I. GENERAL
This technical evaluation presents the Tagum Water Districts Master
Plan for Bulk Water Supply project making used of the selected Hijo River as
source of water supply.
II. PLANNING STAGE
Taking into consideration the target expansion areas and its water
requirement, the TWD master plan will be implemented in two (2) phases
namely: Phase I (to be completed in year 2018) and Phase II (to be completed
in year 2021). Construction period of the Recommended Plan to meet the water
requirement for Phase I will start in 2016 while that for Phase II will start in
2019.
III. BASIC CONSIDERATIONS
1. Service Areas
As of December 2014, TWD serves 13 out of 23 barangays, namely:
Apokon, La Filipina, Magdum Magugpo North, Magugpo East, Magugpo West,
Magugpo South, Magugpo Poblacion, Mankilam, San Miguel, Visayan Village,
Cuambogan and Canocotan.
Phase I of the project will cover 16 barangays adding barangay Madaum,
San Isidro and Pagsabangan.
On the other hand, Phase II of the project will cover the 19 barangays
adding barangays Bincungan, Busaon and Libuganon.
2. Water Sources
a. Present Water Sources
Tagum Water District is presently served by 8 existing deep wells with a
combined output of 32,032 cubic meter per day shows the location of these
deep wells. This is including the newly constructed well near the Tagum City
New City Hall at JV Ayala Avenue, Apokon, with an output of 6,000 cubic meter
per day and made operational last April 27, 2015.
b. Proposed Water Sources
The proposed water sources for TWD is the surface water of Hijo River.
Page 1 of 15
Treatment plant using a Multi-Barrier approach, which is proposed to be
located in Barangay Magdum. The project proposes to abstract 41,000 cubic
meter per day with a 7 to 8% allowance for treatment and transmission pipeline
losses to produce 38,000 cubic meter per day from Hijo River.
3. Pipeline System
From the RBF the water will be pumped to the treatment plant to the
5,000 cubic meter ground storage tank of the Bulk Water Supply. The water
will be transmitted to the Injection Point at the nearest national highway at
Brgy. Magdum to where the mother meter will be installed. This mother meter
will be the basis of the quantity of water that TWD purchase from the Bulk
Water Supplier.
b. Distribution Pipeline
A distribution pipeline will be constructed ranging from 150 mm. diameter
to 50 mm. diameter at the following areas: (see master plan map and
Construction Project 2016 & 2017)
Brgy. Canocotan
Brgy. San Isidro
Brgy. Madaum
Brgy. Pagsabangan
4. Storage Facilities
Page 2 of 15
5 Cristo Rey Subdivision, Magugpo West 630
The total capacity of TWDs existing storage tanks is 1,558 cubic meters.
An on-going construction of 480 and 400 cubic meters storage tanks located
at Mankilam and La Filipina which are expected to be completed this year.
1. System Pressure
The requirement for the velocity of flow in the distribution system was
3m/s maximum at all times while the minimum was set at 0.3 m/s. But to attain
the pressure requirement as per Section IV.1 in our distribution system,
velocity lower than the minimum requirement is allowed.
3. Computer Analysis
4. Project Assumptions/Projections
a. Service Connections
Page 3 of 15
Table 2. Service connections
Number of Target Total Service
YEAR
Service Connections Connection
2014 28,882
2015 3,000 31,882
2016 2,000 33,882
2017 1,000 34,882
2018 4,000 38,882
2019 2,500 41,382
2020 3,100 44,482
2021 2,000 46,482
2022 3,000 49,482
2023 1,500 50,982
2024 1,200 52,182
2025 1,000 53,182
2026 1,000 54,182
2027 1,000 55,182
2028 700 55,882
2029 500 56,382
2030 500 56,882
2031 500 57,382
2032 500 57,882
Page 4 of 15
Table 3 shows the distribution of projected service connections per barangay.
b. Demand Patterns
The usage of water per service connection is not constant throughout the
day. Figure 1 shows the domestic pattern of residential usage while on Figure
2 shows the commercial pattern used for commercial establishments.
c. Non-Revenue Water
Page 5 of 15
The re requirement for Non-Revenue Water (NRW) was considered and was
added to demand of water in the analysis. Table 4 shows the
projections/assumptions of NRW.
Non-Revenue Water
YEAR
(%)
2014 35
2015 33
2016 33
2017 31
2018 31
2019 29
2020 29
2021 27
2022 27
2023 25
2024 25
2025 25
2026 25
2027 25
2028 25
2029 25
2030 25
2031 25
2032 25
d. Average Consumption
The consumption of water per service connections is assumed to be 24
cubic meter per month having 5 persons per service connection. Considering
the per capita will consumed 160 liters of water per day.
Average
Consumption in
YEAR
cubic meter per
month
2014 22
2015 22
Page 6 of 15
2016 22
2017 22
2018 24
2019 24
2020 24
2021 24
2022 24
2023 24
2024 24
2025 24
2026 24
2027 24
2028 24
2029 24
2030 24
2031 24
2032 24
e. Water Supply
After the construction of PS 16, TWD will not consider any addition of
pumping station using ground water as source. From 2014 until the entrance
of Bulk Water Supply, TWD will make used of the exiting pumping station.
When the Bulk Water Supply made operation, TWD will utilize the existing 4
pumping stations in controlled and with scheduled as per hydraulic analysis
recommendations.
Bulk Water Supply scheduled for the first three (3) years a 26,000 cubic
meter per day supply, 32,000 cubic meter per day for another three (3) years
and 38,000 cubic meter per day for the 7th year towards the end of 15 year
contract.
Page 7 of 15
2016 27,800 27,800
2017 27,800 27,800
2018 22,000 26,000 48,000
2019 22,000 26,000 48,000
2020 22,000 26,000 48,000
2021 22,000 32,000 54,000
2022 22,000 32,000 54,000
2023 22,000 32,000 54,000
2024 22,000 38,000 60,000
2025 22,000 38,000 60,000
2026 22,000 38,000 60,000
2027 22,000 38,000 60,000
2028 22,000 38,000 60,000
2029 22,000 38,000 60,000
2030 22,000 38,000 60,000
2031 22,000 38,000 60,000
2032 22,000 38,000 60,000
Page 8 of 15
In April 27, 2015, Pumping Station No. 16 (PS 16) made operational. TWD
water system improved in terms of its supply. Simulating the system adding PS
16 supply, Figure 4 shows TWD water system with PS 16.
PS 16 answered the problem of water shortage in 2014 and gave an extra
supply which can cater approximately 4,500 service connections.
b. Scenario 2015
By the addition of 3,000 service connections and the same supply was used
in the analysis, there were areas in the TWD water system beginning to
encounter low pressure/ no water. See Figure 5.
Considering the 26,000 cubic meter per day supply from Bulk Water
Supplier, the simulation was conducted.
Page 10 of 15
TWD operation
1. A 700 mm. diameter pipeline will be laid from the Bulk Water Supply
source at Magdum up to the Circumferential Road near the Public
Market, Mankilam. See Figure 7.
2. A 500 mm. diameter pipeline will be laid from the end of 700 mm.
diameter pipeline at Circumferential Road near the Public Market,
Mankilam to crossing National Highway fronting Daneco-Substation,
Canocotan. See Figure 8.
Page 11 of 15
3. A 300 mm. diameter pipeline will be laid from Daneco-Substation,
Canocotan to Corner National Highway- Madaum. See Figure 9.
4. A 250 mm. and 200 mm. diameter pipelines will be laid from Corner
Nationa Highway Madaum to entrance of Banana Beach, Madaum.
5. Distribution pipelines will be laid for Canocotan, San Isidro and Madaum.
6. Inter-connections will be conducted connecting the main transmission
pipelines to the existing distribution pipelines of TWD at the following
locations:
Highway Curvada
Suaybaguio District near the Baga Rice Mill
Near Glorius Memorial Park, La Filipina
Crossing Capitol, Mankilam
Page 12 of 15
Capitol Road near North Eagle 5, San Miguel
Canocotan near Renzo Subdivision
Daneco Substation, Canocotan
Corner National Highway- Madaum
7. Installation of Pressure Regulating Valve (PRV) to Pagsabangan
e. Scenario 2019 and 2020 Year 2 and 3 of the Bulk Water Supply
Bulk Water Supply operation continued using the same setting in year 1,
e.g. 26,000 cubic meters per day supply.
TWD operation:
No operation for PS No. 11
Operates PS No. 13 from 5 am to 9 am
Operates PS No. 14 from 4 am to 9 pm
Operates PS No. 15 in 24 hours
Operates PS No. 16 from 4 am to 10 pm
f. Scenario 2021 Year 4 of the Bulk Water Supply
TWD operation
No operation at PS No. 11
PS No. 13 operates from 5 am to 9 am
PS No. 14 operates from 4 am to 9 pm
PS No. 15 operates in 24 hours
PS No. 16 operates from 3 am to 11 pm
1. A 300 mm. diameter pipeline will be laid from Corner Nationa Highway-
Madaum to Corner National Highway-Liboganon. Figure 10. 300 mm.
diameter Pipeline.
Page 13 of 15
2. Distribution pipelines will be laid for Bincungan, Busaon and
Liboganon.
3. Inter-connections will be conducted connecting the existing
transmission pipelines at the following locations:
Corner National Highway-Madaum
Corner National Highway-Liboganon
4. Reinforcing Pipelines:
250 mm. diameter from Daneco Substation to Visayan Village
200 mm. diameter from Reclusado Compound to Bermudez Plains
150 mm. diameter from Prk Rattan to Highway Apokon
5. Construction of 400 cubic meter storage tank at Apokon area
g. Scenario 2022 and 2023 Year 5 and 6 of the Bulk Water Supply
TWD operation:
Page 14 of 15
Bulk Waater Supplier supplies 38,000 cubic meter per day
Two (3) pumps in operation. Each pump has a design of 19,000
cu.m./day at 42 meters head
TWD operation
Computer printouts of the hydraulic analyses year 2032. (See attached file)
Approved:
NELLY M. GENTUGAYA, MM
General Manager
Page 15 of 15