020 Conduiting, Wiring for Split 10 04-Sep-16 15-Sep-16 6-day Workweek with O.T.
16030 MDP, Panel Boards, Main Feeders 10 31-Oct-16 12-Nov-16 6-day Workweek with O.T.
16040 Floor Boxes 10 12-Nov-16 23-Nov-16 6-day Workweek with O.T.
16050 Equipments & Devices 15 23-Nov-16 11-Dec-16 6-day Workweek with O.T.
16060 Ligthing Fixtures 15 11-Dec-16 28-Dec-16 6-day Workweek with O.T.
16070 Tele & Accessories 7 28-Dec-16 05-Jan-17 6-day Workweek with O.T.
16080 Breaker & Q-Net System 15 05-Jan-17 23-Jan-17 6-day Workweek with O.T.

Summary Remaining Work Date Revision Checked Approved


Project : PRIMA 1 - PPSS Sample Project
01-Feb-16 Issued for Approval BPA MPLACE
Milestone Actual Work Layout Name : SAMPLE CALENDAR LAYOUT
Critical Remaining Work Project Baseline Bar TASK filter: All Activities
Page 3 / 4
Activity ID Activity Name Dur Start Finish Calendar 2016 2017
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May un
-
16090 Neon Lights 12 23-Jan-17 06-Feb-17 6-day Workweek with O.T.
SITE DEVELOPMENT
DE 272 11-Feb-16 09-Jan-17 6-day Workweek with O.T.
-16 09-Jan-17, SITE DEVELO
WATER TANK 52 11-Feb-16 12-Apr-16 6-day Workweek with O.T.
-16 12-Apr-16, WATER TANK
20000 Water Tank Earthworks 5 11-Feb-16 17-Feb-16 6-day Workweek with O.T.
20010 Water Tank Lean Concrete 4 17-Feb-16 22-Feb-16 6-day Workweek with O.T.
20020 Water Tank Water Proofing 10 22-Feb-16 05-Mar-16 6-day Workweek with O.T.
20030 Water Tank Concrete Slab/Wall/Roof 23 05-Mar-16 31-Mar-16 6-day Workweek with O.T.
20040 Water Tank Backfilling 10 31-Mar-16 12-Apr-16 6-day Workweek with O.T.
SEPTIC TANK 52 11-Feb-16 12-Apr-16 6-day Workweek with O.T.
-16 12-Apr-16, SEPTIC TANK
20050 Septic Earthworks 5 11-Feb-16 17-Feb-16 6-day Workweek with O.T.
20060 Septic Lean Concrete 4 17-Feb-16 22-Feb-16 6-day Workweek with O.T.
20070 Septic Water Proofing 10 22-Feb-16 05-Mar-16 6-day Workweek with O.T.
20080 Septic Concrete 23 05-Mar-16 31-Mar-16 6-day Workweek with O.T.
20090 Septic Backfilling 10 31-Mar-16 12-Apr-16 6-day Workweek with O.T.
FENCE 220 12-Apr-16 09-Jan-17 6-day Workweek with O.T.
12-Apr-16 09-Jan-17, FENCE
20100 Fence Earthworks 10 12-Apr-16 24-Apr-16 6-day Workweek with O.T.
20110 Fence Lean Concrete 3 24-Apr-16 27-Apr-16 6-day Workweek with O.T.
20120 Fence Concrete Footing 10 27-Apr-16 09-May-16 6-day Workweek with O.T.
20130 Fence Column Neck 10 09-May-16 21-May-16 6-day Workweek with O.T.
20140 Fence Ground Beams 12 21-May-16 04-Jun-16 6-day Workweek with O.T.
20150 DampProofing & Backfilling 12 04-Jun-16 26-Jun-16 6-day Workweek with O.T.
20160 Block Works 15 27-Jun-16 21-Jul-16 6-day Workweek with O.T.
20170 Columns / Tie Beams 12 21-Jul-16 04-Aug-16 6-day Workweek with O.T.
20180 Painting 10 28-Dec-16 09-Jan-17 6-day Workweek with O.T.
OTHERS 108 04-Aug-16 08-Dec-16 6-day Workweek with O.T.
04-Aug-16 08-Dec-16, OTHERS
20190 Manholes 7 04-Aug-16 13-Aug-16 6-day Workweek with O.T.
20200 Curbstone 35 13-Aug-16 22-Sep-16 6-day Workweek with O.T.
20210 Landscaping 40 22-Sep-16 08-Nov-16 6-day Workweek with O.T.
20220 Holland Interlocking Tiles/Granite Band 40 22-Sep-16 08-Nov-16 6-day Workweek with O.T.
20230 Asphalt 8 08-Nov-16 17-Nov-16 6-day Workweek with O.T.
20240 Concrete Wheel Stopper 5 17-Nov-16 23-Nov-16 6-day Workweek with O.T.
20250 Raised Planter 10 23-Nov-16 05-Dec-16 6-day Workweek with O.T.
20260 Sewage Connection 3 05-Dec-16 08-Dec-16 6-day Workweek with O.T.

CLOSE OUT 6 30-Apr-17 06-May-17 6-day Workweek w/o O.T.


30-Apr-17 06-M
30000 Final Testing & Commissioning 3 30-Apr-17 02-May-17 6-day Workweek w/o O.T.
30010 Punch List, Hand Over 3 03-May-17 06-May-17 6-day Workweek w/o O.T.
30020 Project Finish 0 06-May-17 6-day Workweek w/o O.T. 06-M

Summary Remaining Work Date Revision Checked Approved


Project : PRIMA 1 - PPSS Sample Project
01-Feb-16 Issued for Approval BPA MPLACE
Milestone Actual Work Layout Name : SAMPLE CALENDAR LAYOUT
Critical Remaining Work Project Baseline Bar TASK filter: All Activities
Page 4 / 4