PUENTE SOBRE EL RIO CONGO - L= 45 M

1 2 3 4 5 6 7 8
Cantidad $ TOTAL
INFRAESTRUCTURA U nov-15 dic-15 ene-16 feb-16 mar-16 abr-16 may-16 jun-16
LIMPIEZA Y ENCAUZAMIENTO DE RIO M3 8.000,00 1,68 13.440,69 13.440,69
EXCAVACIN Y RELLENO PARA PUENTES M3 2.000,00 3,52 7.047,95 7.047,95
DESALOJO DE MATERIAL (DMT=5KM) M3 2.000,00 1,26 2.515,23 2.515,23
HORMIGON DE CEMENTO PORTLAND CL-E FC=180 KG/CM2 (REPLANTILLO) M3 30,91 131,86 4.075,83 4.075,83
HORM. ESTRUCT./CEM. PORTL.CL-B FC=280 KG/CM2 (INC. INHIBIDOR DE CORROSION ) M3 579,38 280,71 162.638,05 54.212,68 54.212,68 54.212,68
ACERO DE REFUERZO EN BARRAS FY=4200 KG/CM2 KG 44.770,38 1,82 81.589,01 40.794,50 40.794,50
MATERIAL FILTRANTE M3 113,01 20,59 2.326,88 2.326,88
TRANSPORTE DE MATERIAL FILTRANTE DMT =75 KM M3 113,01 18,78 2.122,33 2.122,33
TUBERIA DE PVC ( PARA DRENAJE) D= 4" =110 MM ML 78,00 8,50 662,83 662,83
SONDEOS EXPLORATIVOS DE SUELOS ML 50,00 62,53 3.126,64 3.126,64
PICADA Y DESCABEZAMIENTO DE PILOTES U 66,00 100,24 6.616,07 6.616,07
PILOTE PREFABRICADO DE HORMIGON DE CEMENTO PORTLAND F'C=280 KG/CM2; 0,60 X0,60 M ML 1.171,50 379,92 445.077,20 222.538,60 222.538,60
SUMINISTRO Y COLOCACION DE ENROCADO M3 3.600,00 13,75 49.495,29 24.747,65 24.747,65
TRANSPORTE DE MATERIAL (PEDRAPLEN)DMT =75 KM M3 3.600,00 18,78 67.609,29 33.804,64 33.804,64
GEOTEXTIL PARA SUB-DREN 1600 NT M2 6.000,00 1,09 6.536,00 3.268,00 3.268,00
SUPERESTRUCTURA
HORMIGON DE CEMENTO PORTLAND CL-E FC=180 KG/CM2 (REPLANTILLO) M3 17,16 131,86 2.262,74 754,25 754,25 754,25
HORM. ESTRUCT./CEM. PORTL.CL-B FC=280 KG/CM2 (INC. INHIBIDOR DE CORROCION ) M3 115,83 280,71 32.514,70 10.838,23 10.838,23 10.838,23
ACERO DE REFUERZO EN BARRAS FY=4200 KG/CM2 KG 15.952,95 1,82 29.071,50 9.690,50 9.690,50 9.690,50
SUMIN. E INST. DE PLACA DE NEOPRENO (25X30X7)CM DUREZA SHORE/60 U 10,00 256,12 2.561,17 853,72 853,72 853,72
SUMIN. E INST. DE PLACA DE NEOPRENO (20X20X2)CM DUREZA SHORE/50 U 4,00 196,12 784,47 261,49 261,49 261,49
JUNTAS DE DILATACION TIPO TRANSFLEX MODELO 300 O SIMILAR ML 28,60 1.144,51 32.732,94 10.910,98 10.910,98 10.910,98
SUMINISTRO Y FABRICACION DE ELEMENTOS METALICOS CON ACERO ESTRUCTURAL ASTM A-588 KG 70.480,44 3,53 248.565,34 82.855,11 82.855,11 82.855,11
MONTAJE DE ACERO ESTRUCTURAL ASTM A-588 KG 70.480,44 0,62 43.446,19 14.482,06 14.482,06 14.482,06
SUMINISTRO Y FABRICACION DE ELEMENTOS METALICOS CON ACERO ESTRUCTURAL ASTM A-36 KG 20.167,71 3,53 71.126,03 23.708,68 23.708,68 23.708,68
MONTAJE DE ACERO ESTRUCTURAL ASTM A-36 KG 20.167,71 0,62 12.431,96 4.143,99 4.143,99 4.143,99
TUBERIA DE PVC ( PARA DRENAJE) D= 4" =110 MM ML 7,20 8,50 61,18 20,39 20,39 20,39
HORM. ESTRUCT./CEM. PORTL.CL-B FC=240 KG/CM2 (INC. INHIBIDOR DE CORROCION ) M3 21,22 205,55 4.361,78 1.453,93 1.453,93 1.453,93
SUMINISTRO E INSTALACION DE TUBERIA GALVANIZADA D=4" (RELLENO CON MORTERO POBRE) ML 180,00 18,57 3.342,16 1.114,05 1.114,05 1.114,05