INSPECTION RIG REPORT Date: Page 1 of 30
01 04 04 17
CUSTOMER DATA INTERTEK DATA
Name: REPSOL - PER Intertek Project No.
Calle Begonias 415. Torre Begonias, Piso 13
Address: Client P.O./I.O. to Intertek: 4600006367
San Isidro, Lima 27, Per
Attn: Eng. Jorge Bobadilla Phone: Requisition No:
E-Mail : jebobadillaa@repsol.com Date of Order: 19/10/2015
Sebastian.maurutto@intertek.com; Intertek Contract
Copies to: Luis Bossa
jose.perez@intertek.com Coordinator:
RIG INSPECTION INFORMATION
Date(s) of Visit(s):
RIG INSPECTION CLASS:
TYPE OF RIG
Star Day End Day
WORKOVER ONSHORE RIG
MM DD YY MM DD YY
03 14 2017 03 21 2017
DRILLING OFFSHORE RIG
Comply with
Comply with Requirements No Comply with Requirements
Requirements Partially
INSPECTION DISPOSITION:
Nonconformance(s)
Placed on Hold Other (Explain)
Identified
INSPECTION
DAYS 9 days Project Coordinator: Luis Bossa
TIME :
Petrex S.A. Is a 100% company of the Saipem group (www.saipem.com) that has been
operating in South America since 1983. Currently, they are operating in South America with a
fleet of more than seventy teams between Oil & Gas and Geothermal, Workover and Pulling
distributed in Peru, Venezuela, Colombia, Ecuador, Bolivia and Chile.
General/Back Ground:
Rig Petrex 15 is located in Lote 57, Sagari BX location, well Sagari 4XD.
Summary of Findings:
Pending to build dam to the camp engine.
Some wood bridges and wood stairs are pending to build.
General/Back Ground:
Safety guy has supplied all information required about Trainning, EPP, general safety,
records, and statistics, HSE plans, etc. All this information is in line with the industry
standards and regulations.
The HSE Management System has been the foundation on which Petrex has built his culture,
which is based on the guidelines of his parent company, customer and legal requirements
and his know-how. The HSE Management System is OHSAS 18001 certified.
The line that Petrex top management has outlined, through his Leadership in Health and
Safety Program (LiHS), lies in the empowerment of self-care for himself and for his partners;
This implies that it is necessary to stop operations when security is compromised.
The LiHS Program is implemented from the following stages that are conducted in a
coordinated way. "LiHS Workshop", The LiHS Program begins with the experience of a highly
interactive and emotional workshop; Where managers, supervisors and the entire line of
command have the challenge of thinking differently about health and safety; With practical
tools for personal development as effective influential Leaders in Health and Safety.
"Leading Behaviors", this strategy focuses on five simple, transferable and "non-negotiable"
Behaviors; Carefully chosen. The goal of this Leading Behavior strategy is to challenge and
"Choose Life," this new highly emotional and thoughtful workshop, was developed to impact
our collaborators on the understanding that a health problem can happen to them and
encourage them to make positive decisions about their health; Focusing specifically on
lifestyles, infectious and communicable diseases
Training.
Petrex has a clear HSE training plan; for operation and maintenance area. Petrex people are
trained to operate the man lift, Crain and fork lift; all training certificates are attached to this
report.
PPE
Petrex people use the EPP correctly.
General Safety
Petrex uses the program of permit to work - PTW, according with the Petrex procedure WI-
PTX-HSE-111-S. Petrex uses JSA procedure WI-PTX-HSE-111-S to all tasks they need; All
permit to work should have the JSA attached. In this project, Petrex is working with the
Repsol standards, using all Repsol PTW.
Petrex uses the program to tag/log out, according with the Petrex procedure WI-PTX-HSE-
008-S.
Petrex has an emergency response plan GP-PTX-HSE-063-S, but the specific emergency
plan for the 57 Block with Repsol Operations is in the document PTX-HSE-192-S, it includes
all operational emergency like blow out prevention plan, fire emergency, spills, H2S
emergency, all medical evacuation, etc; all of these emergencies will change depending of
the work area.
Summary of Findings:
Some signs arent posted and/or placed.
Suggestions:
To help to the HSE guy in order to keep all rig and camp area with all signs required.
General/Back Ground:
For this well Sagari 4XD Petrex will use only 2 mud pumps (number 2 and 3); Mud Pump
number 1 is going back to Nuevo Mundo (Repsol Yard), then is going back to Ransa Petrex
yard located in Pucalpa.
Inspection Report done by NOV PLL 036-15 on 30/09/2015; Inspection Report done by SAIS
Cat III-SAIS-PTX-0033-311016 on 31/10/2016.
A manifold is assembled to connect the mud pumps; two outputs from this manifold feed the
double stand pipe, with a stand pipe manifold type H. The rotary hose is in good condition.
All valves were tested with 3.000 PSI. The mud pump 1 connection is correctly sealed with a
hammer union plug.
Summary of Findings:
N/A
Suggestions:
N/A
General/Back Ground:
Summary of Findings:
N/A
Suggestions:
N/A
General/Back Ground:
The low pressure mud system has 3 Shale Shakers Mongoose, 1 mud cleaner 3 in 1 with
dessander with 2 cones 12 and desilter with 16 cones each one 4 and Shale shaker
mongoose; Vacuum degasser, 15 mud agitators 20 HP and one mud agitator 10 HP.
Return tank, 2 suction tanks, 1 active tank, 4 reserve tanks, each tank 250 Bbls. 3 mud
mixers pumps MCM 6*8*13 with electric motor 100 HP. All low mud pressure system was
tested; the mud was circulated by desilter and dessander; mud agitators were running
properly.
Summary of Findings:
Flexible coupling in agitator # 9 is in bad condition.
Shale Shaker junction box without all bolts installed on.
Ground cable in shale shaker vibrator motors arent connected.
Water pipe in the mud tanks is not correctly anchored.
Suggestions:
The flexible coupling should be changed. It is too large; as a suggestion, it is better to
install a short pipe, then to connect with the flexible coupling.
Junction boxes should have installed all bolts.
To connect all ground cables correctly.
General/Back Ground:
The rig PTX 15 has a Fork lift Case mod 721D}; it is in good condition; all deviations founded
in the last inspection were corrected.
The rig PTX 15 has two cranes Mantis, one model 6010 with capacity for 30 Tons, and one
Model 9010 with capacity for 45 Tons. Both working properly.
The rig PTX 15 has a man lift Genie S-45; it is not working because the joystick is in bad
condition.
Summary of Findings:
The caterpillar pads of the mantis crane are in bad condition.
Man lift has the joystick is in bad condition.
Suggestions:
To change the caterpillar pads.
To change the joystick and test the man lift.
General/Back Ground:
The rig has 5 Engine/Generator Sets, each one with a CAT Engine 1.101 kW with CAT
Generator 1400 kVA-980 kW@600 Vac; only three units were installed in this well. The rig
has a power House with a SCR System House designed by Legacy, 5 generator Bays and 4
SCR bays; Siemens rectifiers; 2 containers each one 20 Ft of length, to follow as a heli-rig.
Air conditioners are working properly.
MUD PUMPS TEST AT 80 SPM @ 2.500 PSI MP2 & MP3 AT SAME TIME @ 30 Minutes MAR 17-2017
ENGINE/GEN PARAMETERS SCR PARAMETERS
ITEM ENG/GEN ENG/GEN # ENG/GEN # ENG/GEN ENG/GEN
ITEM DESCRIPTION MP # 1 MP # 2 MP # 3
DESCRIPTION #1 2 3 #4 #5
ENGINE SPEED 1.201 1.201 VOLTS 398 392
FREQUENCY 60 60 AMPS 1.118 1.106
VOLTAGE 600 600 SCR BAY # 1 4 3
MUD PUMPS TEST AT 80 SPM @ 3.000 PSI MP2 & MP3 AT SAME TIME @ 30 Minutes MAR 17-2017
ENGINE/GEN PARAMETERS SCR PARAMETERS
ITEM ENG/GEN ENG/GEN # ENG/GEN # ENG/GEN ENG/GEN
ITEM DESCRIPTION MP # 1 MP # 2 MP # 3
DESCRIPTION #1 2 3 #4 #5
ENGINE SPEED 1.201 1.201 VOLTS 399 395
FREQUENCY 60 60 AMPS 1.274 1.290
VOLTAGE 600 600 SCR BAY # 1 4 3
KW 623 579 ASSIGMENT SWITCH Tripping # 2
KVA 1.121 1.101 SCR BAY LOAD % 79,62 80,62
KVAR 949 930 SPM METER 80 80
AMPS 1.175 1.136 PRESSURE (PSI) 3.123
PF 54,4 52,8 FLOW (GPM) Not tested
ENGINE LOAD
% 94 78 POWER LIMIT % 63,2
The test starts at 18:10. Test was successful. Maximum power to the engine/generator sets were 78%, working 2 generator units. SCR
bays were not too much loaded.
MUD PUMP TEST AT 90 SPM @ 2.500 PSI MP3 @ 30 Minutes MAR 17-2017
ENGINE/GEN PARAMETERS SCR PARAMETERS
ITEM ENG/GEN ENG/GEN # ENG/GEN # ENG/GEN ENG/GEN
ITEM DESCRIPTION MP # 1 MP # 2 MP # 3
DESCRIPTION #1 2 3 #4 #5
ENGINE SPEED 1.201 VOLTS 401
FREQUENCY 60 AMPS 1.128
VOLTAGE 600 SCR BAY # 3
KW 571 ASSIGMENT SWITCH Tripping # 2
KVA 1.062 SCR BAY LOAD % 70,5
KVAR 894 SPM METER 80
AMPS 1.082 PRESSURE (PSI) 2.596
PF 53,85 FLOW (GPM) Not tested
ENGINE LOAD
%
75 POWER LIMIT % 60,5
The test starts at 18:55. Test was successful. Maximum power to the engine/generator sets were 75%, working 1 generator unit. SCR
bays were not too much loaded.
The rig PTX 15 has installed two screw air compressors Atlas Copco model GA30P, each one
with an electric motor 30 kW; each air compressor has the air dryer included. A cold start air
compressor Atlas Copco 21,6 Kw
Summary of Findings:
Floor plates between engine skid # 1 and air compressor skid arent installed
completely.
Top Drive control receptacle was dismounted; 2 cables in going inside the hole.
Cable trays have not installed completely the covers.
Cord grips not installed in the wall cabinets.
Cover of the power generator cables is not installed correctly.
Back up diesel engine Exhaust has not installed the thermal protector.
Cord grips not installed in the power transformer.
Fluorescent Light in the SCR plug panel board is broken.
Control and power cables have the wire outside from the cord grip.
Plug panel board without plate in spare place.
Power cables in the plug panel board without insulation boots.
External wires additional to the control wire of the cables are running in parallel with
the control cable.
Some ground connections are loose.
Suggestions:
All plates should be installed to avoid some incident. It was corrected.
Cables should be connected in its receptacle; the top drive cabin should be sealed.
All cover should be installed to avoid some incident.
If some hole is not used, it should be. It was corrected.
The cover should be installed correctly. It was corrected.
All hot surfaces should have installed the thermal protector.
If some hole is not used, it should be. It was corrected.
The cover should be changed.
All wire cables should be inside the plug barrel.
A plate should be installed on.
All connectors should have the insulator installed.
If the control cable has no more spares, it is better to install another cable with
additional spare cables.
To tight the loose connections.
General/Back Ground:
The rig PTX 15 has installed the firefighting equipment around the rig and the camp; all types
are correctly distributed. PTX has generated a Service Order, to do Maintenance to all
firefighting equipment.
All elements are in good condition. The water pump was not tested.
Summary of Findings:
Main camp alarm has not the battery installed.
Suggestions:
Battery should be installed before to start the operations.
ITEM 9. Fuel & Other Flamable Liquid Storage Tanks, Including Frack Tanks & Non-
Flamable Storage Tanks
General/Back Ground:
The rig has three diesel tanks, each one with a capacity of 12.600 Gls. Only two diesel tanks
were installed in this well. A daily tank was disconnected in this project.
Summary of Findings:
N/A
Suggestions:
N/A
General/Back Ground:
More than two sets of pipe racks were advised in the location.
Summary of Findings:
N/A
Suggestions:
N/A
Pneumatic pumps were tested for Shear / Blind (5000 PSI system); The stop pressure of the pumps is at 4,150 PSI; The pumps start at 3,800 PSI; The
pressure is regulated to 1,500 PSI for Shear / Blind Rams. Load time up to 4,150 PSI was 10'34 ".
Summary of Findings:
Accumulator hydraulic oil is emulsified.
Connector used in the Accumulator control cable is too small compared with the cable
size.
Drain valve of the accumulator dam has not installed the plug.
Suggestions:
To check the oil, and check the use time, in order to do a plan to change.
Connectors should have the correctly size according with the cable they will use.
Drain valves should have installed the plugs in order to avoid nvoluntary operations.
The Derrick was Manufactured by Drillmec, static hook capacity 1.000.000 Lbs. with 12 lines;
Height 147 ft. Serial number 405-M01-01. it has inspection level IV, done in 15/04/2008 by
Drillmec the manufacturer, and level III done in 30/09/2015 done by NOV PLL 036-15
Substructure manufactured by Drillmec, Maximum static rotary load capacity 1.000.000 Lbs.,
setback capacity 600.000 Lbs., Total capacity 1.600.000 Lbs.; Height 30 Ft, Includes a
parallelogram type, raising system powered by two (2) hydraulic winches operating two (2)
The rig has Catwalk manufactures by Canrig, Mod PC3000-26-A-A-A-N-S, Max capacity
10.000 Lbs, S/N 300440, 600 Vac.
The Rig Petrex PTX 15 uses a drilling cable with a size 1- 3/8, Type 6x19S IWRC; the drilling
cable looks in good condition, any crush, any broken rows. New cable was installed on
15/11/2016. As a suggestion, is to install a roof in the drilling cable skid. Compliance
certificate attached.
The raising cable has 3,5 times raising and lowering the derrick. Petrex has a standard, to
use 10 times complete cycle, raising and lowering. The cable looks in good condition, has
compliance certificate; they will inspect the eyes after the third complete cycle.
The dead line anchor is manufactured by Hecules, model 120 T, with load cell sensor E551; It
was tested with the Pason Instrumentation system.
Summary of Findings:
Slack line detector air valve of the Man rider winch is not working properly.
Suggestions:
To adjust the air valve of the Slack line detector.
NOTES:
Control was tested without problems.
Two air winches Ingersoll Rand, each one with a capacity of 10.000 Lbs Ingersoll Rand,
models FA5A.
The rig PTX has a Top Drive Canrig Mod 1250AC-681, 1200 HP, 500 Tons, maximum torque
51.400 Lb-Ft, Continuous Torque Rating 51 400 ft-lb (69 700 Nm) @ 120 RPM , Maximum
Speed Rating 23 500 ft-lb (24920 Nm) @ 265 RPM, Brake Capacity 50 000 ft-lb 67 800 Nm,
Maximum Electric Motor Torque (Make-Up Limit is operator adjustable) 71 000 ft-lb 96 300
Nm, Torque Boost Torque Make-Up 24 000 ft-lb 32 500 Nm and Break Out 37 500 ft-lb 50
800 Nm, Quill Connection 6-5/8 Reg., Circulating Pressure Rating Standard 7.500 PSI,
electric motor GE B20 AC, 1 120 Amps, 690 VAC, 0 - 140 Hz; Hydraulic Power Unit Model
1220 Twin.
The Rig PTX 15 has rotary table National 37 , powered by DWA, 1.000 HP, Maximum
torque 35.000 Lb-ft, with master bushing Varco, Insert bowl N 1 (13- 3/8" & 11- 3/4"), N2
(10- 3/4" & 9- 5/8") and N3 (8- 5/8" & smaller).
Summary of Findings:
Joystick without the boot protector.
Slack line detector air valve of the Man rider winch is not working properly.
Suggestions:
To install new boot protector or to change the joystick, in order to protect the selector
against the rain.
To adjust the air valve of the Slack line detector.
The rig PTX 15 has a set of manual power tongs HT-100; the manual power tongs were
tested making up and breaking with 40.000 Lb-Ft. Equipment working properly.
Summary of Findings:
N/A
Suggestions:
N/A
ITEM 15. Hoisting Tools, Hooks, Bails, Elevators and Other Related Equipment
General/Back Ground:
Summary of Findings:
N/A.
Suggestions:
N/A
General/Back Ground:
The rig has the ladders and hand rails in good condition.
Summary of Findings:
N/A
Suggestions:
N/A
General/Back Ground:
N/A
Summary of Findings:
N/A
Suggestions:
N/A
Summary of Findings:
Cutting hose is twisted.
Suggestions:
To change the cutting hose.
Summary of Findings:
N/A
Suggestions:
N/A
General/Back Ground:
N/A
Summary of Findings:
N/A
Suggestions:
N/A
General/Back Ground:
N/A
Summary of Findings:
N/A
Suggestions:
N/A
Summary of Findings:
N/A
Suggestions:
N/A
Petrex environmental management system, developed on the basis of ISO 14001, serves to
guide and channel it declared environmental commitments in Petrex HSE Policy. The main
environmental commitment of Petrex is the prevention of pollution of the environment,
translated into the identification of environmental aspects and the identification of control
measures to mitigate the potential impacts.
Inter-drill competition called "Green Drill" is an initiative that promotes the participation of all
employees, and is oriented to maintain clean and orderly work environments.
Summary of Findings:
Water leaks in the Rig battery bathroom.
Camp engine has not dam installed.
Suggestions:
All leaks should be corrected, in order to keep low water consumption.
To build the dam to the camp engine.
The Quality Management System of Petrex S.A. Is a key instrument for the efficient
management of the processes of Petrex S.A. And serves them to ensure the satisfaction of
their customers and to meet the relevant requirements of the interested parties.
The Quality Policy of Petrex S.A. Is approved by the Managing Director and is revised
whenever necessary in order to guarantee its suitability.
Summary of Findings:
N/A
Suggestions:
N/A
The rig inspection was conducted in good shape and order, getting all information of each
asset, like maintenance, inspection certificates, tests, etc. done to each one.
All information required was supplied by The Rig Manager Assistant and the HSE Guy.
Al rig inspection certificates were updated, due that the last NDT rig inspection was done 3
months before.
For this purpose, load tests and verification of critical safety and operating systems will be
developed on the Rig PTX 15. During this process, attempts were made to simulate the
drilling conditions as closely as possible to ensure the effective operation of the systems in
accordance with the contracted requirements.
Summary of Findings
All findings can be checked in the photographic report; Just an item with a priority of 2
level was founded; it is the fault in the man rider air winch.
Suggestions:
To solve the main deviation founded in the rig inspection.
OVERALL CONCLUSIONS
The Rig is in good condition; it was performed stress tests, which were satisfactory, obtaining
a maximum load for the system of 63%, being able to say that the drill is in capacity to
develop the SAGARY 4XD well, object of the contract between Repsol and Petrex.