Prepared by
NO NAME ID
Table of Contents:
No Content Page
1 Introduction
i. Company background 2
ii. Task and Distribution 3-4
iii. Discussion of Scenario
5
2 Attachment A
i. Analysis of the current and future need 6
ii. Cabling infrastructure and components for the project 7
iii. Network Design
a. Logical (Overall Network Structure)
8
b. Physical
9
➢Overall structure
10
➢Network Rack Diagram
11
➢Equipment Room
➢Telecommunication Room + Work Area 12
➢Work Area 13
➢Work Area Horizontal Cabling 14
4 Conclusion 29
5 References 30
6 Appendix 32-39
Structured Networks Cabling Project RFP 2
UMP NETWORK SOLUTION SDN BHD (GROUP 1)__________________________________________________
Company Background
UMP Network Solution Sdn. Bhd. is a subsidiary company by UMP Holding Sdn. Bhd.
that was founded in September 2017 by 6 young and ambitious fresh graduate form
University Malaysia Pahang who all work together on providing our clients with the highest
level of service, without an exception. UMPNET is specialized in providing networking solution
to the customer. Some of the service that being offer by us are IT Consultation, Network
Security, Cabling Installation, Preventing Maintenance, Manage Service and more. The field
we are all working in together is always changing, so being able to adapt to new technological
conditions on the market is crucial to our success, as well as success of our clients
Contact us :
• Project Timeframe
• Design horizontal cabling
• Conferring with network users about solving
existing system problems
• Monitor network usage and security.
• Creation of marketing concepts.
• Monitor system performance to ensure that
demands are being met.
Discussion of Scenario
Given Scenario:
A school wants to have their 4 computers labs with Internet connection. Each lab having 26 computers
that directly connected to each other and to the Internet. Each lab is aligned vertically at each floor
from ground to fourth floor. The main Internet connection is located 500 meters away at the school's
office room. The labs are used every day where students access School Net system (online learning).”
Overview solution:
Based on the situation chosen, we were instructed to design and propose the network
architecture that will support the main requirement of the situation need which is 4 new computer
labs with active internet connection. Since this is school network which accommodate hundreds to
thousands of users. We need to follow the best practice in designing good network architecture1. So,
we will implement three-tier LAN design which provide these 4-priciples:
For this project we need to assess the requirement from front end to back end. The front-end
requirement is internet access for 26 PC’s for each lab and there are 4 lab which means at least need
to provide internet access to 104 PC’s. Then start to assess it backward, since the requirement needed
for each lab is located vertically in vertically at each floor so, the best way is to use on switch for each
floor. The situation also mention that internet access sauce is located 500 meters from office, using
UTP as backbone cabling for is no longer an option. Therefore, fiber optic cables will be used as
backbone cabling from office the main distribution frame (MDF) at Block X. As now should already
have three-tier LAN, Core as core switch at the main office (Equipment Room), distribution layer we
be handle by MDF the ground floor and access switch at each floor. All that will cover the hierarchy
part of the design practice. Next, is modularity also will help of the future us of the design. For that,
addition requirement will be added as a reserved. Example since the requirement needed for 26 PC’s
per lab, we will add 4 more as a reserved. Then each faceplate will have at least 2 Rj45 ports. In
addition of that wireless access point (WAP) will allow device to have same access as PC if all the ports
are full. The move on into resiliency, in order always keep the network always up and running there
are two ways will be implemented, one is to use 2 Internet Service Provider (ISP) as a backhaul which
great is one ISP having issue and the second one is the of uninterruptible power supply (UPS) will
become in handy if any power failure occurs towards the main power supply. Last but not least,
flexibility issue for this project should be solve by using the Load balancer that allow traffic load sharing
since the school network resources not will be use 24 hours just for labs. So, load balancer will allow
1
Campus Architecture & Design Principle, Cisco Enterprise Campus 3.0
Structured Networks Cabling Project RFP 7
UMP NETWORK SOLUTION SDN BHD (GROUP 1)__________________________________________________
those networks resources will be allocated to the much use at the time where lab is not being use for
example after 6 PM the network resources will be redirect to hostel that much needed at the time.
** ER – Equipment Room
TR – Telecommunications Room
Drawing Information
TM Metro-E Title: Logical Topology of Network Infra
1Gbps TIME Internet Direct Diagram For Proposed Lab
Static IP 1 Gbps Subsytem involved :
Static IP i. Entrance Facility
Ii. Equipment Room
Ii. Backbone Cabling
Pub lic IP Address 103.53 .32.141 Iii.Work Area
Pub lic IP Address 11.1.2. 5
Servers
Cat 6 Vertical/Horizontal
Cabling
Fiber-Optic Backhoul
Fiber-Optic Backbone
Structured Networks Cabling Project RFP 9
UMP NETWORK SOLUTION SDN BHD (GROUP 1)__________________________________________________
Drawing Information
2 6 X PC
S econd F loor
(2F )
OFFICE
2 6 X PC
CAT 6
Backbone Cabling
CAT 6
Horizontal Cabling
Fiber Backbone
Structured Networks Cabling Project RFP 10
UMP NETWORK SOLUTION SDN BHD (GROUP 1)__________________________________________________
Equipment Room
Network Rack
42U
Media Converter
Multi-WAN Router
Firewall
1 GbE 10 GbE
1 2 3 4 5 6 7 8 1 2 USB MGMT CONS OLE
FortiADC-600E
powered by
a company
Telecommunication Room
Wireless Controller POW ER
STATUS
0
LNK/ 1 POE
ACT
2
3
4
5
6
7
0
3
ACCESS
POINT
STATUS
4
7
8
LNK/ 9 POE
ACT
10
11
12
13
14
15
10
11
8
9
ACCESS
POINT
STATUS
12
13
14
15
16
LNK/ 17 POE
ACT
18
19
20
21
22
23
ACCESS
16
17
18
19
POINT
STATUS
20
21
22
23
m o lex
24
LNK/
ACT
m o lex
25
LNK/
ACT
SERIAL
Network Rack
18U
Core Switch
48-Ports Gigabit
Switch
48-Ports UTP
Patch Panel
UPS
UPS
DRAWING INFORMATION :
TITLE : Network Rack with Equipment Design
LOCATION : Equipment Room and Telecommunication Room
ADDRESS: SMK Gambang Jaya
Version: 1.0
Version Date : 30/11/2017
Created by : Zaini Zainuddin
Company : UMP Network Solution Sdn. Bhd.
Structured Networks Cabling Project RFP 11
UMP NETWORK SOLUTION SDN BHD (GROUP 1)__________________________________________________
Drawing Information
Title: Physical Design Equipment Room
Subsytem involved :
i. Entrance Facility
Ii. Equipment Room
Address :
SMK Gambang Jaya
Lebuhraya Tun Razak
26300 Gambang, Kuantan
Pahang Darul Makmur
Version: 1.0
Version Date : 30/11/2017
Created by : Zaini Zainuddin
Company : UMP Network Solution Sdn
Bhd
EQUIPMENT ROOM
TIME
ENTRACE
FACILITY
CPE
Legend
Terminal
Server Server Server Server
TM
WAN/Internet
Cat 6 Vertical/Horizontal
Cabling
Fiber-Optic Backhoul
Fiber-Optic Backbone
Structured Networks Cabling Project RFP 12
UMP NETWORK SOLUTION SDN BHD (GROUP 1)__________________________________________________
Drawing Information
BLOK X BUILDING Title: Physical Designed of
Riser Telecommunication Room Work Area Proposed Computer Lab
Subsystem Involved:
CO MP UTER LAB 4
i. Telecommunication Room
Ii. Work Area
Fourth Floor (4F) Location : Building X FSKKP
Address :
SMK Gambang Jaya
26 X PC Lebuhraya Tun Razak
Telecommunication Room
26300 Gambang, Kuantan
Riser Work Area
Pahang Darul Makmur
COMP UTER LAB 3
Version: 1.0
Version Date : 26/9/2017
Third Floor (3F)
Created by : Zaini Zainuddin
Riser
Company : UMP Network Solution
Sdn. Bhd.
26 X PC
CO MPLAB
UTER2 LAB 2
Legend
26 X PC
Network Rack
26 X PC
Riser MDF
CAT 6
Backbone Cabling
Drawing Information
Title: Proposed Computer Lab Design
Subsystem involved :
i. Work Area
PC 3 PC 22
PC 9 PC 19 .30
.11
.17 .27
PC 4 PC 23
.12 PC 10 PC 18 .31
.18 .26
PC 5 PC 24 Legend
.13 PC 11 PC 17 .32
.19 .25
Projector
Projector Screen
PC 14
.22 Wireless Access
Point (WAP)
Structured Networks Cabling Project RFP 14
UMP NETWORK SOLUTION SDN BHD (GROUP 1)__________________________________________________
Network Costing
QUANTITY TOTAL
N0 ITEM BRAND / MODEL PRICE
/ UNIT PRICE
RM
Internet Service 10,000.00
RM 10,000.00
1 Provider I TIME Internet Direct ( Installation 1
Fee)
RM
Internet Service 10,000.00
RM 10,000.00
2 Provider II Telekom Malaysia Metro E (Installation 1
Fee)
Peplink / Balance 305 Multi-WAN
Multi-WAN Router RM 8200.00
3 RM 8200.00 1
LinkNet / 48 U
RM 1200.00 1 RM 1200.00
13 Network Rack
LinkNet / 18 U
RM 750.00 4 RM 3000.00
RJ45 port
14 Modular Jack RM 4 / Unit 224 RM 896.00
PVC Faceplate RM 2.45 /
15 RJ45 port 112 RM 274.40
Unit
PVC Angled
16 Surface Back Box RM 0.61 /
45° Angle 112 RM 68.32
Unit
PVC Half Moon
RM 19 /
17 Casing
2” Meter 8 Meter RM 152.00
PVC Conduit RM 1 /
18 1 “ Diameter 30 Meter RM 30.00
Meter
PVC Trunking RM 5 /
19 2” Diameter 56 Meter RM 336.00
Meter
PVC U Clip RM 0.32 /
20 1” Diameter 64 RM 20.48
Unit
PVC Male adapter
21 RM 1.20 /
1” Diameter 224 RM 268.80
Unit
RM 13.00 /
Screw
22 1 KG Box Box 3 Boxes RM 39.00
RM 20 / 100
23 Cable Ties Label Cable Ties With Tag 200 Pcs RM 40.00
Pcs
GRAND TOTAL RM
89,528.77
Structured Networks Cabling Project RFP 17
UMP NETWORK SOLUTION SDN BHD (GROUP 1)__________________________________________________
Attachment B
Horizontal Cabling Project
Structured Networks Cabling Project RFP 19
UMP NETWORK SOLUTION SDN BHD (GROUP 1)__________________________________________________
Structured Networks Cabling Project RFP 20
UMP NETWORK SOLUTION SDN BHD (GROUP 1)__________________________________________________
Structured Networks Cabling Project RFP 21
UMP NETWORK SOLUTION SDN BHD (GROUP 1)__________________________________________________
Structured Networks Cabling Project RFP 22
UMP NETWORK SOLUTION SDN BHD (GROUP 1)__________________________________________________
Structured Networks Cabling Project RFP 23
UMP NETWORK SOLUTION SDN BHD (GROUP 1)__________________________________________________
Structured Networks Cabling Project RFP 24
UMP NETWORK SOLUTION SDN BHD (GROUP 1)__________________________________________________
Structured Networks Cabling Project RFP 25
UMP NETWORK SOLUTION SDN BHD (GROUP 1)__________________________________________________
Structured Networks Cabling Project RFP 26
UMP NETWORK SOLUTION SDN BHD (GROUP 1)__________________________________________________
CAT 5e Measurement
No Name Faceplate Label Length (cm) Extra (cm) Total length (m)
Conclusion
As a conclusion, we able to solve situation given which to provide network infrastructure for
4 computer lab which each lab having 26 computers for the school. This project uses fiber
optic cable interbuilding backbone that can have supported up to 1Gbps the maximum to
transfer data. Then each lab we use wired LAN connection to connect to the network. We use
48-Ports Gigabit Switch each lab that can that have plenty more empty ports for future needs.
By developing this project, its teach how to work together with our team that everyone was
given the task to complete the project. Group members need to solve the problem and task
that have been given from executive manager and make every one of group members
responsible to do the task and finish their work. This project will be given advantages to the
student where students can access School Net System (online learning).
For the LAN connection, our group uses UTP CAT 6 for Vertical Cabling for each level. We use
Multimode Fiber interbuilding backbone that can transfer two-way data. Multi-WAN Router
is used for the server and to provide 3-tier hierarchical access our group use core switch
distributing switch access switch. Wireless control uses for control and manages WAP.
Network rack uses for stack all mount rack compatible device in one place at Equipment Room
(ER).
Last but not least, group member needs to build horizontal cabling each of the group
members. This gives the experience to group member so our group can learn and know how
to create and construct the network. This project gives much new information to our group
that we don’t know. We can apply this skill for our future.
Structured Networks Cabling Project RFP 30
UMP NETWORK SOLUTION SDN BHD (GROUP 1)__________________________________________________
Reference
BOOKS
WEBSITES
Appendix
Structured Networks Cabling Project RFP 32
UMP NETWORK SOLUTION SDN BHD (GROUP 1)__________________________________________________
Structured Networks Cabling Project RFP 33
UMP NETWORK SOLUTION SDN BHD (GROUP 1)__________________________________________________
Structured Networks Cabling Project RFP 34
UMP NETWORK SOLUTION SDN BHD (GROUP 1)__________________________________________________
Structured Networks Cabling Project RFP 35
UMP NETWORK SOLUTION SDN BHD (GROUP 1)__________________________________________________
Structured Networks Cabling Project RFP 36
UMP NETWORK SOLUTION SDN BHD (GROUP 1)__________________________________________________
Structured Networks Cabling Project RFP 37
UMP NETWORK SOLUTION SDN BHD (GROUP 1)__________________________________________________
Structured Networks Cabling Project RFP 38
UMP NETWORK SOLUTION SDN BHD (GROUP 1)__________________________________________________
Structured Networks Cabling Project RFP 39