Government of Andhra Pradesh

Roads & Building Department

From To
Sri K. S. Raghava Rao, M.Tech., M.I.E., The Executive Engineer,
Deputy Executive Engineer (R&B), (R&B) Division,
East Sub – Division, Kakinada. Kakinada.

Letter No. Cyclone damages/VE Road/East/SA/2014, dated 03.01.2015.


Sir,
Sub: - Works(R&B) Division, Kakinada – Cyclone Damages- Cyclone damage repair
by stone dumping and rebuilding of damaged crust of Vakalapudi-Edatam
road for temporary restoration pertaining to East section, Kakinada--
Submitted – Regarding.

The Vakalapudi – Edatam road is an important State Highway in East Godavari


District, having a total length of 46 kms., connects several fishermen villages of Kakinada
Rural, U.Kothapalli and Thondangi mandals to the District Head Quarters and Port City of
Kakinada. This road starts at km.3.500 of Sarpavaram Junction to Vakalapudi light house
peta road (M.D.R.) and crosses Kakinada - Rajanagaram (ADB) road and Samalkota -
Uppada road.

This road is passing through number of fishermen villages upto Tuni and number
of R&B roads and heavy intensity of traffic prevails on the road as the public of all these
villages travels on this road to reach Kakinada City on one side and to reach Pilgrim centre at
Annavaram on other side. The Road stretch from Km.7/000 to 11/000 runs in very close
proximity (i.e., 1.00M to 2.00M) to the Sea i.e., Bay-of-Bengal. Due to "HUDHUD"
Cyclone during 11.10.2014 to 12-10-2014 the Road embankment is eroded including BT
carriageway in the stretch from km.7/300 to 10/6 in bits and necessary temporary restoration
works by stone dumping are being taken up in these stretches.

But due to ASOBA CYCLONE & depression/cyclone during 31.12.2014 to 01-01-


2015 , the stretch from km 6/800 to 7/300 which was not so badly effected during HUDHUD
was eroded badly including BT carriageway in bits and is in very dangerous condition. The
Restoration is very much essential for free flow of traffic. Tidal waves during high tides are
further eroding the embankment and there is every possibility of complete breaching of the
existing road and Sea waters may enter in to the nearby Fields and may cause extensive
damage to Ryths and residents, if protection is not taken up on war footing basis.

No dumping of stone work was taken up earlier in this stretch . Total protection is required
with dumping stones as proposed in the schematic drawing enclosed wih the estimate.

In view of the above, it is top most priority to take up the temporary restoration works
by filling scour portions as well as eroded portions on sea side with Jeddy Stone dumping
using 450mm to 600mm size HBG variety stone for a top width of at least 2.00M for
protecting the road embankment and Juddy stone dump in 1 in 3 slope on Sea side to
prevent the splashes of Tidal waves and erosion of embankment at the time of High tide.

Rebuilding the crust in the damaged portions/breach portions with GSB, WMM and
25 mm thick semi dense Bituminous concrete is also required for smooth flow of
traffic.Hence the following CDR estimates are herewith submitted for according sanction
at an early date .

1) Cyclone Damage Repairs by Stone dumping & rebuilding of crust to Vakalapudi -


Edatam Road from km. 6/8000 to 7/075 in East Godavari District. Estt. Rs. 50.00
Lakhs.

2) Cyclone Damage Repairs by Stone dumping & rebuilding of crust to Vakalapudi -


Edatam Road from km 7/075 to 7/300 in East Godavari District. Estt. Rs. 50.00
Lakhs.

Encl: Detailed estimate in triplicate.

Yours faithfully,

Deputy Executive Engineer


(R&B) East Sub-Divn., Kakinada.
Government of Andhra Pradesh
Roads & Building Department

From To
Sri M. Goving Mohan, B.Tech., The Dy. Executive Engineer,
Asst. Executive Engineer (R&B), (R&B) East Sub-Division,
East Section; Kakinada. Kakinada.

Letter No. /HUDHUD/VE Road/East/RA/2014, dated 18.10.2014.


Sir,
Sub: - Works(R&B) Division, Kakinada – HUDHUD cyclone- Cyclone damage repair
by stone dumping of Vakalapudi-Edatam road for temporary restoration
pertaining to East section, Kakinada-- Submitted – Regarding.

The Vakalapudi – Edatam road,is an important State Highway in East Godavari District,
having a total length of 46 kms., connects several fishermen villages of Kakinada Rural,
U.Kothapalli and Thondangi mandals to the District Head Quarters and Port City of Kakinada. This
road starts at km.3.500 of Sarpavaram Junction to Vakalapudi light house peta road (M.D.R.) and
crosses Kakinada - Rajanagaram (ADB) road and Samalkota - Uppada road.

This road is passing through number of fishermen villages upto Tuni and number of R&B
roads and heavy intensity of traffic prevails on the road as the public of all these villages travels on
this road to reach Kakinada City on one side and to reach Pilgrim centre at Annavaram on other side.
The Road stretch from Km.7/000 to 8/500 runs in very close proximity (i.e., 1.00M to 10.00M) to the
Sea i.e., Bay-of-Bengal. Due to "HUDHUD" Cyclone during 11.10.2014 to 12-10-2014 the Road
embankment is eroded Upto BT carriageway in the stretch from km.7/000 to 10/6 in bits and in very
dangerous condition. The Restoration is very much essential for free flow of traffic. Tidal waves
during high tides are further eroding the embankment and there is every possibility of breaching of the
existing road and Sea waters may enter in to the nearby Paddy Fields and may cause extensive damage
to Ryths and residents, if protection is not taken up on war footing basis.

In view of the above, it is top most priority to take up the temporary restoration works
proposed to fill the Scours with Jeddy Stone dumping using 450mm to 600mm size HBG
variety stone is proposed to a top width of 3.00M for protecting the road embankment on
Sea side and Juddy stone dump on Sea side to prevent the splashes of Tidal wave and
sand deposition at the time of High tide.

1) Cyclone Damage Repairs by Stone dumping to Vakalapudi - Edatam Road from km.
7/000 to 8/500 in East Godavari District. Estimate Rs. 50.00 Lakhs.

2) Cyclone Damage Repairs by Stone dumping to Vakalapudi - Edatam Road from km.
8/500 to 9/300 in East Godavari District. Estimate Rs. 50.00 Lakhs.
3) Cyclone Damage Repairs by Stone dumping to Vakalapudi - Edatam Road from km.
9/300 to 9/850 in East Godavari District. Estimate Rs. 50.00 Lakhs.

4) Cyclone Damage Repairs by Stone dumping to Vakalapudi - Edatam Road from km.
9/850 to 10/400 in East Godavari District. Estimate Rs. 50.00 Lakhs.

Encl: Detailed estimate in triplicate.

Yours faithfully,

Asst. Executive Engineer


(R&B) East Section., Kakinada.
Government of Andhra Pradesh
Roads & Building Department

From To
Sri K. Subba Raju., B.Tech., The Superintending Engineer,
Executive Engineer (R&B), (R&B) Circle,
(R&B) Division, Kakinada. Kakinada.

Letter No. Cyclone damages/VE Road/ATO/2014, dated 03.01.2015.


Sir,
Sub: - Works(R&B) Division, Kakinada – Cyclone Damages- Cyclone damage repair
by stone dumping and rebuilding of damaged crust of Vakalapudi-Edatam
road for temporary restoration pertaining to East section, Kakinada--
Submitted – Regarding.

The Vakalapudi – Edatam road is an important State Highway in East Godavari


District, having a total length of 46 kms., connects several fishermen villages of Kakinada
Rural, U.Kothapalli and Thondangi mandals to the District Head Quarters and Port City of
Kakinada. This road starts at km.3.500 of Sarpavaram Junction to Vakalapudi light house
peta road (M.D.R.) and crosses Kakinada - Rajanagaram (ADB) road and Samalkota -
Uppada road.

This road is passing through number of fishermen villages upto Tuni and number
of R&B roads and heavy intensity of traffic prevails on the road as the public of all these
villages travels on this road to reach Kakinada City on one side and to reach Pilgrim centre at
Annavaram on other side. The Road stretch from Km.7/000 to 11/000 runs in very close
proximity (i.e., 1.00M to 2.00M) to the Sea i.e., Bay-of-Bengal. Due to "HUDHUD"
Cyclone during 11.10.2014 to 12-10-2014 the Road embankment is eroded including BT
carriageway in the stretch from km.7/300 to 10/6 in bits and necessary temporary restoration
works by stone dumping are being taken up in these stretches.

But due to ASOBA CYCLONE & depression/cyclone during 31.12.2014 to 01-01-


2015 , the stretch from km 6/800 to 7/300 which was not so badly effected during HUDHUD
was eroded badly including BT carriageway in bits and is in very dangerous condition. The
Restoration is very much essential for free flow of traffic. Tidal waves during high tides are
further eroding the embankment and there is every possibility of complete breaching of the
existing road and Sea waters may enter in to the nearby Fields and may cause extensive
damage to Ryths and residents, if protection is not taken up on war footing basis.

No dumping of stone work was taken up earlier in this stretch . Total protection is required
with dumping stones as proposed in the schematic drawing enclosed wih the estimate.

In view of the above, it is top most priority to take up the temporary restoration works
by filling scour portions as well as eroded portions on sea side with Jeddy Stone dumping
using 450mm to 600mm size HBG variety stone for a top width of at least 2.00M for
protecting the road embankment and Juddy stone dump in 1 in 3 slope on Sea side to
prevent the splashes of Tidal waves and erosion of embankment at the time of High tide.

Rebuilding the crust in the damaged portions/breach portions with GSB, WMM and
25 mm thick semi dense Bituminous concrete is also required for smooth flow of
traffic.Hence the following CDR estimates are herewith submitted for according sanction
at an early date .

1) Cyclone Damage Repairs by Stone dumping & rebuilding of crust to Vakalapudi -


Edatam Road from km. 6/8000 to 7/075 in East Godavari District. Estt. Rs. 50.00
Lakhs.

2) Cyclone Damage Repairs by Stone dumping & rebuilding of crust to Vakalapudi -


Edatam Road from km 7/075 to 7/300 in East Godavari District. Estt. Rs. 50.00
Lakhs.

Encl: Detailed estimates (2No.s) in Duplicatee.

Yours faithfully,

Executive Engineer (R&B)


(R&B) Division., Kakinada.
Government of Andhra Pradesh
Roads & Building Department

From To
Sri K. S. Raghava Rao, M.Tech., M.I.E., The Executive Engineer,
Deputy Executive Engineer (R&B), (R&B) Division,
East Sub – Division, Kakinada. Kakinada.

Letter No. Cyclone damages/VE Road/East/SA/2014, dated 23.02.2015.


Sir,
Sub: - Works(R&B) Division, Kakinada – Cyclone Damages- Urgent repair by stone
dumping and rebuilding of damaged crust of Vakalapudi-Edatam road East
section, Kakinada-- Submitted – Regarding.

Ref: 1.T.O. Letter No. Cyclone Damages/VE Road/East/SA/2014, dated 03.01.2015


with enclosure of CDR estimates.

The Vakalapudi – Edatam road is an important State Highway in East Godavari


District, having a total length of 46 kms., connects several fishermen villages of Kakinada
Rural, U.Kothapalli and Thondangi mandals to the District Head Quarters and Port City of
Kakinada. This road starts at km.3.500 of Sarpavaram Junction to Vakalapudi light house
peta road (M.D.R.) and crosses Kakinada - Rajanagaram (ADB) road and Samalkota -
Uppada road.

This road is passing through number of fishermen villages upto Tuni and number
of R&B roads and heavy intensity of traffic prevails on the road as the public of all these
villages travels on this road to reach Kakinada City on one side and to reach Pilgrim centre at
Annavaram on other side. The Road stretch from Km.7/000 to 11/000 runs in very close
proximity (i.e., 1.00M to 2.00M) to the Sea i.e., Bay-of-Bengal. Due to "HUDHUD"
Cyclone during 11.10.2014 to 12-10-2014 the Road embankment is eroded including BT
carriageway in the stretch from km.7/400 to 10/6 in bits and necessary temporary restoration
works by stone dumping are being taken up in these stretches.

But due to ASOBA CYCLONE & depression/cyclone during 31.12.2014 to 01-01-


2015 , the stretch from km 6/900 to 7/400 which was not so badly affected during HUDHUD
was eroded badly including BT carriageway in bits and is in very dangerous condition. The
Restoration is very much essential for free flow of traffic. Tidal waves during high tides are
further eroding the embankment and there is every possibility of complete breaching of the
existing road and Sea waters may enter in to the nearby Fields and may cause extensive
damage to Ryths and residents, if protection is not taken up on war footing basis.

No dumping of stone work was taken up earlier in this stretch . Total protection is required
with dumping stones as proposed in the schematic drawing enclosed wih the estimate.
In view of the above, it is top most priority to take up the temporary restoration works
by filling scour portions as well as eroded portions on sea side with Jeddy Stone dumping
using 450mm to 600mm size HBG variety stone for a top width of at least 2.00M for
protecting the road embankment and Juddy stone dump in 1 in 3 slope on Sea side to
prevent the splashes of Tidal waves and erosion of embankment at the time of High tide.

Rebuilding the crust in the damaged portions/breach portions with GSB, WMM and
25 mm thick semi dense Bituminous concrete is also required for smooth flow of
traffic.Hence the following CDR estimates were already submitted in the reference 1st
cited for getting approval. But the same is pending in E-in-C(R&B), State Roads,
Hyderabd.
Now the road condition is very bad and half width of the road is completely damaged
and there is every possibility of breaching/thereby forming missing link to the road at any
time.
Hence the estimates are herewith submitted for getting approval under Corenet OR
grant even though the works are temporary restorations under CDR.

1) Urgent Repairs by Stone dumping & rebuilding of crust to Vakalapudi - Edatam Road
from km. 6/900 to 7/175 in East Godavari District. Estt. Rs. 50.00 Lakhs.

2) Urgent Repairs by Stone dumping & rebuilding of crust to Vakalapudi - Edatam Road
from km 7/175 to 7/400 in East Godavari District. Estt. Rs. 50.00 Lakhs.

Encl: Detailed estimate in triplicate.

Yours faithfully,

Deputy Executive Engineer


(R&B) East Sub-Divn., Kakinada.
Government of Andhra Pradesh
Roads & Building Department
From To
Sri K. Subba Raju., B.Tech., The Superintending Engineer,
Executive Engineer (R&B), (R&B) Circle,
(R&B) Division, Kakinada. Kakinada.

Letter No. Cyclone damages/VE Road/ATO/2014, dated 23.02.2015.

Sir,
Sub: - Works(R&B) Division, Kakinada – Cyclone Damages- Urgent repair by stone
dumping and rebuilding of damaged crust of Vakalapudi-Edatam road East
section, Kakinada-- Submitted – Regarding.

Ref: 1.T.O. Letter No. Cyclone damages/VE Road/ATO/2014, dated 03.02.2015.

. The Vakalapudi – Edatam road is an important State Highway in East Godavari


District, having a total length of 46 kms., connects several fishermen villages of Kakinada
Rural, U.Kothapalli and Thondangi mandals to the District Head Quarters and Port City of
Kakinada. This road starts at km.3.500 of Sarpavaram Junction to Vakalapudi light house
peta road (M.D.R.) and crosses Kakinada - Rajanagaram (ADB) road and Samalkota -
Uppada road.

This road is passing through number of fishermen villages upto Tuni and number
of R&B roads and heavy intensity of traffic prevails on the road as the public of all these
villages travels on this road to reach Kakinada City on one side and to reach Pilgrim centre at
Annavaram on other side. The Road stretch from Km.7/000 to 11/000 runs in very close
proximity (i.e., 1.00M to 2.00M) to the Sea i.e., Bay-of-Bengal. Due to "HUDHUD"
Cyclone during 11.10.2014 to 12-10-2014 the Road embankment is eroded including BT
carriageway in the stretch from km.7/400 to 10/6 in bits and necessary temporary restoration
works by stone dumping are being taken up in these stretches.

But due to ASOBA CYCLONE & depression/cyclone during 31.12.2014 to 01-01-


2015 , the stretch from km 6/900 to 7/400 which was not so badly affected during HUDHUD
was eroded badly including BT carriageway in bits and is in very dangerous condition. The
Restoration is very much essential for free flow of traffic. Tidal waves during high tides are
further eroding the embankment and there is every possibility of complete breaching of the
existing road and Sea waters may enter in to the nearby Fields and may cause extensive
damage to Ryths and residents, if protection is not taken up on war footing basis.

No dumping of stone work was taken up earlier in this stretch . Total protection is required
with dumping stones as proposed in the schematic drawing enclosed wih the estimate.

In view of the above, it is top most priority to take up the temporary restoration works
by filling scour portions as well as eroded portions on sea side with Jeddy Stone dumping
using 450mm to 600mm size HBG variety stone for a top width of at least 2.00M for
protecting the road embankment and Juddy stone dump in 1 in 3 slope on Sea side to
prevent the splashes of Tidal waves and erosion of embankment at the time of High tide.

Rebuilding the crust in the damaged portions/breach portions with GSB, WMM and
25 mm thick semi dense Bituminous concrete is also required for smooth flow of
traffic.Hence the following CDR estimates were already submitted in the reference 1 st
cited for getting approval. But the same is pending in E-in-C(R&B), State Roads,
Hyderabd.
Now the road condition is very bad and half width of the road is completely damaged
and there is every possibility of breaching/thereby forming missing link to the road at any
time.
Hence the estimates are herewith submitted for getting approval under Corenet OR
grant even though the works are temporary restorations under CDR.

1) Urgent Repairs by Stone dumping & rebuilding of crust to Vakalapudi - Edatam Road
from km. 6/900 to 7/175 in East Godavari District. Estt. Rs. 50.00 Lakhs.

2) Urgent Repairs by Stone dumping & rebuilding of crust to Vakalapudi - Edatam Road
from km 7/175 to 7/400 in East Godavari District. Estt. Rs. 50.00 Lakhs.

Encl: Detailed estimate in Duplicate.

Yours faithfully,

Executive Engineer (R&B)


(R&B) Division. Kakinada.
Government of Andhra Pradesh
Roads & Building Department

From To
Sri K. S. Raghava Rao, M.Tech., M.I.E., The Executive Engineer,
Deputy Executive Engineer (R&B), (R&B) Division,
East Sub – Division, Kakinada. Kakinada.

Letter No. Urgent repairs/VE Road/East/SA/2014, dated 04.03.2015.


Sir,
Sub: - Works(R&B) Division, Kakinada – Cyclone Damages- Urgent repair by stone
dumping of Vakalapudi-Edatam road East section, Kakinada-- Submitted –
Regarding.

Ref: 1.T.O. Letter No. Cyclone Damages/VE Road/East/SA/2014, dated 03.01.2015


with enclosure of CDR estimates.

The Vakalapudi – Edatam road is an important State Highway in East Godavari


District, having a total length of 46 kms., connects several fishermen villages of Kakinada
Rural, U.Kothapalli and Thondangi mandals to the District Head Quarters and Port City of
Kakinada. This road starts at km.3.500 of Sarpavaram Junction to Vakalapudi light house
peta road (M.D.R.) and crosses Kakinada - Rajanagaram (ADB) road and Samalkota -
Uppada road.

This road is passing through number of fishermen villages upto Tuni and number
of R&B roads and heavy intensity of traffic prevails on the road as the public of all these
villages travels on this road to reach Kakinada City on one side and to reach Pilgrim centre at
Annavaram on other side. The Road stretch from Km.7/000 to 11/000 runs in very close
proximity (i.e., 1.00M to 2.00M) to the Sea i.e., Bay-of-Bengal. Due to "HUDHUD"
Cyclone during 11.10.2014 to 12-10-2014 the Road embankment is eroded including BT
carriageway in the stretch from km.7/400 to 10/6 in bits and necessary temporary restoration
works by stone dumping are being taken up in these stretches.

But due to ASOBA CYCLONE & depression/cyclone during 31.12.2014 to 01-01-


2015 , the stretch from km 6/900 to 7/400 which was not so badly affected during HUDHUD
was eroded badly including BT carriageway in bits and is in very dangerous condition. The
Restoration is very much essential for free flow of traffic. Tidal waves during high tides are
further eroding the embankment and there is every possibility of complete breaching of the
existing road and Sea waters may enter in to the nearby Fields and may cause extensive
damage to Ryths and residents, if protection is not taken up on war footing basis.

No dumping of stone work was taken up earlier in this stretch . Total protection is required
with dumping stones as proposed in the schematic drawing enclosed wih the estimate.
In view of the above, it is top most priority to take up the temporary restoration works
by filling scour portions as well as eroded portions on sea side with Jeddy Stone dumping
using 450mm to 600mm size HBG variety stone for a top width of at least 3.00M for
protecting the road embankment and Juddy stone dump in 1 in 1.50 slope on Sea side to
prevent the splashes of Tidal waves and erosion of embankment at the time of High tide.

The following CDR estimates were already submitted in the reference 1st cited for
getting approval. But the same is pending in E-in-C(R&B), State Roads, Hyderabd.
Now the road condition is very bad and half width of the road is completely damaged
and there is every possibility of breaching/thereby forming missing link to the road at any
time.
Hence the estimate is herewith submitted for getting approval under Corenet OR grant
even though the works are temporary restorations under CDR.

1) Urgent Repairs by Stone dumping of Vakalapudi - Edatam Road from km. 6/900 to
7/400 in East Godavari District. Estt. Rs. 50.00 Lakhs.

Encl: Detailed estimate in triplicate.

Yours faithfully,

Deputy Executive Engineer


(R&B) East Sub-Divn., Kakinada.