1 WEEK PLANT VISIT 2017

“REPORT ON SUMMER INTERNSHIP TRAINING


PROGRAMME "

"PROJECT : 1 WEEK PLANT VISIT ”

SUBMITTED BY:
ASHISH JAISWAL
USN : 1DS15ME019

DAYANANDA SAGAR COLLEGE OF ENGINEERING

DEPARTMENT OF MECHANICAL ENGINEERING

Shavige Malleshwara Hills, Kumaraswamy Layout, Bangalore-78

1|Page
1 WEEK PLANT VISIT 2017

ACKNOWLEDGEMENT

I would like to express my special thanks of gratitude to my guide


Mr. Dipansu Laskar (AGM ,HR), and Mr. Sourav Bagchi (Senior
Officer ,HR) who gave me the golden opportunity to do this
wonderful project on 1 WEEK INDUSTRIAL VISIT also
helped me in doing a lot of depth search in field and came to
know about so many new things. I are really thankful to them.
Secondly we would also like to thank my parents and friends who
helped me a lot in finalizing this project within the limited time
frame.

2|Page
1 WEEK PLANT VISIT 2017

ABOUT COMPANY:

INTRODUCTION:
A multi-billion-dollar conglomerate, JSW Group is a part of O.P. Jindal Group
and played a key role in India's growth story. Ranked among India's top business
houses, JSW's innovative and sustainable forays into the core sectors of Steel,
Energy, Cement and Infrastructure are helping build a new nation. The Group
continues to strive for excellence with its strengths, differentiated product mix,
state-of-the-art technology, excellence in execution and focus on sustainability.

With a diverse workforce of over 40,000 individuals, JSW is known to be the


“strategic first mover” to venture away from status quo, have the conviction to
make fundamental changes and drive operational excellence.

The flagship company of JSW Group - JSW Steel, is India’s leading primary and
integrated steel producer. It has a production capacity of 18 MTPA with plants

3|Page
1 WEEK PLANT VISIT 2017

located across six locations in South and West India, namely, Karnataka, Tamil
Nadu and Maharashtra.

Incorporated in 1994, JSW Energy is the power utility arm of the JSW Group. The
Company is engaged in power generation, power transmission, mining, power
trading and equipment manufacturing. JSW Energy operates 4,531 MW of power
generation capacity with the vision to achieve 10,000 MW by 2020. The
Company’s presence extends across several Indian states and includes stakes in
natural resource companies in South Africa.

JSW Group's new business foray- JSW Cement, envisions a self-reliant India. Since
its inception in 2009, JSW cement entered the market with a vision to ensure a
sustainable future for the country by producing eco-friendly cement. At
Vijayanagar in Karnataka, Nandyal in Andhra Pradesh and Dolvi in Maharashtra,
JSW Cement utilises slag cement from Group's steel plants to produce green
cement. It is currently upgrading production capacity to 30 MTPA by 2020.

Recently, JSW Group diversified into new age businesses like fund management.
JSW Ventures partners with ambitious and growth oriented entrepreneurs who
leverage technology to build long-term capital efficient businesses. The fund
supports ventures and ideas with JSW Group’s expertise in building scalable and
profitable businesses.

Meanwhile, a commitment to the nation, JSW Infrastructure is dedicated to


developing seaports and terminals, shipyards, port-based special economic zone
(SEZ), industrial clusters and last mile connectivity projects like road, rail, pipeline,
coastal shipping and inland water transport. JSW Infrastructure has plans to
create 200 MMT capacity by 2020 to become one of the India’s leading player in
the infrastructure sector.

4|Page
1 WEEK PLANT VISIT 2017

JSW STEEL PRODUCT

5|Page
1 WEEK PLANT VISIT 2017

1 WEEK PLANT VISIT FLOW CHART

Unique features:

6|Page
1 WEEK PLANT VISIT 2017

Regarded as the world’s Corex showpiece; it was the first Greenfield


project in India and among the first in the world to have successfully used
this technology to produce “green steel”
Houses India’s largest blast furnace and the widest hot strip mill
The only plant in India with pair-cross technology and twin-stand reversible
cold-rolling mill
The highest productivity steel plant in India, producing 800-plus tones per
person per annum
Recognized for its ‘zero-effluent discharge’ status; it reuses more than 95
per cent of process waste
Low carbon footprint as it recycles 96% of coke oven gas for power
generation
Uses sophisticated ambient air control infrastructure beyond and has
reduced gas flaring to lower levels.
Vision 2020:
 Establish state-of-the-art infrastructural facilities in India
 Create port capacity of 100 million tons per annum through
Greenfield and Brownfield expansions
 Ensure effectively mechanized operations
 Be the benchmark global company in the area of operations
 Be environment friendly
 Be socially sustainable

Milestones:

Founded in 1984

Commissioning of first and only UOE Pipe Mill manufacturing

7|Page
1 WEEK PLANT VISIT 2017

LSAW Pipes in Kosi Kalan, India with a capacity of 250,000 M.T


P.A, located about 1200 Kms from nearest west coast port of India

API Line Pipe production commences

First order for ONGC casing Pipe completed

Three major offshore projects awarded by ONGC under


international competitive
bidding - Italian and Japanese being L2 and L3 bidders

Seamless Pipes and Tubes Division commissioned at Nashik.


First Coating plant commissioned at Kosi Kalan

Received first export order

First Induction bending plant commissioned at Kosi Kalan

Commissioning of second LSAW pipe manufacturing facility as


100% export oriented unit using JCO forming process at
Nanakapaya, Mundra to meet the export market with a capacity of
300,000 MT per annum close to Port Mundra – The first major
private port on west coast of India.
Internal coating plant commissioned at Kosi Kalan Commissioning
of second Coating plant at Nanakapaya – Port Mundra

Concrete weight coating plant commissioned at Nanakapaya – Port


Mundra

8|Page
1 WEEK PLANT VISIT 2017

Commissioning of third Coating plant at Samaghogha, Mundra

Commissioning of third Pipe mill manufacturing LSAW Pipe using


JCO forming process in Samaghogha, Mundra with a capacity of
250,000 MT per annum.

Commissioning of fourth Pipe mill manufacturing HSAW (Spiral)


Pipe at Samaghogha, Mundra with capacity of 150,000 MT per
annum

Start up of Integrated Pipe Unit Ductile Iron Pipe manufacturing


plant of 200,000 capacity along with Blast Furnace of 250,000 MT
per annum capacity and a Coke Oven plant

Commissioning of fifth & sixth Pipe mill manufacturing HSAW


(Spiral) pipe at Bellary - Karnataka and Samaghogha-Mundra with a
combined capacity of 390,000 MT per annum. Second Induction
bending plant commissioned at Samaghogha, Mundra

Commissioning of seventh Pipe mill manufacturing LSAW using


JCO forming in Nanakapaya - Port Mundra with capacity of 300,000
MT per annum

Commissioning of 8th Pipe mill manufacturing HSAW (Spiral) pipe


at Kosi Kalan, Mathura, U.P. with capacity of 150,000 MT per
annum This mill is commissioned to cater to the water section with
capacity of 150,000 MT per annum This mill is commissioned to

9|Page
1 WEEK PLANT VISIT 2017

cater to the water sector

Raw Material Handling System:


10 | P a g e
1 WEEK PLANT VISIT 2017

Rated capacity: 6-7 million TPA


Raw materials handled: Iron ore lump and fines
Pellets
Limestone
Dolomite
Quartzite
Manganese ore
Non coking coal
Coke
Major units: 2 wagon tippler
3 stacker cum reclaimer
1 barrel reclaimer
Salient technical feature: Approximately 17 km long
Conveyor System

COKE OVEN:
11 | P a g e
1 WEEK PLANT VISIT 2017

Introduction:
A world class blast furnace operation demands the highest quality of raw
materials, operation, and operators. Coke is the most important raw material fed
into the blast furnace in terms of its effect on blast furnace operation and hot
metal quality. A high quality coke should be able to support a smooth descent of
the blast furnace burden with as little degradation as possible while providing the
lowest amount of impurities, highest thermal energy, highest metal reduction,
and optimum permeability for the flow of gaseous and molten products.
Introduction of high quality coke to a blast furnace will result in lower coke rate,
higher productivity and lower hot metal cost.

Coke Production:
The coke making process involves
carbonization of coal to high
temperatures (1300°C) in an oxygen
deficient atmosphere in order to
concentrate the carbon. The
commercial coke making process
can be broken down into two
categories: a) Recovery Coke
making and b) Non-Recovery Coke
making.

12 | P a g e
1 WEEK PLANT VISIT 2017

Pellet
Plant:
• CAPACITY
• 4.2 MILLION TONNE PER YEAR,
• RAW MATERIAL
• ORE FINES FROM JVSL MINES
• DRYERS EACH
• 2 NOS OF 4.6 M DIA 27.5M LONG, 225 TPH
• GRINDING
• BALL MILL (2 NO) 208 TPH
• MIXER
• LITTLE FORD MAKE 600 TPH
• BALLING DISCS
• 5 NOS , 7.5 M DIA
• INDURATION
• GRATE AREA -464 M2, 4 M WIDE CARS
• STACKER/RECLAIMIN
• 700 TPH / 1100 TPH
G
• < 0.2 GigACal/TONNE
• FUEL CONSUMPTION
• < 54 KWH/TONNE
• POWER CONSUMPTION
• < 100 mg/Nm3
• EMISSION
• < 80 microgram/nM3
• PARTICULATE

Rated capacity: 4.0 million TPA


Pellet size: 6 to 16 mm
Pelletization
Pelletization is the technological process designed to transform fines into 8 to 16
mm size balls with the help of balling disc or balling drum.
Three stages of pelletization process
1. Raw material preparation
2. Formation of green balls
3. Induration of green balls

Raw material

13 | P a g e
1 WEEK PLANT VISIT 2017

1. Iron ore fines


2. Limestone (Additive)
3. Bentonite (Binder)
4. Corex sludge

Sinter Plant:

Salient Features :

2
Sinter Machine Suction Area 204 m

Sinter Machine Width 3m

Sinter Machine Length 77 m

Side wall Height of Pallets 700 mm

Suction below Grate 160 mbar

14 | P a g e
1 WEEK PLANT VISIT 2017

3
Process Gas Volume 1.2 x 10 ^6 m /h

Combined Mixing and Nodulizing


Drum 4.2 m dia x 15 m length

Energy Consumption for Ignition


(Corex Gas) 15,000 Kcal /t of Gross Sinter

Sinter Cooler Type Annular Circular Pressure Cooler

2
Effective Cooling Area 202 m ; Diameter: 22.5 m

Waste Gas cleaning System Electrostatic Precipitators

Production (tpd) 6984 tonnes

Annual production 2.3 MTPA

Power Consumption < 35 Kwh/t

Gas Consumption < 15000 Kcal/t

The Sintering Process


• Sintering is an agglomeration process which produces strong and porous
lumps from a powdered uncompacted mass of iron ore with the application
of heat to the stage of incipient fusion.
• Necessary heat is supplied by the combustion of coke breeze.
• The process is performed on a travelling grate on which 500-600 mm thick
sinter mix consisting of iron ore, flux, coke breeze and industrial wastes
along with moisture are fed continuously.
The complete combustion of coke breeze, initiated in the top layer
produces a temperature of 1200-1300°C and is maintained continuously by
sucking air through the bed

15 | P a g e
1 WEEK PLANT VISIT 2017

• The suction of air makes the combustion zone travel through the bed
raising its temperature layer by layer to sintering temperature.
• Process completes when combustion zone reaches to the lowest layer of
the bed.
• Sinter cake is tipped from the grate in hot condition, broken, screened and
cooled to produce desired fraction.

Sintering Process
• Feed preparation
• Proportion of raw materials
• Moisture addition and mixing
• Layering on sintering machine
• Ignition of top layer
• Sintering- suction of air through bed
• Discharge of sinter from machine
• Cooling of sinter
• Screening of product

Raw Materials for Sintering


The source of iron
• The source of flux and
• The source of heat.
 In addition a large number of in plant wastes containing various quantities
of iron, flux and fuel values are also being included.
Sintering Reaction
• The sintering reaction starts with reduction of the hematite and formation
of the low melting liquid mono calcium ferrite (CaO.Fe2O3) at around
1200ºC by reaction with lime which absorbs silica and more of iron oxide.
• The melt so formed attacks the grain boundaries of hematite and the grains
dislodge into the melt forming CaO.2Fe2O3, 2FeO.SiO2, CaO.FeO.SiO2,
2CaO.Fe2O3, etc..

16 | P a g e
1 WEEK PLANT VISIT 2017

• With increase of temperature more and more hematite along with gangue
goes into solution resulting in more of slag bonded complex sinter structure
SFCA (silica-ferrite of calcium and aluminums).
• At basicity levels of more than 2 calcium ferrite and dicalcium silicate forms
and at lesser than 1.6, glassy silicate and secondary hematite and
magnetite forms.

Blast Furnace:

The purpose of a blast furnace is to chemically reduce and physically convert iron
oxides into liquid iron called "hot metal". The blast furnace is a huge, steel stack
lined with refractory brick, where iron ore, coke and limestone are dumped into
the top and preheated air is blown into the bottom. The raw materials require 6
to 8 hours to descend to the bottom of the furnace where they become the final
product of liquid slag and liquid iron. These liquid products are drained from the
furnace at regular intervals. The hot air that was blown into the bottom of the
furnace ascends to the top in 6 to 8 seconds after going through numerous

17 | P a g e
1 WEEK PLANT VISIT 2017

chemical reactions. Once a blast furnace is started it will continuously run for four
to ten years with only short stops to perform planned maintenance.
Iron oxides can come to the blast furnace plant in the form of raw ore, pellets or
sinter. The raw ore is removed from the earth and sized into pieces that range
from 0.5 to 1.5 inches. This ore is either Hematite (Fe2O3) or Magnetite (Fe3O4)
and the iron content ranges from 50% to 70%. This iron rich ore can be charged
directly into a blast furnace without any further processing. Iron ore that contains
a lower iron content must be processed or beneficiated to increase its iron
content. Pellets are produced from this lower iron content ore. This ore is crushed
and ground into a Powder so the waste material called gangue can be removed.
The remaining iron rich powder is rolled into balls and fired in a furnace to
produce strong, marble-sized pellets that contain 60% to 65% iron. Sinter is
produced from fine raw ore, small coke, sand-sized limestone and numerous
other steel plant waste materials that contain some iron. These fine materials are
proportioned to obtain desired product chemistry then mixed together. This raw
material mix is then placed on a sintering strand, which is similar to a steel
conveyor belt, where it is ignited by gas fired furnace and fused by the heat from
the coke fines into larger size pieces that are from 0.5 to 2.0 inches. The iron ore,
pellets and sinter then become the liquid iron
Produced in the blast furnace with any of their remaining impurities going to the
liquid slag
The coke is produced from a mixture of coals. The coal is crushed and ground into
a powder and then charged into an oven. As the oven is heated the coal is cooked
so most of the volatile matter such as oil and tar are removed. The cooked coal,
called coke, is removed from the oven after 18 to 24 hours of reaction time. The
coke is cooled and screened into pieces ranging from one inch to four inches. The
coke contains 90 to 93% carbon, some ash and sulfur but compared to raw coal is
very strong. The strong pieces of coke with a high energy value provide
permeability, heat and gases which are required to reduce and melt the iron ore,
pellets and sinter.
The final raw material in the iron making process in limestone, the limestone is
removed from the earth by blasting with explosives. It is then crushed and
screened to a size that ranges from 0.5 inch to 1.5 inch to become blast furnace
flux.

18 | P a g e
1 WEEK PLANT VISIT 2017

Since the limestone is melted to become the slag which removes sulfur and other
impurities, the blast furnace operator may blend the different stones to produce
the desired slag chemistry and create optimum slag properties such as a low
melting point and a high fluidity.
All of the raw materials are stored in an ore field and transferred to the stock
house before charging. Once these materials are charged into the furnace top,
they go through numerous chemical and physical reactions while descending to
the bottom of the furnace.

Salient Features

Capacity 2.7 MTPA

Production Avg. 7800 t/working day

Working Volume 3445 m³

Productivity (WV) 2026 thm/m³/day

Inner Volume (IV) 4019 m³

Productivity (IV) 1.94 thm/m³/day

Availability 98%

Tuyeres 36

Top Pressure 2.5 bar

Hot Blast temperature 1250 ºC

Tap holes 4

Coolers (Cast Iron & Copper) Staves Type

19 | P a g e
1 WEEK PLANT VISIT 2017

Top charging PW BLT Unit

Stoves 3 No.

SGP RASA Type

Stoves (combustion) Internal Combustion Type

Hearth bottom cooling Water Type

Direct Reduction Iron Plant :

DR plant will use 100% pellet & COREX gas for making DRI, which will be used in
Electric arc furnace & BOF as coolant.

The Basic design parameters of the facility are summarized as follows:


Operating mode Continuous
Operating hours per annum 8,000 hrs
Number of modules One

20 | P a g e
1 WEEK PLANT VISIT 2017

Export Corex gas available to DR plant 2, 80,000 NCMH


Annual rated production 1.2 MTPA of DRI
Design Feed mix (Pellet : lump ratio) 80 : 20
Product metallization 92 % (min)
Product Carbon content 1.0 % (min)
Major areas in the Plant

STEEL MELTING SHOP:

Rated capacity: 1.62 million TPA liquid steel


No. of units: 2
Heat size / capacity: 120 tonne
Tap-to-tap time: 45 min.
Major units: Hot metal desulfurising station
Hot metal mixer
Basic Oxygen Furnaces
Scrap Yard

21 | P a g e
1 WEEK PLANT VISIT 2017

Ladle preparation and handling bay


Ladle furnace
Gas cooling and cleaning plant
Water recirculation system
Salient Technical features: Pre-treatment hot metal.
Bottom stirring with insert gas in BOF
Suppressed combustion system of gas in BOF

WIRE ROD MILL:

ITEM Salient Featuers

Mill Type Single strand continous WRM

Mill Capacity 0.6 MTPA

Mill Speed 110 m/sec

Input Billet size 165 * 165 * 12000 mm

Product range 5.5 mm to 22 mm

22 | P a g e
1 WEEK PLANT VISIT 2017

Finished coil weight 2500 kg

Grade carbon steel upto 0.85% C and various alloy steels

Wire drawing , Fasteners,Welding electrode,Prestressed


Applications of end product
concrete wire , spring wire, Rope wire etc

Associates

Equipment suppliers Morgan U.S.A,Techint Italy

Consultants Korus Engg solutions Pvt Ltd

BAR MILL:

ITEM Salient Featuers

Mill Type Re Bar Mill

Mill Capacity 1.0 MTPA

Mill Speed 38 m/sec

Input Billet size 165 * 165 * 12000 mm

TMT 8mm to 40mm,Plain rounds 20mm to 63mm,RCS 40MM to 63mm,Equal


Product range
angles 50*50*5 to 90*90*9mm

23 | P a g e
1 WEEK PLANT VISIT 2017

Finished bundle weight 2000 to 5000 kg

Automation Level 2 process

Low good water cooling facilities to achieve desired microstructure as well as good
Metallurgical aspects mechanical properties.

Applications of end product Construction industry,Automotive,Forging industries etc.

Associates

Equipment suppliers Morgan U.S.A,Techint Italy

Consultants Korus Engg solutions Pvt Ltd

HOT STRIP MILL:

24 | P a g e
1 WEEK PLANT VISIT 2017

 Rated Capacity: 2.5 MTPA


 Can roll 1.6mm to 12mm thickness & up to a width of 1290mm
 Rolling all grades including Micro-alloy, Ferritic, LPG and Line pipe
 Automatic Gauge Control, Coil Box, X-ray Gauge, Profile Gauge, Roll
Bending, Advanced Automation System.

COLD ROLLING MILL:

The CRM i.e. Cold Rolling Mill project. As the name indicating rolling is done at a
normal temperature like room temperature is called cold rolling (CRM). There are
various types of CR Mills are available like 20 Hi Mill, 6 hi Mill, 4 Hi Mill, 2 Hi Mill &
Tandam Mill. The names indicating on the basis of how many rollers are used in
the mill. In Tandam mill, series of stands are installed and coil will pass through
the mills one direction and giving the desired thickness of the coils.
Raw material for CRM is Hot Rolled Coils; it is received from HSM2/ HSM-1. The
product of CRM is called CR Coils. In CRM2, the thickness of the products varies
from 0.30 mm to 3.00 as per requirements of the customer. The maximum wide
of the coil is 1950 mm. Normal weight of each coil shall be 25-30 MT. Maximum
speed of our line is 1450mpm
The CR Coils is the raw materials for Galvanizing (GP Line) and CRCA (Cold Rolled
Closed Annealing). The GP Coils is used for making GC sheets, GP sheets,

25 | P a g e
1 WEEK PLANT VISIT 2017

Insulation works, making house hold items etc. The CRCA sheet is using for mainly
automobile industries. The CRM2 is biggest plant in India by capacity 2.30 mpa.
And second biggest is M/s Tata Steel.

LEARNING:
I have learnt how the structure behaves in different circumstances
depending upon different loading conditions & the complete designing &
analysis of the steel structure.

CONCLUSION:
In review this internship has been an excellent and rewarding experience. I have
been able to meet and mingle with so many officials by which I could get help for
my internship.
One main thing that I have learned through this internship is time management
skills as well as self-motivation. When I first started I did not think that I was
going to be able to walk for eight hours a day, five days a week. Once I realized
what I had to do I organized my day and work so that I was not overlapping or
wasting my hours. I learned that I needed to be organized and have questions
ready for when it was the correct time to get feedback. From this internship and
time management I learned to inculcate the habit of being in the office for so
many hours and using the time preciously. The main thing that I came across is
about my working capacity within the given time. That really gives a good
meaning for the training. I came up with various proposals and ideas that the
company is still looking into. I am also sure that this internship training
programme will help me out in my future projects.