You are on page 1of 4

PT.

ENCONA INTI INDUSTRI

5.3 TECHNICAL BID ANALYSIS - ADSORBENT


PROJECT : (filled with Project Name)
CLIENT : (filled with Client Name)
JOB NO : (filled with Project Job No.)
DOC NO : (filled with Document Number)

(*) = Vendor to Indicate / Confirm N/R = not required

NO VENDORS UNIT Datasheet [FILL WITH VENDOR NAME]

1 Reference No. - (filled by EII) (*)


2 Date - (filled by EII) (*)
3 Manufacturing Location - (filled by EII) (*)
4 Approved Manufacture List - (filled by EII) (*)
5 DESIGN DATA - PROCESS FLUID VENDOR COMPLIANCE
Design Case - (filled by EII) (*)
Process Fluid - (filled by EII) (*)
Feed Details - Refer to Datasheet
(*)
Product Details - (Doc. No. )

Operating Pressure psig (filled by EII) (*)


Design Pressure psig (filled by EII) (*)
Operating Temperature o
F (filled by EII) (*)
Design Temperature/ MDMT o
F (filled by EII) (*)
Inlet Water Content of Gas lb/MMscf (filled by EII) (*)
Outlet Water content of gas ppmv (filled by EII) (*)
Outlet Water Dew Point o
F (filled by EII) (*)
Minimum Achievable Turndown % (filled by EII) (*)
6 ADSORBENT DATA
Adsorbent Type
- (*) (*)
[to be developed for each adsorbent type used]
Adsorbent Bed Diameter mm (*) (*)
Adsorbent Height mm (*) (*)
Adsorbent Weight lb (*) (*)
Adsorbent Density lb/ft 3
(*) (*)
Adsorbent Size in (*) (*)
Bed support - (filled by EII) (*)
Fixed Bed Support - (filled by EII) (*)
PT. ENCONA INTI INDUSTRI

5.3 TECHNICAL BID ANALYSIS - ADSORBENT


PROJECT : (filled with Project Name)
CLIENT : (filled with Client Name)
JOB NO : (filled with Project Job No.)
DOC NO : (filled with Document Number)

(*) = Vendor to Indicate / Confirm N/R = not required

NO VENDORS UNIT Datasheet [FILL WITH VENDOR NAME]

1 Reference No. - (filled by EII) (*)


2 Date - (filled by EII) (*)
3 Manufacturing Location - (filled by EII) (*)
Ceramic Ball - (filled by EII) (*)
Volume ft 3
(*) (*)
Density lb/ft 3
(*) (*)
Ingredient - (*) (*)
Configuration - (filled by EII) (*)
Number of Adsorbent Beds (Online) - (filled by EII) (*)
Number of Adsorbent Beds (Regen) - (filled by EII) (*)
Number of Adsorbent Beds (Standby) - (filled by EII) (*)
Adsorbent Bed Life Time / Replenishment
years (filled by EII) (*)
Frequency
Maximum Pressure Fluctuation to prevent
(*) (*)
adsorbent lifting
ADSORPTION CYCLE
Adsorption Times hours/ bed (*)
Flow Direction - (*)
Maximum Pressure Drop across adsorbent psi (*)
REGENERATION CYCLE
Regeneration Gas Type - (filled by EII) (*)
Regeneration Gas Flowrate lb/hr (*) (*)
Heating Mode
Flow Direction - (*) (*)
Water to be removed during
lb/hr (*) (*)
desorption/regeneration
Regeneration Gas Temperature o
F (*) (*)
Regeneration Gas Pressure psig (*) (*)
PT. ENCONA INTI INDUSTRI

5.3 TECHNICAL BID ANALYSIS - ADSORBENT


PROJECT : (filled with Project Name)
CLIENT : (filled with Client Name)
JOB NO : (filled with Project Job No.)
DOC NO : (filled with Document Number)

(*) = Vendor to Indicate / Confirm N/R = not required

NO VENDORS UNIT Datasheet [FILL WITH VENDOR NAME]

1 Reference No. - (filled by EII) (*)


2 Date - (filled by EII) (*)
3 Manufacturing Location - (filled by EII) (*)
Heating up time hours/bed (*) (*)
Maximum Pressure Drop across adsorbent psi (*) (*)
Cooling Mode
Flow Direction - (*) (*)
Cooling Temperature o
F (*) (*)
Cooling down time hours/bed (*) (*)
7 VESSEL DATA
Horizontal/Vertical - (filled by EII) (*)
Shell Diameter ID ft Vendor to indicate (*)
Shell tan to tan Length ft Vendor to indicate (*)
8 QUANTITY
Quantity - Vendor to indicate (*)
9 SCOPE OF SUPPLY
Equipment proper (To be specified according to
- Required (*)
data sheet)
Process Guarantee
[ ]-years service life of adsorbent from start of - Required (*)
operations
Spare Parts
For construction and commissioning - To be separately quoted (*)
For 2-years operation and maintenance
10 SCOPE OF WORK
Design of molecular sieve bed, include :
- Sketch of adsorbent arrangement in
- Required (*)
Vessel
PT. ENCONA INTI INDUSTRI

5.3 TECHNICAL BID ANALYSIS - ADSORBENT


PROJECT : (filled with Project Name)
CLIENT : (filled with Client Name)
JOB NO : (filled with Project Job No.)
DOC NO : (filled with Document Number)

(*) = Vendor to Indicate / Confirm N/R = not required

NO VENDORS UNIT Datasheet [FILL WITH VENDOR NAME]

1 Reference No. - (filled by EII) (*)


2 Date - (filled by EII) (*)
3 Manufacturing Location - (filled by EII) (*)
- Heat and Mass Balance, Pressure &
- Required (*)
Temperature profile during regeneration
- Complete review and vetting of TPEC
- Required (*)
performed design for the system
Performance guarantee - Required (*)
Seaworthy export packing - Required (*)
Export Custom Clearance (if any) - Required (*)
Obtaining any export license or other
- Required (*)
official authorization for exportation
Supervising at site for installation - Vendor to quote separately (*)
11 DELIVERY
Delivery Schedule week Vendor to indicate (*)
FOB Transport - Vendor to indicate (*)
12 TBA Summary
Summary - Technical
- Past Experience