OBRA RESIDENCIAL PARQUE AZUCENAS

PROPIETARIO BECTEK CONTRATISTAS S.A.C.


LUGAR LA LIBERTAD - TRUJILLO - TRUJILLO
FECHA :

PRESUPUESTO ESTRUCTURAS

Item Descripción Und. Metrado Precio S/. Parcial S/. Total S/.

05 CONCRETO ARMADO 69,058.14


05.02 PRIMER NIVEL 69,058.14
05.02.01 COLUMNAS 4,042.22
05.02.01.01 ACERO DE REFUERZO fy=4200 Kg/cm2. kg 301.81 3.73 1,127.06
05.02.01.02 ENCOFRADO Y DESENCOFRADO PARA COLUMNAS m2 40.08 28.00 1,122.24
05.02.01.03 CONCRETO PREMEZCLADO PARA COLUMNAS f'c=210 kg/cm2 m3 6.81 263.28 1,792.93
05.02.02 PLACAS 9,819.11
05.02.02.01 ACERO DE REFUERZO fy=4200 Kg/cm2. kg 928.62 3.73 3,467.77
05.02.02.02 ENCOFRADO Y DESENCOFRADO PARA PLACAS m2 100.93 28.00 2,826.04
05.02.02.03 CONCRETO PREMEZCLADO PARA PLACAS f'c=210 kg/cm2 m3 13.39 263.28 3,525.30
05.02.03 MUROS 11,699.70
05.02.03.01 ACERO DE REFUERZO fy=4200 Kg/cm2. kg 1,597.15 3.73 5,964.27
05.02.03.02 ENCOFRADO Y DESENCOFRADO PARA MUROS m2 69.06 28.00 1,933.68
05.02.03.03 CONCRETO PREMEZCLADO PARA MUROS f'c=210 kg/cm2 m3 14.44 263.28 3,801.74
05.02.04 VIGAS 21,789.55
05.02.04.01 ACERO DE REFUERZO fy=4200 Kg/cm2. kg 3,645.82 3.73 13,614.67
05.02.04.02 ENCOFRADO Y DESENCOFRADO PARA VIGAS m2 111.99 28.00 3,135.72
05.02.04.03 CONCRETO PREMEZCLADO PARA VIGAS f'c=210 kg/cm2 4"-5" USO 67m3 19.14 263.28 5,039.15
05.02.05 LOSA MACIZA 4,890.87
05.02.05.01 ACERO DE REFUERZO fy=4200 Kg/cm2. kg 592.35 3.73 2,212.03
05.02.05.02 ENCOFRADO Y DESENCOFRADO PARA LOSA MACIZA m2 32.58 28.00 912.24
05.02.05.03 CONCRETO PREMEZCLADO PARA LOSA MACIZA f'c=210 kg/cm2 4"-5" m3 6.71 263.28 1,766.60
05.02.06 LOSAS ALIGERADAS 14,227.86
05.02.06.01 ACERO DE REFUERZO fy=4200 Kg/cm2. kg 984.44 3.73 3,676.22
05.02.06.02 APUNTALAMIENTO PARA LOSA ALIGERADA m2 208.44 28.00 5,836.32
05.02.06.03 CONCRETO PREMEZCLADO PARA LOSA ALIGERADA f'c=210 kg/cm2 4"-m3 17.91 263.28 4,715.32
05.02.07 ESCALERA 1,373.23
05.02.07.01 ACERO DE REFUERZO fy=4200 Kg/cm2. kg 141.61 3.73 528.82
05.02.07.02 ENCOFRADO Y DESENCOFRADO PARA ESCALERAS m2 12.01 28.00 336.28
05.02.07.03 CONCRETO PREMEZCLADO PARA ESCALERA f'c=210 kg/cm2 6"-8" USOm3 1.93 263.28 508.13
05.02.08 COLUMNETAS 1,215.61
05.02.08.01 ACERO DE REFUERZO fy=4200 Kg/cm2. kg 128.05 3.73 478.18
05.02.08.02 ENCOFRADO Y DESENCOFRADO PARA COLUMNETAS m2 17.31 28.00 484.68
05.02.08.03 CONCRETO PREMEZCLADO PARA COLUMNETAS f'c=210 kg/cm2 6"-8" m3 0.96 263.28 252.75

Costo Directo 69,058.14


Análisis de precios unitarios

Presupuesto AZUCENAS
Subpresupuesto 001 Estructuras Fecha presupuesto 12/5/2017

Partida 05.01.01.01 Acero de refuerzo para cisterna fy= 4200 kg/cm2 grado 60

Rendimiento kg/DIA MO. 250.0000 EQ. 250.0000 Costo unitario directo por : kg 3.73

Código Descripción Recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Materiales
0204030006 Acero de refuerzo fy=4200 kg/cm2 grado 60 kg 1.05 2.24 2.35
0293010004 Alambre Nº 16 kg 0.06 3.26 0.20
0293010005 Separador para malla 06,08 y 10 cm mll 0.001 200.00 0.20
2.75
Mano de Obra
Capataz hh 0.10 0.00 24.12 0.08
Operario hh 1.00 0.03 20.10 0.64
Peón hh 0.50 0.02 14.85 0.24
Herramientas Manuales % 0.03 0.96 0.03
0.99

Partida 05.01.01.02 Encofrado para cisterna

Rendimiento m2/DIA MO. EQ. Costo unitario directo por : m2 28.00

Código Descripción Recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.

Subcontratos
0405030006 Sc encofrado MO m2 1.00 14.00 14.00
Sc encofrado Materiales m2 1.00 14.00 14.00
28.00

Partida 05.01.02.03 Concreto Viga de Cimentación f'c=210 kg/cm2

Rendimiento m3/DIA MO. 25.0000 EQ. 25.0000 Costo unitario directo por : m3 263.28

Código Descripción Recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Materiales
0207010014 Grava TMN 1/2" m3 0.65 25.42 16.53
0207020004 Arena Gruesa m3 0.65 16.95 11.02
0213010008 Cemento Tipo MS (42.5 kg) bol 8.50 18.47 157.03
0222170002 Plastiment HE 98 cil 0.007 974.60 6.82
0222180002 ADITIVO CURADOR cil 0.004 432.21 1.73
0222240001 Fibra de polipropileno bol 1.00 16.95 16.95
210.08
Subcontratos
Capataz hh 0.10 0.03 24.12 0.77
Operario hh 2.00 0.64 20.10 12.86
Peón hh 8.00 2.56 14.85 38.02
Herramientas Manuales % 0.03 51.65 1.55
53.20
Cantidad Metrado Total en Kg
Acero de refuerzo Columnas 1.05 301.81 316.90 Capataz Columnas
Placas 1.05 928.62 975.05 Placas
Muros 1.05 1,597.15 1677.01 Muros
Vigas 1.05 3,645.82 3828.11 Vigas
Losa Maciza 1.05 592.35 621.97 Losa Maciza
Losas Aligeradas 1.05 984.44 1033.66 Losas Aligera
Escalera 1.05 141.61 148.69 Escalera
Columnetas 1.05 128.05 134.45 Precio por Kg Total S/. Columnetas
Total en kg 8735.84 2.24 S/ 19,568.29

Cantidad Metrado Total en Kg


Alambre N°16 Columnas 0.06 301.81 18.11 Operario Columnas
Placas 0.06 928.62 55.72 Placas
Muros 0.06 1,597.15 95.83 Muros
Vigas 0.06 3,645.82 218.75 Vigas
Losa Maciza 0.06 592.35 35.54 Losa Maciza
Losas Aligeradas 0.06 984.44 59.07 Losas Aligera
Escalera 0.06 141.61 8.50 Escalera
Columnetas 0.06 128.05 7.68 Precio por Kg Total S/. Columnetas
Total en kg 499.19 3.26 S/ 1,627.36

Cantidad Metrado Total en mll


Separador para Malla Columnas 0.001 301.81 0.30 Peón Columnas
Placas 0.001 928.62 0.93 Placas
Muros 0.001 1,597.15 1.60 Muros
Vigas 0.001 3,645.82 3.65 Vigas
Losa Maciza 0.001 592.35 0.59 Losa Maciza
Losas Aligeradas 0.001 984.44 0.98 Losas Aligera
Escalera 0.001 141.61 0.14 Escalera
Columnetas 0.001 128.05 0.13 Precio por mll Total S/. Columnetas
Total en mll 8.32 200 S/ 1,663.97
Herramientas Manuales
Cantidad Metrado Total en hh
0.0032 301.81 0.97
0.0032 928.62 2.97
0.0032 1,597.15 5.11
0.0032 3,645.82 11.67
0.0032 592.35 1.90
0.0032 984.44 3.15
0.0032 141.61 0.45
0.0032 128.05 0.41 Precio por hh Total S/.
Total en hh 26.62 24.12 S/ 642.16

Cantidad Metrado Total en hh


0.032 301.81 9.66
0.032 928.62 29.72
0.032 1,597.15 51.11
0.032 3,645.82 116.67
0.032 592.35 18.96
0.032 984.44 31.50
0.032 141.61 4.53
0.032 128.05 4.10 Precio por hh Total S/.
Total en hh 266.24 20.1 S/ 5,351.33

Cantidad Metrado Total en hh


0.016 301.81 4.83
0.016 928.62 14.86
0.016 1,597.15 25.55
0.016 3,645.82 58.33
0.016 592.35 9.48
0.016 984.44 15.75
0.016 141.61 2.27
0.016 128.05 2.05 Precio por hh Total S/.
Total en hh 133.12 14.85 S/ 1,976.80
Total en
Cantidad Total MO herramientas
0.03 7,970.28 S/ 239.11
Cantidad Metrado Total en m2
SC Encofrado MO Columnas 1 40.08 40.08 SC Encofrado Materiales
Placas 1 100.93 100.93
Muros 1 69.06 69.06
Vigas 1 111.99 111.99
Losa Maciza 1 32.58 32.58
Losas Aligeradas 1 208.44 208.44
Escalera 1 12.01 12.01
Columnetas 1 17.31 17.31 Precio por m2 Total S/.
Total en kg 592.40 14 S/ 8,293.60
Cantidad Metrado Total en hh
Columnas 1 40.08 40.08
Placas 1 100.93 100.93
Muros 1 69.06 69.06
Vigas 1 111.99 111.99
Losa Maciza 1 32.58 32.58
Losas Aligera 1 208.44 208.44
Escalera 1 12.01 12.01
Columnetas 1 17.31 17.31 Precio por m2 Total S/.
Total en hh 592.40 14 S/ 8,293.60
Cantidad Metrado Total en m3
Grava TMN 1/2" Columnas 0.65 6.81 4.43
Placas 0.65 13.39 8.70
Muros 0.65 14.44 9.39
Vigas 0.65 19.14 12.44
Losa Maciza 0.65 6.71 4.36
Losas Aligeradas 0.65 17.91 11.64
Escalera 0.65 1.93 1.25
Columnetas 0.65 0.96 0.62 Precio por m3 Total S/.
Total en kg 52.84 S/ 25.42 S/ 1,343.35

Cantidad Metrado Total en m3


Arena Gruesa Columnas 0.65 6.81 4.43
Placas 0.65 13.39 8.70
Muros 0.65 14.44 9.39
Vigas 0.65 19.14 12.44
Losa Maciza 0.65 6.71 4.36
Losas Aligeradas 0.65 17.91 11.64
Escalera 0.65 1.93 1.25
Columnetas 0.65 0.96 0.62 Precio por m3 Total S/.
Total en kg 52.84 S/ 16.95 S/ 895.57

Cantidad Metrado Total en bolsas


Cemento tipo MS Columnas 8.5 6.81 57.89
Placas 8.5 13.39 113.82
Muros 8.5 14.44 122.74
Vigas 8.5 19.14 162.69
Losa Maciza 8.5 6.71 57.04
Losas Aligeradas 8.5 17.91 152.24
Escalera 8.5 1.93 16.41
Columnetas 8.5 0.96 8.16 Precio por bolsas Total S/.
Total en mll 690.97 S/ 18.47 S/ 12,765.29
Cantidad Metrado Total en hh
Capataz Columnas 0.032 6.81 0.22
Placas 0.032 13.39 0.43
Muros 0.032 14.44 0.46
Vigas 0.032 19.14 0.61
Losa Maciza 0.032 6.71 0.21
Losas Aligeradas 0.032 17.91 0.57
Escalera 0.032 1.93 0.06
Columnetas 0.032 0.96 0.03 Precio por hh Total S/.
Total en hh 2.60 S/ 24.12 S/ 62.74

Cantidad Metrado Total en hh


Peón Columnas 2.56 6.81 17.43
Placas 2.56 13.39 34.28
Muros 2.56 14.44 36.97
Vigas 2.56 19.14 49.00
Losa Maciza 2.56 6.71 17.18
Losas Aligeradas 2.56 17.91 45.85

Escalera 2.56 1.93 4.94


Columnetas 2.56 0.96 2.46 Precio por hh Total S/.
Total en hh 208.10 S/ 14.85 S/ 3,090.32
Cantidad Metrado Total en cil
Plastiment HE 98 Columnas 0.007 6.81 0.05
Placas 0.007 13.39 0.09
Muros 0.007 14.44 0.10
Vigas 0.007 19.14 0.13
Losa Maciza 0.007 6.71 0.05
Losas Aligera 0.007 17.91 0.13
Escalera 0.007 1.93 0.01
Columnetas 0.007 0.96 0.01 Precio por cil Total S/.
Total en cil 0.57 974.6 S/ 554.58

Cantidad Metrado Total en cil


Aditivo Curador Columnas 0.004 6.81 0.03
Placas 0.004 13.39 0.05
Muros 0.004 14.44 0.06
Vigas 0.004 19.14 0.08
Losa Maciza 0.004 6.71 0.03
Losas Aligera 0.004 17.91 0.07
Escalera 0.004 1.93 0.01
Columnetas 0.004 0.96 0.00 Precio por cil Total S/.
Total en cil 0.33 432.21 S/ 140.54

Cantidad Metrado Total en bolsa


Fibra de polopropileno Columnas 1 6.81 6.81
Placas 1 13.39 13.39
Muros 1 14.44 14.44
Vigas 1 19.14 19.14
Losa Maciza 1 6.71 6.71
Losas Aligera 1 17.91 17.91
Escalera 1 1.93 1.93
Columnetas 1 0.96 0.96 Precio por bolsa Total S/.
Total en bolsa 81.29 16.95 S/ 1,377.87
Cantidad Metrado Total en hh
operario Columnas 0.64 6.81 4.36
Placas 0.64 13.39 8.57
Muros 0.64 14.44 9.24
Vigas 0.64 19.14 12.25
Losa Maciza 0.64 6.71 4.29
Losas Aligera 0.64 17.91 11.46
Escalera 0.64 1.93 1.24
Columnetas 0.64 0.96 0.61 Precio por hh Total S/.
Total en hh 52.03 20.1 S/ 1,045.71

Total en
Cantidad Total MO herramientas
Herramientas Manuales 0.03 4,198.78 S/ 125.96
N° Descripción Parcial
1 Acero de refuerzo S/ 19,568.29
2 Alambre N°16 S/ 1,627.36
3 Separador para Malla S/ 1,663.97
4 Grava TMN 1/2" S/ 1,343.35
5 Arena Gruesa S/ 895.57
6 Cemento tipo MS S/ 12,765.29
7 Plastiment HE 98 S/ 554.58
8 Aditivo Curador S/ 140.54
9 Fibra de polopropileno S/ 1,377.87
10 Capataz S/ 704.90
11 Operario S/ 6,397.04
12 Peón S/ 5,067.12
13 Herramientas Manuales S/ 365.07
14 SC Encofrado MO S/ 8,293.60
15 SC Encofrado Materiales S/ 8,293.60
TOTAL S/ 69,058.14