ABSTRACT SHEET FOR AUXILLARY CROSS TYPE TEST BED

Item Quantities Estimated Total Amount


Unit ITEM OF WORK
No. estimated Rates (Rs.) according to

Empty boring to the required depth (measured from bottom of pile cap to founding level) by means of hydraulic pilling rig through all strata like soil, sand, clay, murrum,
gravel, pebble, boulder, cobble, soft rock, etc. for pile of diameter as below, supported with the help of bentonite slurry including all required plant & machineries, disposal of
excavated material with all leads & lifts, mobilisation demobilisation, remobilisation if required, transportation of required plant and machineries, etc. Method of boring shall
1 be as per IS 2911-Part 1 - Section -II.
1) Length of pile shall be measured from bottom of pile cap and upto the founding level.
2) Rate is inclusive of empty boring through overburden (i.e. temporary working platform, etc.)

180.00 Rmt 1200 mm dia pile 4500.00 810000.00

Providing and placing with tremie reinforced cement concrete M35 grade in bored hole using 6 mm to 20 mm machine crushed well graded stone aggregate, natural or crushed
sand of approved quality, OPC 43/53 grade cement with contractor's own concrete mix design as approved by AMC, including necessary , mixing in fully automatic batch mix
plant, transport, curing, casting of pile minimum 1 x dia. of pile above cut off level with all leads & lifts, etc. complete as per execution drawing & specification & as directed
2 204.00 Cum 5706.00 1164024.00
by engineer Incharge. Including mobilisation, demobilisation, remobilisation, transportation of required plant and machineries if required.
1) Excluding reinforcement, initial pile load test, routine load test and M.S. Liners but including temporary liners if required.
2) Rate is inclusive of 10% additional cement to be added over & above the quantity of cement required for design mix M-35 concrete for pile concreting in water.

Providing and placing the reinforcement in designed position, fixing, lowering in position TMT bars Fe 500 D grade conforming to IS 1786 for pile of all categories
& depth, at all levels. The rates includes for supply, loading, unloading, transporting to site, cutting, bending, hooking, placing, tying in position with contractor's own black
annealed binding wire, welding, forming the cage and lowering it in position in pile bore etc. Welding and supporting in position to ensure lines and levels during concreting,
maintaining proper cover / spacing, all leads & lifts, etc. including contractor's own equipment, labour, supervisor, taxes, machineries, etc. complete as per drawings and
3 20.40 MT 55561.0 1133444.40
specification.
1) The waste cut pieces shall not be included in the paying quantity.
2) Black annealed binding wire shall not be included in the paying quantity.
3) The work shall be done as per execution drawing.

Pile Load test


Carrying out load test as per standard procedure laid down in the IS 2911 specification and maintaining complete records of load v/s settlement on test pile constructed for the
purpose including erection and removal of loading platform with all contractor's materials, labour, tools & plants, etc. complete with all necessary instrumentation, high
capacity hydraulic jacks, etc. complete as per specification and for the test load as directed by Engineer-in-charge.
1) Load test shall be continued till test load or soil failure whichever is earlier.
1.00 Nos 2) Testing shall be carried out with loading frame with ground anchors/anchor piles/kentledge with platform including all necessary arrangement required for the test, as 439069.00 439069.00
4
approved by Engineer-in-charge.
3) Boring, concreting & reinforcement of test pile shall be measured separately in respective items subject to successful completion of test.
4) If load test of pile is not completed successfully, payment shall not be made for this test item as well as boring, concreting and reinforcement of test pile for which test
carried out and another test pile shall be constructed.
a) Initial Pile Load Test on piles in non working area in the vicinity of the bridge site excluding cost of test pile.

1.00 Nos b) Routine Pile Load Test on piles on working pile. 439069.00 439069.00
Performing Integrity Test (low strain) on all vertical pile. The item shall include chipping of weak concrete at the top of pile, leveling, bending of reinforcing bars, preparation
of pile head including testing with pile driving analyser or approved equivalent. To be carried out at least 15 days after concreting of piles. A specialist approved Agency shall
5 12.00 Nos 1115.00 13380.00
be employed by the Contractor for the test. The test shall be carried out as per relevant ASTM code. The item is including complete testing with approved apparatus, analysis
of results and conclusions including submission of test reports in three hard copies with soft copy in CD.

Excavation for pile caps, foundation of columns, approach slab, solid slab, pile cap beam,Beam etc. in all categories of soils, such as sand, clay, murrum, gravel, pebble,
boulder, cobble, soft rock, road crust etc. as per specification for depth below ground level as mention. The rate is inclusive of contractor's own machinery and equipment,
labour, taxes, temporary works, consumables, all lead & lifting, shoring, strutting, timbering and buttressing with sand / clay bags and all such measures necessary to retain in
6 208.00 CUM 150.00 31200.00
position the sides of foundation pit and including refilling the approved excavated soil, clearing and carting excess earth. The rate is also inclusive of dewatering by manual or
mechanical means.

Providing and laying in positions machine mixed Plain Cement Concrete M15 grade for leveling course below foundation or below pile cap, pile cap beam, solid slab, approach
7 18.00 CUM slab, etc. at other places as directed by Engineer-in-charge with graded broken stone aggregate from 6 mm to 40 mm including tamping, vibrating, leveling and curing complete 3924.00 70632.00
with all formwork, dewatering wherever required including all materials, labours, plants, machineries & tools, all leads and lifts, etc. complete as per specification.

Providing and casting in-situ Reinforced Cement Concrete M35 grade controlled cement concrete in pile cap, pile cap beam using 6 mm to 20 mm machine crushed well graded
stone aggregate, sand of approved quality, OPC 53 grade cement with contractor's own concrete mix design as approved by AMC, etc. complete as per specification. The rate is
8 172.00 CUM inclusive of all materials, including necessary dewatering, mixing in fully automatic batch mix plant, transport, curing, vibrating, placing in position, shuttering, formworks, 6297.00 1083084.00
deshuttering carefully, making good the damages, fixing embedment, inserts, pockets, wherever necessary, with all lead and lift with contractor's labour, tools & plants,
machineries, as required.

Providing and placing the reinforcement in designed position, fixing, erecting or lowering in position TMT bars Fe 500 D grade conforming to IS 1786 for pile cap, pile cap
beam and other foundation of all categories & depth, at all levels. The rates includes for supply, loading, unloading, transporting to site, cutting, bending, hooking, placing,
tying in position with contractor's own black annealed binding wire, welding, forming the cage and lowering it in position in pile cap etc. Welding and supporting in position to
ensure lines and levels during concreting, maintaining proper cover / spacing, all leads & lifts, etc. including contractor's own equipment, labour, supervisor, taxes,
9 18.92 MT 55561.00 1051214.12
machineries, etc. complete as per drawings and specification.
1) The waste cut pieces shall not be included in the paying quantity.
2) Black annealed binding wire shall not be included in the paying quantity.
3) The work shall be done as per execution drawing.

Preparing shop drawings, supplying, fabricating, delivering at site, hoisting and fixing in position including all temporary staging and supporting work and making all structural
steel work in accordance with the design, drawings prepared by the consultants. the rate of steel work shall include 1 coat of red oxide primer and 2 coats of enamel paint
10 70.00 MT 80000 5600000.00
assembly, welding, jointing, of Yst 310 grade conforming to IS 1161/ plates /chs/rhs cost of fasteners , nuts, bolts and washers), with connections using Circular Pipes, plates,
channels and angles, gusset plate, connection bolts, cleats, fasteners etc. as per drawing, steel conforming to IS :226 and IS :2062-Gr.A

TOTAL 11835116.52

NOTE: KPTL EXPANSION PLAN FOR TEST BED GREATER THAN 30m x 30m will be approximately Rs 1.18 crore