You are on page 1of 6

METHOD STATEMENT

CLEARING AND GRUBBING

1. GENERAL
This Method Statement is to made as an introduction and explanation of works programs
will be applied for land clearing of Secondary Canal and Sub-Secondary Canal, of Civil
Work of Lempuing Secondary Canal Section-2 and Sub-Secondary Canals of Block-
F Package 19 : ICB 11.
This work shall consist of Clearing and Grubbing the ground surfaces of all trees, stumps,
logs, brush, undergrowth, hedges, fences, structure, foundations, debris and rubbish of
any nature, whether designated in the drawings or within the right of way, on the ground
surfaces of borrow pits or as instructed by the Engineer, together with the disposal of all
such materials.

2. SCOPE OF WORKS

2.1 Scope of works :


a. Land Clearing and Grubbing
b. Disposed all material to disposed area/stockpile
c. Burned when in a suitable condition shall be thoroughly burn and reduced to ashes

The scope of the works on this method statement covers as below :


BOQ Description of Works Unit
SECTION II LEMPUING SECONDARY CANAL, SECTION-2
II-1.1 Clearing and Grubbing Sq.m
SECTION III LEMPUING SUB-SECONDARY CANAL, BLOCK-F
III-1.1 Clearing and Grubbing Sq.m
SECTION IV DRAINAGE CANAL
IV-1.1 Clearing and Grubbing Sq.m

For measurement and payment purposed for clearing and grubbing the land surface
classifications based on the site condition.

2.2 Work Area Limits


Work area limits for land clearing and grubbing of Sub-Secondary Canal purposes to
approval Engineer based on Land Acquisition and the ground surface conditions (i.e.
necessity of clearing and grubbing) with explanation as follows L
- Varian of Wide of Sub-Secondary Canal between 10 m 30 m
- Protection of Land Acquisition / DMI (Daerah Milik Irigasi)
- Work area for Method Execution of excavation,earthfill and structure of
Secondary Canal and Sub-Secondary Canal.
Work area for Clearing and Grubbing, will be mutually checked among three parties
with the attached form (Form-4) and subject to the approval of engineer.

i
3. SEQUENCE OF LAND CLEARING AND GRUBBING
Sequence of land clearing and grubbing execution following the chart as below :

Material Inspection
Start Form
Equipment Main Check
Item
Confirming Area of Check Area
Clearing/Grubbing Form 4

Form AU-01
Chain saw Cutting tree
Form EX-05

Removing trees,
stumps, logs and
etc.
BD
EX Disposal area
Clearing/Grubbing

DT Disposal/Burn Taking care of fire

Filling big voids


due to
clearing/grubbing Check condition
with suitable
material

End

i
4. DETAIL OF WORKS (EXECUTION & METHOD)

This works will be execute clearing and grubbing y=the ground surface in works area
limits as approval by the Engineer: of all trees, stumps, logs, brush, undergrowth, hedges,
fences, structures, foundations, debris and rubbish of any nature, whether designated in
the drawing or within the right of way, on the ground syrfaces of borrow pits or as
instructed by the Engineer, together with the disposal of all such materials.
All material or objects resulting from clearing and grubbing operations will be remove to
disposal or off site and will be burned when material in suitable condition.
Equipment to be involbes :
1. Excavator 0,8 m3 : for clearing and grubbing all big trees and removed off site
2. Bulldozer : for clearing and removal of brush, grass and others material
and removed to off Site
3. Dump Truck : for removal to off Site (if necessary)

5. TIME SCHEDULE
BOQ DESCRIPTION OFWORKS DEC12 APR13
II-1-1 Clearing and Grubbing
III-1-1 Clearing and Grubbing
IV-1-1 Clearing and Grubbing

6. EQUIPMENT REQUIREMENT FOR LAND CLEARING AND GRUBBING


No EQUIPMENT TYPE/CAP TOTAL UNIT
1 Excavator 0.8 m3 bucket 2
2 Bulldozer 24 T 1
3 Dump Truck 12 T 1

7. QUALITY PLAN

Clearing and Grubbing the ground surfaces main canal area of all trees, stumps, logs,
brush, undergrowth, hedges, fences, structures, foundations etc, whether designated in the
drawing within the right of way, together with the disposal of all such materials, and all
material or objects resulting from clearing and grubbing operations shall be burned or
disposed of off site at locations provided.
The contractor shall, before starting the clearing and grubbing work, obtain the Engineers
approval regarding work area limits, object that are to remain and the method of work
execution. Due care shall be taken not to damage trees and existing structures outside the
limits of the working area or otherwise identified so as remain, and the Contractor shaal
protect and preserve all such items.
i
8. Responsible Person

No Name of Person at site Position


1 Agung Susilo Supervisor
2 Basuki Surveyor

i
TABLE OF CONTENS

Page

1. General ......................................................................................................................... 1
2. Scope of Works ........................................................................................................... 1
3. Sequence of Earthworks .............................................................................................. 2
4. Detail of Works ........................................................................................................... 3
5. Time Schedule .............................................................................................................. 3
6. Equipment Requipment for Land Clearing and Grubbing .......................................... 3
7. Quality Plan ................................................................................................................. 3
8. Responsible .................................................................................................................. 4

i
Type A : Excavation for canals, roads, drains and other common
excavation above water
Type B : Excavation of sediment and debris for normalization works of
the existing canal above water
Type C : Excavation for structure
Type D : Excavation under water without dewatering for canals and
drains
Type E : Excavation in the river bed for construction of Weir, river dike
and other facilities of which materials containing substantial
quantity of gravels, cobbles and boulders.