DAILY ACTIVITY REPORT (MEC

SL NO. PACKAGE EQUIPMENT CENTRE

PRIMARY CRUSHER/COAL SHED

TRANSFER HOUSE 1

TRANSFER TOWER 2

CONVEYOR 1A & 1B

1 CHP
CONVEYOR 2A &2B
1 CHP

CONVEYOR 3A &3B

CONVEYOR 4A & 4B

CONVEYOR 5A & 5B

SECONDARY CRUSHER HOUSE


BOILER -I

STRUCTURAL

PRESSURE PART
ROTATING EQUIPMENTS

HOT AIR PATH

COLD AIR PATH


FLUE GAS PATH

FUEL PATH

INSULATION

ESP

BOILER -II

STRUCTURAL
PRESSURE PART

2 BOILER & ESP


ROTATING EQUIPMENTS

HOT AIR DUCTING

COLD AIR DUCTING


FLUE GAS DUCTING

FUEL PATH

INSULATION

ESP

TG TO BOILER INTERCONNECTION
RAW WATER PUMP HOUSE

CLARIFIED WATER PUMP HOUSE

CW AND ACW PUMP HOUSE

UTILITY WATER PUMP HOUSE

COMPRESSOR HOUSE

3 LP PIPING
FIRE FIGHTING SYSTEM
LDO SYSTEM

PIPE RACK

FABRICATION &ERECTION OF PIPING

FANS ,GEAR BOXES,PROPELLER SHAFT &


STRUCTURALS

COOLING DISTRIBUTION PIPE LINES


4 TOWER DRIFT ELIMINATORS & SPLASH GUARDS
COOLING
4 TOWER

DECK RAILING WORK.

STRUCTURAL

TURBINE

TURBOGENERATOR

CONDENSER
5 TG BUILDING

AUXILLARIES
FABRICATION &ERECTION OF PIPING

LUBE OIL SYSTEM

AC DUCTING WORK

STRUCTURAL

ERECTION OF EMBEDED PLATES & OPENING


6 ASH SILO
ASH HANDLING EQUIPMENT

ASH TRANFER PIPE LINE

STRUCTURAL
EQUIPMENT ERECTION

WATER
7 TREATMENT
PLANT
FABRICATION & ERECTION OF PIPING

CHEMICAL HOUSE

WATER RESERVOIR
MANPOWER DETAILS
SL NO CONTRACTOR MANPOWER
GIRI
1 CONSTRUCTIONS 28
(HAZEMAG)
2 THERMAX 195
3 GPR 19
4 APT 18
5 SUVENDU SAHU 5
JOSEPH
6 8
CONSTRUCTIONS

7 ION EXCHANGE 5
REPORT (MECHANICAL- CPP) DATE-27.09.13
ACTIVITY AT SITE

Final welding of Vertical bracing in progress. Erection of


feeder breaker platform assembly .

Sheeting work & Final welding completed .

Rework on the main columns of transfer tower-2


completed . Fabrication & welding of staircase column
completed .Alignment work completed and welding in
progress. Side tie members of Main Column structures
being erected.

Column grouting work completed.


Erection & Welding of handrailing is in progress. Grouting
of all the columns completed.

Fixing of Foundation bolts 3A completed foundation work


of 3B is in progress. Assembly of gallery completed & final
welding is in progress.

Levelling of ramp for trussel erection completed. Clearing


of fire wood near TR-5 foundation is in progress.

Assembly work of Structures & final welding completed.

Casting of half portion of 17.0 M slab completed.


Final painting work in progress.

No activity
Completed

Completed

Completed
No activity

Completed

Insulation of Economiser casing completed ,PA


duct,pipes ,SA Duct header connecting to furnace is in
progress. Insulation of duct connecting ID FAN to
chimney in progress & insulation work at SA FAN taken up.
Insulation of vent lines taken up.

No activity

Final painting work in progress. Erection of monorail


support structure & monorail for ID FAN completed &
final welding is in progress. Assembly of monorail support
structure & monorail for PA FAN is in progress. Erection of
balance floor beams at 3.2m floor taken up & is in
progress.
Welding of supporting structures in progress. Erection of
steam vent support completed. Erection & welding of IBD
Vent is in progress.

Erection of ID FAN-3 completed & alignment is in progress.


ID FAN-4 foundation modification in progress &
foundation work for SA FAN completed. Erection of base
frame of PA FAN-3 & 4 completed & alignment is in
progress. Erection of base frame of SA FAN-3 & SA FAN-4
in progress .

Fabrication work of SA fan delivery line completed &


erection is in progress. wind box erection completed.
Erection & welding of PA Duct connecting to windbox is in
progress.

Erection & welding of secondary air duct fitting work in


progress .
Welding work at ID FAN ducting in progress. Erection of
economiser casing completed & Welding of economiser
casing in progress. Connecting duct from furnace to
economiser work is in progress.

MDC welding in progress. Erection & welding of MDC


Bypass to ash seperator completed. Fixing of ceramic
cyclones pipes in MDC completed.Erection of MDC bypass
line taken up.

Insulation work to be taken up.

Assembly of pent house structure is in progress. Emitting


electrode erection in progress. Assembly & welding of
1st,3rd fields Hopper completed. Erection of 1st & 3rd
field hopper completed. Erection of 2nd & 4th field
hopper completedfinal welding of hopper is in progress.

Erection & Welding of connecting beams from TG to Boiler


at 14.4 M LVL completed. Erection of 1 no. cable rack
gallery at 4 M LVL completed. Erection of second cable
rack gallery at 4 M LVL completed final welding is in
progress.Fabrication of Connecting walkway is in progress.
Both Raw water pump sole plates
positioned,levelled,grouted & curing is under progress.

Grouting of columns is in progress.

Erection of cooling water pump(CW) base frame


completed. Fabrication ofmonorail work started.

No activity as monitoring basin Civil work yet to start.

Erection of pipe rack support connecting to main pipe rack


completed.Fabrication of Pipelines in progress. Shifting of
compresed air pipe near boiler is in progress.

Fire fighting pumps have reached transporters


Godown.GPR informed and freight clearance by GPR is
awaited
Two nos. of LDO storage tanks received &unloaded at
site .Clearing of the Cooling Tower materials for
foundation layout is completed & excavation work in
progress. Civil foundation work has started.

Fabrication of remaining pipe racks completed & painting


work is in progress. Erection of pipe rack supporting
column near boiler completed & erection of connecting
beams completed. Fabrication of remaining cable rack
completed &erectionis in progress .Final welding of pipe
rack connecting beams is in progress.

Wrapping coating of 1400NB Pipes for CW line is under


progress. Welding of bend at cooling tower puddle pipe
completed. Assembly of suction line of CW inlet
completed & welding is in progress. Assembly of 1400 NB
pipe near cooling tower started.

All materials shited close to Cooling Tower

No activity

No activity
Railing work at staircase completed .

Final welding of staircase & Fixing of chequered plates for


steps completed. Fixing of handrailing to be taken up.
Hand railing around TG Deck completed.

Shifting of turbine assembly materials to the TG Deck is in


progress.TG Sole plate placed on TG Deck.Erection of Front
Bearing of turbine completed.Turbine exhaust hood
erected in position& final welding with condenser neck is
in progress. Grinding and Blue matching of generator front
& rear bearing pedestals in progress.

Blue matching of bearing pedestal is in progress.

Expansion work of tube end & welding of vaccum pipes to


condenser & Surface finishing work for Condenser dome
assembly completed & finai welding is in progress.

Erection of third BFP completed. Alignment of pump is in


progress.
Fabrication of boiler feed pump delivery line in progress.

Fabrication & Erection of lube oil pipe line & pipe supports
is in progress.

Insulation work of 10.5 M control room roof


completed.Erection of AC duct & rapping of insulation is
in progress.

Final welding is in progress & fixing of gratings completed.


Fixing of Handrailing work is in progress.

No activity

No activity

No activity

Completed
Erection of agitator pump with its assembly taken
up.Assembly of pipes in MGF near cooling tower taken up.
Erection of Two numbers of pumps for ultra filter with all
pipe fittings is completed. Shifting of sand bags to cooling
tower in progress. Erection of 6 nos chemical dosing
Pumps of chemical house completed.

Inter connecting Piping work from MGF-1 to MGF-2


complited. pipe connecting sludge transfer pump
started.Fabrication & erection of connecting pipe from
raw water to clarifier taken up.Pipeing work from
ultrafiltration to DM TANK started.

Erection of purlins completed & levelling completed.

No activity
DATE-27.09.13
PLANNED FOR REMARK
TOMORROW

Hoppers, railings & chutes for feeder


Same to continue breaker awaited at site. Party has been
followed up.

No activity Transfer Chutes awaited at Site

Same to continue

Follow up on for Short Post and


stringers for inclined ramp.
Welding of handrailing will be Idler frames & Idler not received at
coninued. site.

Civil foundation work yet to be


completed

Trussel fabrication completed & gallery


to be received.party not despatching
Erection process to be taken further materials despite of repeated
up. reminders. Rigorous followup required
as party is not able to provide any
evidence of work in progress.

Erection work to start after


transfer house -2 erection
completion.

Civil work to continue. Civil work yet to be completed


All fabrication scraps being cut
for use & house keeping work
to continue. Painting work to
continue.
Same to continue

Same to continue
welding of supporting Refractory work to be taken up during
structures for pipes to the next week.
continue.

Same to continue

Balance Erection work awaiting


Same to continue completion of fan foundation.

Same to continue
Same to continue

Same to continue

Same to continue

Final welding & alignment to


be taken up.
Plastering work of Raw water pump
Assembly &erection work to house is in progress which will be
be taken up. completed and pump erection work
shall start.

Grouting work will be


continued.

Alignment of base frame to be taken


No activity after erection of suction line to pump.

Final Alignment pipe rack


support connecting to main
pipe rack & erection of
connecting beam Pipe fittings awaited at site.
completed.Erection of
compressed airline in pipe
rack to be taken up.

Cables & conduits of fire sensors at TG


Fixing of Fire Sensor Cables Building 10.5M control room roof have
and Conduits to continue. reached Site
Civil foundation work to
Same to continue start.fabricated tank awaited at site

Erection of cable rack


supports to be taken up.

Same to continue

Civil work yet to be completed &


mobilisation to be started by
Same to continue Paltech.Paltech to mobilise site by
15/9/13.

Shifting to continue same as above

Shifting to continue same as above


West side railing work of cooling tower
staircase to be taken up after
completion of deck railing.

Work stopped to give way for


completion of civil work.

Erection Work started .BHEL


Same to Continue. representative awaited at site for
checking various levels and alignments

Same to Continue

Welding work will be


continued.

Alignment of pump base frame All other available equipments have


to be continued. been placed in position.
Approval given by IBR for all pressure
No activity line erection & welding.

Same to continue

Materials indented for supply of


Same to continue cooling water to A.C.Units

Handrailing work to continued.

No activity
Pipe assembly work to be
continued. Alignment of
erected pumps to start.Shifting
of sand bags to cooling tower
will be continued.

Same to Continue

Sheeting work to be done after


No activity completion of grouting of anchor bolts
of purlins.