Professional Documents
Culture Documents
OF
BRIDGE DESIGN
MANUAL
PART 3
APPENDICIES TO PARTS 1 & 2 OF THE
BRIDGE DESIGN MANUAL
2013
Bridge Design Manual – 2013 Table of Contents
TABLE OF CONTENTS
2.15 Bending Moments and Shear Forces due to Vehicular live Loads .......... 2-32
2.16 Strut-and-Tie Modeling of Disturbed Regions ....................................... 2-32
2.17 Detailed Methods of Time-Dependent Analysis..................................... 2-33
2.18 References............................................................................................. 2-33
3 BRIDGE SCOUR REFERENCE ........................................................................... 3-1
3.1 Introduction................................................................................................. 3-1
3.2 Overview of Bridge Scour ........................................................................... 3-1
3.2.1 Bridge Scour Mechanism......................................................................... 3-1
3.2.2 Selection of Countermeasures.................................................................. 3-5
3.2.3 Countermeasures for Contraction Scour.................................................. 3-5
3.2.4 Countermeasures for Local Scour ........................................................... 3-5
LIST OF ILLUSTRATIONS
Chart 2-1: Flowchart for Planning and Design of Prestressed Concrete Bridges...... 2-8
Table 2-1: Typical Prestressed Concrete Bridge Structure and Standard Span Length
............................................................................................................. 2-10
Table 2-2: Ratio Girder Height to Span Length of Prestressed Concrete Bridge.... 2-12
Table 2-3: Example of Capacity of Crane Truck to Erect Girder ............................ 2-13
Table 3-1: Contents of HEC-23 Volume 2 ................................................................. 3-10
1.1 Introduction
This paper examines if the current design live load fits to the actual truck load in Ethiopia.
This paper looks at two aspects as follows;
• The 95thpercentile of truck weight distribution;
• The truck weight deemed to be the maximum.
The Design Vehicular Live Load of AASHTO LRFD Specification is derived from the
Ontario truck weight data. The 95th percentile of the data was 364 kN, which is a little
heavier than that of the Ethiopia data1.
1
Transportation Research Board: Calibration of Load Factors forLRFR Bridge Evaluation, 2001
2
FHWA/NHI: Reference Manual - LRFD Design of Highway Bridges, FHWA/NHI Course 13061, 2003.
The LRFD design live load “HL93” consists of the HS20 truck and a uniform load of 9.3 N
per running mm of lane, as shown in Figure 1-3.Several live load models were examined in
the development of LRFD live load model. The HL93 produces the best fit to the exclusion
loads as follows;
Data is presented as a ratio of a given force effect from the envelope of exclusion loads
divided by the corresponding force effect from each of the live load models considered.
Thus, a value of greater than 1.0
on the vertical axis indicates a situation in which the envelope of the exclusion vehicles
produce more force effect than the design model under consideration. Once again, a
horizontal line, intersecting the vertical axis at a value of 1.0, indicates a perfect match.
So it can be concluded that a long combination vehicle weighing 662 kN(EX 3-S3-5),
which is heavier than a truck deemed to be heaviest in Ethiopia (See Figure 1-7) can run
safely through a bridge designed to AASHTO LRFD Specification.
1.4 Conclusion
It can be concluded that the current design live load fits to the actual truck load in Ethiopia.
Chapter 2
Prestressed Concrete Bridge Bridge Design Manual – 2013
2.1 Introduction
The road network in Ethiopia provides the main form of transportation in Ethiopia. Hence,
the provision of a well planned, constructed, maintained and managed road network is
critical to the prosperity of the country through economic growth and food provision. As
part of the road infrastructure improvements, the ability to construct longer bridges will
greatly enhance access and provide viable alternative routes to reduce travel times.
The design of longer bridge implies the constructionprestressed concrete bridges but
currently there is limited experience in the country for the design and construction of these
types of bridges. For this to be a reality, it will require active support by government to
introduce these types of bridges and to build capacity in their design and construction.
The benefits of introducing prestressed concrete bridgesare as follows:
• Pre-tensioned beam
o Improve quality control within factory conditions which promotes improved
durability for the life of the structure.
o Reduction of site activities in relation to casting of superstructures.
• Post-tensioned beams
o Spans up to 50m can generally be readily achieved.
This chapterprovides guidelines for the planning, design and construction of prestressed
concrete bridges.
It should also be noted that steel member bridges also can be considered for longer bridges.
However, steel has to be imported and is very costly. Therefore, thelikelihood of
constructing steel bridges is low.
• Economy
Structural types, span lengths, and material should be selected with due consideration of
projected costs. Alternative plans of equal safety and serviceability shall be prepared for
comparison with a reinforced concrete bridge. In particular in Ethiopia, regional factors,
availability of materials, equipment and the skill of contractor should also be considered.
• Constructability
Because of the lack of experience in Ethiopia, constructability should be carefully
considered. There are several construction methods for prestressed concrete bridge such as;
o Erection of precast beam (crane erection);
o Erection beam method;
o Stationary false work method (all stage method);
o Cantilever method;
o Traveling false work method;
o Incremental launching method.
Constructability directly depends on construction method. Bridges should be designed to
match the capabilities of local contractors.
• Span length
Span length should be the first thing to consider. Dependent on the standard span length,
several types of bridge are selected and compared with each other in terms of economy,
constructability and maintainability.
• Erection method
The most important condition for the selection of the bridge type is the erection
methodwhich will be dependent on the outcome of the site investigation. Other factors
relevant to Ethiopia that will influence the selection of the erection method will be the
availability of materials and equipment; and the skills of Contactor.
• Others
Other factors which will affect the selection of a suitable structure would befactors such as
alignment, clearance and speed of construction.
Table 2-2: Typical Prestressed Concrete Bridge Structure and Standard Span Length
Span Length
Construction
Classification Structural Type Girder Type
Method
20 40 60 80 100 140 180
Pre-
tentioned
Girder T-Girder Crane erection 18-24m
Precast
Girder
Slab-Girder Crane erection 25-45m
erection beam
method
Post-
Simple
tentioning
Girder
Girder T-Girder Crane erection 20-45m
Bridge
erection beam
method
Table 2-3: Ratio Girder Height to Span Length of Prestressed Concrete Bridge
Ratio(girder
Classification Girder type
height/span)
Slab-Girder 1/14-1/24
Pretentioned
Girder
T-Girder 1/18-1/20
Precast
Girder
Post Slab-Girder 1/23-1/26
Simple Girder
Tentioning
Bridge
Girder T-Girder 1/13-1/18
Box-Girder 1/17-1/20
Cast in place Girder
Continuous hollow Slab 1/20
Box-Girder 1/15-1/20
Continuous
Cast in place Girder
Girder Bridge
Continuous hollow Slab 1/22
Two bridge types are identified as the types most sutiable for construction in the Ethiopian
environment:
2.4 Materials
2.4.1 Concrete
The following materials are required for concrete:
• Cement complying with the requirements of AASHTO M 85. (specific surface,
consolidation time, restriction on detrimental matter, etc.)
• Clean water free from oil, acid, chloride, organic or other deleterious matter.
• Clean, hard sand free from lumps of clay, organic or other deleterious matter.
• Hard, angular, field or quarry stones of such quality that they will not disintegrate
on exposure to water or weathering. The stones shall be free from overburden,
2.5.1 History
The principles of prestressing have been used for centuries. For example, wooden barrels
have always been made by tightening metal straps around barrel staves. In the making of
early wheels, the wooden spokes and rim were first held together by a hot metal tyre
which, upon cooling, became tensioned. This induced radial compression on the rim and
spokes. Other forms of mechanical, chemical and thermal prestressing have been attempted
or used with varying degrees of success.
The use of prestressing for concrete bridge members has been employed with great success
for over five decades. Concrete is strong in compression but relatively weak in tension.
Therefore, prestressing is used to control tensile stresses and to precompress the concrete.
This is analogous to providing the concrete with a “storage” capacity to resist loads which
would otherwise produce tension and cracking in the concrete.
Page 2-16 Ethiopian Roads Authority
Chapter 2
Bridge Design Manual – 2013 Prestressed Concrete Bridge
Another outstanding benefit of high strength (Grade 270) strand is relative cost. While
strand may cost nearly twice as much as mild reinforcement per pound, it provides over
four times the strength of mild reinforcement. Furthermore, prestressing provides a
significant enhancement in the behavior of reinforced concrete members. Thus, the
combination of high-quality, plant-cast concrete with prestressing using high strength steel,
results in the most economical bridge for most situations.
2.6 Flexure
The design of prestressed concrete members in flexure normally starts with determination
of the required prestressing level to satisfy service conditions, using “allowable stress
design” (ASD). All load stages that may be critical during the life of the structure from the
time prestressing is first applied are considered. This is followed by a strength check of the
entire member under the influence of factored loads, using “load factor design” (LFD).
ASD controls the design of most prestressed concrete bridges. Except for rare situations
where strand development length is inadequate, and for some adjacent box applications,
Page 2-22 Ethiopian Roads Authority
Chapter 2
Bridge Design Manual – 2013 Prestressed Concrete Bridge
LFD seldom requires the addition of reinforcement or other design changes. As a result,
the flexural strength of prestressed concrete bridges may be significantly larger than that
required. This gives prestressed concrete bridges greater reserve strength than either
structural steel or reinforced concrete and may be part of the reason that prestressed
concrete beams in bridge structures last longer. Another significant fact is that prestressed
concrete members are essentially “proof tested” during fabrication. When prestress strands
are released in the plant, the prestress level is the highest a member will ever experience
while the concrete strength is at its lowest.
Start
Calculate initial service moment stress in the top and bottom of the
prestressed girder
Calculate final service moment stress in the top and bottom of the
prestressed girder
OK
Check the nominal capacity versus the maximum Select a different girder size or
applied factored moment change strand arrangement
NG
OK
OK
End
Much research has been conducted in recent years on methods of predicting lt and ld.
Prediction formulas have been developed with no clear consensus among researchers. It
should be emphasized, however, that the impact of variability of the transfer length on
design of bridge beams is very small, and is limited to the 2 to 3 ft (0.6 to 1.0 m) at the end
of a member. The impact of variability of development length on bridge beams is also
small. An over-estimation of ld will not significantly increase the cost of beams. However,
ld may become a significant design parameter for some prestressed concrete members, such
as deck panels, which have very short spans, and piles, which may have their largest
bending moment at the pile/cap interface.
For further information, refer to PCI Bridge Manual Chapter8, Section 8.3
2.8 Shear
The design and analysis of precast, prestressed concrete bridge members for vertical shear
is presented in this section. Design and analysis for combined torsion and shear are not
included. The applicable sections in the Standard Specifications and the LRFD
Specifications are covered in detail. In addition, a simplified procedure given in the
Start
Determine bv and dv Eq
Calculate Vp
Calculate εx
Is assumed value of θ greater than the value NO Use the value last determined for
determined based on calculated εx ? θ
YES
NO
YE
End
For further information, refer to PCI Bridge Manual Chapter8, Section 8.4.
Where
Vu = factored shear force acting on the interface
ϕ = strength reduction factor
Vnh = nominal shear capacity of the interface
Design is carried out at various locations along the span, similar to vertical shear design.
Theoretical calculation of the shearing force acting on the interface at a given section is not
simple because the section does not behave as a linear elastic material near ultimate
capacity. If it did, the shear stress, horizontal or vertical, at any fiber in a cross-section
would be calculated from the familiar equation:
ொ
ܸ = (Eq. 2-2)
ூ
where
V = vertical shear force at the section
I = moment of inertia
b = section width at the fiber being considered
Q = first moment of the area above (or below) the fiber being considered
However, at ultimate conditions, the material is no longer elastic and the concrete may be
cracked at the section being considered. Further, the composite cross-section consists of
two different types of concrete with different properties. Therefore, application of the
above equation to design at ultimate, without modification, would yield questionable
results.
Loov and Patnaik (1994) determined that the above equation may yield adequate results if
both the cracked section moment of inertia and area moment of a transformed composite
section are used. The section would be transformed using the slab-to-beam modular ratio
used in flexural design by the allowable stress method.
However, this approach is still too complicated. It confuses the calculations at two limit
states: service and ultimate.
Kamel (1996) used equilibrium of forces to show that:
ܸ = (ௗ) (Eq. 2-3)
ೡ
where
V = factored vertical shear at the section in question
d = effective depth of the member
jd = distance between the tension and compression resultant stresses in the section.
This is the same distance as dv used in the LRFD Specifications.
bv = section width at the interface between the precast and the cast-in-place concrete. It is
important to understand that bv is not the web width.
Another important issue is which loads should be used to calculate Vu at a section. Neither
the Standard Specifications nor the LRFD Specifications give guidance in this regard.
While most designers would use all loads to compute Vu, a strong case can be made for
excluding the self-weight of the precast concrete member and the weight of the deck since
they are present prior to composite action taking effect. Some designers and agencies, such
as the Illinois Department of Transportation, use only the composite loads, which include
the superimposed dead loads (barriers, wearing surface, etc.) and the live loads.
Fortunately, the amount of reinforcement required, even with consideration of all loads, is
reasonable in practical applications.
To determine the shear capacity of the interface, the LRFD Specifications uses a form of
the well-established shear friction theory, while the Standard Specifications uses an
empirical approach based on several investigations, for example, Birkeland and Birkeland
(1966), Mast (1968), Kriz and Raths (1965) and Hofbeck, et al (1969).
The requirements of the Standard Specifications are stated in terms of vertical shear while
those in the LRFD Specifications are stated in terms of horizontal (interface) shear. This
difference in presentation has caused confusion among designers.
For further information, refer to PCI Bridge Manual Chapter8, Section 8.5.
Start
End
For further information, refer to PCI Bridge Manual Chapter8, Section 8.6.
secondary time-dependent stresses are introduced in the structure. These stresses must be
considered in the design of connections and detailing of the end regions of beams.
Finally, axial shortening of precast, prestressed bridge members must be considered when
designing bearings and expansion devices. This information is also helpful in assessing the
impact of superstructure restraint against shortening in jointless bridge systems.
For further information, refer to PCI Bridge Manual Chapter8 Section 8.7.
most locations, these cracks should be prevented because water and deicing chemicals may
penetrate the cracks and cause concrete staining and eventually structural deterioration of
the box beams from corrosion of reinforcement and subsequent spalling of the concrete
cover.
In addition, a transverse connection between box beams is necessary to provide effective
load transfer between beams. Without adequate transverse connection, live load cannot be
distributed across the bridge. Each beam in that case would have to be designed to resist
the full effect of a set of wheel loads.
For further information, refer to PCI Bridge Manual Chapter8, Section 8.9.
2.15 Bending Moments and Shear Forces due to Vehicular live Loads
In designing longitudinal members of bridges, the maximum bending moment and shear
force at each section along the span, are computed for live loads. The load position must be
determined to give the maximum values of shears and moments. The Standard
Specifications use the HS20 design truck while the LRFD Specifications use the HL-93
loading which is a combination of the HS20 design truck and a lane loading of 0.640 kip/ft.
Design for the fatigue limit state in the LRFD Specifications requires that a special design
truck be used. This section gives formulas which may be combined to get the maximum
bending moments and shear forces due to the above loading cases.
Readers are referred to the Standard Specifications for details about the effects of the
equivalent lane loading which must also be considered in design. It can be shown that this
equivalent lane loading may govern the design of spans longer than 144.5 ft(44 m) for
bending moment and 120 ft (36.6 m) for shear force.
For further information, refer to PCI Bridge Manual Chapter8 Section 8.11.
after concrete cracks, elastic methods cannot adequately predict stresses subsequent to
cracking.
For further information, refer to PCI Bridge Manual Chapter8 Section 8.12.
2.18 References
Precast/Prestressed Concrete Institute (PCI), Bridge Design Manual, 3rd Edition,
November 2011.
3.1 Introduction
This reference is a supplement to article 4.8, BDM. This reference refers to Evaluating
Scour at Bridges3(HEC-18) and Bridge Scour and Stream Instability Countermeasures:
Experience, Selection, and Design Guidance-Third Edition4(HEC-23), which are good
engineering practice in the U.S.
This reference consists of two parts. “3.2 Overview of Bridge Scour” provides a brief
overview of the bridge scour mechanism and the countermeasures for bridge scour. “3.3
Scour Depth Calculation”provides the calculation procedure of bridge scour depth and is
extracts from HEC-18.
3
Federal Highway Administration, Evaluating Scour at Bridge s- Fourth Edition, Hydraulic Engineering Circular No. 18,
2001, http://isddc.dot.gov/OLPFiles/FHWA/010590.pdf
4
Federal Highway Administration, Bridge Scour and Stream Instability Countermeasures: Experience, Selection, and
Design Guidance-Third Edition, Hydraulic Engineering Circular No. 23, 2009,
http://www.fhwa.dot.gov/engineering/hydraulics/pubs/09111/index.cfm
Figure3-1:Approach Embankments3
Typical clear-water scour situations include (1) coarse-bed material streams, (2) flat
gradientstreams during low flow, (3) local deposits of larger bed materials that are larger
than thebiggest fraction being transported by the flow (rock riprap is a special case of this
situation),(4) armored streambeds where the only locations that tractive forces are adequate
topenetrate the armor layer are at piers and/or abutments, and (5) vegetated channels
oroverbank areas.
During a flood event, bridges over streams with coarse-bed material are often subjected
toclear-water scour at low discharges, live-bed scour at the higher discharges and then
Clearwater scour at the lower discharges on the falling stages. Clear-water scour reaches
itsmaximum over a longer period of time than live-bed scour (Figure 3-3). This is
becauseclear-waterscour occurs mainly in coarse-bed material streams. In fact, local clear-
waterscour may not reach a maximum until after several floods. Maximum local clear-
water pierscour is about 10 percent greater than the equilibrium local live-bed pier scour.
Critical velocity equations with the reference particle size (D) equal to D50 are used
todetermine the velocity associated with the initiation of motion. They are used as an
indicatorfor clear-water or live-bed scour conditions. If the mean velocity (V) in the
upstream reach isequal to or less than the critical velocity (Vc) of the median diameter
(D50) of the bed material,then contraction and local scour will be clear-water scour. Also, if
the ratio of the shearvelocity of the flow to the fall velocity of the D50of the bed material
(V*/ω) is greater than 2,contraction and local scour may be clear-water. If the mean
velocity is greater than thecritical velocity of the median bed material size, live-bed scour
will occur. An equation todetermine the critical velocity for a given flow depth and size of
bed material is given in Chapter 5, HEC-18.
Contraction scour occurs when the flow area of a stream at flood stage is reduced, either
bya natural contraction of the stream channel or by a bridge. It also occurs when overbank
flowis forced back to the channel by roadway embankments at the approaches to a bridge.
Fromcontinuity, a decrease in flow area results in an increase in average velocity and bed
shearstress through the contraction. Hence, there is an increase in erosive forces in
thecontraction and more bed material is removed from the contracted reach than is
transportedinto the reach. This increase in transport of bed material from the reach lowers
the naturalbed elevation. As the bed elevation is lowered, the flow area increases and, in
the riverinesituation, the velocity and shear stress decrease until relative equilibrium is
reached; i.e., thequantity of bed material that is transported into the reach is equal to that
removed from thereach, or the bed shear stress is decreased to a value such that no
sediment is transportedout of the reach. Contraction scour, in a natural channel or at a
bridge crossing, involvesremoval of material from the bed across all or most of the channel
width. Methods toestimate live-bed and clear-water contraction scour are presented in
Chapter 5, HEC-18.
The basic mechanism causing local scour at piers or abutments is the formation of
vortices(known as the horseshoe vortex) at their base (Figure 3-2). The horseshoe vortex
resultsfrom the pileup of water on the upstream surface of the obstruction and
subsequentacceleration of the flow around the nose of the pier or abutment. The action of
the vortexremoves bed material from around the base of the obstruction. The transport rate
ofsediment away from the base region is greater than the transport rate into the region,
and,consequently, a scour hole develops. As the depth of scour increases, the strength of
thehorseshoe vortex is reduced, thereby reducing the transport rate from the base
region.Eventually, for live-bed local scour, equilibrium is reestablished between bed
material inflowand outflow and scouring ceases. For clear-water scour, scouring ceases
when the shearstress caused by the horseshoe vortex equals the critical shear stress of the
sedimentparticles at the bottom of the scour hole.
In addition to the horseshoe vortex around the base of a pier, there are vertical
vorticesdownstream of the pier called the wake vortex (Figure 3-2). Both the horseshoe
and wakevortices remove material from the pier base region. However, the intensity of
wake vorticesdiminishes rapidly as the distance downstream of the pier increases.
Therefore, immediatelydownstream of a long pier there is often deposition of material.
Factors which affect the magnitude of local scour depth at piers and abutments are
(1)velocity of the approach flow, (2) depth of flow, (3) width of the pier, (4) discharge
interceptedby the abutment and returned to the main channel at the abutment (in laboratory
flumes thisdischarge is a function of projected length of an abutment into the flow), (5)
length of the pierif skewed to flow, (6) size and gradation of bed material, (7) angle of
attack of the approachflow to a pier or abutment, (8) shape of a pier or abutment, (9) bed
configuration, and (10) iceformation or jams and debris.
For Froude Numbersቀ(௬)భ/మ ቁ ≤ 0.80 the recommended design equation for sizing rock
riprap for spill-trough and vertical wall abutments is in the form of the Isbash relationship:
ఱబ మ
௬
= (ௌ ିଵ) ቂ௬ ቃ (14.1)
ೞ
where:
D50 = median stone diameter, ft (m)
V = characteristic average velocity in the contracted section (explained below),
ft/s (m/s)
Ss = specific gravity of rock riprap
g = gravitational acceleration, 32.2 ft/s2 (9.81 m/s2)
y = depth of flow in the contracted bridge opening, ft (m)
K = 0.89 for a spill-through abutment
1.02 for a vertical wall abutment
where
K = 0.61 for spill-through abutments
K = 0.69 for vertical wall abutments
Guide banks (Figure 3-5) are earth or rock embankments placed at abutments. Flow
disturbances, suchas eddies and cross-flow, will be eliminated where a properly designed
and constructedguide bank is placed at a bridge abutment. Guide banks also protect the
highwayembankment, reduce local scour at the abutment and adjacent piers, and move
local scourto the upstream end of the guide bank (Design Guideline 15).
Local scour also occurs at abutments as a result of expanding flow downstream of
thebridge, especially for bridges on wide, wooded floodplains that have been cleared
forconstruction of the highway. Short guide banks extending downstream of the abutment
tothe tree line will move this scour away from the abutment, and the trees will retard
velocitiesso that flow redistribution can occur with minimal scour.
Piers: Three basic methods may be used to prevent damage from local scour at piers.
Thefirst method is to place the foundation of the structure at such a depth that the
structuralstability will not be at risk with maximum scour. This must be done on all new or
replacement bridges. The second method (for existing bridges) is to provideprotection at or
below the streambed to inhibit the development of a scour hole. The thirdmeasure is to
prevent erosive vortices from forming or to reduce their strength and intensity.
Streamlining the pier nose decreases flow separation at the face of the pier, reducing
thestrength of the horseshoe vortices which form at piers. Practical application of this
principleinvolves the use of rounded or circular shapes at the upstream and downstream
faces ofpiers in order to reduce the flow separation. However, flow direction can and does
changewith time and with stage on some streams. Piers oriented with flow direction at one
stage orat one point in time may be skewed with flow direction at another. Also, flow
directionchanges with the passage of bed forms. In general, piers should be aligned with
the mainchannel design flow direction and skew angles greater than 5 degrees should be
avoided.Where this is not possible, a single cylindrical pier or a row of cylindrical columns
willproduce a lesser depth of local scour.
The tendency of a row of columns to collect debris should be considered. Debris can
greatlyincrease scour depths. Webwalls have been used between columns to add to
structuralstrength and to reduce the tendency to collect debris. Webwalls should be
constructed atthe elevation of stream flood stages which carry floating debris and extended
to the elevationof the streambed. When installing a webwall as a countermeasure against
debris, thepotential for significantly increased scour depths should be considered if the
approach flowmight impinge on the wall at a high angle of attack.
Riprap (Figure 3-6) is commonly used to inhibit local scour at piers at existing bridges.
This practice isnot recommended as an adequate substitute for foundations or piling
located belowexpected scour depths for new or replacement bridges. It is recommended as
a retrofit or ameasure to reduce the risk where scour threatens the integrity of a pier
(Design Guideline11).
HEC-23 Volume 2 consists of design guidelines of some countermeasures (Table 3-1).