Professional Documents
Culture Documents
1.0 GENERAL
3.1 GENERAL
3.2 PREPARATORY WORKS AND EQUIPMENT USED
3.3 SAFETY PROCEDURE
3.4 CLEANING OPERATION
4.1 GENERAL
4.2 TESTING OPERATION
4.3 LEAK DETECTION OF PIPELINE
4.4 TEST ACCEPTANCE CERTIFICATE
5.1 SAFETY
5.2 SAFETY EQUIPMENT LIST
5.3 COMMISSIONING
5.4 SAFETY OFFICER SCOPE OF WORK
5.5 HOUSEKEEPING
5.6 OPERATIONAL SAFETY
5.7 MATERIAL REQUIREMENT
5.8 REQUIREMENTS PRIOR TO COMMISSIONING
5.9 DECOMMISSIONING
5.10 FINAL TIE-IN AND COMMISSIONING DETAIL
5.11 AFTER COMMISSIONING
5.12 LEAK TEST PROCEDURE
APPENDICES
Appendix 1 - Schematic Drawing
1
1.0 GENERAL
This procedure covers all operations for the internal cleaning, testing, and
commissioning of the following gas pipeline system:
This procedure describes methods which will be employed for the following
operations:
3.1 GENERAL
Medium used to blow internal of pipelines is air by using compressor. The inlet
pressure shall not be lower than 30 psig and shall be applied continuously for no
less than 5 minutes per run.
The pipeline shall be determined as free of dirt and foreign particles after a
series of blow runs and subject to the satisfaction of GMB. The final run shall be
witnessed and certified by GMB representative.
Upon completion of cleaning operation for the service pipeline, the installation of
tapping saddle shall take place. Tapping saddle location shall be free of water to
prevent foreign material entering the cleaned pipe. The pipeline pneumatic
testing shall commence after completion of cleaning activity and installation of
pipeline appurtenance such as service valves, saddle tee, reducers etc.
Preparatory Works
2
For Launching end: A launcher is prefabricated and installed by flanged
connections. Launcher shall be equipped with relief
valve and pressure inlet point.
For Receiver end: A receiver and shall be opened pipe and installed
wire netting to trap the pig.
All materials used in the pressure test shall be thoroughly checked to meet the
test pressure requirement.
3.3.1 All site staff and workers shall be briefed of sequences of operations and safety
procedures to be adhered to before commencing of work. AITESBs project
manager or their representative shall be present to supervise the safety aspect
during the cleaning, pressure test and commissioning activities.
3.3.2 Before commencing, signboards shall be placed around launcher and receiver
area to warn public of cleaning operations taking place. Safety barriers will be
located where necessary.
3.3.3 Communication points will be established between launcher and receiver to
ensure prompt action can be taken during cleaning operations.
3.3.4 Receiver end shall be directed away from the public. AITESB shall provide
adequate protective shield such as pig arrester net at the outlet.
Upon confirmation of all equipment and personnel are ready, cleaning operations
shall commence with the presence of GMB representative.
Pressure will be built up to and released into the pipeline to push out any dirt or
foreign particles in the pipeline. The discharge at the receiving end shall be
observed to determine the condition of discharge.
1. The 63mm PE service line to be cleaned by launching the pig from the 2
riser, until satisfaction of GMB.
3
2. Upon completion of cleaning activity, install 63mm end cap at the open end
of new 63mm service.
4.1 GENERAL
Instruments used i.e. pressure gauges and pressure chart recorder shall be
inspected prior of testing commencement. AITESB shall provide calibration
certificate to GMB, minimum 1 day before the scheduled pressure testing.
The testing pressure shall be minimum of 1.5 times the Design Pressure, which is
1.5 x 60 Psi = 90 Psi. To accommodate pressure fluctuation as a result from
temperature effect, the minimum test pressure is recommended at 100 Psi. Upon
achieving the testing pressure, the nitrogen source shall be isolated from the
pipeline system.
The test duration shall be as follow, commence from the stabilized testing
pressure, which is 100 Psi minimum. Refilling of testing medium is totally
prohibited during the official test. Test pressure and temperature shall be
monitored and recorded using forms as per Appendix.
Any reduction of pressure during test period shall indicate leak on pipeline
system, once ascertained that equipment do not contribute to pressure drop.
Leakage shall be located by either physical discharge of sound or identified by
soap solution to pinpoint exact location of leakage.
4
Upon locating the leakage, remedial works shall be done on that portion of the
pipeline and retest shall be conducted.
The repair shall be done by cut out with a spacing of 300mm on both sides of the
leak points.
The pressure test shall be repeated until the pressure test requirement is fully
complied.
5.0 COMMISSIONING
5.1 SAFETY
The configuration of the existing pipeline will be determined and a safe method
of preparing for tie-in will be developed. Following are the steps to be taken.
5.3 COMMISSIONING
5
effect of local unusual circumstances must be considered in determining any
required safety procedures.
2. Always use the procedures and methods of operations laid down in this
procedure and the local rules and regulations.
3. Always use the correct tools and equipment for the job, and wear the correct
protective clothing.
d. Ensure that all personnel under their control or direction are familiar with
safety requirements of the job.
e. Stop any dangerous work practice immediately and report any such
actions to the appropriate authority.
f. Rectify or report any defects in plant or equipment that may affect safety,
taking any necessary.
The Safety Officer will be responsible for all aspects of safety control and
prevention of accidents during the testing, commissioning and hand-over
operations period.
ii) Ensuring that, before entry onto the site, all supervisory, construction and
operating personnel are fully conversant with the Safety Regulations on work
procedures in force.
iii) Ensuring that all personnel are equipped with and use of appropriate protective
clothing and that all hazard warning signs and devices, notices and barriers are
installed and maintained.
iv) Carry out routine inspection on fire fighting equipment and first aid facilities, and
check these are in place and are properly serviced.
v) Stopping any dangerous work practice and immediately reporting them to the
Construction Manager.
5.5 HOUSEKEEPING
i) Floors, walkways and stairways are kept free from obstructions at all times.
All personnel involved with the commissioning operations should be familiar with
the safe action to take under emergency condition. Report the emergency to the
Project Manager and Safety Officer for assistance if required.
In case of emergency, conditions (fire, explosion, gas leakage, etc) the following
action is required:-
i) All personnel, other than those assigned to fire fighting duties, shall assemble at
the nearest assembly point.
ii) All personnel to be accounted for and any injured persons removed to safety. Any
missing personnel to be located quickly by a systematic search by a nominated
search team.
iv) Investigate damage, repair, and return the station to operational status.
7
The following list of materials, consumable items, tool and equipment represent
the basic requirements of the commissioning activities:-
a) Suitable Range of hand tools, spanners, socket sets etc. (On set each for the
central commissioning control location and individual commissioning groups).
b) Lubrication equipment, grease guns, lubricant etc. (One set each for the central
commissioning control location and individual commissioning groups).
c) 1 unit of gas detector.
a) All equipments such as fittings, spanner, non spark tools or any other
equipment shall be on site and confirm in good condition by the site supervisor.
b) Site personnel to be briefed on work activity before commencement of any work.
c) Commissioning can commence only after:
- Pneumatic testing completed.
- Commissioning site cleaned.
- Obtain Approval to Operate (ATO)
- Obtain work permit from GMB O & M Department.
5.9 DECOMMISIONING,
6. The completed pipeline shall be packed with 0.5 bar N2 before the
commissioning works.
7. Install hose at venting point (P2), service station area.
8. Open PE-SV-1 to start displacing the N2 inside the new line. The nitrogen
shall be pushed by natural gas and shall be released at purge point P2.
9. Commissioning is completed.
8
Each connection shall be leak tested and confirm by GMB.
All flanged and threaded connections for the entire pipeline system will have to
be checked to ensure that they are leak free with each step in pressure increase.
All flanges are to be taped prior to any pressurization and a needle sized hole
made at a location easily observable.
Any leak will be detected by observing the formation of bubbles after the
application of Snoop liquid at the needle size hole. Should there be no bubbles
observed after one minute of observation it can be concluded that the fit up is
leak free.
Any leaks will be classified as the observation of bubble formation after the
application of snoop leak detection fluid at the following locations:
All leaks will have to be fixed prior to the commencement of any further steps.