You are on page 1of 17

Cabinet

Cabinet Easergy T300IV1


Project : ............................................... Date : ....................................... Page : 1/17
Commissioning
SUBSTATION : .................................................................. Equipment serial N° : ...............................
Before starting below operations, cabinet must be installed as per installer guide NT00380-xx. T300 must be
powered off, battery taken out of cabinet, harting connectors to switchgear disconnected.

1/ PART I – T300 POWER OFF


1.1 – Identify installed modules
Informations are located at the front panel of equipments.

PS50 : (version at right side of PS50) (1) 24DC (PS50-24)…. 48DC (PS50-50)….

HU250 : (note modem type) modem in slot 1 (nearest HU250) ……….. modem in slot 2……….
Nota : Modem type written on green part of equipment (2)
Nota : 3G modem with an antena. RS232/RS485 modem with RJ45 connector (2)

SC150 : Count Number of installed SC150 : ………………

SC150 (LPVT or CAPACITOR) ) (3) SC01 ………. SC02 ………. SC03 ………. SC04 ………. Formatted: Font: Bold

(1) (2)) (23)

Formatted: Font: (Default) Arial

1.2 – Verification of AC supply and grounding

To ensure EMC and safety, cabinet must be grounded. A special stud of diameter 8 mm is provided under cabinet,
use a cross-section cable greater or equal to 16 mm²

- Check connection of enclodure enclosure to ground (cable > 16 mm²) (1) 


- Check connection to AC supply (without ground cable)  (Cut ground cable if connected)
- Check connection of PS50 0V and ground (2) 
- Check connection of PS50 to AC supply (3) 

- Check battery voltage (not connected) : Battery voltage 12V ………………………….


Battery voltage must be between X and Y V

(1) (2) (3)


Cabinet

Cabinet Easergy T300IV1


Project : ............................................... Date : ....................................... Page : 2/17
Commissioning
SUBSTATION : .................................................................. Equipment serial N° : ...............................
1.3 – Identification

Identify SC150 : (1) (Give a name, direction or number to each SC150 – put a label).
Nota : From HU250, 1st SC150 is SC01, 2nd SC150 is SC02 and so on.

Identify link from SC150 to harting connectors : (2) (Each cable has a label attateached) (3)

Identify cables from cubicle : (4) (Pin code and identify harting cable from cubicle according to SC150). Name
the cubicle

Way 1 : identify SC01 (5)  Pin code done (6)  Cubicle name……………….
Way 2 : identify SC02 (5)  Pin code done (6)  Cubicle name ……………….
Way 3 : identify SC03 (5)  Pin code done (6)  Cubicle name ……………….
Way 4 : identify SC04 (5)  Pin code done (6)  Cubicle name ……………….

(1) (2) (2) (3)

Way 4

Way 3

Way 2

Way 1

(4) (5) (6)


Cabinet Easergy T300IV1
Affaire : ............................................... Date : ....................................... Page : 3/17
Commissioning
POSTE : ............................................................................. N° Série équipement : ..............................
1.4 – CT connections
CT must be installed in on the cable of the MV cubicle.

1/ Insert CT cables in cabinet and identify cables with corresponding SC150, 1 for CT connected to SC01, 2 for
CT connected to SC02, and so on.

2/ Connect CT cable (4 or 6 x 1.5 mm wires) to (4 ou 6 x 1.5 mm) to 6 pts connectror (1) delivered with cabinet.
Nota : Depending on number of CTs, we will connect 4 (3 phaes phases CT) or 6 wires (3 phases CT and 1 zero
sequence CT) (2)

CT way 1 : identify 1  CT connected to 6pts connector 


CT way 2 : identify 2  CT connected to 6pts connector 
CT way 3 : identify 3  CT connected to 6pts connector 
CT way 4 : identify 4  CT connected to 6pts connector 

3/ Control of CT installation within cubicle :

- A/ Check correct mounting of CT (CTs marking : Up/Down)


- B/ Check grounding strip inside CT
- C/ Check CT continuity from SC150 connector
Nota 1 : Control A and B can be done on cubicle without cubicle lockgout (possibility to have a lookout on CTs) . In
others cases cubicle lockout is mandatory.
Nota 2 : Control C can be done without cubicle lockout using CAPTEST(*) accessory or multimeter. (3) Commented [EW-S1]: Consult us for availabity

CT way 1 : Control A  Control B  Control C 


CT way 2 : Control A  Control B  Control C 
CT way 3 : Control A  Control B  Control C 
CT way 4 : Control A  Control B  Control C 

4/ Screw CT connector in SC150 corresponding slot.


Nota : Extended connectors plate is available as an option. The plate can be mounted on right side of cabinet. If
option available in cabinet, connect 6pts connector to the plate. SC01 is at the bottom and SC04 is at the top. (4)

CT way 1 : Connected to SC01 


CT way 2 : Connected to SC02  (4)
CT way 3 : Connected to SC03 
CT way 4 : Connected to SC04 

(1) (2) (3)


Cabinet Easergy T300IV1
Affaire : ............................................... Date : ....................................... Page : 4/17
Commissioning
POSTE : ............................................................................. N° Série équipement : ..............................
1.5 – Control of MV voltage presence
SC150 can be connected to different types of voltage detectors.
For each type of detector, an adapter must be installed. (1)

1/ MV voltage type detection :


Ask your project manager for installed detector.

SC01 : LPVT LV  VDS  VPIS  PPACS  None 


SC02 : LPVT LV  VDS  VPIS  PPACS  None 
SC03 : LPVT LV  VDS  VPIS  PPACS  None 
SC04 : LPVT LV  VDS  VPIS  PPACS  None 

Nota 1 : For type LPVT and VT detectors one needs a LPVT SC150 type LPVT (voltage measuring)
Nota 2 : For type VDS, VPIS, VDS et PPACS one needs a type CAPA SC150 (voltage samplingmeasuring is less
acurate) Commented [EW-S2]: C’eszt quoi la différence entre voltager
sampling et voltage measuring ? Que veut-on dire ?
2/ Connecting voltage adapter :
- Adapter must be installed and connected to voltage sensor. (Normally adapter is installed in cubicle box).
- Connect an ethernet RJ45 cable (straight) between adapter and SC150 RJ45. (2)

(1) (1) (1) (2)


LPVT adapter

3/ Control of voltage detector :


Control of voltage detector can be done with CAPTEST(*) accessory. Commented [EW-S3]: Consult us for availability
CAPTEST device allow secure testing of live voltage detector.
Control available :
- sensors are correctly connected (no fuzzy contact).
- summation of three sensors voltage is correct
- sensors measurementss are consistant.

- SC01 : Check volatage presence with CAPTEST  ................................. Not applicable 


- SC02 : Check volatage presence with CAPTEST  ................................. Not applicable 
- SC03 : Check volatage presence with CAPTEST  ................................. Not applicable 
- SC04 : Check volatage presence with CAPTEST  ................................. Not applicable  Commented [EW-S4]: On ne peut pas demander à l’utilisateur
de faire ces opérations sous tension. Le commisionning se fait hors
tension pour des questions de sécurité. Je comprends que CAPTEST
1.6 – Verification of MV switch control polarity permet de faire hors et sous tension mais nous devons préconiser
The switches can be controlled by a 0V or +V polarity (24/48 V). officiellement que le hors tension !!!
The control polarity is selected by the connector position (1)

- Check switch control polarity +V….. 0 V…..


Cabinet Easergy T300IV1
Affaire : ............................................... Date : ....................................... Page : 5/17
Commissioning
POSTE : ............................................................................. N° Série équipement : ..............................
1.7 – PS50
Visual check of PS50 connectors

- Check 24/48V connector for harting (1) Conform…..


- Check 12V connector for HU250 power (2) Conform…..

- Note coding wheel value (3) up (défaut default 0) ..……..…… down (default défaut 1) ..……..…….

(1) (2) (3)

1.8 – HU250
- Check green jumper between HU250 and SC150 (1) ….
Nota 1 : 1 jumper per SC.
- Check 12V wired jumper between HU250 and SC150 (2)…..
Nota 1 : Check no crossing (red or black) wire on daisy chain.

(1) (2)
Cabinet Easergy T300IV1
Affaire : ............................................... Date : ....................................... Page : 6/17
Commissioning
POSTE : ............................................................................. N° Série équipement : ..............................
2/ PART II – T300 Energized

2.1 – Power On T300


Harting cable must be disconnected from T300
Turn on T300 (circuit-breaker), without battery. Wait 1 minute.

2.2 – PS50 Indicators


- Indicator 1 flashing green 
- Indicator 2 off 
- Indicator 3 solid red 
- Indicator 4 off 
- Indicator 5 solid green 
- Indicator 6 solid green 
- Indicator 7 solid green 
- Indicator 8 flashing orange 

2.3 – HU250 Indicators

Set HU250 in Local mode by pressing Local/Remote button


- Higher Lower indicator light in solid red (same on all SC) 
Set HU250 in Remote mode by pressing Local/Remote button
- Lower Higher indicator light in solid green (same on all SC) 

- Indicator 1.1 solid green 


- Indicator 1.2 off 
- Indicator 1.3 off in remote, solid green in local 
- Indicator 1.4 off 

- Indicator 1 solid green 


- Indicator 2 solid green 
- Indicator 3 solid green 
- Indicator 4 off 
- Indicator 5 solid red 
Cabinet Easergy T300IV1
Project : ............................................... Date : ....................................... Page : 7/17
Commissioning
SUBSTATION : .................................................................. Equipment serial N°: ................................
2.4 – SC150 Indicators

- SC01 - Indicator ON solid green  Indicator equipment fault off 


- SC02 - Indicator ON solid green  Indicator equipment fault off 
- SC03 - Indicator ON solid green  Indicator equipment fault off 
- SC04 - Indicator ON solid green  Indicator equipment fault off 

2.5 – Battery connection


- HU250- Battery indicator green  - PS50- Battery indicator off 

2.6 – PS50 Verification of voltage presence and battery presence outputs


Only necessary if outputs is used and wired.
Check with an ohmmeter.
Contact B open (battery connected)  Contact B close (battery disconnected) 
Contact C open (AC supply off)  Contact C close (AC supply on) 
Not applicable (outputs not connected) 

2.7 – LOCAL mode test using test plugs


Test plug is an accessory for sending simulated commands without cubicle lockout.

Set T300 in LOCAL mode. LOCAL indicator light in solid red on HU250 and all SC150.
Way 1 is at the back(wall side) and way 4 is at the front (door side).

- Connect a T300 test plug on way 1.


Check on SC01 (leftmost SC150) that switch position indicator stop flashing 
Send a open command (button OK+ON), check corresponding position indicator is green (vertical bar) 
Send a close command (button OK+OFF), check corresponding position indicator is red (slant bar) 

Repeat test for all installed SC150.


SC02 : Conform Yes  No  Non applicable 
SC03 : Conform Yes  No  Non applicable 
SC04 : Conform Yes  No  Non applicable 

Nota : Check wiring between SC150 and harting connector in case of failure and change indentification done in
chapter 1.3
Cabinet Easergy T300IV1
Project : ............................................... Date : ....................................... Page : 8/17
Commissioning
SUBSTATION : .................................................................. Equipment serial N° : ...............................
3/ PART III – CONNEXION to WEB SERVER
3.1 – Connection to WEB server
You do not need to change IP configuration on your PC to do this connection.
There is a DHCP server embedded in T300 for that automatically set your an NIC IP address once the physical
connection is made.

- Connect an Eethernet (straight or cross-wired) on PC and HU250 RJ45 connector (near green jumper).
- Start an internet browser (Google Chrome recommended)
- Type URL (https://192.168.0.254) in address bar and hit ‘Enter’. Pourquoi recommander Field Code Changed
- Choose your language in the pop up windows, then click on ‘OK’. Chrome (en plus c'est
- Type ‘Installer’ in user field pas dans la version
- Type ‘Installer1!’ in password field française) ?
- Click on ‘Open session’ Dung : Il n’y a que
chrome qui affiche par
Following web pages are from version 0.6.4-2932 défaut dans la boite de
choix de langue
l’anglais. Dans les autres
- Display ‘Substation’ page navigateurs le champ est
vide

3.2 – Verification of SC150 ordering


Before sending commands to cubicle, one must ascertain correct ordering of SC150.
SC01 should be in line with way 1, SC02 with way 2 and so on.
We will send simulated commands.

Cables from cubicle still remain disconnected.

- Set REMOTE mode on HU250


- Click on SC01, find ‘Simulation’ (1) zone.
- Click on ‘Close switch’ in ‘Simulation’ then ‘send command ‘ in pop up window.
- Check on SC01 that indicator light in solid red. (leftmost SC150) - Conform….
Nota : The indicator stay lighted for 30 seconds

- Click on ‘Open switch’ in ‘Simulation’ then ‘send command ‘ in pop up window.


- Check on SC01 that indicator light in solid green. (leftmost SC150) -Conform….

Repeat test on all installed SC150.


SC02 : Conform Yes  No  Not applicable 
SC03 : Conform Yes  No  Not applicable 
SC04 : Conform Yes  No  Not applicable 
Nota : In case of mismatch order, re-order modules.
Coffret Easergy T300IV1
Affaire : ............................................... Date : ....................................... Page : 9/17
Commissioning
POSTE : ............................................................................. N° Série équipement : ..............................
3.3 – MV switchgear control order real tests
Once SC150 are correctly ordered, we can test switch command control order (realactual).
Connect cubicle cables to cabinet.

Display ‘Substation’ page on web server (insure T300 is in REMOTE mode).

- Click on SC01 part and check if display is real actual state (1)
- Click on ‘Close switch’ (real) then ‘Send command’ in popup.
Check if real switch is closing opening and close position on SC01 front panel - Conform…..

- Click on ‘Open switch’ (real) then ‘Send command’ in popup.


Check if real switch is opening and open position on SC01 front panel - Conform…..
(1) webserver dislay must match real cubicle state

= = REAL SWITCH STATE

Repeat for all installed SC150.


SC02 : Conform Yes  No  Not applicable 
SC03 : Conform Yes  No  Not applicable 
SC04 : Conform Yes  No  Not applicable 
Nota : In case of failure, check wiring between cabinet and cubicle.

3.4 – Customization of web server


Optional part, customization of different pages using ‘Edit’ function.
A page is customizable if ‘Edit’ present. (1) (generally at the top right)
If ‘Edit’ present, click for displaying ‘Edition’ symbol. (2)
Click on ‘Edition’ symbol to show editable elements.

You can change :


- Drawing of busbar lines between SC150
- Change symbol for switch. (line sectionalizer, breaker, switchgear,…)
- Display direction of feeder
- Name the way. (example : Direction hospital)

(1) (2)
Cabinet Easergy T300IV1
Project : ............................................... Date : ....................................... Page : 10/17
Commissioning
SUBSTATION : .................................................................. Equipment serial N°: ................................
3.5 – Check informations from cubicle
Necessary if informations are in use and wired.
Informations connected to harting connectors

1/ Grouding cubicle. Not applicable 


Activate Grounding on way 1 cubicle and check ground indicator (red) on SC01 
Activate Grounding on way 2 cubicle and check ground indicator (red) on SC02 
Activate Grounding on way 3 cubicle and check ground indicator (red) on SC03 
Activate Grounding on way 4 cubicle and check ground indicator (red) on SC04 

2/ Verify under voltage detection relays. (RV10, VD23, RPTI….)


SC01 : Not applicable 
MV present on way 1, check red indicator on SC01 
MV abscent on way 1, check red indicator on SC01 

Repeat test on all installed SC150.


SC02 : Conform Yes  No  Not applicable 
SC03 : Conform Yes  No  Not applicable 
SC04 : Conform Yes  No  Not applicable 
Nota : The Indicator is orange if voltage not present on at least one phase.

3/ Check acquisition of measured current and/or voltage.


Display ‘Substation’ page.
Measured current from CT
Measured voltage from voltage sensors connected to voltage RJ45 of SC150.

SC01 Almost identical current measure on 3 phases 


SC01 Almost identical voltage measure on 3 phases 

Repeat test on all installed SC150.


SC02 : Conform Yes  No  Not applicable 
SC03 : Conform Yes  No  Not applicable 
SC04 : Conform Yes  No  Not applicable 
Nota : In case of wrong measurements, check wiring between cabinet and sensors (voltage and/or current).

3.6 – Check HU250 inputs/outputs


Necessary if information’s are used and wired.
Activate then dé-activate each input, check status on web page ‘Monitoring’Substation’.
Click on subview HU250 to show inputs/outputs status (2)

(1) (2)
Cabinet Easergy T300IV1
Project : ............................................... Date : ....................................... Page : 11/17
Commissioning
SUBSTATION : .................................................................. Equipment serial N°: ................................
- 4 digital inputs (free for use) (1)

DI1  - identification………………… DI2  - identification…………………

DI3  - identification………………… DI4  - identification…………………

- 4 dedicated digital inputs (2)


Voltage presence  Door open  Local  Remote 

- 1 analog input for PT100 temperature sensor (2 or 3 wires) (3)


Value is displayed in page ‘Monitoring/Substation’ PT100 

- 2 digital dry contact output (free for use). (4)


Activate outputs in web page ‘Monitoring/Substation/Subview HU’ DO1  DO2 

- 2 polarized analog output for external indicators (5)


Use ‘test indicator’ button to test outputs. Indicator 1  Indicator 2 

(1) (2) (3) (4) (5)

3.7 – Menu MAINTENANCE (web server)


Page CLOCK : Set equipment time 
Nota : Switch to manual mode to change date/time (Set Datetime)

Page IP CONFIG : (Note informations or modifications)


LAN network
- Address IP / Mask………………………………………………. DHCP Enable…. Disable…..…..

WAN network
- Address IP / Subnet Mask………………………………………… Fixed IP.. Automatic IP….

WIFI network
- Address IP / Mask……………………………………………… SSID………………………………………
- Passphrase…………………………………. DHCP Enable…. Disable…..
Nota : See maintenance document to change SSID

ROUTER - Address IP / Mask…………………………………………………………

- Router IP ……………………………………………………………………..

Page SOFTWARE : - Current firmware version (HU250 version)……………………………………


Nota : See maintenance document to upgrade HU250 firmware
Coffret Easergy T300IV1
Affaire : ............................................... Date : ....................................... Page : 12/17
Commisioning
POSTE : ............................................................................. N° Série équipement : ..............................
3.8 – Menu settings – HU250
Configuration of HU250 parameters :
- Protocol SCADA (slave) (IEC60870-5-101 et 104, DNP3).
- Protocol master (Modbus-master).
- Physical port (RS485 for PS50 link, modem box RS232/485, etc.).
- Synchronisation.

Nota : Check with project manager for parameters.

HU250 parameters Yes  No 

3.9 – Menu settings – PS01


Configuration of PS50 parameters :
- Supervise AC input
- Battery
- Supervise telecom 12V supply
- Backup supply

Nota : Check with project manager for parameters.

PS01 parameters Yes  No 

3.10 – Menu settings – SC150


Configuration of SC150 parameters :
- Current sensor. (CT)
- Switch controls
- Voltage or current Presence/Abscence.
- Fault detection and signalizations

Nota : Check with project manager for parameters.

SC01 parameters Yes  No 


SC02 parameters Yes  No 
SC03 parameters Yes  No 
SC04 parameters Yes  No 

Version of SC150 is displayed in the menu : (page settings/SCxx/settings)

Version SC01…………… Version SC02…………… Version SC03…………… Version SC04……………

3.11 – Check WIFI connection


In order to check wifi connection, your PC must have been configured.

Set T300 in LOCAL mode.


If your PC has been correctly configured, WIFI connection id automatic.
Start an internet browser, and type https://192.168.2.254 in address bar. Field Code Changed

Login page of T300 must appear

Conform : Yes  No  NA 
Coffret Easergy T300IV1
Affaire : ............................................... Date : ....................................... Page : 13/17
Commissioning
POSTE : ............................................................................. N° Série équipement : ..............................
3.12 Backup configuration
1/ / Easergy builder allow backup of entire configurationBackup configuration using webserver.
2/ Each SC150. Parameters could be backuped individually.

1/ Backup entire configuration :


- Start Easergy Builder
- Connect to T300
- Read configuration

Backup entire configuration : Yes  No  File name…………..………..

2/ Backup SC150 parameters :


- Create a folder (SC01) on PC.
- Start an internet browser, use URL http://192.168.0.1 for first SC150 Field Code Changed
- Right click on ‘Get : SC_Settings.xml’ and ‘save link as’ in filder SC01.

URL for 2nd SC150 : http://192.168.0.2 , and so on Field Code Changed

Repeat for all installed SC150.

SC01 : Not applicable  Backup SC_Settings.xml Yes  No  File name…………..


SC02 : Not applicable  Backup SC_Settings.xml Yes  No  File name…………..
SC03 : Not applicable  Backup SC_Settings.xml Yes  No  File name…………..
SC04 : Not applicable  Backup SC_Settings.xml Yes  No  File name………….. Commented [EW-S5]: Avec le V1 plus besoin d’Easergy
builder. Possible de backuper à travers le webserver
Coffret Easergy T300IV1
Affaire : ............................................... Date : ....................................... Page : 14/17
Commissioning
POSTE : ............................................................................. N° Série équipement : ..............................
3.13 – Check fault detection with current injection case CTs primary side
Cubicle must be locked out, earthed, and CT accessible.
Test fault detection by injecting current in CT.

Before testing, note below parameters, we’ll have to modify them.


Don’t forget to set these parameters to original values after testing.

Menu Settings/SC01/Fault indication/Fault confirmation mode : None… Voltage…. Current….


Menu Non_Directionnal_Fault_detection then setting group 1
Note PhPTOC inst 1 Enabled No….. Yes…..
Note PhPTOC inst 2 Enabled No….. Yes…..
Note PhPTOC inst 3 Enabled No….. Yes…..
For PhPTOC inst 3 note Threshold value A ……………..
Note EfPTOC inst 1 Enabled No….. Yes…..
Note EfPTOC inst 2 Enabled No….. Yes…..
Note EfPTOC inst 3 Enabled No….. Yes…..
Note for EfPTOC inst 3 Threshold value A ……………..

Modification before test :


Menu Settings/SC01/Fault indication/Fault confirmation mode : Select >> None
Menu Non_Directionnal_Fault_detection then setting group 1
For PhPTOC inst 1 and 2 > Set ‘Enable’ to No
For PhPTOC inst 3 Set ‘Enable’ to Yes and change ‘Threshold value A’ to 500 then SAVE
For EfPTOC inst 1 and 2 > Set ‘Enable’ to No
For EfPTOC inst 3 Set ‘Enable’ to Yes and change ‘Threshold value A’ to 90 then SAVE

Test were made with a high intensity current injection case 1 I (350A)
Adapt procedure according to the device used.

Before test check that CTs are correctly installed (TOP side on top)

Zero sequence fault detection test :


- Insert injection cable in 3 phases CTs ATTENTION same direction (1) Commented [EW-S6]: Voir compatibilié avec Offer Safety
- Increase injected current until 20A. SC150 must not detect any fault.
- Display page Monitoring/Substation in webserver.
- Check displayed current value (20A) for 3 phases. (2) Conforme Yes… No….
- Increase injected current until configured threshold. (90/3=30A)
Nota : threshold for I0 set at 90A, one must inject 90/3=30A to trigger zero sequence fault.
- When value is above threshold (30A), FPI indicator on SC150 is lighted (3) Conform Yes… No….
- Set injected current to 0
- Check creation of an event in ‘Events’ log file. (4)
- Reset fault with blue button on HU250, or click on ‘R4 on ‘Substation’ page.

(1) (2) (3) (4)

Interpretation of result for a threshold I0 of 90A :


Fault detected at 30A = conform
Fault detected at 45A = One CT is incorrectly connected.
Fault at 90A = Two CTs incorrectly connected, or one CT is upside down.
Coffret Easergy T300IV1
Affaire : ............................................... Date : ....................................... Page : 15/17
Commissioning
POSTE : ............................................................................. N° Série équipement : ..............................
Fault I MAX test :
Procedure to be adapted for equipment used.
In example equipment used can deliver current of 350A.

IMAX threshold set to 500A

- Insert injection cable multiple several time in 2 out of 3 CTs, and in opposite direction. (5)
Nota : Number of turn depends on available power of test set. In the example, there are 2 turn in 2 of CTs, in
oposite direction..
- Increase injected current to 30A. (60A for CTs with 2 turns)
- SC150 must not detect fault.
- Display ‘Monitoring/Substation’ page in web server for tested SC150.
- Check current value (60A) displayed for all phases. (6) Conform Yes… No….

- Increase injected current 250A. (500A for CTs with 2 turns)


- When value is above threshold FPI indicator on SC150 is lighted Conform Yes… No….
- Set injected current to 0
- Check creation of an event in ‘Events’ log file. (4)
- Reset fault with blue button on HU250, or click on ‘R4 on ‘Substation’ page.

(5) (6) (7)

Repeat test for all installed SC150.


SC01 : Zero sequence  IMAX fault  Non applicable 
SC02 : Zero sequence  IMAX fault  Non applicable 
SC03 : Zero sequence  IMAX fault  Non applicable 
SC04 : Zero sequence  IMAX fault  Non applicable 

Set original parameters value for modofied parameters.


SC01 : Set original parameters values 
SC02 : Set original parameters values 
SC03 : Set original parameters values 
SC04 : Set original parameters values 
Coffret Easergy T300 IV1
Page : 16/17
Commissioning

3.14 – Verification of fault detection with 3I/3U test case CTs secondary side

Repeat test on all installed SC150.

SC01 : Zero sequence  IMAX fault  Non applicable 


SC02 : Zero sequence  IMAX fault  Non applicable 
SC03 : Zero sequence  IMAX fault  Non applicable 
SC04 : Zero sequence  IMAX fault  Non applicable 

3.15 – Verification of fault detection with SIM test CTs secondary side
SIM test case is a Schneider Electric accessory

Repeat test on all installed SC150.

SC01 : Zero sequence  IMAX fault  Non applicable 


SC02 : Zero sequence  IMAX fault  Non applicable 
SC03 : Zero sequence  IMAX fault  Non applicable 
SC04 : Zero sequence  IMAX fault  Non applicable 

End of commissioning comments


Coffret Easergy T300 IV1
Page : 17/17
Commissioning

N0xxxx-FR-05 Edition : xxxxxxxx

Approbation Schneider Electric : Approbation Customer :


Name : Signature : Name : Signature :,