You are on page 1of 1

SHEET 1 OF 1 DATA SHEET NO.

EQUIPMENT DATA SHEET REV 0 1479-23 52 34-1/1


PROJECT TITLE : ECOLEAN PACKAGING
PACKAGED FIRE TUBE HOT PROJECT NO. : FND/1479
WATER BOILER LOCATION : LAHORE, PAKISTAN
DATA REV
DESCRIPTION UNIT UNIT
(IPS) (IPS) (SI) (SI)
1 IDENTIFICATION SYMBOL - HWB / 01 & 02 - HWB / 01 & 02
2 SPECIFICATIONS REFERENCE - 23 52 34 - 23 52 34
3 FND CALC. REF. NO. - - - -
4 QUANTITY Nos. 2 Nos. 2
5 ALTITUDE FT 705 m 215
6 HEATING CAPACITY MBH 1540 kW 450
7 HOT WATER ENTERING TEMPERATURE °F 120 °C 48.9
8 HOT WATER LEAVING TEMPERATURE °F 140 °C 60
9 WATER FLOW RATE USGPM 155 L/min 587
10 FUEL
NATURAL GAS / LPG (AIR MIX.) @ 885 BTU / CFT BY BY
11 • Cft/hr m3/hr
(7911 KCal/m3) MANUFACTURER MANUFACTURER
BY BY
12 • DIESEL OIL, @ 19,500 BTU/LB (10833 KCal/Kg) Lb/hr Kg/hr
MANUFACTURER MANUFACTURER
BY BY
13 ELECTRIC POWER HP kW
MANUFACTURER MANUFACTURER
14 POWER SUPPLY V/P/Hz 230/1/50 V/P/Hz 230/1/50

HOT WATER HOT WATER


15 APPLICATION - GENERATION FOR - GENERATION FOR
SPACE HEATING SPACE HEATING

16 MAXIMUM DESIGN PRESSURE Psig 100 Kpa 690


17 MAXIMUM DESIGN TEMPERATURE °F 250 °C 121.1
18 CONSTRUCTION
19 TYPE - FIRE TUBE - FIRE TUBE
20 REMARKS - - - -
21
22
23 NOTE:
24 1) BOILER SHALL BE DUAL FUEL {NATURAL GAS / RLNG & DIESEL}
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
REVISION 0
STATUS ISSUED FOR TENDER
DATE 22/12/2017
CHECKED/SIGN ADNAN HANIF
APPROVED FAHIM I. SIDDIQUI
THE INFORMATION ON THIS DATA SHEET IS CONFIDENTIAL TO FAHIM, NANJI & DESOUZA (PVT.) LTD.
AND SHALL NOT BE DISCLOSED TO A THIRD PARTY WITHOUT PRIOR WRITTEN PERMISSION