RM#10 SITE REPORT STATUS NAMBI SUNDAR RAJ.

A
TECHNOSYS

SR.NO EQUIPMENT/BOARD NAME SIGNATURE/STATUS REMARKS


1 MCC C1
PT ---- CORRECTION NEEDED
CT 90% COMPLETED CORRECTION NEEDED
CB 98% COMPLETED CORRECTION NEEDED
BUSBAR COMPLETED
CONTROL TRAFO COMPLETED
BREAKER RELAY ----- REPORT PENDING
2 PDB 2-6
PT ---- CORRECTION NEEDED
CT COMPLETED
CB ----- CORRECTION NEEDED
BUSBAR COMPLETED
CONTROL TRAFO ----- CORRECTION NEEDED
BREAKER RELAY ----- REPORT PENDING
3 PDB 1-9
PT COMPLETED
CT COMPLETED
CB ----- CORRECTION NEEDED
BUSBAR COMPLETED
CONTROL TRAFO COMPLETED
BREAKER RELAY ----- REPORT PENDING
4 MLDB 13
PT COMPLETED
CT COMPLETED
BUSBAR COMPLETED
CONTROL TRAFO ---- CORRECTION NEEDED
5 MLDB 12
PT ---- CORRECTION NEEDED
CT COMPLETED
BUSBAR COMPLETED
CONTROL TRAFO ---- CORRECTION NEEDED
6 MLDB 11
PT ---- CORRECTION NEEDED
CT COMPLETED
BUSBAR COMPLETED
CONTROL TRAFO COMPLETED
7 MCC CC1
PT ---- CORRECTION NEEDED
CT COMPLETED
BUSBAR COMPLETED
CONTROL TRAFO COMPLETED
CB 80% COMPLETED CORRECTION NEEDED
BREAKER RELAY ----- REPORT PENDING
8 MCC CC2
PT ----
CT 20% COMPLETED CORRECTION NEEDED
BUSBAR COMPLETED
CONTROL TRAFO ----- CORRECTION NEEDED
CB 80% COMPLETED CORRECTION NEEDED
BREAKER RELAY ----- REPORT PENDING
9 LCSS 10B
PT ----- CORRECTION NEEDED
CT 98% COMPLETED CORRECTION NEEDED
BUSBAR COMPLETED
CONTROL TRAFO ----- CORRECTION NEEDED
CB 99% COMPLETED CORRECTION NEEDED
AUX REALY 98% COMPLETED MISSING VTT
BREAKER RELAY ----- REPORT PENDING
10 LCSS 10A
PT ---- CORRECTION NEEDED
CT ---- REPORT PENDING
BUSBAR COMPLETED
CONTROL TRAFO COMPLETED
CB COMPLETED
AUX REALY 98% COMPLETED PENDING VTT
BREAKER RELAY ----- REPORT PENDING
11 HVMCC-2(8.4M)
AUXILIARY RELAY COMPLETED
SURGE ARRESTER COMPLETED
CT CHAMBER COMPLETED
CT SECONDARY INJECTION COMPLETED
PT REPORT STATUS COMPLETED
CT GENERAL COMPLETED
PT GENERAL COMPLETED
BUSBAR COMPLETED
CT PRIMARY INJECTION 90% COMPLETED CORRECTION NEEDED
CB TESTING 94% COMPLETED CORRECTION NEEDED
12 HVMCC-2(8.4M)
AUXILIARY RELAY COMPLETED
SURGE ARRESTER COMPLETED
CT CHAMBER COMPLETED
CT SECONDARY INJECTION COMPLETED
PT REPORT STATUS COMPLETED
CT GENERAL COMPLETED
PT GENERAL COMPLETED
BUSBAR COMPLETED
CT PRIMARY INJECTION ----- REPORT PENDING
CB TESTING 94% COMPLETED CORRECTION NEEDED
13 CABLE TESTING COMPLETED
14 TRANSFORMER 98% COMPLETED
15 HVMCC- 1&2 SCHEME (ATS, ACS, ) ----- REPORT PENDING
16 NUMERICAL RELAY REPORT COMPLETED
17 SYNCH & SPAM RELAY REPORT COMPLETED
19 BUSDUCT COMPLETED