DISEO DE LA LINEA DE CONDUCCION

Proyecto : MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE Y SANEAMIENTO EN LOS SECTORES DE HUANAPAMPA, TOMAC, COLLAY Y NUEVO PROGRESO
DE LA LOCALIDAD DE ALLAUCA DISTRITO DE TAYABAMBA, PROVINCIA DE PATAZ - LA LIBERTAD
Lugar : LOC.: ANEXO NUEVO PROGRESO; DIST.: TAYABAMBA; PROV.: PATAZ; REGION: LA LIBERTAD
Consultor:
Fecha: FEBRERO-2016
1. DATOS DE DISEO
Dato
Datos: Donde : Resultado

Leyenda
C= 150 C: Coeficiente de Hazen-William. Fijo
QP = 0.13 lts/Seg. 0.1493226 QP : Demanda Total de agua potable. Jalado
Qmd = 0.17 lts/Seg. 2.5802941 Qmd : Caudal Mximo Diario. (Diseo de L.C.) corregir
Qmh = 0.25 lts/Seg. Qmh : Caudal Mximo Horario

2. CALCULO DE PRESIONES EN DISTINTOS PUNTOS DE LA LINEA DE CONDUCION

Frmula de Hazen-William.

DC : Dimettro Comercial. DT : Dimetro Terico. hf : Prdida de Carga.

Q = 0.0178 * C * D2.63 * S0.54 DT= (Q / ( 0.0178 * C * S0.54) )1/2.63 hf = (Q * L0.54 / (0.0178 *C * D2.63))1/0.54

Tramo Cota Cota H Pendiente Long. DT DC Area Veloc. hf L. G. P. Presin Presin Observ.
P. inicio P. final inicial final (m) (%) (m) (pulg) (pulg) (m2) m/seg (m) (m) (m) Esttica

CAPTACIN CRP-T6 (1) 3998.60 3940.00 58.60 210.04 279.00 0.48 1 0.0001 1.30 47.08 3951.52 11.52 58.60 OK. !

CRP-T6 (1) CRP-T6 (2) 3940.00 3875.00 65.00 213.82 304.00 0.48 1 0.0001 1.30 51.29 3888.71 13.71 65.00 OK. !

CRP-T6 (2) CRP-T6 (3) 3875.00 3808.00 67.00 202.42 331.00 0.48 1 0.0001 1.30 55.85 3819.15 11.15 67.00 OK. !

CRP-T6 (3) CRP-T6 (4) 3808.00 3740.00 68.00 204.20 333.00 0.48 1 0.0001 1.30 56.19 3751.81 11.81 68.00 OK. !

CRP-T6 (4) CRP-T6 (5) 3740.00 3675.00 65.00 206.35 315.00 0.48 1 0.0001 1.30 53.15 3686.85 11.85 65.00 OK. !

CRP-T6 (5) J-15 3675.00 3617.50 57.50 209.85 274.00 0.48 1 0.0001 1.30 46.23 3628.77 11.27 57.50 OK. !

J-15 CRP-T6 (6) 3617.50 3531.32 86.18 173.05 498.00 0.50 1 0.0002 1.08 52.82 3564.68 33.36 86.18 OK. !
CRP-T6 (6) CRP-T6 (7) 3531.32 3449.80 81.52 173.08 471.00 0.50 1 0.0002 1.08 49.96 3481.36 31.56 81.52 OK. !

CRP-T6 (7) CRP-T6 (8) 3449.80 3381.90 67.90 173.21 392.00 0.50 1 0.0002 1.08 41.58 3408.22 26.32 67.90 OK. !

CRP-T6 (8) CRP-T6 (9) 3381.90 3305.90 76.00 173.12 439.00 0.50 1 0.0002 1.08 46.57 3335.33 29.43 76.00 OK. !

CRP-T6 (9) CRP-T6 (10) 3305.90 3233.82 72.08 172.85 417.00 0.50 1 0.0002 1.08 44.23 3261.67 27.85 72.08 OK. !

CRP-T6 (10) J-16 3233.82 3166.00 67.82 175.70 386.00 0.50 1 0.0002 1.08 40.94 3192.88 26.88 67.82 OK. !

J-16 RESERVORIO 3166.00 3165.10 0.90 90.00 10.00 0.57 1 0.0005 0.33 0.06 3165.94 0.84 0.90 OK. !

#REF!

3. RESULTADOS FINALES
NOTA:

CLASE diametro Cantidad Long total Und. Se esta considerando la tubera de diametro de 1", por la seguridad
C - 10 1" 889.80 4449.00 m y por solicitud de los beneficiarios, y que la velocidad minima es de 0.60 m/s
segn norma de diseo, el cual cumple.

TOTAL 4449.00 Se empleara Tubera PVC SAP/C-10, segn NTP 399.002, Longitud Tuberia es de 5m
LINEA DE GRADIENTE HIDRAULICA

Proyecto : MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE Y SANEAMIENTO EN LOS SECTORES DE HUANAPAMPA, TOMAC, COLLAY Y NUEVO PROGRESO
DE LA LOCALIDAD DE ALLAUCA DISTRITO DE TAYABAMBA, PROVINCIA DE PATAZ - LA LIBERTAD
Lugar : LOC.: ANEXO NUEVO PROGRESO; DIST.: TAYABAMBA; PROV.: PATAZ; REGION: LA LIBERTAD
Consultor:
Fecha: FEBRERO-2016

1. DATOS DE DISEO
Dato
Datos: Donde : Resultado

Leyenda
C = 150 C: Coeficiente de Hazen-William. Fijo
QP = 0.13 lts/Seg. QP : Demanda Total de agua potable. Jalado
Qmd = 0.17 lts/Seg. Qmd : Caudal Mximo Diario. (Diseo de L.C.) corregir
Qmh = 0.25 lts/Seg. Qmh : Caudal Mximo Horario

2. CALCULO LINEA DE GRADIENTE HIDRAULICA

Frmula de Hazen-William.

DC : Dimettro Comercial. DT : Dimetro Terico. hf : Prdida de Carga.

Q = 0.0178 * C * D2.63 * S0.54 DT= (Q / ( 0.0178 * C * S0.54) )1/2.63 hf = (Q * L0.54 / (0.0178 *C * D2.63))1/0.54

Tramo Cota Cota H Pendiente Long. DT DC Area Veloc. hf L. G. P. Presin Presin Observ.

P. inicio P. final inicial final (m) (%) (m) (pulg) (pulg) (m2) m/seg (m) (m) (m) Esttica

CAPTACIN CRP-T6 (1) 3998.60 3940.00 58.60 210.04 279.00 0.48 0.75 0.0003 0.58 6.53 3992.07 52.07 58.60 OK. !

CRP-T6 (1) CRP-T6 (2) 3940.00 3875.00 65.00 213.82 304.00 0.48 0.75 0.0003 0.58 7.12 3932.88 57.88 65.00 OK. !

CRP-T6 (2) CRP-T6 (3) 3875.00 3808.00 67.00 202.42 331.00 0.48 0.75 0.0003 0.58 7.75 3867.25 59.25 67.00 OK. !

CRP-T6 (3) CRP-T6 (4) 3808.00 3740.00 68.00 204.20 333.00 0.48 0.75 0.0003 0.58 7.80 3800.20 60.20 68.00 OK. !

CRP-T6 (4) CRP-T6 (5) 3740.00 3675.00 65.00 206.35 315.00 0.48 0.75 0.0003 0.58 7.38 3732.62 57.62 65.00 OK. !

CRP-T6 (5) J-15 3675.00 3617.50 57.50 209.85 274.00 0.48 0.75 0.0003 0.58 6.42 3668.58 51.08 57.50 OK. !

J-15 CRP-T6 (6) 3617.50 3531.32 86.18 173.05 498.00 0.50 0.75 0.0003 0.58 11.66 3605.84 74.52 86.18 OK. !
CRP-T6 (6) CRP-T6 (7) 3531.32 3449.80 81.52 173.08 471.00 0.50 0.75 0.0003 0.58 11.03 3520.29 70.49 81.52 OK. !

CRP-T6 (7) CRP-T6 (8) 3449.80 3381.90 67.90 173.21 392.00 0.50 0.75 0.0003 0.58 9.18 3440.62 58.72 67.90 OK. !

CRP-T6 (8) CRP-T6 (9) 3381.90 3305.90 76.00 173.12 439.00 0.50 0.75 0.0003 0.58 10.28 3371.62 65.72 76.00 OK. !

CRP-T6 (9) CRP-T6 (10) 3305.90 3233.82 72.08 172.85 417.00 0.50 0.75 0.0003 0.58 9.77 3296.13 62.31 72.08 OK. !

CRP-T6 (10) J-16 3233.82 3166.00 67.82 175.70 386.00 0.50 0.75 0.0003 0.58 9.04 3224.78 58.78 67.82 OK. !

J-16 RESERVORIO 3166.00 3165.30 0.70 70.00 10.00 0.60 1.00 0.0005 0.33 0.06 3165.94 0.64 0.70 OK. !

4053.00

3. RESULTADOS FINALES
NOTA:
CLASE diametro Cantidad Long total Und. Se esta considerando la tubera de diametro de 1", por la seguridad

C - 10 1" 810.60 4053.00 m y por solicitud de los beneficiarios, y que la velocidad minima es de 0.60 m/s
segn norma de diseo, el cual cumple.

TOTAL 4053.00 Se empleara Tubera PVC SAP/C-10, segn NTP 399.002, Longitud Tuberia es de 5m
DISTRIBUCION DE CAUDALES EN NUDOS

MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE Y SANEAMIENTO EN LOS SECTORES DE


Proyecto: HUANAPAMPA, TOMAC, COLLAY Y NUEVO PROGRESO DE LA LOCALIDAD DE ALLAUCA DISTRITO DE
TAYABAMBA, PROVINCIA DE PATAZ - LA LIBERTAD

Lugar: LOC.: ANEXO NUEVO PROGRESO; DIST.: TAYABAMBA; PROV.: PATAZ; REGION: LA LIBERTAD
Consultor:
Fecha: FEBRERO-2016

RESUMEN DE DISTRIBUCIN DE CAUDALES EN NUDOS

QMH Caudal Mximo Horario 0.25


Caudal
qu Unitario 0.0127

NUDO # LOTES DEMANDA (L/s)


J-4 0 0.000
J-5 1 0.013
J-6 2 0.025
J-7 3 0.038
J-8 0 0.000
J-9 2 0.025
J-10 3 0.038
J-11 2 0.025
J-12 2 0.025
J-13 2 0.025
J-15 0 0.000
J-16 3 0.038
TOTAL 20 0.25
OS

TO EN LOS SECTORES DE
DAD DE ALLAUCA DISTRITO DE
RTAD

REGION: LA LIBERTAD
PRESIONES EN NUDOS

NUMERO DE COTA DEMANDA DE PRESION


NUDO LOTES TERRENO AGUA DINAMICA
(Hab.) (m) (L/s) (m H2O)

J-4 0 3134.000 0.000 34


J-5 1 2990.000 0.013 25
J-6 2 2979.000 0.025 35
J-7 3 3152.000 0.038 17
J-8 0 3130.000 0.000 39
J-9 2 3090.000 0.025 28
J-10 3 3050.000 0.038 12
J-11 2 2910.000 0.025 18
J-12 2 2980.000 0.025 11
J-13 2 2950.000 0.025 40
J-15 0 3617.500 0.000 14
J-16 3 3162.000 0.038 11
TOTAL 20 0.25
METRADO DE TUBERIA EN LINEA DE ADUCCION Y REDES DE DISTRIBUCION

Proyecto : MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE Y SANEAMIENTO EN LOS SECTORES DE HUANAPAMPA, TOMAC,
COLLAY Y NUEVO PROGRESO DE LA LOCALIDAD DE ALLAUCA DISTRITO DE TAYABAMBA, PROVINCIA DE PATAZ - LA
LIBERTAD
Lugar: LOC.: ANEXO NUEVO PROGRESO; DIST.: TAYABAMBA; PROV.: PATAZ; REGION: LA LIBERTAD
Consultor:
Fecha: FEBRERO,2016

1. TOTAL TUBERIA

LONGITUD NUDO NUDO DIAMETRO


TRAMO TUBERIA CLASE
(m) INICIAL FINAL (")
P-6 141.00 RESERVORIO PVC DE 2.5 M3 J-7 1.00
P-7 80.00 J-7 J-4 1.00
P-24 10.00 J-16 RESERVORIO DE 1.00
P-29 279.00 CAPTACION CRP T6-N 01 1.00
P-30 304.00 CRP T6-N 01 CRP T6 - N 02 1.00
P-31 331.00 CRP T6 - N 02 CRP T6-N 03 1.00
P-32 333.00 CRP T6-N 03 CRP T6 - N 4 1.00
P-33 315.00 CRP T6 - N 4 CRP T6 - N 5 1.00
P-34 274.00 CRP T6 - N 5 J-15 1.00 PVC SAP
10
P-39 356.00 J-4 CRP T7 - N 03 1.00 NTP 399.002
P-40 60.00 CRP T7 - N 03 J-10 1.00
P-53 498.00 J-15 CRP T6-N 6 1.00
P-55 471.00 CRP T6-N 6 CRPT6- N 7 1.00
P-56 392.00 CRPT6- N 7 CRP T6-N8 1.00
P-57 439.00 CRP T6-N8 CRP T6- N 9 1.00
P-59 417.00 CRP T6- N 9 CRP T6 - 10 1.00
P-60 386.00 CRP T6 - 10 J-16 1.00

P-5 411.00 J-5 J-6 0.75


P-8 448.00 J-7 J-8 0.75
P-13 190.00 J-12 J-13 0.75
P-35 38.00 J-8 CRP T7-N 01 0.75
P-36 90.00 CRP T7-N 01 J-9 0.75 PVC SAP
10
P-37 498.00 J-4 CRP T7-N 02 0.75 NTP 399.002
P-38 106.00 CRP T7-N 02 J-5 0.75
P-47 545.00 J-10 CRP T7- N 04 0.75
P-48 108.00 CRP T7- N 04 J-12 0.75
P-49 632.00 J-10 CRP T7- N 5 0.75
P-50 95.00 CRP T7- N 5 J-11 0.75

METRADO DE TUBERIA EN LINEA DE ADUCCION Y REDES DE DISTRIBUCION

LINEA DE ADUCCION TUBERIA PVC SAP C-10/NTP 399.002,=1" 141.00 m

LINEA DE CONDUCCION TUBERIA PVC SAP C-10/NTP 399.002,=1" 4449.00 m

TUBERIA PVC SAP C-10/NTP 399.002,=1" 496.00 m


REDES DE DISTRIBUCION
TUBERIA PVC SAP C-10/NTP 399.002,=3/4" 3161.00 m
TOTAL TUBERIA REDES DE DISTRIBUCION 8247.00 m