You are on page 1of 22

The Babcock & Wilcox Company

Chapter 45
Condition Assessment

The assessment of accumulated damage, or condi-


tion assessment, has a long history in the boiler in-
dustry. Whenever a component was found to contain
damage or had failed, engineers asked what caused
the damage and whether other components would fail.
These questions typically pertained to tubing and
headers, which caused the majority of downtime. As
boiler cycling became more common, the need for more
routine condition assessment increased to avoid com-
ponent failure and unscheduled outages.
Condition assessment includes the use of tools or
methods in the evaluation of specific components and
then the interpretation of the results to identify 1) the
components remaining life and 2) areas requiring
immediate attention.
A boiler components damage assessment, typically
compared to its design life, is based on accumulated
damage, and can be performed in three phases. In
Phase 1 of the assessment, design and overall operat-
ing records are reviewed and interviews are held with
operating personnel. In Phase 2, nondestructive ex-
aminations, stress analysis, verification of dimensions,
and operating parameters are undertaken. If required,
the more complex Phase 3 includes finite element
analysis, operational testing and evaluation, and
material properties measurement.1 (See Fig. 1.)

Condition assessment examination


methods
The major boiler components must be examined by
nondestructive and destructive tests.
Nondestructive examinations Fig. 1 Three phases (levels) of boiler damage assessment (courtesy
Most nondestructive examination (NDE) methods of the Electric Power Research Institute).1
for fossil fuel-fired plants have been in use for many
years, although new methods are being developed for tromagnetic acoustics, acoustic emissions, metallo-
major components. Nondestructive testing does not graphic replication, strain measurement and tempera-
damage the component. ture measurement.
The NDE methods used in evaluating electric util- Visual Whether the inspected component is subject
ity power stations and industrial process plants include: to mechanical wear, chemical attack, or damage from
visual, magnetic particle, liquid penetrant, ultrasonic, thermal stress, visual examination can detect and iden-
eddy current, radiography, nuclear fluorescence, elec- tify some of the damage. Visual inspection is enhanced

Steam 41 / Condition Assessment 45-1


The Babcock & Wilcox Company

by lighting, magnification, mirrors, and optical equip- material due to oxidation, corrosion or erosion. UTT
ment such as borescopes, fiberscopes and binoculars. is relatively fast and is used extensively for measur-
Magnetic particle Magnetic particle testing (MT) ing wall thicknesses of tubes or piping.
and wet fluorescent magnetic particle testing (WFMT) The surface of the component must first be thor-
detect surface and near surface flaws. Because a mag- oughly cleaned. Because ultrasonic waves do not pass
netic field must be imparted to the test piece, these tests through air, a couplant such as glycerine, a water
are only applicable to ferromagnetic materials.2 The soluble gel, is brushed onto the surface. The trans-
choice between these techniques generally depends on ducer is then positioned onto the component surface
the geometry of the component and the required sen- within the couplant. A high frequency (2 to 5 MHz)
sitivity. For typical power plant applications, one of two signal is transmitted by the transducer and passes
methods is used: 1) the component is indirectly mag- through the metal. UTT is performed using a longi-
netized using an electromagnetic yoke with alternat- tudinal wave which travels perpendicular to the con-
ing current (AC), or 2) the part is directly magnetized tacted surface. Because the travel time for the reflected
by prods driven by AC or direct current (DC). wave varies with distance, the metal thickness is de-
In magnetic particle testing, any discontinuity dis- termined by the signal displacement, as shown on the
rupts the lines of magnetic force passing through the oscilloscope screen (Fig. 2).
test area creating a leakage field. Iron particles ap- Ultrasonic oxide measurement In the mid 1980s, B&W
plied to the area accumulate along the lines of mag- developed an ultrasonic technique specifically to
netic force. Any leakage field created by a discontinu- evaluate high temperature tubing found in superheat-
ity is easily identified by the pattern of the iron par- ers and reheaters. This NDE method, called the Non-
ticles. Dry magnetic particle testing is performed us- destructive Oxide Thickness Inspection Service
ing a dry medium composed of colored iron particles (NOTIS), measures the oxide layer on the internal
that are dusted onto the magnetized area. In areas surfaces of high temperature tubes. The test is gen-
where a dry medium is ineffective, such as in testing erally applicable to low alloy steels because these ma-
overhead components or the inside surfaces of pres- terials are commonly used in outlet sections of the su-
sure vessels, the wet fluorescent method is more ef- perheater and reheater.
fective. With this method, fluorescent ferromagnetic Low alloy steels grow an oxide layer on their inter-
particles are suspended in a liquid medium such as nal surfaces when exposed to high temperatures for
kerosene. The liquid-borne particles adhere to the test long time periods (Fig. 3). The NOTIS test is not ap-
area. Because the particles are fluorescent, they are plicable to stainless steels because they do not develop
highly visible when viewed under an ultraviolet light. a measurable oxide layer.
Liquid penetrant Liquid penetrant testing (PT) de- The technique used for NOTIS testing is similar to
tects surface cracking in a component. PT is not de- UTT; the major difference between the two is the fre-
pendent on the magnetic properties of the material quency range of the ultrasonic signal. A much higher
and is less dependent on component geometry.2 It is frequency is necessary to differentiate the interface
used by The Babcock & Wilcox Company (B&W) in between the oxide layer and inside diameter (ID) sur-
limited access areas such as tube stub welds on high face of the tube. Using data obtained from this NOTIS
temperature headers which are generally closely testing, tube remaining creep life can also be calcu-
spaced. PT detects surface flaws by capillary action of lated as discussed later in Analysis techniques. NOTIS
the liquid dye penetrant and is only effective where and UTT are methods in which the transducer is
the discontinuity is open to the component surface. placed in contact with the tube using a couplant gel.
Following proper surface cleaning the liquid dye is Because of the high sensitivity of the NOTIS method,
applied. The penetrant is left on the test area for about it is less tolerant of rough tube surfaces or poor sur-
ten minutes to allow it to penetrate the discontinuity. face preparation.
A cleaner is used to remove excess penetrant and the Ultrasonic measurement of internal tube damage Sev-
area is allowed to dry. A developer is then sprayed onto eral ultrasonic methods have been investigated for
the surface. Any dye that has been drawn into the sur- detecting damage within boiler tubes. All techniques
face at a crack bleeds into the developer by reverse
capillary action and becomes highly visible.
Ultrasonic Ultrasonic testing (UT) is the fastest de-
veloping technology for nondestructive testing of pres-
sure components. Numerous specialized UT methods
have been developed. A piezoelectric transducer is
placed in contact with the test material, causing dis-
turbances in the interatomic spacings and inducing an
elastic sound wave that moves through the material.3
The ultrasonic wave is reflected by any discontinuity
it encounters as it passes through the material. The
reflected wave is received back at the transducer and
is displayed on an oscilloscope.
Ultrasonic thickness testing Ultrasonic thickness test-
ing (UTT) is the most basic ultrasonic technology. A
common cause of pressure part failure is the loss of Fig. 2 Typical ultrasonic signal response.4

45-2 Steam 41 / Condition Assessment


The Babcock & Wilcox Company

Immersion ultrasonic testing In immersion ultrasonic


testing, the part is placed in a water bath which acts
as the couplant. B&W uses a form of immersion UT
for tube wall thickness measurements. In two-drum
industrial power boilers, process recovery boilers and
some utility power generation boilers, most of the tubes
in the convective bank between the drums are inac-
cessible for conventional contact UTT measurements.
For these applications, an ultrasonic test probe was
developed which is inserted into the tubes from the
steam drum; it measures the wall thickness from in-
side the tubes. As the probe is withdrawn in measured
increments, the transducers measure the tube wall
thicknesses. A limitation of this technique is that the
ID surface of the tubes must be relatively clean.
Shear wave ultrasonic testing This is a contact ultra-
sonic technique in which a shear wave is directed at
an angle into the test material. Angles of 45 and 60
deg (0.79 and 1.05 rad) are typically used for defect
detection and weld assessment. The entire weld must
be inspected for a quality examination.
Time of flight defraction (TOFD) TOFD is an ultrasonic
technique that relies on the diffraction of ultrasonic
energies from defects in the component being
Fig. 3 Steam-side oxide scale on ID surface. tested. The primary application is weld inspection on
piping, pressure vessels, and tanks. TOFD is an au-
use contact UT where a transducer is placed on the tomated inspection that uses a pitch-catch arrange-
outside diameter (OD) or tube surface using a ment with two probes, one on each side of the weld.
couplant, and an ultrasonic signal is transmitted The weld material is saturated with angled longitu-
through the material. The techniques can be catego- dinal waves to inspect for discontinuities. Because the
rized by type of signal evaluation: backscatter, the time separation of the diffracted waves is directly re-
evaluation of UT wave scatter when reflected by dam- lated to flaw size (height), TOFD can detect both the
aged material; attenuation, the evaluation of UT signal flaw and allow estimation of the flaw size.
loss associated with transmission through damaged Eddy current Measuring the effects of induced eddy
material; and velocity, the measurement and compari- currents on the primary or driving electromagnetic
son of UT wave velocity through the tube material.4 field is the basis of eddy current testing. The electro-
When a longitudinal wave passes through a tube, magnetic induction needed for eddy current testing
part of the signal is not reflected to the receiver if it is created by using an alternating current. This de-
encounters damaged material. The damaged areas velops the electromagnetic field necessary to produce
reflect part of the wave at various angles, backscat- eddy currents in a test piece.
tering the reflected signal. The loss of wave amplitude Eddy current testing is applicable to any materials
that is received back at the transducer is then used to that conduct electricity and can be performed on mag-
evaluate the degree of damage. netic and nonmagnetic materials. The test is therefore
Damage in the tube can also be assessed by evalu-
ating the loss of signal amplitude (attenuation) as a
shear wave is transmitted through the tube wall. The
technique uses a fixture with two transducers
mounted at angles to each other. One unit transmits
a shear wave into the tube and the second transducer,
the receiver, picks up the signal as the wave is reflected
from the tube ID. A drop in signal amplitude indicates
damage in the tube wall.
This technology is the basis of the B&W patented Fur-
nace wall Hydrogen damage Nondestructive Examina-
tion Service (FHyNES)test method (Fig. 4). The ve-
locity test method uses either longitudinal or shear
ultrasonic waves. As a wave passes through a chordal
section of tube with hydrogen damage, there is a
measurable decrease in velocity. Because the signal
is not reflected from the tube inside surface, ultrasonic
velocity measurement is not affected by damage to the
inside of the tube and therefore specifically detects
hydrogen damage. Fig. 4 Shear wave technique for detecting hydrogen damage.

Steam 41 / Condition Assessment 45-3


The Babcock & Wilcox Company

applicable to all metals encountered in power station netic sources. The first magnetic source modulates a
condition assessment work. time-dependent magnetic field by electromagnetic in-
Parameters affecting eddy current testing include duction as in eddy current testing. A second constant
the resistivity, conductivity, and magnetic permeabil- magnetic field provided by an AC or DC driven elec-
ity of the test material; the frequency of the current tromagnet or a permanent magnet is positioned near
producing the eddy currents; and the geometry and the first field. The interaction of these two fields gen-
thickness of the component being tested. erates a force, called the Lorentz force, in the direc-
Radiography Radiography testing (RT) is the most tion perpendicular to the two other fields. This Lorentz
common NDE method used during field erection of a force interacts with the material to produce a shock
boiler. Radiography is also valuable in condition as- wave analogous to an ultrasonic pulse, eliminating the
sessments of piping. As x-rays and gamma rays pass need for a couplant.
through a material, some of the rays are absorbed. Fig. 5 shows the basic principles of EMAT operation.
Absorption depends upon material thickness and den- A strong magnetic field (B) is produced at the surface
sity. When the rays passing through an object are of the test piece by either a permanent magnet or elec-
exposed to a special film, an image of the object is pro- tromagnet. Eddy currents (J) are induced in the test
duced due to the partial absorption of the rays. material surface. An alternating eddy flow in the pres-
In practical terms, a radioactive source is placed on ence of the magnetic field generates a Lorentz force
one side of a component such as a pipe, at a weld, and (F) that produces an ultrasonic wave in the material.
a film is placed on the opposite side. If x-rays are di- For boiler tubes that are electromagnetically conduc-
rected through the weld and there is a void within the tive (including alloys such as SA-213T22), the EMAT
weld, more rays pass through this void and reach the technology is ideal.
film, producing a darker image at that point. By exam- B&W, working with the Electric Power Research
ining the radiographic films, the weld integrity can be Institute (EPRI), developed a nondestructive rapid
determined. During the field erection of a boiler and scan system to inspect boiler tubes using EMAT tech-
power station, thousands of tube and pipe welds are nology. This EMAT based system is known as the Fast-
made and radiographed. (See also Chapters 38 and 39.) Scanning Thickness Gage (FST-GAGE ) and was
The major disadvantage of radiography is the harm- developed specifically to scan boiler tubes and provide
ful effect of excessive exposure to the radioactive rays. a continuous measurement of tube wall thickness.
RT is also limited in its ability to provide the orienta- (See Fig. 6.) The system conducts tests at exceptional
tion and depth of an indication. speeds, allowing scanning of thousands of feet (m) of
Nuclear fluorescence The primary use of this test- boiler tubing in a single shift. To perform an inspec-
ing in condition assessment is the verification of al- tion, the FST-GAGE system is manually scanned
loy materials in high temperature piping systems. along individual boiler tubes. System sampling rates
When certain elements are exposed to an external greater than 65 samples per second supports rapid
source of x-rays they fluoresce (emit) additional x-rays scanning of tubes. During a scan, the system provides
that vary in energy level. This fluorescence is charac- an immediate display of both tube wall thickness and
teristic of the key alloys common to high temperature signal amplitude. At the conclusion of each tube scan,
piping and headers. Chromium and molybdenum are a complete record of the inspection is electronically
the key elements measured. The nuclear alloy ana- stored and is traceable to each boiler tube and position.
lyzer is a portable instrument that contains a low level As with conventional UT, the FST-GAGE system can
source of x-rays. A point on the surface of the pipe is assess internal tube damage by evaluating the loss of
exposed to x-rays emitted from the analyzer. As the signal amplitude (attenuation) as a shear wave is trans-
source x-rays interact with the atoms of the metal, the mitted through the tube wall. By monitoring and indi-
alloys emit x-rays back to the analyzer. Within the cating signal amplitude, the system can also be used to
detector system of the analyzer, the fluoresced x-rays detect tube damage such as hydrogen damage, similar
are separated into discrete energy regions. By mea- to B&Ws patented FHyNES technique. The FST-GAGE
suring the x-ray intensity in each energy region, the has also demonstrated the ability to detect internal tube
elemental composition is also determined. pitting, caustic gouging, and under-deposit corrosion.
Electromagnetic acoustics Electromagnetic acous-
tics combine two nondestructive testing sciences, ul-
trasonics (UT) and electromagnetic induction. This Magnet
technology uses an electromagnetic acoustic trans- J (Eddy
ducer (EMAT) to generate high frequency sound waves Currents)
in materials, similar to conventional ultrasonics. Con- Conducting F (Lorentz
Force)
ventional UT transducers used for field testing con- Material
B (Magnetic
vert electrical impulses to mechanical pulses by use Force)
of piezoelectric crystals. These crystals must be
coupled to the test piece through a fluid couplant. For Ultrasonic
Wave
electrically conductive materials, ultrasonic waves can
be produced by electromagnetic acoustic wave genera-
tion.5 In contrast to conventional contact UT where a
mechanical pulse is coupled to the material, the acous- Eddy Current Coil
tic wave is produced by the interaction of two mag- Fig. 5 Basic principles of EMAT operation.

45-4 Steam 41 / Condition Assessment


The Babcock & Wilcox Company

pitting at the lower portion of the horizontal tube in-


ternal surface. The test is accomplished by scanning
along the outside of the horizontal tube at either the
To Scan
3 or 9 oclock positions with an EMAT transducer gen-
erating a Lamb wave (ultrasonic waves that travel at
right angles to the tube surface) which is focused at
the 6 oclock position on the tube.
B&W has also developed a surface wave EMAT
application to show surface indications including axi-
ally oriented cracks in boiler tubes. Conventional sur-
face nondestructive test methods were unsatisfactory
because they lacked adequate sensitivity and had slow
production rates for testing on large areas. A tone burst
EMAT technique was developed that uses a bidirec-
tional focused surface wave EMAT that follows the tube
surface circumferentially until the signal is reflected
back from a longitudinally orientated OD crack.
Acoustics Acoustics refers to the use of transmitted
sound waves for nondestructive testing. It is differ-
Fig. 6 B&Ws Fast-Scanning Thickness Gage (FST-GAGE) EMAT entiated from ultrasonics and electromagnetic acous-
based system can provide continuous measurement of tube wall tics in that it features low frequency, audible sound.
thickness.
B&W uses acoustic technology in testing tubular air
heaters. Because the sound waves are low frequency,
As with any NDE method, surface preparation is they can only be transmitted through air. A pulse of
important for effective testing with EMATs. However, sound is sent into the air heater tube. As the wave
EMAT is not as sensitive to scale as conventional UT travels along the tube, it is reflected by holes, block-
since it produces the ultrasonic wave within the ma- age or partial obstructions. By evaluating the reflected
terial. Some scales, such as magnetite oxide of uniform wave on an oscilloscope, the type of flaw and its loca-
thickness, have no detrimental effect on the signal tion along the tube can be determined.
generation of the EMAT probe. When the plant burns Acoustic emissions Acoustic emissions (AE) detect
a clean fuel such as natural gas, testing may be con- subsurface crack growth in pressure vessels. When a
ducted without any special surface cleaning. To pro- structure such as a pipe is pressurized and heated,
tect the coil from damage, surface preparation will the metal experiences mechanical and thermal
normally be required for boilers firing oil or solid fu- stresses. Due to the stress concentration at a defect
els. Some gas-fired units may require surface clean- such as a crack, a small overall stress in the pipe can
ing if external buildup or corrosion is present. Grit produce localized yield and fracture stresses result-
blasting or water blasting are effective methods of ing in plastic deformation. These localized yields re-
cleaning larger areas. Smooth metal is the preferred lease bursts of energy or stress wave emissions that
surface to ensure rapid testing. are commonly called acoustic emissions. AE testing
EMAT technology continues to be applied where its uses acoustic transducers that are positioned along the
unique properties have advantages over conventional vessel being monitored. AE signals are received at
UT techniques. B&W and EPRI are developing a sys- various transducers on the vessel. By measuring the
tem for the detection of cracking in boiler tubes asso- time required for the signal to reach each of the trans-
ciated with corrosion fatigue. Waterside corrosion fa- ducers, the data can be interpreted to identify the lo-
tigue is a serious boiler tube failure mechanism. The cation of the defect.
failures usually occur close to attachments such as Metallographic replication Metallographic replica-
buckstay welds, windbox attachment welds, or mem- tion is an in situ test method that enables an image of
brane welds. The combination of thermal fatigue the metal grain structure to be nondestructively lifted
stresses and corrosion leads to ID-initiated cracking from a component. Replication is important in evalu-
that is oriented along the tube axis. The EMAT sys- ating high temperature headers and piping because
tem under development for corrosion fatigue has it allows the structure to be examined for creep dam-
unique characteristics that enhance its ability to scan age. Prior to the use of replication techniques, it was
past welds and attachments and scan the full circum- necessary to remove samples of the material for labo-
ference of the boiler tube. The EMAT equipment uses ratory analysis. The replication process involves three
a tone burst EMAT signal allowing the use of horizon- steps: grinding, polishing and etching, and replicat-
tally polarized shear wave (SH waves) to detect crack- ing. In the first step, the surface is rough ground then
ing adjacent to external tube attachment welds. flapper wheel ground with finer grit paper. In the sec-
B&W has developed an EMAT application to inspect ond step, the surface is polished using increasingly
horizontal banks (i.e., economizer, reheater) of tubing finer grades of diamond paste while intermittently
within the boiler. Horizontal bank tubing may expe- applying a mixture of nitric acid and methanol in so-
rience tube failures caused by out of service corrosion lution. The acid solution preferentially attacks the
pitting forming aligned voids in the tube ID. The pur- grain boundaries of the metal. In the final step, the
pose of this EMAT test is to detect the internal aligned replica, which is a plastic tape, is prepared by coating

Steam 41 / Condition Assessment 45-5


The Babcock & Wilcox Company

one face of the tape with acetone for softening. The piping and drums. The shape of the cut allows the
tape is then firmly pressed onto the prepared surface. material to be replaced by welding. Because the repairs
Following a suitable drying time, the tape is removed and usually require post weld heat treating, the use of boat
mounted onto a glass slide for microscopic examination. samples is expensive. In most instances, replication is
Strain measurement Strain measurements are ob- adequate for metallographic examination of these com-
tained nondestructively by using strain gauges. ponents and boat sample removal is not required.
Gauges used for piping measurements are character-
ized by an electrical resistance that varies as a func-
tion of the applied mechanical strain.6 For high tem- Condition assessment of boiler
perature components, the gauge is made of an alloy, components and auxiliaries
such as platinum-tungsten, which can be used at tem-
peratures up to 1200F (649C). The gauge is welded to In Phase 1 of a condition assessment program, in-
the surface of the pipe and the strain is measured as terviews of plant personnel and review of historical
the pipe ramps through a temperature-pressure cycle maintenance records help identify problem compo-
to operating temperature. Strain gauges used for lower nents. These components are targeted for a closer on-
temperature applications such as for analysis of hanger site examination during Phase 2 of the program. Non-
support rods are made of conventional copper-nickel al- destructive and destructive examination methods can
loy (constantan). These low temperature gauges are then be used to evaluate the remaining life of the boiler
made of thin foil bonded to a flexible backing and are components and its major auxiliaries.
attached to the test surface by a special adhesive.
Temperature measurement Most temperature mea-
Boiler drums
surements can be obtained with sheathed thermo- Steam drum The steam drum is the most expensive
couples (TC). In special applications where tempera- boiler component and must be included in any com-
ture gradients are needed such as detailed stress prehensive condition assessment program. There are
analysis of header ligaments, special embedded TCs two types of steam drums, the all-welded design used
are used. The embedded unit is constructed by drill- predominantly in electric utilities where the operat-
ing a small hole into the header. A sheathed TC wire is ing pressures exceed 1800 psi (12.4 MPa), and drums
then inserted and peened in place. (See Chapter 40.) with rolled tubes. The steam drum operates at satu-
ration temperature [less than 700F (371C)]. Because
Destructive examinations of this relatively low operating temperature, the drum
B&W tries to minimize the use of sample analysis is made of carbon steel and is not subject to signifi-
because it is generally more expensive to perform destruc- cant creep. Creep is defined as increasing strain at a
tive testing. However, for certain components, complete constant stress over time.
evaluation can only be done by removing and analyz- Regardless of drum type, damage is primarily due
ing test samples. Destructive testing is described for two to internal metal loss. The causes of metal loss include:
types of specimens, tube samples and boat samples. corrosion and oxidation, which can occur during ex-
Tube samples Tubes are the most common destruc- tended outages; acid attack; oxygen pitting; and
tively tested components. Tube samples are generally chelant attack discussed in Chapter 42. Damage can
removed from water- and steam-cooled circuits. A rela- also occur from mechanical and thermal stresses on
tively large number of samples may be removed for the drum that concentrate at nozzle and attachment
visual inspections, from which a smaller number are welds. These stresses, most often associated with boil-
selected for complete laboratory analysis. A tube ers that are on/off cycled, can result in crack develop-
analysis usually includes the following: 1) as-received ment. Cyclic operation can lead to drum distortion
sample photo documentation, 2) complete visual in- (humping) and can result in concentrated stresses at
spection under magnification, 3) dimensional evalu- the major support welds, seam welds, and girth welds.
ation of a ring section removed from the sample, 4) The feedwater penetration area has the greatest ther-
material verification by spectrographic analysis, 5) op- mal differential because incoming feedwater can be
tical metallography, and 6) material hardness mea- several hundred degrees below drum temperature.
surement. On waterwall tubes removed from the A problem unique to steam drums with rolled tube
boiler furnace, the analysis includes a measurement seats is tube seat weepage (slight seeping of water
of the internal deposit loading [g/ft2 (g/m2)] and el- through the rolled joint). If the leak is not stopped, the
emental composition of the deposit. On steam-cooled joint, with its high residual stresses from the tube roll-
superheater and reheater tubes, the thickness of the ing operation, can experience caustic embrittlement.
high temperature oxide layer is also provided. (See Chapter 42.) In addition, the act of eliminating
Specialized tests are performed as required to pro- the tube seat leak by repeated tube rolling can over-
vide more in-depth information. Failure analysis is a stress the drum shell between tube seats and lead to
common example. When failures occur in which the ligament cracking.
root cause is not readily known from standard tests, Condition assessment of the steam drum can in-
fractography is performed. Fractography involves clude visual and fiber optic scope examination, MT,
examination of the fracture surface using a scanning PT, WFMT, UT and replication.
electron microscope. Lower drum The lower or mud drum is most often
Boat samples Boat samples are wedge shaped slices found in industrial boilers. (See Chapter 27.) Part of
removed from larger components such as headers, the boilers water circuit, the lower drum is not sub-

45-6 Steam 41 / Condition Assessment


The Babcock & Wilcox Company

ject to large thermal differentials or mechanical sessment includes UTT measurements on nondrainable
stresses. However, as in steam drums with rolled tubes, sections and on the extrados (outside surface) of bends.
seat weepage and excessive stresses from tube rolling When access is available it is advantageous to perform
can occur. In most cases, visual inspection, including internal visual inspection with a fiber optic or video probe.
fiber optic probe examination of selected tube penetra-
tions, is sufficient. Kraft recovery boiler lower drums Headers
are subject to corrosion of the tube-drum interface on Headers and their associated problems can be
the OD. This area of the drum is inaccessible, there- grouped according to operating temperature. High
fore inspections are conducted from the ID using UTT temperature steam-carrying headers are a major con-
and EMATs to check for cracking and wall thinning. cern because they have a finite creep life and their
The downcomers carry water from the steam drum replacement cost is high. Lower temperature water-
to the mud drum and the various wall circuits. Two and steam-cooled headers are not susceptible to creep
areas on the downcomers that should be inspected are but may be damaged by corrosion, erosion, or severe
termination welds for cracks and horizontal runs of thermal stresses.
piping for internal corrosion pitting and thinning. High temperature The high temperature headers
are the superheater and reheater outlets that oper-
Boiler tubing ate at a bulk temperature of 900F (482C) or higher.
Steam-cooled Steam-cooled tubing is found in the Headers operating at high temperature experience
superheater and reheat superheater. Both compo- creep under normal conditions. The mechanics of creep
nents have tubes subjected to the effects of metal crack initiation and crack growth are further dis-
creep. Creep is a function of temperature, stress and cussed in the data analysis section of this chapter. Fig.
operating time. The creep life of the superheater tubes 7 illustrates the locations where cracking is most likely
is reduced by higher than expected operating tem- to occur on high temperature headers. In addition to
perature, thermal cycling, and by other damage material degradation resulting from creep, high tem-
mechanisms, such as erosion and corrosion, causing perature headers can experience thermal and me-
tube wall thinning and increased stresses. Excessive chanical fatigue. Creep stresses in combination with
stresses associated with thermal expansion and me- thermal fatigue stress lead to failure much sooner
chanical loading can also occur, leading to tube cracks than those resulting from creep alone.
and leaks independent of the predicted creep life. There are three factors influencing creep fatigue in
As discussed in Chapters 19, 21, 29 and 45, super- superheater high temperature headers: combustion,
heater tubing can also experience erosion, corrosion, steam flow and boiler load. Heat distribution within
and interacting combinations of both. the boiler is not uniform: burner inputs can vary, air
Condition assessment of the superheater tubes in- distribution is not uniform, and slagging and fouling
cludes visual inspection, NOTIS, UTT and tube can occur. The net effect of these combustion param-
sample analysis. Problems due to erosion, corrosion, eters is variations in heat input to individual super-
expansion, or excessive temperature can generally be heater and reheater tubes. When combined with
located by visual examination. steam flow differences between tubes within a bank,
Water-cooled Water-cooled tubes include those of significant variations in steam temperature entering
the economizer, boiler (generating) bank and furnace. the header can occur. (See Fig. 8.) Changes in boiler
The convection pass side wall and screen tubes may load further aggravate the temperature difference
also be water-cooled as discussed in Chapter 19. These between the individual tube legs and the bulk header.
tubes operate at or below saturation temperature and As boiler load increases, the firing rate must increase
are not subject to significant creep. Modern boilers in to maintain pressure. During this transient, the boiler
electric utilities and many industrial plants operate is temporarily over fired to compensate for the increas-
at high pressures. Because these boilers are not tol- ing steam flow and decreasing pressure. During load
erant of waterside deposits, they must be chemically decreases, the firing rate decreases slightly faster than
cleaned periodically, which results in some tube ma- steam flow in the superheater with a resulting de-
terial loss. As discussed in Chapter 42, proper water crease in tube outlet temperature relative to that of
chemistry control will limit tube inside surface mate- the bulk header (Fig. 9). As a consequence of these
rial loss due to ongoing operations and cleaning.
With the exception of creep deformation, the factors
that reduce steam-cooled tube life can also act upon
water-cooled tubes. Erosion is most likely to occur on
tube outside surfaces in the boiler or economizer bank
from sootblowing or ash particle impingement. Cor-
rosion of the water-cooled tubes is most common on
internal tube surfaces and results from excessive
waterside deposits. Deposit accumulations promote
corrosion, caustic gouging or hydrogen damage.
Risers The riser tubes are generally found in the
penthouse or over the roof of the boiler. They carry
the saturated steam-water mixture exiting the upper
waterwall headers to the steam drum. Condition as- Fig. 7 Header locations susceptible to cracking.

Steam 41 / Condition Assessment 45-7


The Babcock & Wilcox Company

Fig. 9 Superheater tube leg temperatures vary with load.

This test is considered the most effective. Ideally, the


Fig. 8 Steam temperature variation in a header. evaluation should correspond to the hottest location
along the header.
Low temperature The low temperature headers are
temperature gradients, the header experiences local- those operating at temperatures below which creep is
ized stresses much greater than those associated with a consideration. These include waterwall headers,
steam pressure and can result in large ligament cracks economizer inlet and outlet headers, and superheater
as shown in Fig. 10. inlet and intermediate headers. Any damage to the
In addition to the effects of temperature variations, low temperature headers is generally caused by cor-
the external stresses associated with header expan- rosion or erosion.
sion and piping loads must be evaluated. Header ex- Waterwall headers, found in most electric utility
pansion can cause damage on cycling units resulting and industrial power generation boilers, are generally
in fatigue cracks at support attachments, torque located outside the hostile environment of the combus-
plates, and tube stub to header welds. Steam piping
flexibility can cause excessive loads to be transmitted
to the header outlet nozzle. These stresses result in
externally initiated cracks at the outlet nozzle to
header saddle weld.
Condition assessment of high temperature headers
should include a combination of NDE techniques that
are targeted at the welds where cracks are most likely
to develop. Creep of the header causes it to swell; the
diameter should be measured at several locations on
the header and the outlet nozzle. All major header
welds, including the outlet nozzle, torque plates, sup-
port lugs, support plates and circumferential girth
welds, should be examined by MT or PT. A percent-
age of the stub to header welds should be examined
by PT. Each section of the header should be examined
by eddy current or acid etching to locate the seam if it
is not readily apparent. The seam weld is examined
for surface indications by MT or PT, and ultrasonic
shear wave testing is performed to locate subsurface
flaws. To examine the header for creep damage, met-
allographic replication is performed. The last test that
should be performed on any high temperature header
is internal examination of at least two tube bore holes. Fig. 10 Large ligament cracks on header ID.

45-8 Steam 41 / Condition Assessment


The Babcock & Wilcox Company

tion zone. One exception is the economizer inlet


header; this may be in the gas stream and is subject
to unique problems associated with cycling. Boilers
that are held overnight in a hot standby condition
without firing can experience severe damage to the
economizer inlet header in a very short time. This
damage is typically caused by thermal shock.
The magnitude of the thermal shock is a function
of the temperature differential between the feedwater
and the inlet header. It is also a function of water flow,
which is usually large because the feedwater piping/
valve train is sized for rated boiler capacity. The ther-
mal shock is worst near the header feedwater inlet and
rapidly decreases as flow passes into the header and
tubes. The primary concern with other low tempera- Fig. 12 Failed attemperator spray head.
ture headers is internal and external corrosion dur-
ing out of service periods. Lower waterwall headers
on stoker-fired boilers that burn coal or refuse may radiograph plugs before and after the attemperator
experience erosion along the side walls adjacent to the to better view the critical liner welds.
stoker grates.
High temperature piping
Attemperators Damage mechanisms Damage to high temperature
The attemperator, or desuperheater, is located in piping systems operating at more than 800F (427C)
the piping of the superheater and is used for steam arises from creep, cycle fatigue, creep fatigue, and
temperature control. (See Chapter 19.) The spray at- erosion-corrosion.
temperator is the most common type used. (See Fig. Most modern high temperature piping systems are
11.) In the spray unit, high quality water is sprayed designed for temperatures ranging from 950 to 1050F
directly into the superheated steam flow where it va- (510 to 566C), or higher. The American Society of Me-
porizes to cool the steam. The attemperator is typi- chanical Engineers (ASME) allowable material
cally located in the piping between the primary su- stresses at these temperatures may produce creep
perheater outlet header and the secondary super- rupture in approximately 30 to 40 years. Systems
heater inlet header. Steam exiting the primary header designed from 1950 through 1965, that used 1-1/4 Cr-
at temperatures of 800 to 900F (427 to 482C) enters 1/2 Mo alloy steel, may be underdesigned by todays
the attemperator, where relatively cool water [approxi- standards because the ASME Code has evolved, low-
mately 300F (149C)] is sprayed into the steam and re- ering the allowable high temperature stress for this
duces the temperature to the inlet of the secondary material.
superheater. Because of the large temperature differ- Fatigue damage to a piping system is caused by
ence between the steam and spray water, parts of the repeated cyclic loading, which can be the result of
attemperator experience thermal shock each time it mechanical loads, thermal expansion and contraction,
is used. Over a period of years this can lead to ther- and vibration. Most piping systems are designed with
mal fatigue and eventual failure (Fig. 12). some degree of fatigue resistance. This built-in flex-
Condition assessment of the attemperator requires ibility comes from hangers and supports.
removal of the spray nozzle assembly. The thermal Creep and fatigue can occur together and interact
stresses occurring in the attemperator are most dam- to cause more damage than each mechanism by itself;
aging at welds, which act as stress concentrators. The it is not fully understood which mechanism is the pri-
spray head and welds on the nozzle assembly are ex- mary cause. This combination of conditions is by far
amined visually and by PT to ensure there are no the most prominent because most power piping sys-
cracks. With the spray head removed, the liner can tems are highly dynamic.
be examined with a video or fiber optic probe. For Erosion-corrosion is not as prominent as the creep
larger attemperators, it may be necessary to remove fatigue failure mechanisms. It is defined as wall thin-
ning that is flow induced and occurs on the fluid side
of the piping system. Factors that contribute to ero-
sion-corrosion include bulk fluid velocity, material
composition and fluid percent moisture.
Overall evaluation program When evaluating high
temperature piping, condition assessment is usually
necessary if the following conditions exist: piping op-
erates above 1000F (538C); was manufactured of
SA335-P11 or P22 material, or manufactured of long
seam welded material; has had hanger problems; was
manufactured with specific weld joint types; has a
history of steam leaks; or operates above design con-
Fig. 11 Typical attemperator assembly. ditions. Once a priority list is developed, the evalua-

Steam 41 / Condition Assessment 45-9


The Babcock & Wilcox Company

tion can begin. This evaluation program should be as


complete as economically possible. Table 1
Detailed evaluation program Typical Piping System Tests
Phase I To determine where physical testing is re- Test Area Test Type Optional*
quired, the following preliminary steps are part of a
Phase I evaluation: plant personnel interviews, plant Circumferential welds A, B, D, E, F, G, H C, I, J
history review, walkdowns, stress analysis, and life Longitudinal welds A, B, D, E, F, G, H C, I, J
fraction analysis. Wye blocks A, B, E, F, G, H C, D, I, J
Plant personnel interviews are conducted to gather Hanger shear lugs A, B C, F, G, J
Hanger bracket and
information that is not readily available from plant supports A, B C, F, G, J
records. Significant history may only be found in rec- Branch connections A, B, D, E, F, G, H C, I, J
ollections of experienced personnel. RT plugs A, B C, F, G, I
Operating history reviews complement personnel Misc. taps and drains A, B C, I
interviews. They can provide problem histories and Elbows/bend A, E, F B, C, G
design or operating solutions.
Piping system walkdowns serve three major func- A - Visual F - Replication
tions: to evaluate pipe supports and hangers, to find B - Magnetic particle G - Material ID
C - Liquid penetrant H - Dimensional
major bending or warpage, and to verify changes. D - Ultrasonic shear I - Radiography
Pipe hangers and supports should be carefully ex- E - Ultrasonic thickness J - Metallography
amined. This can be done by creating a baseline in-
spection record of all supports. * Optional tests should be used to gather more detailed
While the data are being taken on the piping information.
walkdown, the general appearance should also be
noted. In particular, inspections may reveal the fol-
lowing damages: necked-down rods or yokes, spring the pipe has deformed, it has undoubtedly gone
coil fractures, deterioration of the hanger can, and through a severe thermal shock. The high strain be-
deterioration of tiebacks into building steel. tween the upper and lower sections of pipe can cause
Many times a walkdown reveals that a modification permanent deformation.
was performed. If the entire system was not reviewed Two final common failure areas are the boiler outlet
during the modification, other problems may result. headers and turbine stop (throttle) valves. These areas
Stress analysis of the piping system can now be should always be considered in any piping evaluation.
performed. Typically, a computer program is used to
perform the stress calculations based on design and Low temperature piping
any abnormal conditions found during the walkdown. Low temperature piping operating at less than 800F
Once a piping system is modeled, the analysis allows (427C) is not damaged by creep. These systems typi-
the engineer to pinpoint high stress locations. The cally fail due to fatigue, erosion or corrosion. The
objective is to limit the nondestructive examination evaluation methods are the same as those for high
work to these high stress areas. temperature piping; however, a finite life is not pre-
Life fraction analysis (LFA) of a pipe is done if the dicted. Low temperature pipes, if maintained, last
primary failure mode is creep due to operating tem- much longer than their high temperature counter-
peratures above 900F (482C). The LFA is based on the parts. Typical systems are reheat inlet steam lines,
units operating history and stress levels are calcu- extraction lines, feedwater lines and general service
lated using design conditions and minimum wall water lines.
thicknesses. This analysis is discussed at length later. Typical failures Many high temperature failure
Phase II Phase II of the evaluation includes all modes occur in low temperature pipes. Cold reheat
physical testing of the piping system. The majority of lines experience thermal shock because the reheat
the testing should be nondestructive; however, some temperature control is typically an in-line attempera-
destructive testing may be required. The results from tor. The attemperator spray can shock the line if the
Phase I testing provide test location priority. Specific liner is damaged or the nozzle is broken. Economizer
test recommendations are shown in Table 1. discharge lines that run from the economizer outlet
The test data generated from the inspections must header to the boiler drum can be damaged during
be evaluated to determine the remaining component startup sequences. If the economizer is steaming and
life. This is known as the Phase III evaluation and is flow is initiated as a water slug, the line can experi-
covered under Analysis techniques. ence severe shocks. This can cause line distortion and
Typical failures The most typical steam pipe fail- cracking at the end connections and support brack-
ure is cracking of attachment welds (support welds or ets. Other low temperature piping can be damaged by
shear lugs). These cracks are caused by thermal fa- oxygen pitting caused by inadequate water treatment.
tigue, improper support, or improper welding. Erosion due to flow cavitation around intrusion points
Radiograph plugs often have cracked seal welds. can cause severe wall thinning. If solid particles are
Although the plug threads are the pressure bearing entrained in the fluid, erosion of pipe elbows results.
surfaces, they can become disengaged over time due General corrosion of the inside pipe surface can be caused
to corrosion, creep swelling or oxidation. by extended outage periods. Proper line draining is rec-
Steam pipe warping is another serious problem. If ommended unless protective materials are in place.

45-10 Steam 41 / Condition Assessment


The Babcock & Wilcox Company

Tubular air heaters The structural members of the boiler must be re-
Tubular air heaters are large heat exchangers that viewed during a condition assessment inspection.
transfer heat from the boiler flue gas to the incoming Normally these members, along with the support rods
combustion air, as discussed in Chapter 20. On large above the boiler and auxiliaries, last the life of the
utility boilers, tubular air heaters can contain up to boiler. However, because nonuniform expansion can
90,000 tubes with lengths of 50 ft (15.2 m) each. These lead to boiler load movement, the support system
2 in. (50.8 mm) OD tubes are densely grouped with should be examined during the boiler outage inspec-
spacings of 3 to 6 in. (76.2 to 152.4 mm) centers in two tions. Particular attention should be given to header
directions. Flue gas flow direction is typically oppo- and drum supports that could be damaged if the ves-
site that of the combustion air to maximize thermal sel is distorted.
efficiency. Unfortunately, this promotes corrosion on
the gas side cold end. Analysis techniques
Condensate formation promotes acid corrosion from
the flue gas which causes wall thinning. If left un- Once the testing is complete and the data are com-
checked for several years the tubes eventually corrode piled, the next step in condition assessment is to de-
through, causing air leakage from the air to gas side. cide whether to repair, replace or re-inspect certain
Because access to air heater tubes is limited, eddy components. For high temperature components with
current and acoustic technologies are used to test for finite lives, this decision is aided by computers that
blockage, holes and wall thinning. Eddy current tech- predict failures by modeling analyses.
nology is used to measure wall thicknesses of thin Component end of life is defined as the point at
[< 0.065 in. (< 1.65 mm)] nonferrous heat exchanger which failures occur frequently, the costs of inspection
tubing. Holes and partial and complete blockage are and repair exceed replacement cost, or personnel are
located using acoustic technology. When an audible at risk. Therefore, remaining life can be considered
sound is introduced into a tube it travels the length of as the interval between the present time (tp) with ac-
the tube and exits the open end. If a hole exists in the cumulated damage and the time at end of life (te). This
tube, however, it changes the signal pitch in the same can be written as:
manner as a flutist changes a note pitch. In a like
manner, partial or total tube blockage yields a pitch R.L. = te tp (1)
change. B&W uses The Acoustic Ranger inspection For waterwall tubing that is eroding at a linear rate,
probe for this test. (See Fig. 13.) the remaining life is as follows:
Boiler settings
R.L. =
(tc tr )
The boiler components that are not part of the (2)
e.r.
steam-water pressure boundary are general mainte-
nance items that do not have a significant impact on where
remaining life of the unit. The nonpressure compo- R.L. = remaining life
nents include the penthouse, boiler casing, brickwork tc = current wall thickness, in. (mm)
and refractories, and flues and ducts. Deterioration tr = preset replacement wall thickness, in. (mm)
of these components results from mechanical and ther- e.r. = erosion rate, in./yr (mm/yr)
mal fatigue, overheat, erosion and corrosion. In all
cases, condition assessment is done by performing a Remaining life of headers is calculated using mod-
detailed visual inspection. For flues, ducts and casing, eling software due to the complexity of crack growth.
it is of value to inspect the in-service boiler to detect
hot spots, air leaks and flue gas leaks that can indi- Steam-cooled tubes
cate a failed seal. Steam-carrying superheater and reheater tubes
operating at temperatures above 900F (482C) are
subject to failure by creep rupture. The creep life of a
tube can be estimated from tabulated data, provided
the applied (hoop) stress and the operating tempera-
ture are known.
When a tube is put in service, the metal contacting
the steam begins to form a layer of oxide scale known
as magnetite (Fe3O4). As the life progresses, the ID
oxide layer grows at a rate that is dependent on tem-
perature. This scale acts as a heat transfer barrier and
causes an increase in the tube metal temperature as
discussed in Chapter 4. The metal temperature, there-
fore, also gradually increases with time.
Internal oxide thickness measurements are neces-
sary for estimating a tubes operating temperature and
remaining creep life as well as for assessing the over-
Fig. 13 Acoustic Ranger schematic. all condition of the superheater. In the past, these

Steam 41 / Condition Assessment 45-11


The Babcock & Wilcox Company

measurements have been obtained by removing tube From the LMP equation, the expected time to fail-
samples for laboratory examination. To avoid destruc- ure (tf ) can be calculated:
tive tests, B&W developed the NOTIS NDE technique
discussed earlier. LMP = (T + 460 ) ( 20 + log tf )
Life prediction methodology The prediction of tube (5)
creep life begins with creep rupture data taken in tf = 150, 000 h
short-term laboratory studies. Creep specimens, simi-
lar to cylindrical tensile specimens, are machined from If this tube has operated for 100,000 hours at these
various tube steels. Each specimen is heated to a tem- parameters, the creep life fraction expended is:
perature (T ) and is pulled uniaxially at a stress (S )
until failure occurs; at this point, a time to failure (t) 100, 000
fexpended = t / tf = = 0.6667 (6)
is measured. A matrix of stress and temperature val- 150, 000
ues has been tested.
The Larson-Miller parameter (LMP) is a function The creep life fraction remaining is:
relating T, S, and t. This parameter is defined as:
fremaining = 1 texpended = 1 0.6667 = 0.3334
LMP = (T + 460 ) ( 20 + log t ) tremaining = fremaining tf
where tremaining = 0.3334 150, 000 (7)
T = constant temperature applied to the creep tremaining = 50, 000 h
specimen, F
t = time at temperature T, h
Example Part II
Every tube in service has an associated LMP num- Assume that, after operating at 1050F (566C) for
ber that increases with time. These LMP data can be 100,000 hours, tube temperature increases to 1065F
related to stress, as is illustrated in Fig. 14. This rela- (574C).
tionship between stress and LMP can then be used to Using the same effective LMP, the LMP equation
predict a time to creep rupture for a superheater or is used to calculate tf at 1065F (574C) as follows:
reheater tube. Knowing two of the three factors affect-
ing creep rupture, i.e., hours in service and hoop stress, LMP = (T + 460 ) ( 20 + log tf )
the third factor, temperature history, can be estimated.
(8)
There are numerous mathematical models relating tf = 85, 000 h
steam-side oxide thickness, time, and mean metal tem-
perature for low chromium-molybdenum alloys. The Therefore, a new tube operating at 1065F would
following relationship is most widely used to calculate have an expected life of 85,000 hours. However, from
oxide thickness (x) in mils: Part I, this tube has used up two-thirds of its life at
1050F and has a remaining life fraction of 0.33.
log x = 0.00022 (T + 460 ) ( 20 + log t ) 7.25 (3)
Although this formula works well with 1-1/4 Cr-Mo
alloys, it must be modified for use with higher chro-
mium alloys and carbon steels.
Creep life fraction analysis The life fraction is de-
fined as the ratio of the time a tube withstands a given
stress and temperature (t) to the time for creep rup-
ture conditions (tf).
Robinsons Rule of life fractions states that if the
applied stress and temperature conditions are varied,
the sum of the life fractions (or damage) associated
with each set of conditions equals 1 at failure. It may
also be written as follows:

(t / t )
f 1
+ (t / tf ) 2 + + (t / tf ) n = 1 (4)
where subscripts 1 through n indicate unique stress
temperature conditions.
Example Part I
Assume a tube operates at a hoop stress of 5 ksi
(34,474 kPa) and a temperature of 1050F (566C). What
is the predicted time to failure? Using these param-
eters and the stress-LMP curve presented in Fig. 14,
the effective LMP at failure is 38,015. Fig. 14 Stress versus Larsen-Miller parameter (LMP).

45-12 Steam 41 / Condition Assessment


The Babcock & Wilcox Company

Robinsons Rule can be applied to determine the Capabilities and limitations At elevated temperatures,
higher temperature service life after the tube is ex- the external and internal surfaces of boiler tubes
posed to 100,000 hours at 1050F. slowly oxidize. The external scale is normally removed,
Recall Robinsons Rule the sum of the life frac- whereas the internal scale usually remains intact.
tions is equal to 1: Typically, the multilaminated scale that is formed on
the inner surface is characterized by an iron-rich in-
(t / t )
f 1050
+ (t / tf ) 1065 = 1 ner layer and an oxygen-rich outer layer. The latter
generally contains a large number of pores or voids.
100, 000 / 150, 000 + t / 85, 000 = 1 (9) The ultrasonic response with the NOTIS system from
t = 28, 000 h the inner/outer layer interface is small compared to
the signals associated with the metal/oxide and oxide/
Note that in this example, the total tube life would air interfaces. Therefore, a tightly adhering porous
be 100,000 + 28,000, or 128,000 hours. oxide does not affect the accuracy of the NOTIS sys-
Analysis procedure The following analysis procedure tem. However, if the two oxide layers become dis-
is used with tube wall oxide thickness measurements banded due to exfoliation processes, the NOTIS op-
from the NOTIS system. erator may only measure the oxide thickness to the
disbanded area and therefore indicate that the oxide
1. The life of the tube, past and future, is broken into is exfoliating. Exfoliation is the flaking of scale par-
time intervals, each of length t: ticles off of the internal oxide layer.
An oxide growth rate is determined knowing the
present oxide thickness and the time in service and Water-cooled tubes
assuming the initial oxide thickness was zero. Water-carrying tubes operate at or below satura-
Once a mathematical function describing oxide tion temperature and are not subject to creep dam-
thickness with respect to time and temperature age. Therefore, these tubes have no defined design life
is defined, the thickness in each analysis interval as do high temperature components. However, erosion,
can be calculated. The tube metal temperature in corrosion, thermal expansion and mechanical stresses
each interval, taking into account the insulating act on water carrying tubes. This limits useful practi-
property of the oxide, is also calculated. cal life.
A linear wall thinning rate is determined for the Outside tube wall thinning Erosion and corrosion
tube, knowing the present wall thickness as mea- are the most common causes of OD wall thinning. Ero-
sured by NOTIS, the original wall thickness, and sion typically occurs on the tube outside diameter in
the service time of the tube. Once a function de- the form of wall thickness loss. A tubes wall thickness
scribing wall thickness with respect to time is is designed to the ASME Boiler and Pressure Vessel
defined, the wall thickness in each analysis inter- Code to withstand a given pressure, temperature, and
val can be calculated. The hoop stress is calculated mechanical load. An example is as follows:
using the ASME Boiler Code Section I tube for-
mula in each interval. Given: Design pressure (P) = 2400 psi (16.5 MPa)
2. The creep life fraction used up in each interval is Design temperature (T) = 700F (371C)
determined: Tube outside diameter (OD) = 3 in. (76.2 mm)
Given the stress, the LMP value may be found Tube material = SA210 A1
from the creep rupture database. Given the operat- From the ASME Code the wall thickness formula is:
ing temperature and the LMP, the time a new tube
would last at these conditions (tf) is determined. The PD
interval creep life fraction used up is then t/ tf. t = + 0.005 D (10)
3. Because the life fractions, summed over the analy- 2S + P
sis intervals, are equal to 1, the remaining life is where
obtained by subtracting the tube service time from
this total life. t = minimum wall thickness
P = design pressure
Accuracy of creep life prediction analysis Life fraction D = outside diameter
analysis is the most accurate and widely accepted S = allowable stress
method for estimating tube life. Although this method
is straightforward and well documented, it is not precise. By knowing the material and temperature, the al-
Result inaccuracies are due to inherent material lowable stress can be found in the ASME Code. In this
property variations. Additionally, during service, short case, the allowable stress is 14,400 psi (99,285 kPa).
excursions to higher temperatures lower the remain- Solving the equation gives t = 0.245 in. (6.22 mm).
ing life fraction. In the case of industrial and utility boilers, the next
Rather than attempting to determine the precise higher standard tube thickness would be supplied. In
time of a creep rupture, the evaluation places each the case of a chemical recovery boiler used in the pulp
tube into a band of expected remaining lives. These and paper industry a much higher thickness would
bands take into account the shortcomings of the life be used. This allows for wall thickness reduction when
fraction analysis, as well as the inaccuracy of the op- operated in a reducing atmosphere. (See Chapter 28.)
erating parameters for the unit being assessed. In As a guide, the following are B&W recommenda-
effect, these bands are confidence limits. tions for utility and industrial boiler tubes:

Steam 41 / Condition Assessment 45-13


The Babcock & Wilcox Company

The final step is the development of results from


1. Water-cooled tubes should be repaired to original
Steps 1 and 2. These results are the remaining life or
wall thickness or replaced if reduced to 70% of
crack growth curves that are presented two ways. The
original.
first is a plot of crack versus time. This curve is expo-
2. Steam-cooled tubes should be repaired to original
nential because the crack grows faster as it becomes
wall thickness or replaced if reduced to 85% of
larger. The second curve is the inverse of the first,
original.
plotting size versus remaining life. Remaining life is
Inside tube wall corrosion Internal corrosion due to based on a critical predetermined through-wall crack
hydrogen damage, caustic gouging and under-deposit size. Once the crack reaches this value, the remain-
corrosion is more difficult to evaluate for remaining ing life is zero. From the previous equation, this can
life because it is not easily quantified. be written:
In addition to wall thickness, other factors, such as
the effect of water quality, microstructure and dam- ac da
aged area size, must also be considered. Internal cor-
R.L. = ai bC tm (12)
rosion data can be mapped similarly to that for ultra-
sonic wall thickness. where ac is the critical crack depth and ai is the initial
Internal deposits Internal deposits lead to tube fail- crack depth.
ures and provide initiation sites for hydrogen damage Leak before break analysis (LBBA) When evaluat-
and under-deposit corrosion as discussed in Chapter ing cracks that are growing at a stable rate, even
42. The type of corrosion depends upon the nature of though they are through-wall, a condition occurs
the deposit (dense or porous) and the composition of where fluid leaks through the crack but does not cause
the chemicals beneath the deposit. Chemical cleaning
of the boiler removes these deposits. The cleaning fre-
quency depends on the type of unit, operating pres-
sure, fuel, and water treatment program. The hours Step 1
of operation and data from tube samples also deter-
mine the cleaning frequency.
Tube samples should be taken from locations with
the heaviest deposits which are usually located in the
high heat input burner zone areas of the furnace.

Headers and piping


High temperature headers and piping typically fail
Crack Growth Creep
due to creep, fatigue, or a combination of the two. Al- Specimens Specimen
though a header is more complex in geometry, it is
essentially a pipe with tubes welded to it. Therefore,
many of the remaining life analyses are similar to
those for tubes. However, it must be noted that the
root cause of damage can be different in headers.
On thick walled sections, where thermal and stress da
gradients can occur, remaining life is based on crack Log
dt da Log =A n
=bC mt
initiation and propagation. Calculational methods, dt
statistics, dimensional measurements, metallographic
methods, and post service creep rupture testing are Log
Log Ct
considered mainly with crack initiation and the events Crack Growth Behavior Creep Deformation Behavior
preceding it. When dealing with thick sections, these
analytical techniques must be followed by crack
Step 2
growth analyses. Once a component is cracked, the
pre-crack evaluation methods do not apply.
Crack growth analysis (CGA) There are three steps
used in predicting crack propagation based on time de- Step 3
pendent fracture mechanics. (See also Chapter 8.) The
schematic shown in Fig. 15 illustrates the various steps.
Step 1 consists of identifying the creep growth and ai = Initial
deformation behavior of the material. Step 2 consists Ct = f( , A, n, a, t)
Life Crack Size
of the expressions for the crack tip driving force for
creep, Ct. The basic expression for Ct is:
ai
da Cracked Residual Life
= bC m
t (11) Component Curve
dt
where a is crack depth, t is time, and both b and m
are material constants. Fig. 15 Three-step methodology for crack growth analysis.

45-14 Steam 41 / Condition Assessment


The Babcock & Wilcox Company

a catastrophic rupture. If the flaw is characterized by


depth a and length 2C, then the following expression
applies to leak before break:
ac da Ccr dc
R.L. = ai bC tm
= Ci bC m
t
(13)

where Ccr and Ci are the critical crack and initial crack
half lengths respectively. Because all variables except
C i are known or determined, the equation can be
solved for Ci. B&W has developed a software code,
Failure Analysis Diagram (PCFAD), that models
many crack scenarios encountered in header and pip-
ing systems. The failure assessment procedure uses
a safety/failure plane diagram. The plane is defined
by the stress intensity factor/fracture toughness ratio
( Kr) as the ordinate and the applied stress/net section
plastic collapse stress ratio ( Sr ) as the abscissa. If an Fig. 16 Sample PCFAD failure plant diagram.
assessment point lies within the curve (Fig. 16), the
structure is safe. The distance from a point to the curve where
indicates the margin of safety. Chapter 8 provides
further discussion. These two approaches allow the x = number of different stress modes
engineer to determine 1) how long a flaw will take to j = jth stress level
reach a predetermined critical size (crack growth, PC cj = number of cycles at stress level
CREEP), and 2) whether the flaw will cause a leak or Cj = number of cycles to failure at stress level
catastrophic failure. This simple approach requires detailed operating
Life fraction analysis Life fraction analyses (LFA) history. In addition, it only provides a gross estimate
are performed on piping at temperatures above 900F of expected life.
(482C) in which the primary failure mode is creep. Stress calculation The calculation of stresses for
Stress levels are calculated using design conditions. headers is complex because of tube stub geometry, tube
To determine the minimum creep rupture life, pub- bank loading, differential tube temperatures, and
lished creep rupture data (LMP) are used. The calcu- piping stresses on the outlet nozzle. Using specially
lation is similar to that for steam-cooled tubes, how- developed software codes, it is possible to perform a fi-
ever piping is not influenced by gas stream heat flux nite element analysis for the entire header. B&W has
and, therefore, operates at a fairly consistent tempera- performed finite element analysis on the tube stub liga-
ture. The life fraction expended (LFE) is expressed as: ment region and found that this area contains very high
stresses, especially during temperature transients.
t
LFE = (14) The total stress (St) applied to the flaw is equal to
tm the sum of the primary stresses (axial or hoop) (Sp),
bending stresses (Sb) and pressure stresses on the
By using Minors sum, an expression can be created crack face (Sc):
to represent the units history of operating at differ-
ent conditions: St = S p + Sb + Sc (17)
ti The primary stress is determined by the orienta-

z
LFE = (15)
i =1
tmi tion of the flaw. If the flaw is located axially along the
length of the component, then the hoop stress is pri-
where mary. If it is located circumferentially, then the axial
stress is primary. Bending stresses are caused by dead
z = number of different conditions loads, hanger spacing, thermal differentials and re-
i = ith temperature and stress level straints. The pressure stresses applied to the crack face
ti = time of operation at given conditions are only considered when the crack is open to the pres-
tmi = minimum time to creep rupture (LMP) sure. When this is the case, the applied stress is equal
to the internal pressure.
When considering only creep rupture stress, a long
BLESS Code analysis BLESS is an acronym for
remaining life results. However, most piping systems
Boiler Life Evaluation and Simulation System. The
are also subjected to fatigue stress. Fatigue damage
complete BLESS code considers crack initiation and
can be calculated by using standard fatigue curves.
growth in headers as well as crack growth in pipes.
By combining the creep rupture and fatigue compo-
The BLESS Code can also perform leak before break
nents, the expression becomes:
analysis (LBBA) of axial cracks in pipes. The Code was
developed for EPRI by B&W as a subcontractor to
ti cj
General Atomics. The BLESS Code was derived from
z x
LFE = + (16)
i =1
tmi j =1
Cj B&Ws previous software codes for failure analysis

Steam 41 / Condition Assessment 45-15


The Babcock & Wilcox Company

(PCFAD) and crack growth analysis (PC CREEP). electric pressure transducer to detect acoustic energy
Because stress calculations in headers and piping re- emitted by a leak, the detection of smaller leaks be-
quire difficult finite analysis due to complex geom- came possible. Leak noise is transmitted by air and by
etries, simplifying assumptions were made in the de- the structure. Boiler tube leaks are best detected
velopment of the BLESS Code to allow for analysis. through an airborne sensor because of the large boiler
The BLESS Code greatly facilitates the life assess- structure volume. Feedwater heaters, headers and
ment of elevated temperature headers and piping by piping leaks are best detected through a structural
eliminating the need for finite element thermal and sensor. Because these components are small and self-
stress analysis and utilizing developments in nonlin- contained, direct contact monitoring is used.
ear creep-fatigue crack growth. The evaluation in- Leak noise is caused by a fluctuating pressure field
cludes both crack initiation and crack growth. The associated with turbulence in the fluid. Turbulence is
Code permits the evaluation of the effects of extremely a condition of flow instability in which the inertial
detailed thermal and mechanical load histories on effects are highly dominant over the viscous drag ef-
headers with very complicated geometric details. The fects. Once turbulence is established, the acoustic
estimated remaining life is calculated by BLESS ei- energy radiated from a leak increases strongly with
ther as a single value (when re-run in the determin- pressure and flow rates.
istic mode) or a statistical distribution. This distribu- Acoustic leak detection technology has been dem-
tion is obtained when BLESS is run in the probabilis- onstrated through laboratory work, field testing and
tic mode and defines the probability of failure as a operational experience. The sensitivity of the sensor
function of time. Such information can be useful in depends on three factors: sound radiated from the
making run/repair/replace and re-inspection decisions leak, attenuation of sound between the leak and the
for aging or cracked headers and piping. sensor, and background noise. Leak noise occurs in a
Flaw characterization Flaws found in headers and broad band, ranging from below 1 kHz to above 20 kHz.
piping must be characterized prior to crack growth, Because of the low frequency background noise and
LBBA, or BLESS analysis. This characterization in- the greater attenuation of high frequencies, most air-
volves accurately determining the flaws length and borne systems operate in the range of 1 to 25 kHz. This
depth. Through-wall depth is considered the most criti- is important because the acoustical signal diminishes
cal. The most common characterization methods include in amplitude as it travels away from the source. There-
standard NDE techniques such as MT, PT, RT and UT. fore, in designing a system, there is a tradeoff between
sensor spacing and minimum detectable leak.
Destructive samples Table 2 shows typical leak monitor signals for boiler
Destructive sampling is frequently done when data tubes, feedwater heaters, steam piping, and crack
from nondestructive evaluations are inconclusive. detection acoustic emissions.7
Material properties, damage and deposits can be Boiler leak detection The background noise in a
quantified. Tube samples and boat samples are dis- boiler is primarily due to combustion in the furnace.
cussed earlier under Destructive examinations. Direct measurement of background noise is needed to
determine the spectral characteristics. In addition, the
Leak detection background noise level must be stable. The magni-
Leaks in boilers, piping and feedwater heaters are tudes of background noise from different parts of the
major contributors to power plant unavailability and boiler are similar; a large component is due to soot-
performance losses. In their early stages, leaks are blower operation.
often undetected because they are inaudible and/or Using background noise and leak characterization
concealed by insulation. data, full scale tests have been run to optimize sensor
In the early 1980s, acoustic monitoring equipment listening distances, sensor orientation, and signal pro-
began to be used for leak detection. By using a piezo- cessing equipment. A typical 500 MW utility boiler can

Table 2
Typical Acoustic Monitoring Signals8
Leak Detection Crack Detection
Boiler Tubes Feedwater Heaters Steam Lines Steam Lines/Headers

Acoustic path Gasborne Waterborne Metalborne Metalborne Metalborne


Detection band 0.5 to 25 kHz 5 to 25 kHz 100 to 400 kHz 200 to 500 kHz 100 to 500 kHz
Background noise
frequency Below 2 kHz Below 8 kHz Below 125 kHz Below 200 kHz Below 200 kHz
Background noise
amplitude* 20 to 30 dB 40 to 60 dB 30 to 50 dB 40 to 60 dB 40 to 60 dB
Total system gain 60 dB 50 to 60 dB 40 to 60 dB 40 dB 60 to 80 dB
Number of sensors 12 to 18 1 to 2 per heater 1 per heater Every 20 ft Every 10 to 20 ft
(6.1 m) (3 to 6.1 m)
* Reference 1 bar

45-16 Steam 41 / Condition Assessment


The Babcock & Wilcox Company

be monitored using 16 to 24 sensor channels. Fig. 17


shows a typical airborne sensor and waveguide ar-
rangement.
Waveguides are installed through the boiler enclo-
sure at various locations. A typical sensor has a de-
tection range of approximately 50 ft (15.2 m).
Header and piping leak detection Headers and pip-
ing are monitored with structural sensors similar to
those of feedwater heaters. The sensors are placed
approximately 15 to 20 ft (4.6 to 6.1 m) apart.
These sensors can also be used to detect crack
growth. When a crack grows, it emits acoustic energy
that can be detected. The processing of crack growth
signals from leak detection sensors requires different,
more powerful computing hardware than the systems
required for leak detection. With structural leak de-
tection sensors installed, and the proper fitting and
signal processing hardware, periodic monitoring for
crack growth can be performed.

Cycling effects and solutions


In assessing a boilers ability to withstand cycling,
those components most vulnerable to cycling are re-
viewed first. These components are discussed from two
standpoints: the operating methods which minimize
cyclic damage, and design modifications which permit
the component to better withstand cycling conditions. Fig. 17 Typical airborne noise sensors.

Cycle definition during the load decrease and increase are usually not
Two types of cycling service are usually considered: excessive, but would represent load cycling conditions
load cycling and on/off cycling. The on/off type has also for the economizer.
been called two shifting. During the banked period, there is some air leak-
A cycle is considered to start at full load, full tem- age through the boiler with a resulting decay in boiler
perature steady-state conditions. It goes through a pressure. As this happens, the drum water level de-
load change, then returns to the initial conditions. A creases. At the same time, the leaking air passing
typical load cycle is then composed of three phases: through the boiler is heated to near saturation tem-
perature, and that air then heats the economizer. An
1) load reduction,
economizer metal temperature can increase at 30 to
2) low load operation, and
50F/h (17 to 28C/h) during this period and can ap-
3) reloading.
proach saturation temperatures. When the drum level
A typical on/off cycle has four phases: drops, the operator usually refills the boiler so that it
is ready for firing. Because there is no extraction steam
1) load reduction,
available, the feedwater temperature is low. This slug
2) idle,
of cold water quickly chills the economizer, causing ther-
3) restart, and
mal shock as indicated by the solid lines in Fig. 18. The
4) reload.
inlet header and tubes receive the greatest shock.
The phase that is often ignored, the idle period, can of- When the boiler is fired in preparation for turbine
fer the greatest potential for reducing cyclic damage. restart, rollup, and synchronization, the economizer
heats up rapidly, often nearing saturation tempera-
Economizer thermal shock ture. Feedwater is started when the initial load is
On boilers that are on/off cycled, economizers often applied to the turbine. Because little extraction heat-
show more cyclic damage than the other components. ing is available, feedwater temperature is low. A se-
The economizer receives water from the extraction feed- vere shock occurs at this point, as the temperature can
water heater system, and the inner metal surfaces fol- increase 300F (167C) in a few minutes.
low the feedwater temperature with practically no time Typically, early damage consists of cracks initiat-
delay. As a result, high rates of metal temperature ing in the tube holes of the inlet header which are clos-
change can occur with resultingly high local stresses. est to the feedwater inlet connection (Fig. 19).
Fig. 18 shows economizer inlet temperatures dur- Other damage has also been seen from this cyclic
ing an overnight shutdown cycle. The first two hours service. Outlet headers have shown damage similar
are for load reduction, followed by eight hours of idle to inlet headers. Furthermore, some tube bank sup-
or banked condition. Next, the boiler is fired in prepa- port systems can not accommodate the high tempera-
ration for restart. The rates of temperature change ture differences between rows.

Steam 41 / Condition Assessment 45-17


The Babcock & Wilcox Company

A second method of reducing thermal shock is to


permit the economizer to reheat during the idle pe-
riod and then to provide higher temperature feedwater
for restart. This can occur by pressurizing a high pres-
sure heater with steam from an auxiliary source or
from the drum of the unit. The quantity of steam re-
quired is low because it only heats the initial low flow
of feedwater.
Furnace subcooling
Several drum boilers that have been subjected to
on/off cycling have developed multiple cracks in lower
furnace wall tubes where the tubes are restrained from
diameter expansion or contraction. Typical cracking
areas have been at the lower windbox attachment where
filler bars or plates are welded to the tubes (Fig. 20).
Investigation of these failures indicated that, dur-
ing the shutdown or idle period, relatively cold (cooled
below saturation temperature) water settled in the
lowest circuits of the furnace bottom. When circula-
tion was started by initial firing or the circulating
pump, the cold water interface moved upward through
the walls, rapidly cooling the tubes. As the interface
moved, its temperature gradient decreased and the
rate of cooling decreased, therefore reducing damage
higher in the furnace. Experience indicates that if the
subcooling can be limited to 100F (56C), there is a low
Fig. 18 Economizer temperatures during overnight shutdown cycles. probability of damage.
An out-of-service circulating pump system may be
used to limit the subcooling (Fig. 21). This is a low
Solutions are available to reduce the frequency and capacity pump that draws from the bottom of the down-
magnitude of thermal shocks. These have taken two forms comers and discharges water to the drum, therefore
and address the out of service and restart conditions.
The first solution is called trickle feed cooling. Very
small quantities of feedwater are frequently intro-
duced during the shutdown and restart periods. This
prevents the inlet header from reheating and reduces
the cooling rate during feedwater introduction. Be-
cause feedwater introduction is controlled to limit
economizer temperature rise, some drum blowdown
may be necessary to prevent a high water level.

Fig. 19 Cracking in economizer inlet header occurs first in bore


holes nearest water inlet. Fig. 20 Lower windbox attachment cracking due to subcooling.

45-18 Steam 41 / Condition Assessment


The Babcock & Wilcox Company

and variable drum pressures, as shown in Fig. 23. In


this example, for constant drum pressure, the maxi-
mum differential occurs at 50% load (hour 1) and is:
1000F 685F = 315F (538C 363C = 175C)
The minimum difference is at the end of the idle pe-
riod (hour 10) and is:
655F 570F = 85F (346C 299C = 47C)
This is a stress range proportional to:
315F 85F = 230F (157C 29C = 128C)
For variable drum pressure, the maximum differ-
ence occurs at 35% load and is:
1000F 540F = 460F (538C 282C = 256C)
The minimum temperature difference at the end of the
idle period is:
655F 400F = 255F (346C 204C = 142C)
producing a stress range proportional to:
460F 255F = 205F (238C 124C = 114C)
The variable drum pressure mode of operation is then
Fig. 21 Out-of-service circulating pump system. slightly less severe for the superheater and reheater
outlets and much less severe for the reheater inlet.
In considering operational changes, it should be
preventing the stratification temperatures of water noted that the steam temperature characteristics
within the unit. shown are the maximum available at a given load.

Tube leg flexibility


The enclosure walls of most boilers are water- or
steam-cooled. The water-cooled circuits carry boiling
water, and the steam-cooled circuits carry steam from
the drum. As a result, they operate near the satura-
tion temperature corresponding to the drum pressure.
Whether the boiler is being fired or shut down, con-
siderable heat absorption or loss is necessary to change
the temperature of the walls. As a result, they change
temperature more slowly than the other components.
The economizer, superheater and reheaters pen-
etrate these walls; the penetrations are designed to be
gas-tight. At the point of penetration the expansion
then follows saturation temperature. However, the
header that forms the inlet or outlet of the other cir-
cuits expands with the temperature of the steam or
water that it is handling. Fig. 22 shows the motions
of the header end and the outermost connecting leg
for a superheater or reheater outlet. Note that the
greatest deflection is when the header temperature is
at a maximum.
In the case of economizers and the reheater inlet,
the deflection is in the opposite direction because these
headers operate below saturation temperature. For
these components the greatest temperature difference,
and therefore the greatest deflection, is at low loads.
Regardless of the direction, the greatest tempera-
ture difference produces the maximum differential
expansion and the maximum bending stresses in the
connecting legs. The stress range and amplitude dic-
tate component fatigue life.
Consider the superheater outlet and the drum (pen-
etration point) temperature differences at constant Fig. 22 Superheater tube leg flexibility.

Steam 41 / Condition Assessment 45-19


The Babcock & Wilcox Company

differences develop during pressure reduction, when


little or no steam is being taken from the drum.
If drum pressure is rapidly lost during the idle pe-
riod, top to bottom differentials develop and the drum
humps. Because most drums have two point supports,
the humping is unrestrained and causes little change
in the drum or support stress levels. However, the
drum acts as a stiff beam, and connected parts move
with it (Fig. 24). If those parts do not have sufficient
flexibility they can experience unacceptably high
stresses.
While most recent units were designed with flex-
ibility in the drum connections, there are some older
units where the front furnace wall tubes are routed
directly to the drum and are supported by the drum.
In such cases, it is difficult to add flexibility by rerout-
ing and the humping must be limited.
Developments
Symptoms of advanced creep and fatigue have been
found in some older superheater and reheater outlet
headers. Diametral swelling has been observed. In-
terior cracking around the header ID tube holes and
along the length has also been present. To better un-
derstand the failure mechanism, finite element stress
analyses have been performed. These analyses con-
sider steady-state temperature differences between
individual tubes and the bulk header and transient
Fig. 23 Overnight shutdown temperatures. temperature changes of both.

Lower temperature differences of 50 to 75F (28 to 42C) Advances in nondestructive examinations


may be obtained in practice.
The first indications of cyclic damage are external Innovative techniques are being developed to re-
cracks on the tube to header welds or the stub to tube place or enhance existing NDE methods. Some are
welds of the outermost header legs. This damage is becoming viable due to advancements in microproces-
relatively easy to inspect and repair. Successive dam- sor technology. Others are relatively new and may
age is also usually limited to closely adjacent legs be- replace current methods. Advanced techniques in-
cause they have experienced similar stress levels. Most clude: 1) infrared scanning,8 2) automated Phased
sensitive are high temperature headers which are a Array UT, 3) pipe and wall scanners which automati-
short distance from the penetration seal on wide units. cally cover large areas, and 4) through-insulation ra-
diography. EMAT technology is being refined and
Drums studied for further applications in the NDE field.
It is important to limit the rate of saturation tem-
perature change in a steam drum. When operating
in a variable drum pressure mode, considerable
overfiring or underfiring is necessary to quickly
change the drum pressure. These firing effects on
steam temperature control also prevent rapid drum
pressure changes.
Top to bottom drum temperature differences must
also be limited. Only small differences result when
pressure changes are made under load. The greatest Fig. 24 Drum humping.

45-20 Steam 41 / Condition Assessment


The Babcock & Wilcox Company

References
1. Condition Assessment Guidelines for Fossil Fuel Power 5. Bar-Cohen, Y., and Mal, A.K., Ultrasonic Inspection,
Plant Components, Report GS-6724, pp. l-l to 1-6, Elec- Metals Handbook, Ninth Ed., Vol. 17, Nondestructive
tric Power Research Institute (EPRI), Palo Alto, Califor- Evaluation and Quality Control, pp. 255-256, ASM Inter-
nia, March, 1990. national, Metals Park, Ohio, 1989.
2. Guide for the Nondestructive Inspection of Welds, 6. Bar-Cohen, Y., and Mal, A.K., Strain Measurement for
American National Standards/American Welding Society Stress Analysis, Metals Handbook, Ninth Ed., Vol. 17,
(ANSI/AWS) B1.10:1999, American Welding Society, Mi- Nondestructive Evaluation and Quality Control, pp. 448-
ami, Florida, 1999. 449, ASM International, Metals Park, Ohio, 1989.
3. Bar-Cohen, Y., and Mal, A.K., Ultrasonic Inspection, 7. Acoustic Leak Detection, Technical Brief
Metals Handbook, Ninth Ed., Vol. 17, Nondestructive TB.CCS.32.9.87, Electric Power Research Institute (EPRI),
Evaluation and Quality Control, pp. 232-233, 254, ASM Palo Alto, California, September, 1987.
International, Metals Park, Ohio, 1989. 8. Atlantic Electric Demonstrates Infrared Inspection of
4. Alcazar, D.G., et al., Ultrasonic Detection of Hydro- Boiler Waterwalls, First Use, Electric Power Research
gen Damage, Materials Evaluation, Vol. 47 (3), March, 1989. Institute (EPRI), Palo Alto, California, December, 1989.

Steam 41 / Condition Assessment 45-21


The Babcock & Wilcox Company

Electromagnetic acoustic transducer (EMAT) technology is one method used to determine remaining life of boiler tubes.

45-22 Steam 41 / Condition Assessment

You might also like