33 KV line on H-Beams 152 X 152 mm., 37.1 Kg./Mtr. 13 Mtr. Long supports with AB Cable 2010-
11
Total 1,252,296
15 Centages :
1 2 3 4 5 6 4
1 Line supports H-Beams 152 X 152 mm., 37.1
Kg./m,13 Mtr. Long Nos. 20 18154 363075 20
2 33 KV Panther Upper and middle DC Cross arm
( ISMC 5' centre 100X50 mm ) Set 40 2658 106320 20
3 Supporting angle(IS angle 4' centre 65X65X6 mm)
for Upper cross arm No. 40 1598 63920 20
4 33 KV Panther Lower DC Cross arm ( ISMC 8'
centre 100X50 mm) Set 20 2299 45980 20
5 Supporting angle(IS angle 4' centre 65X65X6 mm)
for Lower cross arm No. 40 1598 63920 40
6 Earthing Set (Coil earth ) Nos. 20 126 2520 20
7 33 KV Strain insulator( 70 KN Disc Insulator)
Nos. 60 420 25200 60
polymer
8 Hardware fitting - Single suspension type Set 60 604 36240 60
9 Angle Cleat(IS angle, 250 mm long, 65X65X8 mm)
( for hanging suspension string) Set 60 252 15120 60
10 Strain plate(IS MS flat, 250 mm long, 65X8 mm)
(for strengthing of DC cross arm- 3 sets for upper Set 180 146 26280 180
& 6 lower )
11 Panther Conductor with 5 % Sag Kms. 3.15 100217 315684 3.15
12 Mid span Joints suitable for Panther Conductor Nos. 3 344 1032 3
13 Repairing Sleeve for Panther Conductor Nos. 6 116 696 6
14 Stay set 25 mm. complete with back clamp , stay
insulator, stay wire 7/4.0 mm. (8.5 kg.stay wire per Sets 10 1426 14255 10
stay set )
15 Concreting of H-Beam @ 0.8 Cmt. per pole, @
0.3 cmt. per stay and 0.05 cmt for base pad( of Cmt. 173.0 2501 432673 173.0
pole)
16 Red oxide paint Ltrs. 20 100 2000 20
17 Aluminium paint Ltrs. 30 163 4890 30
18 Anti climbing devices Nos. 20 214 4280 20
19 Danger Boards Nos. 20 68 1360 20
20 Binding wire / tape Kgs. 5 105 525 5
21 Carpet guarding { with ISMC 10' center DC cross
arm( 1 set), G.I. Wire -- 3x6SWG + 1x8 SWG for Span 1 5200 5200 1
lacings)}
22 M.S.Nuts and Bolts Kgs. 280 58 16240 280
23 Stay clamp for H-Beam support(MS flat-65X65X8
mm) Set 120 122 14640 120
Total 1562050
25 Centages :
(i) Stores incidental charges 2.5%
(ii) Contingencies 5%
11.5% 179636 '11.5%
(iii W/c. establish ment 2.5%
(iv) T & P 1.5%
Labour charges @15% 234308
26 Transport charges upto 50 Kms. Average leads
from area stores to construction camp including 15000