BCG, Inc. Was retained to evaluate pile installation procedures. A practical grout mix incorporating both Portland cement and granulated blast furnace slag could be developed. The thermal consequences from heat of hydration of grout in the interior of the piles were also evaluated.
BCG, Inc. Was retained to evaluate pile installation procedures. A practical grout mix incorporating both Portland cement and granulated blast furnace slag could be developed. The thermal consequences from heat of hydration of grout in the interior of the piles were also evaluated.
BCG, Inc. Was retained to evaluate pile installation procedures. A practical grout mix incorporating both Portland cement and granulated blast furnace slag could be developed. The thermal consequences from heat of hydration of grout in the interior of the piles were also evaluated.
depth of 181 m below mudline. The marine contractor for this work, Heerema McDermott Aust. Pty. Ltd. elected not to use “float shoes” on the ends of the insert piles which would have kept grout out of the insert piles. However, due to this lack of float shoes concern was raised both re- garding:
(a) The influence of the proposed grout
placement procedures on the quality of the grout (b) The thermal consequences from heat of hydration of grout in the interior of the piles
Pre-cast concrete segmental inserts. Ben C. Gerwick, Inc. was retained to
assist Woodside to evaluate the con- sequences of the marine contractor’s The Goodwyn “A” steeljacket offshore proposal to allow the grout to flow up Elevation of the Goodwyn “A” offshore platform. platform is piled to the seafloor in 130 the interior of the insert pile and then m deep water on the North West Shelf out through staggered port holes in the annular space. of Australia. BCG, Inc. was retained to drilled in the sides of the insert piles, (b) Thermal stresses resulting from the evaluate pile installation procedures. thus filling the annular space between heat of hydration of the grout on the insert pile and the primary pile and the interior of the insert piles would In 1993, Woodside Offshore Petroleum the calcarenite soils. In order to help be unacceptable, even when using Pty. Ltd. completed construction of the evaluate the proposed grouting proce- low heat of hydration grouts. Goodwyn “A” steel jacket offshore plat- dures, Heerema McDermott conducted Consequently, a system for replac- form which will be piled to the seafloor large scale physical grout flow tests, ing much of the grout in the interior in 130 m deep water on the Northwest and physical heat of hydration tests, as of the piles was developed, using Shelf of Australia. Due to the difficult well as finite element analysis. precast concrete segmental inserts. soil conditions at the Goodwyn “A” These were lowered into the site, considerable attention has been After review of the findings of these, interior of the insert piles after they paid to the foundations. It was decided and other studies, it was concluded had been installed. This system to use 2.65 m O.D. driven primary that: proved adequate to limit the heat of piles to a depth of 116 m below the hydration and the consequent mudline, and then to install two m O.D. (a) A practical grout mix, incorporating thermal stresses. drilled and grouted insert piles to a both Portland cement and granu- Ben C. Gerwick, Inc. 06-094e-02a
lated blast furnace slag could be
developed that could flow through Year of Completion: 1993 Services Performed: reasonably spaced and sized side Design Fee: $65,000 • Large-Diameter Piles ports in the insert piles without undue reduction in grout bond • Non-linear Soil-Pile Interaction Client: Woodside Offshore Petroleum Pty. Ltd. quality due to such factors as • Concrete Mix Design having the grout mix with sea water