Professional Documents
Culture Documents
AUDITORS: ANSH ENERGY SOLUTIONS PVT. LTD., Gayatri Dham, Lower Bazar,
Modinagar – 201204 (UP)
Page | 0
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
Contents
S.No. Description Page No.
1. Executive Summary 2
2. Overview 4
3. Scope of Audit 4
4. Assumptions 5
5. Equipment Verbal Picture 5
6. Energy management Plan 7
7. Maintenance recommendations 8
8. Technical Supplement 8
9. Standard Calculations and Assumptions 17
10. SWOT 19
11. Thermal references 20
12. Appendix – 1 21
13. Appendix – 2 23
14. Electrical bill analysis 2008 24
15. Electrical Bill Analysis 2009 25
16. Electrical Parameters 32
17. Harmonics 41
18. Motor Power Factor 47
19. Scope of Energy Savings in electrical motors 56
20. Comparison of Low efficiency and EED 60
21. Conversion of LV Drives to MV drives 74
pg. 1
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
EXECUTIVE SUMMARY
The boiler in this report is referred as Boiler No. 1 (IBL). The efficiency was calculated as
below:
Boiler 1 Boiler 2
Average Direct Efficiency 80.20 % NA
The operation has been observed carefully and few areas of carelessness have been
observed. The best achievable efficiencies of 85% + have a path of nearly 5% to be
travelled and continuous monitoring and efforts are required.
The suggested methodology of improvement is diagrammatically represented as below:
pg. 2
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
pg. 3
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
OVERVIEW
The client M/s Sandeep Paper Mills (P) Ltd. with registered office at A-20/6, Noida is
operating for production of various grades of paper for which utilities used are Steam,
Water, Compressed air and Electricity (Grid power). The top management of company
includes Mr. Jatinder Singh Jolly and Mr. Sandeep Arora (ED) and they are committed to
cost reduction and energy conservation for betterment of company as well as
environment. The Audit has been done specifically for the steam generating unit and
Electricity Load Distribution. Company possesses 6 TPH capacity of steam generation F &
A 100oC with pressure rating of 10 kg/cm2 and a CD of 1250 KVA at 33,000V distributed
through a 1250 KVA 33KV/433V single Core outlet transformer. The target is to achieve
a reduction of recurring cost to improve business viability.
Scope of Audit
The aim and scope of audit is to quantify and justify the fuel consumption as well as
energy consumption and consumption quality, total and specific steam generation,
boiler efficiency monitoring, load balancing, run-ability optimization and achieving best
possible fuel to steam ratio. The audit will thus cover parameter detection of:
1. Feed water inlet flow.
2. Blow Down flow estimation (If possible).
3. Inlet air temperature.
4. Temperature of exhaust to stack.
5. Feed water quality.
6. Cycle of concentration
7. Variance in phase loading of motors ACB’s and Transformer
8. Heat loss in cabling
9. Heat loss due to poor operation of motors
10. Losses due to poor capacitor behavior or installation faults.
11. Losses due to uneven load pattern.
12. Losses due to voltage variations.
pg. 4
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
The completion of audit will achieve identification of all types of boiler losses and
almost all possible ECOs (Energy Conservation Opportunities). It will highlight the
efficiency improvement possibilities in motors, capacitors and voltage variations.
This inspection report reflects the conditions of the equipment at the time of the inspection only.
Please note that equipment conditions change with time and use and the conditions noted in this
report may change in appearance and severity as time progresses or with mishandling. Hidden or
concealed defects cannot be included in this report. An earnest effort was made on our behalf to
discover all fallacies; however in the event of an oversight no liability is acceptable. No warranty is
either expressed or implied. This report is not an insurance policy, nor a warranty service.
pg. 5
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
2. Boiler no.2 is similar to above boiler in make and fire side arrangement however
it carries a Brownian furnace and is capable of burning baggasse as fuel.
The electrical circuit consists of an incoming state electricity board line of 33KV which is
received by a 1250 KVA 33/0.433KV single transformer. The transformer is installed with
OLTC AVR and is capable of handling voltage range of +7.5% to – 12.5% of the rated
incomer. The State owned meter and VCB precedes transformer. Multiple single core
cables carry energy from transformer to the MCC which is installed with ACB through
which 2 Separate PCC are connected.
The plant operates mostly inductive load along with some inverting electronic load to
govern the use of inductive load. The premises has been observed to be maintaining
good power factor and good voltage conditions however ACBs installation seems to be
very negligent.
A wide range of VFDs have been installed to compensate for major electrical energy
losses and more or less the aim has been successfully achieved.
pg. 6
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
pg. 7
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
Maintenance Recommendations
The following maintenance activities need constant attention:
1. The furnace fire doors need to be proper and closed during operation to avoid
major heat loss at temperatures nearly 900oC. The ambient temperature at 2
mtrs of distance from furnace fire doors was found to be 74 degree celcius which
is dramatically high. WE RECOMMEND USE OF CI DOORS WITH INTERNAL LINING
OF FIRE PROOF CEMENT.
2. Record should be kept, monitored and counter checked for APH cleaning in Boiler
1 as it was observed to be carrying fly ash in itself despite of rotary dust remover
at bottom.
3. The feed water quality needs to be monitored very closely as this may lead to
corrosion and slow damage.
> ? @
A
B
Finally, <%#". " %=%"-=/ 0
@>
pg. 8
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
pg. 9
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
pg. 10
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
pg. 11
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
pg. 12
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
pg. 13
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
pg. 14
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
d) Loss due to furnace leakage can be brought down by nearly 1 % in this case as
the furnace doors and feed hoppers allow lot of heat to escape. This is due to
carelessness of man power involved and due to absence of any provision of
keeping the furnace pressure negative. The flames have been evidently
coming out due to furnace high pressure. The best solution to this problem
shall be to control fan speeds by variable speed drives for which controls are
either with wise operators or alternately a pressure transmitter controls the
flow of FD air.
e) Lastly the blow down losses has been observed to be very high. The water test
report clearly indicates the malpractice being followed. The blow down
should only be made when TDS of drum water reaches 3500ppm. The present
values show operation at very low cycle of concentrations which lead to heat
loss and more significantly costly water loss. The drum pH is also low. The
ideal pH shall be 11. The solution to above mentioned problem is either
vigilant checking of water parameters or installation of an automatic blow
down control system.
f) The list of improvements suggested is not exhaustive and can be revisited.
Further suggested approach is pinch analysis.
pg. 15
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
Now, Oxygen monitoring can reduce excess oxygen by 6% in flue gases. This will
lead to increase in efficiency by 4% in boiler 1.
Thus saving of boiler 1 shall be 4 x Rs. 104028 per month = Rs. 416114
KL
Hence simple payback for Continuous oxygen probe in boiler 1 = 30 0
MNM
19 (/ and
P
Alternatively payback for one portable probe shall be = 30 0 5.76 (/
MNM
However the most lucrative option shall be a continuous monitoring probe for
boiler 1 as it will also iron out any possibilities of man power negligence.
There is as strong need to bring down the radiation and surface losses to under 1
% i.e. savings of 1.76 % or saying monetarily = 1.76 R 104028 0 ST. UVWXVY
pg. 16
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
The tentative investment in fire doors and better mud coating and insulation all
together is estimated to be Rs. 40,000.
M
Hence a payback period of R 30 (/ 0 6.55 is attainable which is
PZP[
remarkable.
We strongly recommend immediate change of fire doors and better coating of
boiler and water wall body.
Audit Recommendations
The point wise recommendations are listed below:
1. Installation of Continuous oxygen monitoring on stack of boiler no. 1
2. Adequate staff training and cross checking so as to control blow down frequency
and water’s operating parameters.
3. For maintaining feed water pH we shall suggest installation of a water softener
with capacity of 2 m3/hr. this softener shall feed the RO plant totally and 0.3
m3/hr shall be bypassed directly from RO plant i.e. 0.3 m3/hr shall flow directly
from softener to feed water tank. Alternatively pH booster chemical should be
used as per demand to maintain the pH.
4. The doors of furnace need to be changed to CI casted fire grade doors with cavity
on back so as to be filled with casteable cement for reduction in heat loss.
Appendix
1. Lab Testing Reports.
2. Data collection tables.
pg. 17
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
3. SWOT Analysis.
pg. 18
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
SWOT Analysis
STRENGTHS WEAKNESSES
1. Sufficient Capacity installed. 1. Unavailability of process
2. Availability of down time for instrumentation.
installation of additional 2. Negligence of staff to monitor actual
equipments as interconnecting parameters.
pipeline is already installed.
3. Willingness of management for
improving existing set-up
OPPORTUNITIES THREATS
1. Vast scope of improvement of 1. Instrumentation if installed might
efficiencies. not work properly due to lack of
2. Reduction of loss can be monitoring or knowledge.
achieved by using 2. Biased mindset regarding possibility
instrumentation and of improvements.
monitoring. 3. Lack of equipment maintenance.
3. Monitoring instruments are
readily available in market so
no long lead times.
pg. 19
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
References
1. BEE Manual on Energy Efficiency testing (Book 4)
2. www.emerson.com
3. Perry’s Handbook of Chemical Engineers (2003)
4. www.lenntech.com/boiler-feedwater.htm
pg. 20
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
Appendix 1
Qualitative Analysis
PURPOSE
The purpose of this experiment is to identify the boiler operating parameters by getting to know the
TDS, Alkalinity and ph of blow down and feed water of boiler system. The results will help in better
water management and thus will let us control the proper operation practices to enhance equipment
life and maintain low fuel consumption.
DATA
STEP SUBSTANCE Parameter (Std. RESULT INFERENCE
Value)
pH (11-12) A lot of fresh
1 Blow down water 9.20 treated water is
Boiler 1 being inputted or
excessive blow
down is being
operated.
Excessive Blow
2 Blow down water T. Alk as CaCO3 140 ppm Down Operation.
Boiler 1 (750 ppm)
pg. 21
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
Conclusions
Boiler water monitoring at site is poor and careless. Excessive blow down is being operated and lot of
valuable heat is being wasted. The water treatment for feed water is done by complete Reverse Osmosis
Plant. However this plant is usually not suitable to maintain pH and hardness of feed water. The
observed pH is neutral which could cause mild damage to the boiler tubes and drum. Also the Hardness
of water is higher than the set limits.
Recommendations
Installation of a Soft water treatment plant and that soft water should be inputted to RO system. Only
60% of total feed water should go through RO plant and balance 40% should be taken from softener
itself so as to maintain pH value. The operation of such a system after installation is to be monitored
strictly so that the ratio of 60:40 shall be balanced as per site requirements.
pg. 22
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
APPENDIX - 2
Client: M/s Sandeep Paper Mills Pvt. Ltd., A-20/6, Noida
Tests to be done: Proximate Analysis of Fuel, Ultimate Analysis of Fuel, GCV
Sample collected by: Dr. Shubhangi Gupta (MD, AESPL)
Sample collection date: 20.01.09
Sample: Petcoke (Source Jamnagar Refinery of Reliance Industries Ltd.)
Qualitative Analysis
PURPOSE
The purpose of this experiment is to identify the Fuel Chemical Composition so the reaction and
consequences inside the furnace can be calculated. The results will help in better Furnace operation,
loss detection and will let us control the proper operation practices to enhance equipment life and
maintain low fuel consumption.
pg. 23
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
pg. 24
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
14 AVG 1060 206573 0.99 169805 233316 107718 510840 1788564 1956208 3.85
SD 35671.92 58208.91 27366.23 117480.125
Page | 24
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
pg. 25
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
1200
1126 1106
1099 1099 1080 1074 1072 1064
1000 1023
987 980
925
800
600
400
200
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
pg. 26
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
1
1.00
0.995 0.99 0.99 0.99 0.99 0.99 0.99
0.99 0.99 0.99
0.99
0.985
0.98
0.98
P. F.…
0.975
0.97
0.97
0.965
0.96
0.955
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
pg. 27
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
4.50
3.50
3.00
2.50
2.00
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
pg. 28
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
1140
1129
1120
1100
1092
1085
1080
1072 1070
1060 1059 1059 1056
1044
1040 1039
1034
1020 1018
1000
980
960
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
pg. 29
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
0.990 0.990
0.99 0.989
0.987 0.987
0.986 P. F.…
0.985
0.98
0.975
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
pg. 30
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
4.50
4.26
4.00
3.96
3.86 3.82 3.85
3.78 3.76 3.75
3.71 3.72
3.63 3.64
3.50
3.00
2.50
2.00
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
pg. 31
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
L. T. side measurement:
Voltage - R - Y = 411 V Current - R phase = 917 Amp
Y - B = 417 V Y phase = 945 Amp
B - R = 412 V B phase = 909 Amp
Average phase to phase Voltage = 413 V Average phase Current = 924 A
Average Measured Power Factor:- 0.996
∴ % Loading on Transformer
NP.Z ^
0 0 52.66%
K
Page | 32
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
nopqop r UXX
% ghhijikljm 0
nopqop b stTTkT
ukvTowkT nopqop r UXXX r UXX
0
ukvTowkx nopqop r UXXX b ys b ss r z{
Where,
NL = No load Losses in Watts
LL = Load losses in watts at full load at 75 C
TF = Temperature correction factor
PF = Load power factor
The basic D.C. resistance copper losses are assumed to be 90% of the load losses.
Eddy current losses (in conductors) are assumed to be 10% of the load losses.
Basic I2R losses increase with temperature, while eddy losses decreases with
increase in temperature. Thus, 90% of the load losses vary directly with rise in
temperature and 10% of the load losses vary inversely with temperature.
pg. 33
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
Calculations are done for an assumed temperature rise, and the rise in
temperature is dependent on the total losses to be dissipated.
Rt – op = F + T amb + T rise
Rt – ref F + T ref
pg. 34
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
pg. 35
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
L. T. side measurement:-
Voltage:- R to Y = 422 V Current:- R phase = 1024 Amp
Y to B = 436 V Y phase = 1098 Amp
B to R = 434 V B phase = 1001 amp
We have observed that you already have OLTC voltage control panel but it is
running on Last step of its setting. So we are giving you some other suggestion for
voltage balance in your system.
a. Lighting loads of the plants are to equally balance on all the three phases.
b. Single-phase motor loads of the plants are to equally balance on all the three
phases
c. All the loose connections in the plants are to be tightened.
d. Request power supply board. to tightened their H.T. line connections for
balancing incoming loads.
pg. 37
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
pg. 38
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
Im Io
pg. 39
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
Assuming, transformer works 365 days in a year. The no load losses generated
during the year as under.
6 % of No load losses of the year = 17520 KW H x 0.06 = 1051.20 KWH say 1052
KWH
(Detailed calculation In Final Report)
Cost of 6 % no load losses of the year = 1052 KWh x Rs. 3.81/-
(Average unit rate for year – 2009)
= Rs. 4008.12/- say Rs. 4010/- per year.
pg. 40
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
What is Harmonics:-
At the time of the designing any A.C. machine, it is assumed that voltage and
current wave from at the output terminals of A. C. machines is assumed to be
sinusoidal and consists of only one frequency which is called fundamental
frequency or 1st harmonics and such sinusoidal wave from dose not contain
harmonics of other frequency.
Due to non linear system load such as thyristorised control, variable frequency
drive and D. C. motor, a harmonics are generated at the output side of the A.C.
machines and hence original sinusoidal wave form are disturbed and wave form
becomes complex and non sinusoidal in nature generating 2nd, 3rd, 4th and so on
frequencies of the fundamental frequency.
The above phenomenon is shown in the below given diagram.
These 2nd, 3rd, 4th frequencies are called harmonics of the fundamental frequency.
In short waveform with frequencies other than fundamental frequency is called
harmonics.
2nd, 4th etc frequencies are called even harmonics and 3rd, 5th, 7th, etc frequencies
are called harmonics.
Harmonics in transformer:-
The non-sinusoidal nature of the magnetizing current necessary to produce a sine
wave of flux produces harmonics in current and voltage wave –forms of the three
phase transformers.
pg. 41
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
Arcing Devices
1. Discharge lighting.
2. Arc furnaces, welding equipments.
Ferromagnetic devices.
1. Transformers operating near saturation level.
2. Magnetic ballasts.
3. Induction heating equipment chokes.
Appliances
1. TV sets air conditioners, washing machines, and microwave
ovens.
2. Fax machines, photocopiers, and printers.
Higher RMS current and voltage in the system are caused by
harmonic currents, which can result in any of the problems listed
below:
1. Blinking of Incandescent Lights- Transformer Saturation.
2. Capacitor Failure- Harmonic Resonance.
3. Circuit Breakers Tripping- Inductive Heating and Overload.
4. Electronic Equipment Shutting down- Voltage Distortion.
5. Flickering of Fluorescent lights- Transformer Saturation.
6. Fuses Blowing for no apparent reason- Inductive heating and
Overload.
pg. 42
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
Overcoming Harmonics
Tuned Harmonics filters consisting of a capacitor bank and reactor in
series are designed and adopted for suppressing harmonics by
providing low impedance path for harmonic component. The
harmonic filters connected suitably near the equipment generating
harmonics help to reduce THD to acceptable limits. For overcoming
and troubleshooting of some problems in the electrical power system
pg. 43
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
Observations-
1. THD Levels in both Voltage and Current are above the permissible limits.
This is because of many VFD Drives in your system.
2. These higher THD Level create problems in system for example ACB tripping
without any fault flag, Burning of capacitors, Motor winding Bursting,
Frequent tripping of machinery on voltage fluctuation, and we advise to
install harmonic Filters in your Electrical network.
In case of alternating current power supply system current is always lag behind
the voltage. This is due to the fact that the A.C. machines works on the principle
of electromagnetic induction and these A.C. machines consume reactive power
for their own needs for formation of magnetic flux and this phenomenon will
cause current vector to lag behind the voltage vector and this will generates the
P.F. in the system. The above fact is shown in below sine wave diagram.
pg. 44
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
Here we can discuss the use of static capacitor and there advantages for
improving
pg. 45
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
∴ When static capacitor is connected parallel to the inductive load, the inductive
load starts receiving reactive power of opposite nature at leading power factor
from the capacitors and thus this reactive power neutralizes the inductive power
requirement of the load and thereby improves the P. F. of the load.
The above Explanations are made simple with the below mentioned Vector
Diagram.
pg. 46
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
Vector diagram and physical diagram of inductive load with use of capacitor
pg. 47
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
pg. 48
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
Vector Diagram
Reactive power-(KVAr) = 0
-: Vector Diagram :-
pg. 49
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
Line Current = I (line) at P.F of 0.90 = 155 Amp./ 0.80 = 194 Amp
Active Current = I active = I(line) x Cos ↓ = 194 x 0.80 = 155 Amp
Reactive Current = I reactive = I(line) x Sin ↓ = 194 x 0.599 = 116 Amp
-: Vector Diagram :-
Active power – (KW) = 100 KW
↓ = 36.8°
Voltage Vector - V
Reactive power–(KVAr) = 75
Current vector - A
From the above vector diagrams and below mentioned calculation it can be
seen that at
(A) 100 KW load and P. F. = 1 ∴KVA = 100 KVA
∴ Demand charges = 100 x Rs.200 = Rs.20000/-
(Assuming Demand Charges = Rs. 200 /KVA)
pg. 50
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
Distribution losses of plant are the losses occurring in main L.T. Cables, L.T.
Switch Gear, L.T. Bus -Bar etc. = 7 % (Of total yearly Consumption)
Now % loss reduction due to improvement of average P.F. from 0.94 to 0.99
Now Plant copper losses at 0.94 P.F. 0
.[M ^ .[M
0
.PPZN
0 ] R 1.1317
Now Plant copper losses at 0.99 P.F . 0
.[[ ^ .[[
pg. 51
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
0 ] R 1.0203
Thus Plant heat loss reduction by improving PF at consumption point
277". a 5 0.94 \4 277". # 5 0.99 \4
0
277". # 5 0.94 \4
] R 1.1317 1.0203
0
] R 1.1317
0.1114
0
1.1317
0 0.0984 / 10 %
Thus, by improvement in P.F. from 0.94 to 0.99, there will be a plant loss
reduction of 10 %. However the exact saving percentage can’t be calculated as
all motors are running at various PF varying form 0.7 – 0.9. But it is evident
that heat loss reduction is enormous and substantial, as per the example
calculation above.
Distribution losses of plant are those electrical losses occurring in the L.T.
Cables, Fuse links, bus bars and Meters etc and which is standardized at the
rate of 7 % of the yearly energy consumptions of the plant.
pg. 52
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
pg. 53
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
5. Heat losses in any electrical machine = k x 1/P.F. and hence high P. F. will
generate less heat.
6. Reduction of plant electrical losses due to improvement of P. F. =
}A ~
1
~
7. KVA reduction =a6 R
~ ~ K
pg. 54
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
.[K
=1
.[P
= 1 – 0.8812
= 0.1188
= 11.88 %
When current I amperes flow through any electrical machines having resistances
R ohms for t seconds the electrical energy expended is I² x R x t joules.
∴Heat produced = I² x R x t / 4187 kilocalories.
∴Heat produced at PF 1 (0.92) = k [1/ (PF 1)2] & Heat produced at PF 2 (0.98) = k
[1/(PF 2)2]
∴Reduction in heat generation due to improvement of P. F.
=R
~
~ K
= k x [ 1.1814 – 1.0412 ]
= k x 0.1402 Calories
Sample Calculation for input to the motor, % shaft loading on motor and load
factor Table – (A) for Sr. No.1. (Assuming average η of motor = 82 %)
Input Power in KW
1.73 R 3 R R 2
0
1000
1.73 R 425 R 155 R 0.87
0
1000
0 99.14 ]9 / 99 ]9
pg. 55
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
= 99 x100 = 44 %
225
Similarly the others motor’s shaft loading and Load factor had been summer
breaks but completion.
Energy Saving Flat Belt Drive is made from Nylon (Super Polyamide) and Chrome
leather materials while that of V – belt drive is made from Rubber and hence
Energy Saving in Flat Belt Drive is possible.
1. Thick rigid sections of V- belt drive absorb a great deal of useful power and
add to running costs. Theses power losses are typically dissipated in the
form of heat. Which in-turn has a deleterious effect on the belt life.
pg. 56
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
1. Efficiency of Energy Saving Flat Belt Drive is 98 % while that of V – belt drive
is 86 % and hence 12 % Energy Saving is possible with Flat Belt Drive.
2. Energy Saving Flat Belt Drive is generate very less vibrations while that of V
– belt drive generate more vibrations and hence long life of bearings and
machines with less noise are possible with Flat Belt Drives.
3. Energy Saving Flat Belt Drive is made from Nylon (Super Polyamide) and
Chrome leather while that of V – belt drive is made from Rubber and hence
less weight are possible with Flat Belt Drive which results high load transfer
with
4. High transmission efficiency.
5. Energy Saving Flat Belt Drive is vibrations free, slip free and maintenance
free while in that of V – belt drive above actions are not possible.
6. 5 % Energy Saving in Flat Belt Drive is possible while in that of V – belt drive
is not possible
There is total 14 big and major Motors which are running on V – Belt drive , so
total KW of those motors is 916 KW.
pg. 57
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
1. The Total Effective Load V – belt drive Motor = 916 KW x 0.83 = 760 KW
pg. 58
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
4. Cost of converting one no. Of V – belt drive in to Flat Belt Drive with other
Exp.
= Rs32000/- (assumed average)
5. Salvage value of existing Of V – belt drive = Rs.2000/-
6. Net Cost of converting one no. Of V – belt drive in to Flat Belt Drive
= Rs32000/-- - Rs.2000/- = Rs.30000/-
7. Net Cost of converting 14 no. Of V – belt drive in to Flat Belt Drive
= Rs.30000/- x 14
= Rs. 4,20,000/-
8. The payback period for all conversion = Net cost of V - belt drive
conversion
Total yearly saving by conversion
= Rs. 420000/-
Rs. 839446/-
Remarks:-
(1) The annual saving in energy bill is 4 % = Rs. 839446/- for all 14 Nos. Motors.
(2) KVA demand saving of Rs. 74400/-
(3) Total saving in Rs. Due to conversion of V belts to flat belt drive. = (1) + (2)
= Rs.
913846/-
(4) The payback period on investment is only Six months
(5) Rate of annual interest on capital invested is 200 % and hence installations of
Flat Belts drive are strongly recommended.
pg. 59
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
(B) Energy saving by replacing Old Low Efficiency Motors by New Energy
Efficient Motors.
We have observed that in your plant there are so many old Low Efficiency motors
are working. Old Low Efficiency motor and rewinded motors consumed more
energy as compared to New Energy efficient Motor.
Motor Specifications
Rated power = 7.5 kW/10 HP
Voltage = 415 Volt
Current = 17 Amps
Speed = 935 RPM
Connection = Delta
pg. 60
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
0
(c) Stator Copper Losses at Full Load Pst.cu 120 C
= 3 x (17/1.73) 2 x 3.48
= 1008.32 Watt
[Z
(d) Full Load Slip = 0
= 0.065
Thus, Input to Rotor =
L
0
.N
L
0
.[Z
pg. 61
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
= 8021.40
nopqop
(E) Motor efficiency at Full Load = r UXX
lqop
= 82.09 % say 82 %
Above test clearly shows that Old and many times rewind Motors have very low
efficiency as compared to new Energy efficient Motor. New Energy Efficient
Motors have efficiency up to 95%.
So you are advised to change all possible old motors in one go and install New
Energy efficient Motors.
Cost benefits analysis of New Energy Efficient Motor in place of Old Motor
Sample calculations for 100 KW Motor – (Old) with compare to new 100 KW
Energy efficient Motor.
2. Power Consumption for 100 KW – New Motor Considering 0.95 % On Full load.
= 100 KW/0.95 = 105.26 KW Input Power
pg. 62
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
From above calculations we can save 16.68 Unit per Hour By replacing Old motor
with new motor
(Considering running motor on Full Load)
Area S.No. Motor HP VFD Make RPM Rated Voltage Measured Efficiency Present Required
Details (kw) current(A) Measured current(A) % current at
loading 90%
of efficiency
Motors and 75%
loading
PM-1
1 Vacuum 7.5 5.5 Kirloskar 2800 7.8 410 5 68.41 75.0 4.5
separator
2 Holly Roll 3.5 2.5 ABB 960 3.5 410 4.4 100.0 3.5
8 Vacuum 270 200 NGEF 1440 340 260 96.64 76.5 142.8
Pump
9 Blower 1 20 15 ABB 1440 21 13.5 48.39 63.4 11.5
Boiler
pg. 63
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
The approx. Net cost of conversion of all old Motor Rs. 6,50,000/- (we have
considered a thumb rule of Rs. 2300 per KW) (Salvage value of Old Motor has
been Considered)
The payback Period = Cost Of Conversion = Rs.650000/- = 0.22 Years x 12 Month = 3 Months
Yearly Saving Rs. 2932356/-
Looking to the above benefits and yearly saving of Rs. 2932356/- every year, you
are recommended to change motors in one go with new energy efficient motor.
New motors have energy saving benefits, long life and trouble free operation, less
maintenance cost and with manufacturer guarantee. So we suggest you to
implement this change as early as possible.
pg. 64
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
pg. 66
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
250 45 50 50 60 65 70
pg. 67
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
Electrical motors accounts for a major part of the total electrical consumption. So
a careful attention should be given to the performance of this utility.
Measurements of the different electrical parameters of the major motors of the
plant are given in Table
The efficiency of the induction motor and loading condition of the motors are
directly proportional to each other. Higher the loading and higher is the efficiency
of the motors. The best efficiency of the motors is achieved at a load very much
near to the rated load.
pg. 68
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
Moreover at lower loads the power factor is on the lower side increasing the load
current and thereby increasing the copper losses, resulting in lower efficiency, the
rating of the motors should be decided after carefully understanding the process
requirement in the absence of which the motor might come out to be oversized.
Also one should run a motor, which has been rewound more than once as every
time a motor is rewinded it losses 2 – 5% of its actual efficiency.
Mostly all the motors are old or rewound at least once. A good saving can be
achieved if higher efficient ones replace them. Though it’s a scheme with higher
initial investment but can be implemented phase wise. Induction motors are
characterized by power factors less than unity, leading to lower overall efficiency
(and higher overall operating cost) associated with a plant’s electrical system.
Capacitors connected in parallel (shunted) with the motor are typically used to
improve the power factor. The impacts of PF correction include reduced KVA
demand (and hence reduced utility demand charges), reduced I2R losses in cables
(leading to improved voltage regulation), and an increase in the overall efficiency
of the plant electrical system.
It should be noted that PF capacitor improves power factor from the point of
installation back to the generating side. It means that, if a PF capacitor is installed
at the starter terminals of the motor, it won’t improve the operating PF of the
motor, but the PF from starter terminals to the power generating side will
improve, i.e., the benefits of PF would be only on upstream side.
pg. 69
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
The size of capacitor required for a particular motor depends upon the no-load
reactive KVA (KVAR) drawn by the motor, which can be determined only from no-
load testing of the motor. Higher capacitors could result in over-voltages and
motor burnouts. Alternatively, typical power factors of standard motors can
provide the basis for conservative estimates of capacitor ratings to use for
different size motors. The capacitor rating for power connection by direct
connection to induction motors is shown in Table
pg. 70
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
pg. 71
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
i). Daily: -
Clean the motor and starter.
ii). Weekly: -
Clean slip rings with soft brush dipped in white spirit.
iii). Monthly: -
Check earth connections of motor and starter.
Blow through motor and starter with dry compressed air at 2 Kg/Cm .
Check tightness of cable connections.
pg. 72
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
Check motor for overheating and abnormal noise / sound, sparking and
for proper bedding of brushes.
Tighten belts and pulleys to eliminate excessive losses.
iv). Quarterly: -
Check motor terminal voltage for balanced supply. If more than +1% of
average, then check from transformer onward.
Carry out SPM checks viz. vibrations and sound of bearing. Record reading
and
compare With earlier / other motor readings.
Slip Ring: - Inspect the brushes and make sure that they move freely in the
brush holder clips.
Clean brushes, holder chip and wipe with cloth dipped and in gasoline.
Replace
the brush if they are worn out less than 5 mm in length from brush
holder.
Clean the starter and motor contacts with white spirit.
pg. 73
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
As it is clearly evident in all cases that the cabling, transmission, core and iron losses etc are
related to current which in turn is inversely proportional to the voltage it is a fact that changing
certain drives from 415 V to 6.6 KV may reduce energy consumption due to reduced losses and
variations.
Below is the list of proposed motors which can be converted to the MV operation.
pg. 74
ANSH ENERGY SOLUTIONS PVT. LTD. Task Specific Audit: Steam Generating
admin@anshenergy.com Boilers & Electrical distribution netwrok
Client: Sandeep Paper Mills (P) Ltd.
Auditor: Anshul Singh Yadav
Auditor Registration: EA-3267
As the market price of drives for 6.6 KV is not very standard as of date and
availability of the panels in this segment is poor we have not calculated the
payback or investments for this operation. However the idea can be stored for
future reference as we may sometime achieve better pricing or better availability
in the same. Higher rating motors like 300 KW are still viable for this operation.
pg. 75