You are on page 1of 1

Goodwyn "A"

Steel Jacket Offshore Platform, Australia


depth of 181 m below mudline.
The marine contractor for this work,
Heerema McDermott Aust. Pty. Ltd.
elected not to use “float shoes” on the
ends of the insert piles which would
have kept grout out of the insert piles.
However, due to this lack of float
shoes concern was raised both re-
garding:

(a) The influence of the proposed grout


placement procedures on the
quality of the grout
(b) The thermal consequences from
heat of hydration of grout in the
interior of the piles

Pre-cast concrete segmental inserts. Ben C. Gerwick, Inc. was retained to


assist Woodside to evaluate the con-
sequences of the marine contractor’s
The Goodwyn “A” steeljacket offshore proposal to allow the grout to flow up Elevation of the Goodwyn “A” offshore platform.
platform is piled to the seafloor in 130 the interior of the insert pile and then
m deep water on the North West Shelf out through staggered port holes in the annular space.
of Australia. BCG, Inc. was retained to drilled in the sides of the insert piles, (b) Thermal stresses resulting from the
evaluate pile installation procedures. thus filling the annular space between heat of hydration of the grout on
the insert pile and the primary pile and the interior of the insert piles would
In 1993, Woodside Offshore Petroleum the calcarenite soils. In order to help be unacceptable, even when using
Pty. Ltd. completed construction of the evaluate the proposed grouting proce- low heat of hydration grouts.
Goodwyn “A” steel jacket offshore plat- dures, Heerema McDermott conducted Consequently, a system for replac-
form which will be piled to the seafloor large scale physical grout flow tests, ing much of the grout in the interior
in 130 m deep water on the Northwest and physical heat of hydration tests, as of the piles was developed, using
Shelf of Australia. Due to the difficult well as finite element analysis. precast concrete segmental inserts.
soil conditions at the Goodwyn “A” These were lowered into the
site, considerable attention has been After review of the findings of these, interior of the insert piles after they
paid to the foundations. It was decided and other studies, it was concluded had been installed. This system
to use 2.65 m O.D. driven primary that: proved adequate to limit the heat of
piles to a depth of 116 m below the hydration and the consequent
mudline, and then to install two m O.D. (a) A practical grout mix, incorporating thermal stresses.
drilled and grouted insert piles to a both Portland cement and granu-
Ben C. Gerwick, Inc. 06-094e-02a

lated blast furnace slag could be


developed that could flow through
Year of Completion: 1993 Services Performed:
reasonably spaced and sized side
Design Fee: $65,000 • Large-Diameter Piles
ports in the insert piles without
undue reduction in grout bond • Non-linear Soil-Pile Interaction
Client: Woodside Offshore
Petroleum Pty. Ltd. quality due to such factors as • Concrete Mix Design
having the grout mix with sea water

You might also like