You are on page 1of 1

METAL STRUCTURAL WORK E.I.R.

PRESUPUESTO REFERENCIAL
Proyecto: Cerco Perimetrico
Cliente: Top Consult
Ubicacin Piura - Peru
Fecha: Diciembre, 2017
PRESUPUESTO
DESCRIPCION UNIDAD METRADO
UNITARIO( /. S) PARCIAL( /. S) TOTAL( /. S)
03.00.00 INSTALACIONES ELECTRICAS S/. 14,820.00
03.01.00 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y HERRAMIENTAS glb 1.00 S/. 2,500.00 S/. 2,500.00
SUMINISTRO E INSTALACION DE MALLA OLIMPICA EN CERCO PERIMETRICO, CON
03.01.01 ml 88.00 S/. 140.00 S/. 12,320.00
TUBO DE 2" DE POSTES
6.00.00 VARIOS S/. 80.00
06.01.01 LIMPIEZA FINAL DE OBRA glb 1.00 S/. 80.00 S/. 80.00

COSTO DIRECTO S/. 14,900.00


GASTOS GENERALES ( 10% ) S/. 1,490.00
UTILIDAD ( 6% ) S/. 894.00
VIATICOS ( 4% ) S/. 596.00
SUB TOTAL S/. 17,880.00
I.G.V ( 18% ) S/. 3,218.40
S/. 21,098.40