HV TEST FOR 230 KV GIS
High Voltage level of injection is below

Highest voltage level 380 kv is calculated from 80% of factory Hi Voltage injection Level
304 kV is 80% of 380kv
170 kv is 1.2X Un/ rot 3
132 kv is Un/ rot 3

PD measurement curve at 132kv & 170 voltage level

converted by W eb2PDFConvert.com
Thursday, April 26, 2012
THE STORY OF TRANSFORMER STABILITY
The transformer stability test used to conform the CT connections for Differential and REF protection.
This test also used as a primary injection test for HV & LV side BCT's.

Example Transformer Data


Voltage Ratio : 230/ 34.5/13.8 kV
MVA Rating : 100/133
MVA
Vector Group: YNyn0(d5)
% Impedence : 12.24 @ 100 MVA BASE.

CALCULATION TO FIND THE PRIMARY AND SECONDARY CURRENT

PRIMARY SIDE : -

HV side full load current = Power / √3 x Voltage = 100×10^3 = 100000000 = 251 Amps
√3 × 230× 1000 399050

HV side Impedence = HV side Voltage = 230× 1000 = 916 Ohms


HV side full load current 251

HV side Impedence/ Phase = HV side Impedence X % Impedence = 916 X 12.24 = 112 Ohms
100

HV side current / Phase = Applied Voltage / HV side Impedence/ Phase

= 380 / 112 = 3.38 Amps

LV side SIDE : -

Transformer Ratio = 230/ 34.5 = 6.66

LV side current = 6.6666* 3.38 = 22.53 Amps

TEST -1 Three Phase Balanced Injection


Test connection: Three phase short circuit outside protected zone on 34.5kV side. Three phase
voltage injected on HV side = 380V

The balanced current can measured in the relay as follows

Relay - Primary Current


(A)

converted by W eb2PDFConvert.com
HV LV
3.326<0° 22.201<181.141
°
3.205<241.5 22.935<59.28°
°
3.288<121.5° 23.573<299.34°

Note : -

1. LV current 180 dec phase sifted from HV current.

2. No return current in Neutral

TEST -2 Three Phase Unbalanced condition


To make this condition open any one of CT FT fingers and short by insert the FT jack.

The Unbalanced current can measured in the relay as follows

Relay- Primary Current (A)


HV LV
0.00 21.985
0.00 22.226
0.00 22.265

TEST -3 Three Phase REF balanced condition


Test connection: Three phase short circuit outside protected zone on LV side. Single Phase
Injection was done one by one on the primary to check the stability and sensitivity.

1. No return current in Neutral


2. During single phase injection voltage will developed in the one phase Tertiary winding. If winding is
connected with ground a circulating current will flow through ground during stability.

TEST -4 Three Phase REF Unbalanced condition


Polarity of the neutral BCT was reversed at the protection panel to simulate the unstable condition.

TEST -5 BCT primary injection


PRIMARY INJECTION HV & LV WINDING :

Test connection: Three phase short circuit outside protected zone on LV side. Three phase voltage
injected on HV side = 380V
PRIMARY INJECTION TERTIARY WINDING :

Test connection : The shorting and grounding bar was removed from the Delta winding and current
was injected with Severker Test Kit and secondary currents were measured in the Transformer LCP
panel.

Thursday, April 5, 2012

TIMINGS & TIME SETTINGS

converted by W eb2PDFConvert.com
Newer Posts Home Older Posts

Subscribe to: Posts (Atom)

Blog Archive
► 2017 (3)
► 2016 (17)
► 2014 (3)
► 2013 (24)
▼ 2012 (46)
► December (3)
► October (2)
► September (4)
► August (5)
► July (7)
► June (1)
► May (3)
▼ April (3)
HV TEST FOR 230 KV GIS High Voltage level of inje...
THE STORY OF TRANSFORMER STABILITY The transformer...
TIMINGS & TIME SETTINGS
► March (3)
► February (6)
► January (9)
► 2011 (35)
► 2010 (13)

converted by W eb2PDFConvert.com
About Me
SIVAKUMAR
THIS IS SIVA T&C ENGINEER IN NCC LTD - SAUDI.
View my complete profile

converted by W eb2PDFConvert.com

You might also like