PROJECT : THE CONSTRUCTION, COMPLETION AND MAINTENANCE OF UPGRADING WORKS FOR PHASE 1 BERTH 5 & 6 AT

PELABUHAN TANJUNG PELEPAS (SEQUENCE 3)

DATE : 25-08-17

MATERIAL TAKE OFF

NO. DESCRIPTIONS SEQUENCE 3 REMARKS


PIPES & FITTINGS

1 250mm X 6000mm SF & SPIGOT 3


2 250mm X 6000mm PIPE (SPIGOT) 17
3 250mm X 500mm D/F SHORT PIECE 2
4 250mm X 1000mm S/F SHORT PIECE 4
5 250mm X 1575mm S/F SHORT PIECE 1
6 250mm X 1300mm S/F SHORT PIECE 2
7 250mm X 1055mm S/F SHORT PIECE 1
8 250mm X 1780mm S/F SHORT PIECE 1
9 250mm X 5700mm S/F SHORT PIECE 1
10 250mm X 2420mm D/F SHORT PIECE 1
11 250mm X 80mm FLANGED TEE 2
12 80mm X 400mm D/F SHORT PIECE 2
13 80mm X 560mm D/F SHORT PIECE 2
14 80mm X 670mm D/F SHORT PIECE 2
15 80mm SLUICE VALVE 2
16 80mm X 90 D/F SHORT BEND 4
17 80mm GKM WATER METER 2
18 80mm SCREW-DOWN HYDRANT TO BS 750 2
19 250mm SLUICE VALVE (PERMANENT) 1
20 250mm MECHANICAL COUPLING 4

RUBBER PAD

21 900 x 300 x 12(mm) (SADDLE A) 2


22 900 x 150 x 12(mm) (SADDLE B) 25

GASKETS

23 250mm RUBBER GASKET PN 16 (ID-250) 12


24 250mm RUBBER GASKET PN 16 (ID-270) 0
25 80mm RUBBER GASKET PN 16 16

BOLT AND NUTS

26 M24 X 75 HDG BOLT NUT (250mm) 144


27 5/8'' X 2 1/2'' M/S B/NUTS (80mm) 128

PETROLATUM TAPE SYSTEM

28 DENSO TAPE (100mm X 10m) 38


29 DENSO TAPE (150mm X 10m) 150
30 DENSYL MASTIC (3.0kg/block) 65

HOT DIPPED GALVANIZED M.S STRAP

31 STRAP FOR SADDLE A (500mm) 4


32 STRAP FOR SADDLE B (450mm) 25