TRANSFER HOUSE 1
TRANSFER TOWER 2
CONVEYOR 1A & 1B
1 CHP
CONVEYOR 2A &2B
1 CHP
CONVEYOR 3A &3B
CONVEYOR 4A & 4B
CONVEYOR 5A & 5B
STRUCTURAL
PRESSURE PART
ROTATING EQUIPMENTS
FUEL PATH
INSULATION
ESP
BOILER -II
STRUCTURAL
PRESSURE PART
FUEL PATH
INSULATION
ESP
TG TO BOILER INTERCONNECTION
RAW WATER PUMP HOUSE
COMPRESSOR HOUSE
3 LP PIPING
FIRE FIGHTING SYSTEM
LDO SYSTEM
PIPE RACK
STRUCTURAL
TURBINE
TURBOGENERATOR
CONDENSER
5 TG BUILDING
AUXILLARIES
FABRICATION &ERECTION OF PIPING
AC DUCTING WORK
STRUCTURAL
STRUCTURAL
EQUIPMENT ERECTION
WATER
7 TREATMENT
PLANT
FABRICATION & ERECTION OF PIPING
CHEMICAL HOUSE
WATER RESERVOIR
MANPOWER DETAILS
SL NO CONTRACTOR MANPOWER
GIRI
1 CONSTRUCTIONS 28
(HAZEMAG)
2 THERMAX 195
3 GPR 19
4 APT 18
5 SUVENDU SAHU 5
JOSEPH
6 8
CONSTRUCTIONS
7 ION EXCHANGE 5
REPORT (MECHANICAL- CPP) DATE-27.09.13
ACTIVITY AT SITE
No activity
Completed
Completed
Completed
No activity
Completed
No activity
No activity
No activity
Railing work at staircase completed .
Fabrication & Erection of lube oil pipe line & pipe supports
is in progress.
No activity
No activity
No activity
Completed
Erection of agitator pump with its assembly taken
up.Assembly of pipes in MGF near cooling tower taken up.
Erection of Two numbers of pumps for ultra filter with all
pipe fittings is completed. Shifting of sand bags to cooling
tower in progress. Erection of 6 nos chemical dosing
Pumps of chemical house completed.
No activity
DATE-27.09.13
PLANNED FOR REMARK
TOMORROW
Same to continue
Same to continue
welding of supporting Refractory work to be taken up during
structures for pipes to the next week.
continue.
Same to continue
Same to continue
Same to continue
Same to continue
Same to continue
Same to continue
Same to Continue
Same to continue
No activity
Pipe assembly work to be
continued. Alignment of
erected pumps to start.Shifting
of sand bags to cooling tower
will be continued.
Same to Continue