You are on page 1of 56

HIGHWAY DESIGN MANUAL 870-1

July 15, 2016

designer may also require input from fluvial


CHAPTER 870 geomorphologists (or engineers with geomorphology
BANK PROTECTION - EROSION training), geologists and biologists. The District
Hydraulic Engineer will typically be able to assist
CONTROL with flood analysis, water surface elevations/profiles,
shear stress computations, scour analysis, and
Topic 871 - General hydraulic analysis for placement of in-stream
structures. A geomorphologist can provide input
Index 871.1 - Introduction regarding characterization of channel form and
Highways, bikeways, pedestrian facilities and dominant geomorphic processes and hydraulic
appurtenant installations are often attracted to geometry relationships such as an analysis of lateral
parallel locations along man-made channels, streams, and longitudinal channel adjustment. The
and rivers. These locations may be effected from the geomorphologist can also make an identification of
action of flowing water, and may require protective the processes responsible for forming and
measures. maintaining key habitats and assist in making an
assessment of the long-term project effects.
Bank protection can be a major element in the design,
construction, and maintenance of highways. This There are a number of ways to deal with the problem
section deals with procedures, methods, devices, and of bank erosion as follows:
materials commonly used to mitigate the damaging
• Although not always feasible or economical, the
effects of flowing water on transportation facilities
simplest way and generally the surest of success
and adjacent properties. Potential sites for such
and permanence, is to locate the facility away
measures should be reviewed in conjunction with
from the erosive forces. Locating the facility to
other features of the project such as long and short
higher ground or solid support should be
term protection of downstream water quality,
considered, even when it requires excavation of
aesthetic compatibility with surrounding
solid rock, since excavated rock may serve as a
environment, and ability of the newly created
valuable material for bank protection.
ecological system to survive with minimal
maintenance. See Index 110.2 for further • The most commonly used method of bank
information on water quality and environmental protection is with a more resistant material like
concerns related to erosion control. See Chapter 880 rock slope protection. Other protection methods
for shore protection along coastal zones and lake (e.g., training systems) are discussed in Index
shores that are subjected to wave attack. 873.4 and summarized in Table 872.1.
Refer to Index 806.2 for definitions of drainage • A third method is to reduce the force of the
terms. attacking water. This is often done by various
plantings such as willows. Plantings once
871.2 Design Philosophy
established not only reduce stream velocity near
In each district there should be a designer or advisor, the bank during heavy flows, but their roots add
usually the District Hydraulic Engineer, structure to the bank material.
knowledgeable in the application of bank protection
principles and the performance of existing works. • Another method is to re-direct flows away from
Information is also available from headquarters the embankment. In the case of stream attack, a
specialists in the Division of Design and Structures new channel can be created or the stream can be
Design in the Division of Engineering Services diverted away from the embankment by the use
(DES). The most effective designs result from of baffles, deflectors, or spurs.
involvement with Design, Environmental, Landscape Combinations of the above four methods may be
Architecture, Structures, Construction, and used. Even protective works destroyed in floods
Maintenance (for further discussion on functional have proven to be effective and cost efficient in
responsibilities see Topic 802). For channel and minimizing damage to transportation facilities.
habitat characterization and assessment relative to
design and obtaining project specific permits, the
870-2 HIGHWAY DESIGN MANUAL
July 15, 2016

Design of protective features should be governed by increasing the mass of stones. See Index
the importance of the facility and appropriate design 873.3(3)(a)(2)(b) for equation to estimate rock
principles. Some of the factors which should be size.
considered are:
• Selection. Selection of class and type of
• Roughness. Revetments generally are less protection should be guided by the intended
resistant to flow than the natural channel bank. function of the installation.
Channel roughness can be significantly reduced
• Limits. Horizontal and vertical limits of
if a rocky vegetated bank is denuded of trees and
protection should be carefully designed. The
rock outcrops. When a rough natural bank is
bottom limit should be secure against toe scour.
replaced by a smooth revetment, the current is
The top limit should not arbitrarily be at high-
accelerated, increasing its power to erode,
water mark, but above it if overtopping would
especially along the toe and downstream end of
cause excessive damage and below it if floods
the revetment. Except in narrowed channels,
move slowly along the upper bank. The end
protective elements should approximate natural
limits should reach and conform to durable
roughness and simulate the effect of trees and
natural features or be secure with respect to
boulders along natural banks and in overflow
design parameters.
channels.
• Undercutting. Particular attention must be paid
871.3 Selected References
to protecting the toe of revetments against Hydraulic and drainage related publications are listed
undercutting caused by the accelerated current by source under Topic 807. References specifically
along smoothed banks, since this is the most related to slope protection measures are listed here
common cause of bank failure. for convenience.
• Standardization. Standardization should be a (a) FHWA Hydraulic Engineering Circulars (HEC)
guide but not a restriction in designing the -- The following seven circulars were developed
elements and connections of protective to assist the designer in using various types of
structures. slope protection and channel linings:
• Expendability. The primary objective of the • HEC 14, Hydraulic Design of Energy
design is the security of the transportation Dissipators for Culverts and Channels
facility, not security of the protective structure. (2006)
Less costly replaceable protection may be more
• HEC 15, Design of Roadside Channels with
economical than expensive permanent structures.
Flexible Linings (2005).
• Dependability. An expensive structure is
• HEC 18, Evaluating Scour at Bridges (2012)
warranted primarily where transportation
facilities carry high traffic volumes, where no • HEC 20, Stream Stability at Highway
reasonable detour is available, or where facility Structures (2012)
replacement is very expensive.
• HEC 23, Bridge Scour and Stream Instability
• Longevity. Short-lived structures or materials Countermeasures (2009)
may be economical for temporary situations.
Expensive revetments should not be placed on • HEC 25, Highways in the Coastal
banks likely to be buried in widened Environment (2008 with 2014 supplement)
embankments, nor on banks attacked by transient • HEC 26, Culvert Design for Aquatic
meander of mature streams. Organism Passage (2010)
• Rock Materials. Optimum use should be made (b) FHWA Hydraulic Design Series (HDS) No. 6,
of local materials, considering the cost of special River Engineering for Highway Encroachments
handling. Specific gravity of stone is a major (2001) -- A comprehensive treatise of natural and
factor in bank protection and the specified man-made impacts and responses on the river
minimum should not be lowered without
HIGHWAY DESIGN MANUAL 870-3
July 15, 2016

environment, sediment transport, bed and bank 30-meter grid intervals, where ”x” and “y” represent
stabilization, and countermeasures. horizontal position coordinates of a topographic
point and “z” is its elevation. These data files and the
(c) AASHTO Highway Drainage Guidelines --
USGS 7.5-minute quadrangle image files can be
General guidelines for good erosion control
imported into software programs, including the
practices are covered in Volume III - Erosion and
Watershed Modeling System (WMS), AutoCAD
Sediment Control in Highway Construction
Civil 3D, and ArcGIS.
(d) AASHTO Drainage Manual (2014) – Refer to
Nearby bridges that are located along the same
Chapters; 11 – Energy Dissipators; 16 – Erosion
stream reach should be reviewed for site history and
and Sediment Control; 17 – Bank Protection.
changes in stream cross-section. All bridge files are
The manual provides guidance on engineering
located in the Division of Maintenance, Office of
practice in conformance with FHWA’s HEC and
Structures Maintenance.
HDS publications and other nationally
recognized engineering policy and procedural District biologist staff should be consulted early on
documents. during the project planning phase for subject matter
expertise regarding fisheries, habitat, and wildlife
(e) U.S. Army Corps of Engineers EM 1110-2-1601
and to perform an initial stream habitat assessment.
Hydraulic Design of Flood Control Channels
Manual. Contact information for Department biologists can be
accessed through the CalBioRoster.
(f) California Department of Fish and Wildlife
California Salmonid Stream Habitat Restoration For channel and habitat characterization and
Manual. preliminary assessment relative to design and
acquisition of project specific permits, the initial site
Topic 872 - Planning and Location investigation team should include the project
Studies engineer, the district hydraulic engineer, and a
biologist. Depending on the complexity of the
872.1 Planning project, it may be necessary to include Caltrans staff
that are trained to perform a geomorphic assessment
The development of sustainable, cost effective and
and/or a geologist during the site investigation.
environmentally friendly protective works requires
careful planning and a good understanding of both The selection of the type of protection can be
the site location and habitat within the stream reach determined during or following the site investigation.
and overall watershed. Planning begins with an For some sites the choice is obvious; at other sites
office review followed by a site investigation. several alternatives or combinations may be
applicable. See the FHWA’s HDS No. 6, River
Google Earth can be a useful tool for determining site
Engineering for Highway Encroachments for a
location, changes to stream planform (pattern), bend
complete and thorough discussion of hydraulic and
radius to channel width ratio (to estimate rock size
environmental design considerations associated with
per Index 873.3(3)(a)(2)(b), and location within the
hydraulic structures in moveable boundary
overall watershed. USGS StreamStats will facilitate
waterways.
simple watershed delineation and provide basin
characteristics such as area, cover and percentage of Some specific site conditions that may dictate
impervious cover, average elevation, stream slope, selection of a type of protection different from those
mean annual precipitation, and peak flow from shown in Table 872.1 are:
regression equations. When more detailed watershed
• Available right of way.
delineation is required, United States Geological
Survey (USGS) 7.5-minute quadrangle maps are • Available materials.
used to trace the tributary area and sub-basins. The
• Possible damage to other properties through
USGS maps are found in graphic image form, such
streamflow diversion or increased velocity.
as TIFF and JPEG, and are also found in the form of
a Digital Elevation Model (DEM). A DEM contains • Environmental concerns.
x-y-z topographic data points usually at 10 or
870-4 HIGHWAY DESIGN MANUAL
July 15, 2016

• Channel capacity or conveyance. The second step is the selection and layout of
protective elements in relation to the highway
• Conformance to new or existing structures. facility.
• Provisions for side drainage, either surface 872.2 Class and Type of Protection
waters or intersecting streams or rivers.
Protective devices are classified according to their
The first step is to determine the limits of the function. They are further categorized as to the type
protection with respect to length, depth and the of material from which they are constructed or shape
degree of security required. For more detailed stream of the device. For additional information on specific
reconnaissance considerations, see HEC 20, Index material types and shapes see Topic 873, Design
4.2.1 (Appendix C and D) and the FHWA’s HDS No. Concepts.
6, River Engineering for Highway Encroachments
(Table 8.1). There are two basic classes of protection, armor
treatment and training works. Table 872.1 relates
Considerations at this stage are: different location environments to these classes of
• The severity of stream attack. protection.
• The present alignment of the stream or river and 872.3 Geomorphology and Site
potential meander changes. Consideration
• The ratio of cost of highway replacement versus The determination of the lengths, heights, alignment,
cost of protection. and positioning of the protection are affected to a
large extent by the facility location environment.
• Whether the protection should be permanent or
temporary. An evaluation is required for any proposed highway
construction or improvement that encroaches on a
• Analysis of foundation and materials floodplain. See Topic 804, Floodplain
explorations. Encroachments for detailed procedures and
• Access for construction. guidelines.
• Bank slope (H:V). (1) Geomorphology. An understanding of stream
morphology is important for identifying both
• Bed and bank material gradations. stream instability and associated habitat
• Stream stability (lateral and vertical). Caltrans problems at highway-stream locations. A study
Hydromodification Requirements Guidance of the plan and profile of a stream is very useful
Storm Water Best Management Practices Rapid in understanding stream morphology. Plan view
Assessment of Stream Crossings Higher Level appearances of streams are varied and result from
Stream Stability Analysis presents 13 channel many interacting variables. Small changes in a
characteristics that are indicators of present variable can change the plan view and profile of
stream stability. See Index 4.1. a stream, adversely affecting a highway crossing
or encroachment. This is particularly true for
• Local stream profile. alluvial streams. Conversely, a highway crossing
• Vegetation type and location. or encroachment can inadvertently change
multiple variables such as Manning’s “n-value”,
• Physical habitat (temperature, shade, pools, channel width, and average velocity, which may
riffles, sediment supply). adversely affect the stream.
• Toe scour/bank failure mode (see Table 872.2). Chapter 2 in HEC 20 presents an overview of
general landform and channel evolutionary
• Thalweg location.
processes to illustrate the dynamics of alluvial
• Hardpoint location(s). channel systems. It discusses lateral stability,
factors effecting bed elevation changes, and the
• Total length of protection needed.
HIGHWAY DESIGN MANUAL 870-5
July 15, 2016

Table 872.1
Guide to Selection of Protection
Armor Training
Flexible Rigid Bendway Weirs Check
Guide Banks
Mattresses and Spurs Dams

Drop Structure
Location

Grouted Rock

Grouted Rock
Conc. Lined
Conc. Rock

Bulk Heads
Vegetation

Gabions
Rip Rap

Conc. F

Piling

Piling

Piling
Other

Other
Cribs

Earth
Rock

Rock

Rock

Rock
Cross Channel
Young Valley X X X X X
Mature Valley X X X X X X X X X X X X
Parallel Encroachment
Young Valley X X X X X
Mature Valley X X X X X X X X X X X X X X X
Desert-wash
Top debris cone X X X X X
Center debris cone X X X X X
Bottom debris cone X X X X X
Overflow and X X X X X X
Floodplain
Artificial Channel or X X X X X X
Roadside Ditch X X
(Ch. 860)
Culvert
Inlet X X X
Outlet X X X
Bridge
Abutment X X X
Upstream X X X X X X
Downstream X X X X X X X X X
870-6 HIGHWAY DESIGN MANUAL
July 15, 2016

sediment continuity principle to provide an systems, such as bank erosion, sediment


introduction to alluvial channel response to transport, and bed material sorting.
natural and human-induced change.
This section is intended to give the engineer
River morphology and river response is background, perspective, and respect of stream
discussed in detail in Chapter 5 of FHWA’s HDS processes and their dynamics when designing
No. 6, River Engineering for Highway and constructing bank protection for natural
Encroachments. streams and to lay the groundwork for
application of the concepts of open-channel flow,
(2) Stream Processes. Prior to the current interest in
fluvial geomorphology, sediment transport, and
ecology, water quality, and the environment, few
river mechanics to the design, maintenance, and
engineers involved with highway crossings and
environmental challenges associated with
encroachments considered the short-term and
highway crossings and encroachments.
long-term changes that were possible or the
Encroachment is any occupancy of the river and
many problems that humans can cause to
floodplain for highway use. Encroachments
streams. It is imperative that anyone working
usually present no issues during normal stages,
with rivers, either on localized areas or entire
but require special protection against floods.
systems, have an understanding of the many
Classifying the regions requiring protection, the
factors involved, and of the potential for change
possible types of protection, the possible flow
within the river system. Highway construction
conditions, the possible channel shapes, and the
can have significant general and local affects on
various geometric conditions aids the engineer in
the geomorphology and hydraulics of river
selecting the design criteria for the conditions
systems. Hence, it is necessary to consider
encountered.
induced short-term and long-term effects of
erosion and sedimentation on the surrounding (a) Types of Encroachment. In the vicinity of
landscape and the river. The biological response rivers, highways generally impose a degree
of the river system should also be considered and of encroachment. In some instances,
evaluated. Certain species of fish can only particularly in mountainous regions or in
tolerate large quantities of suspended sediment river gorges and canyons, river crossings can
for relatively short periods of time. This is be accomplished with absolutely no
particularly true of the eggs and fry. It is useful encroachment on the river. The bridge and
for the project engineer to understand what is its approaches are located far above and
important for regulators. Some of the most beyond any possible flood stage. More
common topics include: commonly, the economics of crossings
require substantial encroachment on the river
• Site geomorphology and steam stability
and its floodplain, the cost of a single span
• Stressors to historic aquatic organism habitat over the entire floodplain tends to be
prohibitive. The encroachment can be in the
• Locations of hydraulic constrictions form of earth fill bridge approach
Only with such knowledge can the project embankments on the floodplain or into the
engineer develop the necessary arguments to main channel itself, reducing the required
make the case that erosion control measures must bridge length; or in the form of piers and
be designed to avoid significant deterioration of abutments or culverts in the main channel of
the stream environment not only in the the river. Longitudinal encroachments may
immediate vicinity of the highway encroachment exist that are not connected with river
or crossing, but in many instances for great crossings. Floodplains often appear to
distances downstream. provide an attractive low cost alternative for
highway location, even when the extra cost
Fluvial geomorphology is the science dealing of flood protection is included. As a
with the shape of stream channels and includes
consequence, highways, including
the study of physical processes within river interchanges, often encroach on a floodplain
over long distances. In some regions, such
HIGHWAY DESIGN MANUAL 870-7
July 15, 2016

as mountainous regions, river valleys (or of hydraulic forces exerted on the bed and
canyons) provide the only feasible route for banks. These changes may be gradual or
highways. This is true in areas where a rapid and may be the result of natural causes
floodplain does not exist. In many locations or human activities. At any location in a
the highway encroaches on the main channel stream, the cross-sectional shape is
itself and the channel is partly filled to allow dependent upon the volume flow-rate (flow),
room for the roadway. See Figure 872.4. In the composition of sediment transported
some instances, this encroachment becomes through a section, and the integrity or
severe, particularly as older highways are gradation of the bed and bank materials. As
upgraded and widened. water flows through the stream channel, it
exerts a fluid shear stress on the bed and
(b) Effects of River Development Works. These
banks. For a constant and stable cross-
works may include water diversions to and
sectional shape for a given flow at a specific
from the river system, dams, cutoffs (channel
location, the resisting bed and bank material
straightening), levees, navigation works, and
shear stress must be equal to the fluid stress
the mining of sand and gravel. It is essential
at every point in the stream cross section
to consider the probable long-term plans of
perimeter. In this state, a stream is in the
all agencies and groups as they pertain to a
threshold condition where each point along
river when dealing with the river in any way.
the perimeter is at the threshold of movement
For example, dams serve as traps for the
or incipient motion. This condition also
sediment normally flowing through the river
indicates a dynamic equilibrium with scour
system. With sediment trapped in the
and deposition of sediment being equal. As
reservoir, essentially clear water is released
flow, velocity, and fluid shear stress
downstream of the dam site. This clear water
increase, the amount of scour and sediment
has the capacity to transport more sediment
deposition will change, which will also
than may be immediately available.
change the stream cross section for a given
Consequently the channel begins to supply
bed/bank gradation.
this deficit with resulting degradation of the
bed or banks. The degraded or widened main Alluvial streams are commonly trapezoidal
channel causes steeper gradients on tributary in cross section through their straight reaches
streams in the vicinity of the main channel. and become asymmetric through their bends.
The result is degradation in the tributary When streams incise in response to possible
streams. It is entirely possible, however, that instability, their depth increases and the
the additional sediments supplied by the stream takes on a more rectangular cross-
tributary streams would ultimately offset the sectional shape. Also, streams with very
degradation in the main channel. Thus, it large flows may become rectangular as the
must be recognized that downstream of bed width increases to convey the large
storage structures the channel may either flows, especially if bedrock outcroppings are
aggrade or degrade (most common) and the present on the banks preventing them from
tributaries will be affected in either case. flattening.
(c) Alluvial Streams. Most streams that (d) Non-Alluvial Streams. Some streams are not
highways cross or encroach upon are alluvial. The bed and bank material is very
alluvial; that is, the streams are formed in coarse, and except at extreme flood events,
materials that have been and can be do not erode. These streams are classified as
transported by the stream. In alluvial stream sediment supply deficient, i.e., the transport
systems, it is the rule rather than the capacity of the streamflow is greater than the
exception that banks will erode; sediments availability of bed material for transport.
will be deposited; and floodplains, islands, The bed and bank material of these streams
and side channels will undergo modification may consist of cobbles, boulders, or bedrock.
with time. Alluvial channels continually In general these streams are stable, but
change position and shape as a consequence should be carefully analyzed for stability at
870-8 HIGHWAY DESIGN MANUAL
July 15, 2016

large flows. A study of the plan and profile under control. The points that should be
of a stream is useful in understanding stream stressed are that a river through time is
morphology. Plan view appearances of dynamic and that human-induced change
streams are varied and result from many frequently sets in motion a response that can
interacting variables. Small changes in a be propagated upstream or downstream for
variable can change the plan view and profile long distances.
of a stream, adversely affecting a highway
In spite of their complexity, all rivers are
crossing or encroachment. This is
governed by the same basic forces. The
particularly true for alluvial streams.
design engineer must understand, and work
Conversely, a highway crossing or
with these natural forces:
encroachment can inadvertently change a
variable, adversely affecting the stream. • Geological factors, including soil and
seismic conditions.
(e) Dynamics of Natural Streams. Long-term
climatic and tectonic fluctuations have • Hydrologic factors, including possible
caused major changes of river morphology, changes in flows, runoff, and the
but rivers can display a remarkable hydrologic effects of changes in land
propensity for change of position and use.
morphology in time periods of a century. For
shorter time periods river channels will shift • Geometric characteristics of the stream,
through erosion and deposition at bends and including the probable geometric
may form chutes, islands or oxbow lakes. alterations that will be activated by the
Lateral migration, erosion and deposition changes a project and future projects will
rates are not linear; i.e., a river may maintain impose on the channel.
a stable position for several years and then • Hydraulic characteristics such as depths,
experience rapid movement. At low flow the slopes, and velocity of streams and what
bed of a sand bed stream can be dunes, but at changes may be expected in these
large flows the bed may become plane or characteristics in space and time.
have antidune flow. With dunes, resistance
to flow is large and bed material transport is • Sea level rise may also cause river
low. Whereas, with plane bed or antidune instability, particularly when the 75-year
flow the resistance to flow is small and the design life of a bridge is considered.
bed material transport is large. Much, (f) Basic Stream Pattern. The three basic stream
therefore, depends on flood events, bank patterns are straight, braided, and
stability, permanence of vegetation on banks meandering as seen in aerial or plan view.
and the floodplain and watershed land use. Pattern is one way of classifying a stream and
In summary, archaeological, botanical, generalizing its behavior, another is
geological, and geomorphic evidence sediment load. See Figure 872.1.
supports the conclusion that most rivers are Commonly, stream patterns are identified by
subject to constant change as a normal part sinuosity, which is defined as channel length
of their morphologic evolution. Therefore, divided by valley (floodplain) length. For
stable or static channels are the exception in straight and braided streams, sinuosity varies
nature. between 1.0 and 1.5, while meandering
If an engineer modifies a river channel streams have sinuosity greater than 1.5.
locally, this local change may cause These different patterns and their associated
unintended modification of channel gradients contribute to changes and
characteristics both up and down the stream. adjustments in streams, and specifically
The response of a river to human-induced influence flow resistance that effects
changes often occurs in spite of attempts by sediment transport and formation of cross-
engineers to keep the anticipated response sectional shape. Engineers using any stream
HIGHWAY DESIGN MANUAL 870-9
July 15, 2016

Figure 872.1
Stream Classification
870-10 HIGHWAY DESIGN MANUAL
July 15, 2016

classifications should be aware that they are (h) Braided Streams. Similar to straight streams,
artificial constructs, and no strict science streams with braided pattern have low
laws or principles of classification (such as sinuosity, but have the highest gradient of
used in biology) are possible. Although we any of the stream patterns. Braided streams
may assign channel reaches to discrete have many sub-channels within the main
categories based on arbitrary thresholds of stream channel that interweave and
slope, sinuosity, bed material size, sediment crisscross. The sub-channels are separated
load, width-depth ratio, etc., these quantities by islands or bars which are visible during
vary continuously, and channels tend to low flows and normally submerged under
behave in rather individualistic fashion. high flows. Because braided streams have
Different types of streams occur within a steep slopes, they possess the higher energy
given subregion. Index 3.9 of Caltrans necessary to erode and transport sediment
Hydromodification Requirements Guidance that comprises the bars and islands. Even
presents the various stream forms within though braided streams have high energy,
each of the physiographic subregions of these streams will deposit their coarser and
California available at the following website: larger material that cannot be physically
transported by the stream’s average velocity
http://www.dot.ca.gov/hq/oppd/stormwtr/gu
and shear stress. In other words, the process
idance/CT-Hydromodification-
of braiding occurs during flood events as a
Requirements-Guidance.pdf
stream adjusts in response to the larger
(g) Straight Streams. Straight river channels can sediment and debris loads that cannot be
be of two types. The first forms on a low- sustained while trying to find dynamic
gradient valley slope, has a low width-depth equilibrium. This deposition of larger
ratio channel, and is relatively stable. The material creates the bars and islands. See
first type of straight channel may contain Figure 872.2. As flow and velocity fluctuate
alternate islands or bars that result in a during a flood event, it is common to see
sinuous thalweg (flow path connecting movement and re-creation of bars, islands,
deepest points in successive cross sections) and sub-channels.
within the straight channel. It may seem that
the first type of straight stream is very stable Figure 872.2
because of low slope and energy, but Diagram of a Braided River
alternating sediment deposits can cause
lateral instability. In general, it is more
Channel
natural for a stream to meander than to have
a straight stream pattern, therefore it is
difficult to find low-gradient straight streams
in the field, especially long reaches.
The second type is a steep gradient, high
width-depth ratio, high energy river that has
many islands or bars, and at low flow is
braided. It is relatively active. (i) Meandering Streams. Meandering is the
most common stream pattern, having a series
In general, the designer should not attempt to of alternating curves or bends, and is
develop straight channels fully protected associated with flatter valleys. Meandering
with riprap. In a straight channel the stream types have the highest sinuosity
alternate islands or bars and the thalweg are because of their longer stream length, due to
continually changing; thus, the current is not several alternating curves, with respect to
uniformly distributed through the cross- valley length, see Figure 872.6. One way
section but is deflected toward one bank and that streams seek dynamic equilibrium is to
then the other. dissipate energy through erosion of their
banks, creating meandering patterns. When
HIGHWAY DESIGN MANUAL 870-11
July 15, 2016

meanders are created, overall stream length because the bed material is transported at the
is increased, and energy is released through capacity of the stream and is functionally
the work necessary to scour its banks, which related to measurable hydraulic variables.
brings a stream closer to dynamic The washload is not transported at the
equilibrium. Streambank revetments are capacity of the stream. Instead, the washload
often constructed through these meanders to depends on availability and is not
prevent excessive erosion that may cause functionally related to measurable hydraulic
instability of nearby or adjacent variables.
transportation facilities.
The division size between washload and bed
Once curves have been created in a stream’s sediment load is sediment size finer than the
alignment, velocity increases as the flow of smallest 10 percent of the bed material. It is
water moves through the outside bank of a important to note that in a fast flowing
bend caused by secondary circulation mountain stream with a bed of cobbles the
currents. Given the geometry of a curve, washload may consist of coarse sand sizes.
velocity is resolved into three components For these conditions, the transport of sand
described in the longitudinal, width-wise, sizes is supply limited. In contrast, if the bed
and vertical directions, contrary to straight of a channel is silt, the rate of bed load
reaches of stream. transport of the silt sizes is less a question of
supply than of capacity.
As flow moves through a curve, the
circulation currents and their turbulence are When a river reaches equilibrium, its
influenced by radius of curvature, stream transport capacities for water and sediment
bottom width, flow depth, curve deflection are in balance with the rates supplied. In
angle, and Reynolds Number. As often fact, most rivers are subject to some kind of
occurs, turbulence is magnified by counter- control or disturbance, natural or human-
circulating currents from an upstream bend induced that gives rise to non-equilibrium
merging with circulating currents of an conditions. HDS No. 6, Index 4.3.2, states
immediate downstream bend. The increased total sediment load can be expressed by three
turbulence usually increases the amount of equations:
scour at the outside bend, and the transported
1. By type of movement
material is deposited on the inside bend at the
downstream reversing curve creating a point 𝐿𝐿 𝑇𝑇 = 𝐿𝐿𝑏𝑏 + 𝐿𝐿𝑠𝑠
island or bar.
2. By method of measurement
Another characteristic of flow through a
𝐿𝐿 𝑇𝑇 = 𝐿𝐿𝑚𝑚 + 𝐿𝐿𝑢𝑢
curve is that the top of the water surface will
superelevate along the outside bank of a 3. By source of sediment
curve as it is pulled by centrifugal forces
𝐿𝐿 𝑇𝑇 = 𝐿𝐿𝑤𝑤 + 𝐿𝐿𝑏𝑏𝑏𝑏
while the bottom water surface at the bed is
being pulled toward the inside of a bend. Where:
These two actions will cause skewing of the LT = Total load;
circulating current contributing to increased
erosion around a bend. Lb = Bed load which is defined as the
transport of sediment particles that
(j) Sediment Transport. For engineering are close to or maintain contact
purposes, the two sources of sediment with the bed;
transported by a stream are: (1) bed material
that makes up the stream bed; and (2) fine Ls = Suspended load defined as the
material that comes from the banks and the suspended sediment passing
watershed (washload). Geologically both through a stream cross-section
materials come from the watershed, but for above the bed layer;
the engineer, the distinction is important
870-12 HIGHWAY DESIGN MANUAL
July 15, 2016

Lm = Measured sediment; stress acting on the particle as water flows


over them. The fluid stress can be expressed
Lu = Unmeasured sediment that is the
as an average boundary shear stress acting on
sum of bed load and a fraction of
a stream bed considering steady, uniform
suspended load below the lowest
flow:
sampling elevation;
𝜎𝜎0 = 𝑔𝑔𝑔𝑔𝑆𝑆𝑓𝑓
Lw = Wash load which is the fine
particles not found in the bed Where:
material (Ds < D10), and originates
from available bank and upstream σ0 = Shear stress = Force per unit area in
supply; flow direction;

Lbm = Capacity limited bed material g = Specific weight of water;


load. D = Flow-depth;
Streams are unique from other hydraulic Sf = Friction slope.
conveyance facilities, such as engineered
Particle movement can be further expressed
channels and pipes, in that its boundaries are
at a specific point in a stream bed as incipient
mobile, and they move sediment within their
motion, which is the initial movement of a
water column or along the bed by skipping
particle. The calculation of a critical shear
and rolling, which is a complicated
stress or critical velocity can be performed at
interrelationship. The suspended sediment
the threshold movement condition that
load is carried through the flow by
assumes active hydraulic forces are equal to
turbulence and is typically fine sand, silt, and
particle resistant forces. At the point of
clay. Bedload is coarser possibly as large as
critical shear stress or critical velocity, a
boulders, and moves along the bed by fluid
particle is just about to move. This means
stress action, see Figure 872.3. Sediment
that values of shear stress or velocity greater
supply and its movement are the life of a
than critical shear stress or critical velocity
stream that can become unstable when this
cause particles to be in motion, while
process is interrupted if supply becomes
particles will be at rest with values of shear
limited or if a stream is unable to transport its
stress and velocity lower than critical shear
excess downstream.
stress and velocity. An incipient motion
Instability can be seen through channel calculation can provide an indication of
incision, where the stream bed degrades and erosion potential and stream stability.
banks over steepen, excessive meandering, Fischenich (2001) provides a variation of the
or large alignment shifts as a stream attempts widely accepted and industry standard
to control energy as it searches for dynamic Shields equation for approximated critical
equilibrium. The ability of a stream to shear stress considering different materials:
control and manage its sediment is not the
only influence on stream stability, but one of Clays: 𝜎𝜎𝑐𝑐𝑐𝑐 = 0.5𝑑𝑑(𝑔𝑔𝑠𝑠 − 𝑔𝑔𝑤𝑤 ) tan 𝐹𝐹
the more important factors. Silts & Sands:
Within a stream bed, immersed sediment 𝜎𝜎𝑐𝑐𝑐𝑐 = 0.25𝑑𝑑0 − 0.6𝑑𝑑(𝑔𝑔𝑠𝑠 − 𝑔𝑔𝑤𝑤 ) tan 𝐹𝐹
particles resting on the stream bed over other Gravels & Cobbles:
particles exert their effective weight in the 𝜎𝜎𝑐𝑐𝑐𝑐 = 0.06𝑑𝑑(𝑔𝑔𝑠𝑠 − 𝑔𝑔𝑤𝑤 ) tan 𝐹𝐹
form of a vertical force, which can be divided
Where:
into normal and tangential components based
1�
on the stream bed slope. Simply stated, in 𝑑𝑑0 = 𝑑𝑑[(𝐺𝐺 − 1)𝑔𝑔𝜈𝜈 −2 ] 3;
order for sediment particles to become
mobile, a force greater than their normal σcr = Critical shear stress;
weight must be applied to them. This force F = Soil grain angle of repose;
that causes mobility is a drag force or fluid
HIGHWAY DESIGN MANUAL 870-13
July 15, 2016

Figure 872.3
Bed Load and Suspended Load
870-14 HIGHWAY DESIGN MANUAL
July 15, 2016

capacity modeling. Several empirical


Figure 872.4 sediment transport functions used in
Longitudinal Encroachments modeling have been developed and named
after their creators, such as Einstein, Acker
and White, Laursen-Copeland, Meyer-Peter
Muller, and Yang. These functions are
complex and notoriously data intensive.
Three classic sediment transport formulae
are discussed in detail in Index 4.5 of HDS
No. 6 to illustrate sediment transport
processes. While not often, resource
agencies and flood control districts may
request this type of analysis during the
permit review process. If sediment modeling
is necessary, HEC-RAS v4.1 (or higher), the
Army Corps of Engineers’ river and stream
modeling software, contains sediment
transport modeling capabilities using these
transport functions and others.
(k) Stream Channel Form. Major factors
affecting alluvial stream channel forms are:
• stream discharge, viscosity, temperature;
• sediment discharge;
• longitudinal slope;
• bank and bed resistance to flow;
• vegetation;
• geology, including types of sediments
Highway 49, North Fork Yuba River (Near Downieville) and;
and Highway 190, Furnace Creek, (Death Valley)
• human activity.
d = Soil diameter;
At any location in a stream, the cross-
gs = Sediment unit weight; sectional shape is dependent upon the
volume flow-rate (flow), the composition of
gw = Water unit weight;
sediment transported through a section, and
G = Sediment specific gravity; the integrity or gradation of the bed and bank
g = Gravity; materials. As water flows through the stream
channel, it exerts a fluid shear stress on the
ν = Water/sediment mixture kinematic bed and banks. For a constant and stable
viscosity. cross-sectional shape for a given flow at a
The Shields equation and the beginning of specific location, the resisting bed and bank
motion is described in more detail in Index material shear stress must be equal to the
3.5 of HDS No. 6. fluid stress at every point in the stream cross
section perimeter. In this state, a stream is in
Modeling of a stream reach, although the threshold condition where each point
complex, can be performed in order to along the perimeter is at the threshold of
predict sediment transport potential on a movement or incipient motion. This
larger scale, transport rates, volume, and condition also indicates a dynamic
HIGHWAY DESIGN MANUAL 870-15
July 15, 2016

equilibrium with scour and deposition of floodplain overbanks will differ from the
sediment being equal. As flow, velocity, and main channel due to uniqueness of form
fluid shear stress increase, the amount of (shape), gradient, alignment, and likely the
scour and sediment deposition will change, flow resistance (roughness) of the floodplain
which will also change the stream cross versus the stream channel. Therefore, water
section for a given bed/bank gradation. will move and deposit varying sediment
types differently, also at different frequency,
The form and appearance of a stream can
creating a separate floodplain form. Once
also be influenced by features within the
sediment is moved to the floodplain, coarser
stream profile, such as riffles and pools
sediment is generally deposited along the
because of their affects on the acting fluid
streambanks forming levees, while finer
shear stress and velocity. Riffles are
sediment is dropped between the valley walls
longitudinal sections of streams with higher
and the levees on the floodplain floor.
velocity, where lower flow-depth usually
Sediment is stored and becomes dormant
caused by obstructions, such as gravels,
until larger flows return to the floodplain that
cobbles, and boulders created by island or
may convey the sediment down-valley.
bar development. On the contrary, pools
have higher flow-depth and lower velocity, Similar to the stream channel, floodplain
and are typically comprised of finer silts and form is directly linked to the sediment
sands compared to a riffle. These bed transport process, as well as floodplain
materials associated with pools and riffles stability affected by sediment supply and its
have an affect on resisting bed shear stress movement. Fluid shear stress and velocity
that will influence stream shape and stability. control the sediment/debris degradation and
The alternating pool and riffle sequence is deposition properties within the floodplain
common for nearly all perennial streams that that impact its form, landscape, and
have gravel to boulder size bed formations. appearance. Because the floodplain can be
Different types of streams occur within a dormant for considerable time depending on
given subregion. Index 3.9 of Caltrans watershed hydrology, its form can remain
Hydromodification Requirements Guidance relatively constant and preserved for
presents the various stream forms within extended periods, as well as be less dynamic
each of the physiographic subregions of than the stream channel.
California, see:
(m) Streambank Erosion. Simply defined,
http://www.dot.ca.gov/hq/oppd/stormwtr/gu streambank erosion occurs when the soil
idance/CT-Hydromodification- resisting strength is less than the driving
Requirements-Guidance.pdf forces acting on the bank. It can occur
through bank-toe scour below the water line
(l) Floodplain Form. From a geomorphic
and bank mass failure from above. This
perspective, floodplains are flatter lands
erosion occurs first as a geotechnical failure
adjacent to a river main channel that are dry
followed by the hydraulic action that
until larger flows force water out of the
removes the failed soil and sediment by fluid
stream channel into these overbank lands
shear stress. The hydraulic action further
during significant flood events. Floodplains
causes lateral scour of the bank and is the
typically include the following features: the
principal contributor to bank-toe failure.
main stream channel itself, point islands or
This is a natural process for both stable and
bars, oxbows and lakes, natural raised berms
unstable streams, but is exaggerated in the
(levees) above floodplain surface, terraces,
latter case. The degree of erosion can be
sloughs and depressions, overbank fine and
influenced by impervious development in the
coarse sediment deposition, scattered debris,
watershed, agricultural use, and changes in
and vegetation.
climate. With or without these influences
When water exceeds the capacity of the main and whether a stream is stable or unstable,
channel, the conveyance of flow through the streambank erosion will take place at some
870-16 HIGHWAY DESIGN MANUAL
July 15, 2016

level. Therefore, scour must be reduced at of unstable banks typically exceed


critical locations to protect highway 30 percent, where a cover of woody
structures and preserve public safety, vegetation is rarely present. At a bend,
although restraint needs to be exercised the point island or bar opposite of an
during the project development process so unstable cut bank is likely to be bare at
that a stream does not greatly change its normal stage, but it may be covered with
morphology in response to the protection annual vegetation and low woody
measures. vegetation, particularly willows. Where
very rapid erosion is occurring, the
The driving and resisting forces for
bankline may have irregular
streambank erosion, mentioned above, are
indentations. Fissures, which represent
controlled by a series of factors. The factors
the boundaries of actual or potential
that influence the calculation of the driving
slump blocks along the bankline indicate
(active) forces within geotechnical failure
the potential for rapid bank erosion.
are soil saturated unit weight, pore pressure,
bank height, and angle of repose, as well as (2) Unstable banks with slow to moderate
object surcharges within and above the bank erosion rate occur when a bank is partly
such as vegetation. The effects of driving graded (smooth slope) and the degree of
forces are commonly seen through soil instability is difficult to assess where
saturation as a result of intense precipitation reliance is placed mainly on vegetation.
with subsequent increase in pore pressure The grading of a bank typically begins
and bank soil saturated unit weight that can with the accumulation of slumped
cause mass bank failure. The forces that will material at the base such that a slope is
resist and give soil its strength from formed, and progresses by smoothing of
geotechnical type failure are dependent upon the slope and the establishment of
effective soil cohesion, normal stress, pore vegetation.
pressure, and soil effective angle of friction.
(3) Stable banks with very slow erosion rate
During streambank erosion, the bank soil can occur where banks tend to be graded to a
fail by different modes. Generally speaking, smooth slope and the slope angle is
steep slopes present slab-type or toppling usually less than about 30 percent. In
failures where large slabs (blocks of soil) of most regions, the upper parts of stable
the bank break away from the top and fall banks are vegetated, but the lower part
into the stream, while mild slopes show a may be bare at normal stage, depending
rotational failure that begins at the bank toe on bank height and flow regime of the
causing soil to slide from above into the stream. Where banks are low, dense
stream. Once the eroded soil reaches flowing vegetation may extend to the water's
water, it is usually transported downstream edge at normal stage. Mature trees on
depending upon its size and composition. graded bank slopes are particularly
convincing evidence for bank stability.
As for bank-toe scour, its main influences are
Where banks are high, occasional
derived from bank soil composition and
slumps may occur on even the most
gradation, volume of sediment in transport,
stable graded banks. Shallow mountain
stream flow and stream gradient. These
streams that transport coarse bed
factors and the principles of scour and
sediment tend to have stable banks.
sediment movement from hydraulic forces
are a reoccurring theme in fluvial For a more detailed discussion of bank
geomorphology. The following paragraphs stability and the mechanics of bank failure
summarize the characteristics of unstable see HEC 20.
and stable banks;
(n) Young Valley. Typically young valleys are
(1) Unstable banks with moderate to high narrow V-shaped valleys with streams on
erosion rate occur when the slope angle steep gradients. Relief elevation greater than
HIGHWAY DESIGN MANUAL 870-17
July 15, 2016

1,000 ft is regarded as mountainous, while to erosion-resistant banks or


relief in the elevation range of 100 to 1,000 ft outcrops.
is regarded as hilly. Streams in mountainous
• Structural inadequacy at points of
regions are likely to have steep slopes, coarse
impingement overtopping.
bed materials (gravel or cobble-boulder),
narrow floodplains, and have nonalluvial • Inadequate rock size, see Table
characteristics (i.e., supply-limited sediment 872.2.
transport rates). At flood stage, the stream
flow covers all or most of the valley floor. • Lack of proper gradation/ layering/
The usual situation for such locations is a RSP fabric, leading to loss of
structure crossing a well-defined channel in embankment, see Table 872.2.
which the design discharge will flow at a Any of the more substantial armor
moderate to high velocity. treatments can function properly in such
(1) Cross-Channel Location. A cross exposures providing precautions are
channel location is a highway crossing a taken to alleviate the probable causes of
stream on normal or skewed alignment. failure. If the foundation is questionable
The erosive forces of parallel flow for concreted-rock or other rigid types it
associated with a normal crossing are would not be necessary to reject them
generally less of a threat than the from consideration but only to provide a
impinging and eddy flows associated more acceptable treatment of the
with a skewed crossing. The effect of foundation, such as heavy rock or sheet
constriction by projection of the piling.
roadway embankment into the channel Whether the highway crosses a stream
should be assessed. channel on a bridge or over a culvert,
Characteristics to be considered include: economic considerations often lead to
constriction of the waterway. The most
• Stream velocity. common constriction is in width, to
shorten the structure. Next in frequency
• Scouring action of stream.
is obstruction by piers and bents of
• Bank stability. bridges or partitions of multiple culverts.
• Channel constrictions (artificial or Figure 872.5
natural).
• Nature of flow (tangential or Slope Failure Due to Loss of Toe
curvilinear).
• Areas of impingement at various
stages.
• Security of leading and trailing
edges.
Common protection failures occur from:
• Undermining of the toe (inadequate
depth/size of foundation), see Figure
872.5 and Table 872.2.
• Local erosion due to eddy currents.
• Inadequate upstream and
downstream terminals or transitions
870-18 HIGHWAY DESIGN MANUAL
July 15, 2016

Table 872.2
Failure Modes and Effects Analysis for Riprap Revetment
Effects on Other Effects on Compensating
Failure Modes Detection Methods
Components Whole System Provisions
• Reduce bank
slope
• Mound of rock
Translational at bank toe • Use more angular
Disruption of Catastrophic
slope or slump or smaller rock
armor layer failure • Unprotected
(slope failure)
upper bank • Use granular
filter rather than
geotextile fabric
• Rock moved
downstream
Loss of armor • Increase rock size
Particle erosion Progressive from original
layer, erosion of location • Modify rock
(rock undersized) failure
filter gradation
• Exposure of
filter
• Scalloping of
upper bank
Piping or erosion • Use appropriate
Displacement of Progressive • Bank cutting
beneath armor granular or
armor layer failure
(improper filter) • Void beneath geotextile filter
and between
rocks
• Slumping of • Increase size,
Displacement or rock
Loss of toe or key Catastrophic thickness, depth
disruption or
(under designed) failure • Unprotected or extent of toe or
armor layer
upper bank key
HIGHWAY DESIGN MANUAL 870-19
July 15, 2016

The risk of constricting the width of the considered in the economic studies to
waterway is closely related to the choose a bridge length which minimizes
relative conveyance of the natural total cost.
waterway obstructed, the channel scour,
Accurate estimates of anticipated scour
and to the channel migration.
depths are a prerequisite for safe, cost
Constricting the width of flow at
effective designs. Design criteria
structures has the following effects:
require that bridge foundations be
• Increase in the upstream water placed below anticipated scour depths.
surface elevation (backwater For this reason the design of protection
profile). to control scour at such locations is
seldom necessary for new construction.
• Increase in flow velocity through However, if scour may undercut the toes
the structure opening (waterway). of dikes or embankments positive
• Causes eddy currents around the methods including self-adjusting armor
upstream and downstream ends of at the toe, jetties or retards to divert
the structure. scouring currents away from the toe, or
sill-shaped baffles interrupting
Unless protection is provided the eddy transport of bedloads should be
currents can erode the approach considered.
roadway embankment and the
accelerated flow can cause scour at There is the potential for instability
bridge abutments. The effects of from saturated or inundated
erosion can be reduced by providing embankments at crossings with
transitions from natural to constricted embankments projecting into the
and back to natural sections, either by channel. Failures are usually reported
relatively short wingwalls or by as "washouts", but several distinct
relatively long training embankments or processes should be noted:
structures. • Saturation of an embankment
Channel changes, if properly designed, reduces its angle of repose.
can improve conditions of a crossing by Granular fills with high
reducing skew and curvature and permeability may "dissolve"
enlarging the main channel. steadily or slough progressively.
Unfortunately there are "side effects" Cohesive fills are less permeable,
which actually increase erosion but failures have occurred during
potential. Velocity is almost always falling stages.
increased by the channel change, both
• As eddies carve scallops in the
by a reduction of channel roughness and
embankment, saturation can be
increase of slope due to channel
accelerated and complete failure
shortening. In addition, channel
may be rapid. Partial or total losses
changes affecting stream gradient may
can occur due to an upstream eddy,
have upstream and/or downstream
a downstream eddy, or both eddies
effects as the stream adjusts in relation
eroding toward a central
to its sediment load.
conjunction. Training devices or
At crossing locations, lateral erosion armor can be employed to prevent
can be controlled by positive protection, damage.
such as armor on the banks, rock spurs
• If the fill is pervious and the
to deflect currents away from the banks,
pavement overtopped, the buoyant
retards to reduce riparian velocity, or
pressure under the slab will exceed
vertical walls or bulkheads. The life
the weight of slab and shallow
cycle cost of such devices should be
870-20 HIGHWAY DESIGN MANUAL
July 15, 2016

overflow by the pressure head of the meanders or where highway


hydraulic drop at the shoulder line. embankment encroaches on the main
A flat slab of thickness, t, will float channel.
when the upstream stage is 4t higher
The encroaching parallel location is
than the top of the slab. Thereafter
very common, especially for highways
the saturated fill usually fails
following mountain streams in narrow
rapidly by a combination of erosion
young valleys or canyons. Much of the
and sloughing. This problem can
roadway is supported on top of the bank
occur or be increased when curbs,
or a berm and the outer embankment
dikes, or emergency sandbags
encroaches on the channel in a zone of
maintain a differential stage at the
low to moderate velocity. Channel
embankment shoulder. It is
banks are generally stable and
increased by an impervious or less
protection, except at points of
pervious mass within the fill.
impingement, is seldom necessary.
Control of flotation, insofar as bank
protection is concerned, should be The constricting parallel location is an
obtained by using impervious extreme case of encroaching location,
armor on the upstream face of the causing such impairment of channel
embankment and a pervious armor that acceleration of the stream through
on the downstream face. the constriction increases its attack on
the highway embankment requiring
Culvert problem locations generally
extra protection, or additional waterway
occur in and along the downstream
must be provided by deepening or
transition. Sharp divergence of the high
widening along the far bank of the
velocity flow develops outward
stream.
components of velocity which attack
the banks directly by impingement and In young valleys, streams are capable of
indirectly by eddies entrained in quieter high velocity flows during flood stages
water. Downward components and the that may be damaging to adjacent
high velocity near the bed cause the highway facilities. Locating the
scour at the end of the apron. highway to higher ground or solid
support is always the preferred
Standard plans of warped wingwalls
alternative when practical.
have been developed for a smooth
transition from the culvert to a Characteristics to be considered
trapezoidal channel section. A rough include:
revetment extension to the concrete
• High velocity flow.
wingwalls is often necessary to reduce
high velocity to approximate natural • Narrow confined channels.
flow. Energy dissipaters may be used to
• Accentuated impingement.
shorten the deceleration process when
such a transition would be too long to be • Swift overflow.
economical. Bank protection at the end
of wingwalls is more cost effective in • Disturbed flow due to rock outcrops
most cases. on the banks or within the main
channel.
(2) Parallel Location. With parallel
locations the risk of erosion damage • Alterations in flow patterns due to
along young streams increases where the entrance of side streams into the
valleys narrow and gradients steepen. main channel.
The risk of erosion damage is greatest Protective methods that have proven
along the outer bend of natural effective are:
HIGHWAY DESIGN MANUAL 870-21
July 15, 2016

• Rock slope protection. dominant discharge. A discussion of


dominant discharge may be found in
• Concreted-rock slope protection. Hydraulic Design Series No. 6, but the
• Walls of masonry and concrete. bankfull flow condition is recommended for
use where a detailed analysis of dominant
• Articulated concrete block discharge is not feasible. In addition to the
revetments. general information previously given, the
• Sacked concrete. following applies to mature valleys:

• Cribs walls of various materials. (1) Cross-Channel Location. The usual


situation is a structure crossing a
(o) Mature Valley. Typically mature valleys braided or meandering normal flow
are broad V-shaped valleys with associated channel. The marginal area subject to
floodplains. See Figure 872.6. The gradient overflow is usually traversed by the
and velocity of the stream are low to highway on a raised embankment and
moderate. Streams in regions of lower relief may have long approaches extending
are usually alluvial and exhibit more from both banks.
problems because of lateral erosion in the
channels. Vegetative cover, land use, and Characteristics to be considered
flow depth on the floodplain are also include:
significant factors in stream channel • Shifting of the main channel.
stability. Changes in channel geometry with
time are particularly significant during • Skew of the stream to the structure.
periods when alluvial channels are • Foundation in deep alluvium.
subjected to high flows, and few changes
occur during relatively dry periods. Erosive • Erodible embankment materials.
forces during high-flow periods may have a • Channel constrictions, either
capacity as much as 100 times greater than artificial or natural, which may
those forces acting during periods of affect or control the future course of
intermediate and low-flow rates. the stream.
Figure 872.6 • Variable flow characteristics at
Mature Valley with Meandering various stages.
Stream • Stream acceleration at the structure.
Armor protection has proven effective
to prevent erosion of road approach
embankments, supplemented if
necessary by stream training devices
such as guide dikes, permeable retards
or jetties to direct the stream through the
structure. The abutments should not
depend on the training dikes to protect
them from erosion and scour. At bridge
ends one of the more substantial armor
types may be required, but bridge
Russian River near Geyserville
approach embankments affected only
When considering the stability of alluvial by overflow seldom require more than a
streams, in most instances it can be shown light revetment, such as a thin layer of
that approximately 90 percent of all changes rocky material, vegetation, or a fencing
occur during that small percentage of the along the toe of slope. For channel flow
time when the flow equals or exceeds
870-22 HIGHWAY DESIGN MANUAL
July 15, 2016

control upstream, the size and type of designs that consist of riprap, concrete,
training system ranges from pile wings or other inert structures alone may be
for high velocity, through permeable unacceptable for lack of environmental
jetties for moderate velocity, to the earth and aesthetic benefits. Resource
dike suitable for low velocity. agencies have increased interest in
designs that combine vegetation and
The more common failures in this
inert materials into living systems that
situation occur from:
can reduce erosion while providing
• Lack of upstream control of channel environmental and aesthetic benefits.
alignment.
(3) Desert Wash Locations. Particular
• Damage of unprotected consideration should be given to highway
embankments by overflow and locations that traverse natural geographical
return flow. features of desert washes, sand dunes, and other
similar regions.
• Undercut foundations.
Desert washes are a prominent feature of the
• Formation of eddies at abrupt physiography of California. Many long
changes in channel. stretches of highway are located across a
• Stranding of drift in the converging succession of outwash cones. Infrequent
channel. discharge is typically wide and shallow,
transporting large volumes of solids, both
(2) Parallel Location. Parallel highways mineral and organic. Rather than bridge the
along mature rivers are often situated on natural channels, the generally accepted
or behind levees built, protected and technique is to concentrate the flow by a series
maintained by other agencies. Along of guide dikes leading like a funnel to a
other streams, rather extensive relatively short crossing.
protective measures may be required to
control the action of these meandering An important consideration at these locations is
streams. instability of the channel, see Figure 872.7. For
a location at the top of a cone (Line A),
Channel change is an important factor discharge is maximum, but the single channel
in locations parallel to mature streams. emerging from the uplands is usually stable. For
The channel change may be to close an a location at the bottom of the cone (Line C),
embayment, to cut off an oxbow, or to instability is maximum with poor definition of
shift the alignment of a long reach of a the channel, but discharge is reduced by
stream. In any case, positive means infiltration and stream dispersion. The energy
must be adopted to prevent the return of of the stream is usually dissipated so that any
the stream to its natural course. For a protection required is minimal. The least
straight channel, the upstream end is desirable location is midway between top and
critical, usually requiring bank bottom (Line B), where large discharge may
protection equivalent to the facing of a approach the highway in any of several old
dam. On a curved channel change, all channels or break out on a new line. Control
of the outer bend may be critical, may require dikes continuously from the top of
requiring continuous protection. the cone to such a mid-cone site with slope
Continuous and resistive bank protection added near the highway where the
protection measures, such as riprap and converging flow is accelerated. See Figure
longitudinal rock toes are primarily 872.8, which depicts a typical alluvial fan.
used to armor outer bends or areas with
impinging flows. These continuous and Also common are roadway alignments which
concentrated high velocity areas will longitudinally encroach, or are fully within the
generally result in reduced aquatic desert wash floodplain, see Figure 872.9. Re-
habitat. Since streambank protection alignment to a stable location should be the first
HIGHWAY DESIGN MANUAL 870-23
July 15, 2016

consideration, but restrictions imposed by Figure 872.8


federal or state agencies (National Park Service,
USDA Forest Service, etc.) may preclude that
Alluvial Fan
option, somewhat similar to transverse
crossings. The designer may need to consider
allowing frequent overtopping and increased
sediment removal maintenance since an “all
weather design” within these regimes can often
lead to large scale roadway washout.

Figure 872.7
Alternative Highway Locations
Across Debris Cone

Typical multi-channel stream threads on alluvial fan.


Note location of roadway crossing unstable channels.
A. Cross at a single definite channel
Figure 872.9
B. A series of unstable indefinite channels and
C. A widely dispersed and diminished flow
Desert Wash Longitudinal
Encroachment
Characteristics to be considered include:
• The intensity of rainfall and subsequent run-
off.
• The relatively large volumes of solids that
are carried in such run-off.
• The lack of definition and permanence of
the channel.
• The scour depths that can be anticipated.
• The lack of good foundation. Road washout due to longitudinal location in desert
wash channel
Effective protective methods include armor
along the highway and at structures and the The Federal Emergency Management Agency
probable need for baffles to control the direction (FEMA) Flood Hazard Mapping website
and velocity of flow. Installations of rock, contains information on recognizing alluvial fan
fence, palisades, slope paving, and dikes have landforms and methods for defining active and
been successful. inactive areas. See their “Guidelines for
Determining Flood Hazards on Alluvial Fans” at
http://www.fema.gov/fhm/ft_tocs.shtm.
870-24 HIGHWAY DESIGN MANUAL
July 15, 2016

(4) Construction, Easements, Access and Staging. Numerous State and Federal agencies are
A primary site consideration for any bank responsible for fish management in California -
protection design is its constructability. This including California Department of Fish and
may include the need for supplemental plans and Wildlife, the National Marine Fisheries Service
temporary construction easements for stage and the United Stated Army Corps of Engineers.
construction to accommodate equipment access. Each agency has its own guidelines and
See Figure 872.10. jurisdiction. For example, detailed information
on the requirements for fish habitat in riparian
Figure 872.10 corridors may be found in Volume One and Two
Stage Construction of the California Salmonid Stream Habitat
Restoration Manual:
http://www.dfg.ca.gov/fish/Resources/Habitat
Manual.asp
872.4 Data Needs
The types and amount of data needed for planning
and analysis of channel protection varies from
project to project depending upon the class and
extent of the proposed protection, site location
environment, and geographic area. See Index 872.1.
The data that is collected and developed including
preliminary calculations, and alternatives
considered should be documented in project
development reports (Environmental Document,
Project Report, etc.) or as a minimum in the project
(5) Biodiversity. The riparian area provides one of file. These records serve to guide the detailed
the richest habitats for large numbers of fish and designs, and provide reference background for
wildlife species, which depend on it for food and analysis of environmental impacts and other needs
shelter. Many species, including coho and such as permit applications and historical
Chinook salmon, steelhead, yellow-billed documentation for any litigation which may arise.
cuckoo, and the red-legged frog, are threatened See Index 873.3(3)(a)(2)(b) for rock sizing equation
or endangered in California. Natural riparian parameters.
habitat also includes the assortment of native Recommendations for data needs can be requested
plants that occur adjacent to streams, creeks and from the District Hydraulics Engineer or determined
rivers. These plants are well adapted to the from Chapter 8 of FHWA’s HDS No. 6, for a more
dynamic and complex environment of complete discussion of data needs for highway
streamside zones. A key threat to fish species in crossings and encroachments on rivers. Further
any migrating corridor therefore will include references to data needs are contained in Chapter
loss of riparian habitat and instream cover 810, Hydrology and FHWA's HDS No. 2, Highway
affecting juvenile rearing and outmigration. Hydrology and HEC 20, Stream Stability at Highway
For channel and habitat characterization and Structures.
preliminary assessment relative to designing 872.5 Rapid Assessment
and obtaining project specific permits, District
biologist staff should be consulted early on The National Pollutant Discharge Elimination
within the project planning phase for subject System (NPDES) permit mandates a risk-based
matter expertise regarding fisheries, habitat, and approach to be employed during planning and
wildlife. District biologist staff can also design for assessing stream stability at highway
perform an initial stream habitat assessment. crossings. This approach involves conducting a
Contact information for Department biologists rapid pre-project assessment of the vertical and
can be accessed through the CalBioRoster. lateral stability of the receiving stream channel
HIGHWAY DESIGN MANUAL 870-25
July 15, 2016

related to an existing or planned highway crossing will provide recommendations for temporary and
structure. If the rapid stability assessment (RSA) permanent erosion and sediment control measures.
indicates potential problems, more detailed The Caltrans Bank and Shore Protection Committee
engineering analyses are required to determine if is available on request to provide advice on
countermeasures are needed to stabilize the crossing extraordinary situations or problems and to provide
to prevent the release of sediment. Therefore, if evaluation and formal approvals for acceptable non-
available, stream stability assessments for nearby standard designs. See Index 802.3 for further
highway crossings should be included in the site information on the organization and functions of the
consideration for channel protection. Committee.
Section 3 of Caltrans Hydromodification Combinations of armor-type protection can be used,
Requirements Guidance Storm Water Best the slope revetment being of one type and the
Management Practices Rapid Assessment of Stream foundation treatment of another. The use of rigid,
Crossings Higher Level Stream Stability Analysis is non-flexible slope revetment may require a flexible,
an excellent resource for understanding the concepts self-adjusting foundation for example: concreted-
of basic geomorphology and California earth rock on the slope with heavy rock foundation below,
science. or PCC slope paving with a steel sheet-pile cutoff
wall for foundation.
Table 8 of Assessing Stream Channel Stability at
Bridges in Physiographic Regions (FHWA-HRT- Bank protection may be damaged while serving its
05-072) presents an extensive listing of factors primary purpose. Lower cost replaceable facilities
affecting stream stability. may be more economical than expensive permanent
structures. However, an expensive structure may be
Topic 873 - Design Concepts economically warranted for highways carrying large
volumes of traffic or for which no detour is
873.1 Introduction available.
No attempt will be made here to describe in detail all Cost of stone is extremely sensitive to location.
of the various devices that have been used to protect Variables are length of haul, efficiency of the quarry
embankments against scour. Methods and devices in producing acceptable sizes, royalty to quarry and,
not described may be used when justified by necessity for stockpiling and rehandling. On some
economic analysis. Not all publicized treatments are projects the stone may be available in roadway
necessarily suited to existing conditions for a excavation.
specific project.
873.2 Design High Water and Hydraulics
A set of plans and specifications must be prepared to
define and describe the protection that the design The most important, and often the most perplexing
engineer has in mind. These plans should show obligation, in the design of bank and shore
controlling factors and an end product in such detail protection features is the determination of the
that there will be no dispute between the appropriate design high water elevation to be used.
construction engineer and contractor. To serve the The design flood stage elevation should be chosen
dual objectives of adequacy and economy, plans and that best satisfies site conditions and level of risk
specifications should be precise in defining associated with the encroachment. The basis for
materials to be incorporated in the work, and flexible determining the design frequency, velocity,
in describing methods of construction or backwater, and other limiting factors should include
conformance of the end product to working lines and an evaluation of the consequences of failure on the
grades. highway facility and adjacent property. Stream
stability and sediment transport of a watercourse are
Recommendations on channel lining, slope critical factors in the evaluation process that should
protection, and erosion control materials can be be carefully weighted and documented. Designs
requested from the District Hydraulic Engineer, the should not be based on an arbitrary storm or flood
District Materials Branch and the Office of Highway frequency.
Drainage and Water Quality Design in
Headquarters. The District Landscape Architect
870-26 HIGHWAY DESIGN MANUAL
July 15, 2016

A suggested starting point of reference for the damage should always be anticipated during
determination of the design high water level is that high water stages.
the protection withstands high water levels caused
Essential to the design of streambank protection
by meteorological conditions having a recurrence
is sufficient information on the characteristics of
interval of one-half the service life of the protected
the watercourse under consideration. For proper
facility. For example, a modern highway
analysis, information on the following types of
embankment can reasonably be expected to have a
watercourse characteristics must be developed
service life of 100 years or more. It would therefore
or obtained:
be appropriate to base the preliminary evaluation on
a high water elevation resulting from a storm or • Design Discharge
flood with a 2 percent probability of exceedance
• Design High Water Level
(50 year frequency of recurrence). The first
evaluation may have to be adjusted, either up or • Flow Types
down, to conform with a subsequent analysis which
considers the importance of the encroachment and • Channel Geometry
level of related risks which may include • Flow Resistance
consideration of historic high water marks and
climate change. Scour countermeasures protecting • Sediment Transport
structures designed by the Division of Engineering Refer to Chapter 810, Hydrology, for a general
Services (DES) may include consideration of floods discussion on hydrologic analysis and
greater than a 1 percent probability of exceedance specifically to Topic 817, Flood Magnitudes;
(100 year frequency of recurrence). Topic 818, Flood Probability and Frequency;
There is always some risk associated with the design and Topic 819, Estimating Design Discharge.
of protection features. Special attention must be For a detailed discussion on the fundamentals of
given to life threatening risks such as those alluvial channel flow, refer to Chapter 3, HDS
associated with floodplain encroachments. No. 6, and to Chapter 4, HDS No. 6, for further
Significant floodplain risks are classified as those information on sediment transport.
having probability of: (2) Ocean & Lake Shore Locations. Refer to
• Catastrophic failure with loss of life. Chapter 880 for information needed to design
shore protection.
• Disruption of fire and ambulance services or
closing of the only evacuation route available to 873.3 Armor Protection
a community. (1) General. Armor is the artificial surfacing of
Refer to Topic 804, Floodplain Encroachments, for bed, banks, shore or embankment to resist
further discussion on evaluation of risks and erosion or scour. Armor devices can be flexible
impacts. (self-adjusting) or rigid.

(1) Streambank Locations. The velocity along the Hard armoring of stream banks, primarily with
banks of watercourses with smooth or uniformly rock slope protection (RSP), has been the most
rough tangent reaches may only be a small common means of providing long-term
percentage of the average stream velocity. protection for transportation facilities, and most
However, local irregularities of the bank and importantly, the traveling public. With many
streambed may cause turbulence that can result years of use, dozens of formal studies and
in the bank velocity being greater than that of thousands of constructed sites, RSP is the armor
the central thread of the stream. The location of type for which there exists the most quantifiable
these irregularities is not always permanent as data on performance, constructability,
they may be caused by local scour, deposition of maintainability and durability, and for which
rock and sand, or stranding of drift during high there exist several nationally recognized design
water changes. It is rarely economical to protect methods.
against all possibilities and therefore some
HIGHWAY DESIGN MANUAL 870-27
July 15, 2016

Due to the above factors, RSP is the general assistance together with specifications and
standard against which other forms of armoring details for the vegetative portion of this work.
are compared.
(a) Flexible Types.
The results of internal research led to the
• Rock slope protection.
publication of Report No. FHWA-CA-TL-95-
10, “California Bank and Shore Rock Slope • Gabions, Standard Plan D100A and
Protection Design”. Within that report, the D100B.
methodology for RSP design adopted as the
Departmental standard for many years, was the • Precast concrete articulated blocks.
California Bank and Shore, (CaBS), layered (b) Rigid Types.
design. The CaBS layered design methodology
and its associated gradations have become • Concreted-rock slope protection.
obsolete. For reference only, the full report is • Partially-grouted rock slope protection.
available at the following website:
• Sacked concrete slope protection.
http://www.dot.ca.gov/hq/oppd/hydrology/hydr
oidx.htm. • Concrete filled cellular mats.
FHWA Hydraulic Engineering Circular No. 23 (2) Bulkheads. The bulkhead types are steep or
(HEC 23) presents guidelines for RSP for a vertical structures, like retaining walls, that
range of applications, including: RSP on support natural slopes or constructed
streams and river banks, bridge piers and embankments which include the following:
abutments, and bridge scour countermeasures • Gravity or pile supported concrete or
such as guide banks and spurs. These guidelines masonry walls.
were formally adopted by the Caltrans Bank and
Shore Protection Committee with a modified • Crib walls
version of HEC 23 gradations. See Tables • Sheet piling
873.3A and 873.3B as well as HEC 23, Volume
1, Chapter 5 and Design Guideline 4, 5, 11, 12, (a) General Design Criteria. In selecting the
15 and 16 from Volume 2. Section 72 of the type of flexible or rigid armor protection to
Standard Specifications provides all use the following characteristics are
construction and material specifications for RSP important design considerations.
designs. While standards (i.e., Standard Plans, (1) The lower limit, or toe, of armor should
Standard Specifications and/or SSP’s) do exist be below anticipated scour or on
for some other products discussed in this bedrock. If for any reason this is not
Chapter (most notably for gabions, but also for economically feasible, a reasonable
certain rolled or mat-style erosion control degree of security can be obtained by
products), their primary application is for placement of additional quantities of
relatively flat slope or shallow ditch erosion heavy rock at the toe which can settle
control (gabions are also used as an earth vertically as scour occurs.
retaining structure, see Topic 210 for more
details). (2) In the case of slope paving or any
expensive revetment which might be
Rigid and other armor types listed below are seriously damaged by overtopping and
viable and may be considered where conditions subsequent erosion of underlying
warrant. Although the additional step of embankment, extension above design
headquarters approval of any nonstandard high water may be warranted. The
designs is required, designers are encouraged to usual limit of extension for streambank
consider alternative designs, particularly those protection above design high water is
that incorporate vegetation or products naturally 1 foot to 2 feet in unconstricted reaches
present in stream environments. The District
Landscape Architect can provide design
870-28 HIGHWAY DESIGN MANUAL
July 15, 2016

and 2 feet to 3 feet in constricted (3) Flexible Revetments.


reaches.
(a) Streambank Rock Slope Protection.
(3) The upstream terminal can be
(1) General Features. This kind of
determined best by observation of
protection, commonly called riprap,
existing conditions and/or by measuring
consists of rock courses placed upon the
velocities along the bank.
embankment or the natural slope along
The terminal should be located to a stream. Rock, as a slope protection
conform to outcroppings of erosion- material, has a number of desirable
resistant materials, trees, shrubs or other features which have led to its
indications of stability. widespread application.
In general, the upstream terminal on It is usually the most economical type of
bends in the stream will be some revetment where stones of sufficient
distance upstream from the point of size and quality are available, it also has
impingement or the beginning of curve the following advantages:
where the effect of erosion is no longer
• It is flexible and is not impaired nor
damaging.
weakened by slight movement of
(4) When possible the downstream terminal the embankment resulting from
should be made downstream from the settlement or other minor
end of the curve and against adjustments.
outcroppings, erosion-resistant
materials, or returned securely into the • Local damage or loss is easily
bank so as to prevent erosion by eddy repaired by the addition of similar
currents and velocity changes occurring sized rock where required.
in the transition length. • Construction is not complicated and
(5) The encroachment of embankment into special equipment or construction
the stream channel must be considered practices are not usually necessary.
with respect to its effect on the (Note that Method A placement of
conveyance of the stream and possible very large rock may require large
damaging effect on properties upstream cranes or equipment with special
due to backwater and downstream due lifting capabilities).
to increased stream velocity or • Appearance is natural, and usually
redirected stream flow. acceptable in recreational and
(6) A smooth surface will generally scenic areas.
accelerate velocity along the bank, • If exposed to fresh water,
requiring additional treatment (e.g., vegetation may be induced to grow
extended transition, cut-off wall, etc.) at through the rocks adding structural
the downstream terminal. Rougher value to the embankment material
surfaces tend to keep the thread of the and restoring natural roughness.
stream toward the center of the channel. See Index 873.3(3)(a)(2)(d) for
(7) Heavy-duty armor used in exposures further vegetative rock slope
along the ocean shore may be protection information.
influenced or dictated by economics, or • Additional thickness (i.e., mounded
the feasibility of handling heavy toe design) can be provided at the
individual units. toe to offset possible scour when it
is not feasible to found it upon
bedrock or below anticipated scour.
HIGHWAY DESIGN MANUAL 870-29
July 15, 2016

• It is salvageable, may be stockpiled Army Corps of Engineers. Based


and reused if necessary. on the flume studies at the Corps’
Waterways Experiment Station, the
In designing the rock slope protection
program is primarily used by the
for a given embankment the following
Corps for RSP designs on streams
determinations are to be made for the
with 2 percent or lesser gradients,
typical section.
but contains an option for scour
• Depth at which the stones are depth estimates in bends for sand
founded (bottom of toe trench). channels. CHANLPRO is available
at the following USACE website:
• Elevation at the top of protection. http://chl.erdc.usace.army.mil/chan
• Thickness of protection. lpro along with a user guide
containing equations, charts,
• Need for geotextile or rock filter assumptions and limitations to the
material. method and example problems.
• Face slope. (c) Embankment Considerations.
(a) Placement. Two different methods Embankment material is not
of placement for rock slope normally carried out over the rock
protection are allowed under slope protection so that the rock
Section 72 of the Standard becomes part of the fill. With this
Specifications: Placement under type of construction fill material
Method A requires considerable can filter down through the voids of
care, judgment, and precision and is the large stones and that portion of
consequently more expensive than the fill above the rocks could be
Method B. Method A should be lost. If it is necessary to carry
specified primarily where large embankment material out over the
rock is required, but also for rock slope protection a geotextile is
relatively steeper slopes. required to prevent the loses of fill
material.
(b) Foundation Treatment. The
foundation excavation must afford The embankment fill slope is
a stable base on bedrock or extend usually determined from other
below anticipated scour. considerations such as the angle of
repose for embankment material, or
Terminals of revetments are often the normal 1V:4H specified for
destroyed by eddy currents and high-standard roads. If the
other turbulence because of necessary size of rock for the given
nonconformance with natural exposure is not locally available,
banks. Terminals should be consideration should be given to
secured by transitions to stable bank flattening of the embankment slope
formations, or the end of the to allow a smaller size stone, or
revetment should be reinforced by substitution of other types of
returns of thickened edges. protection. On high embankments,
While a significant amount of alternate sections on several slopes
research is currently being should be compared, practically and
conducted, few methods exist for economically; flatter slopes require
estimating scour along stream smaller stones in thinner sections,
banks. One of the few is the method but at the expense of longer slopes,
contained in HEC 23 Volume 1, a lower toe elevation, increased
Index 4.3.5 and the CHANLPRO embankment, and perhaps
Program developed by the U.S. additional right of way.
870-30 HIGHWAY DESIGN MANUAL
July 15, 2016

Where the roadway alignment is where CA Fish & Wildlife and


fixed, slope flattening will often NOAA Fisheries strongly
increase embankment discourage the use of RSP Fabric, a
encroachment into the stream. gravel filter is usually necessary
When such an encroachment is with most native soil conditions to
environmentally or technically stop fines from bleeding through
undesirable, the designer should the typical RSP classes. A gravel
consider various vertical, or near filter will be specified and placed
vertical, wall type alternatives to between the native base soil and
provide adequate stream width, RSP for hybrid revetments to avoid
allowing natural channel migration conflicts associated with planting
and the opportunity for enhancing vegetation and placing RSP fabric
habitat. together. A universal gravel filter
gradation is presented in Design
(d) Rock Slope Protection Fabric.
Information Bulletin No. 87 (see
Rock Slope Protection fabrics are
Table H, Index 7.1.2), which should
described in Standard Specification
work for many stream sites in
Section 96. The RSP fabric
California and eliminate the need
placement ensures that fine soil
for a site-specific gravel filter
particles do not migrate through the
design for every project.
RSP due to hydrostatic forces and,
thus, eliminate the potential for When a gravel filter is to be placed,
bank failure. The use of RSP fabric the designer is advised to work with
provides an inexpensive layer of the District Materials Office to get a
protection retaining embankment recommendation for the necessary
fines in lieu of placing a gravel filter gradation to work effectively with
of small, well graded materials. See both the native backfill and the base
Index 873.3(3)(a)(1)(e) “Gravel layer of the RSP that is being
Filter.” placed. Among the methods
available for designing the gravel
Stronger and heavier RSP fabrics
filter are the Terzaghi method,
than those listed in the Standard
developed exclusively for situations
Specifications are manufactured.
where the native backfill is sand,
They are used in special designs for
and the Cisten-Ziems method,
larger than standard RSP sizes, or
which is often used for a broad
emergency installations where
variety of soil types and
placement of large RSP must be
recommended in HEC 23. Where
placed directly on the fabric. These
streambanks must be significantly
heavy weight fabrics have unit
rebuilt and reconfigured with
weights of up to 16 ounces per
imported material before RSP
square yard. Contact the
placement, the designer must
Headquarters Hydraulic Engineer
ensure that the imported material
for assistance regarding usage
will not bleed through the designed
applications of heavy weight RSP
gravel filter. See HEC 23 Volume
fabrics.
2, Design Guideline 16, Index
(e) Gravel Filter. Generally RSP 16.2.1 Granular Filter Design
fabric should always be used unless Procedure and 16.3.1 Granular
there is a permit requirement that filter (design example).
precludes the placement of fabric.
(2) Streambank Protection Design. In the
Where RSP fabric cannot be placed,
lower reaches of larger rivers wave
such as in stream environments
action resulting from navigation or
HIGHWAY DESIGN MANUAL 870-31
July 15, 2016

wind blowing over long reaches may be material to slough into local scour
much more serious than velocity. A holes (i.e., mounded toe).
2 foot wave, for example, is more
• Reinforce critical zones on outer
damaging than direct impingement of a
bends subject to impinging flow,
current flowing at 10 feet per second.
using heavier stones, thicker
Therefore, consideration of a wave
section, and deeper toe.
attack based design may be necessary.
See Chapter 880 for further • Be constructed of rock of such
information. shape as to form a stable protection
Well designed streambank rock slope structure of the required section.
protection should: Rounded boulders or cobbles must
not be used on prepared ground
• Assure stability and compatibility surfaces having slopes steeper than
of the protected bank as an integral 2.5H:1V.
part of the channel as a whole.
(a) Stone Shape. The shape of a stone
• Connect to natural bank, bridge can be generally described by
abutments or adjoining designating three axes of
improvements with transitions measurement: major, intermediate,
designed to ease differentials in and minor, also known as the “A, B,
alignment, grade, slope and and C” axes, as shown in Figure
roughness of banks. 873.3A.
• Eliminate or ease local embayments Figure 873.3A
and capes so as to streamline the
protected bank. Stone Shape
• Consider the effects of backwater
above constrictions,
superelevations on bends, as well as
tolerance of occasional
overtopping.
• Not be placed on a slope steeper
than 1.5H:1V. Flatter slopes use
lighter stones in a thinner section
and encourage overgrowth of
vegetation, but may not be
Riprap stones should not be thin and
permissible in narrow channels.
platy, nor should they be long and
• Use stone of adequate weight to needle-like. Therefore, specifying a
resist erosion, derived from Index maximum allowable value of the
873.3(3)(a)(2)(b). ratio A/C, also known as the shape
factor, provides a suitable measure
• Prevent loss of bank materials of particle shape, since the B axis is
through interstitial spaces of the intermediate between the two
revetment. Rock slope protection extremes of length A and thickness
fabric should be used. C. A maximum allowable value for
• Rest on a good foundation on A/C of 3.0 is recommended.
bedrock or extend below the depth Based on field studies, the
of probable scour. If questionable, recommended relationship between
use heavy bed stones and provide a stone size and weight is given by:
wide base section with a reserve of
870-32 HIGHWAY DESIGN MANUAL
July 15, 2016

Table 873.3A
RSP Class by Median Particle Size(3)
Nominal RSP Class by
d15 d50 d100 Placement
Median Particle Size(3)
Class (1), (2) Size (in) Min Max Min Max Max Method
I 6 3.7 5.2 5.7 6.9 12.0 B
II 9 5.5 7.8 8.5 10.5 18.0 B
III 12 7.3 10.5 11.5 14.0 24.0 B
IV 15 9.2 13.0 14.5 17.5 30.0 B
V 18 11.0 15.5 17.0 20.5 36.0 B
VI 21 13.0 18.5 20.0 24.0 42.0 A or B
VII 24 14.5 21.0 23.0 27.5 48.0 A or B
VIII 30 18.5 26.0 28.5 34.5 48.0 A or B
IX 36 22.0 31.5 34.0 41.5 52.8 A
X 42 25.5 36.5 40.0 48.5 60.5 A
XI 46 28.0 39.4 43.7 53.1 66.6 A
NOTES:
(1) Rock grading and quality requirements per Standard Specifications.
(2) RSP-fabric Type of geotextile and quality requirements per Section 96 Rock Slope Protection Fabric of the Standard
Specifications. For RSP Classes I thru VIII, use Class 8 RSP-fabric which has lower weight per unit area and it also
has lower toughness (tensile x elongation, both at break) than Class 10 RSP-fabric. For RSP Classes IX thru XI, use
Class 10 RSP-fabric.
(3) Intermediate, or B dimension (i.e., width) where A dimension is length, and C dimension is thickness.
HIGHWAY DESIGN MANUAL 870-33
July 15, 2016

Table 873.3B
RSP Class by Median Particle Weight(3)
Nominal RSP Class by
W15 W50 W100 Placement
Median Particle Weight
Class (1), (2) Weight Min Max Min Max Max Method
I 20 lb 4 11 15 27 140 B
II 60 lb 14 39 50 94 470 B
III 150 lb 32 94 120 220 1,100 B
IV 300 lb 63 180 250 440 2,200 B
V 1/4 ton 110 300 400 700 3,800 B
VI 3/8 ton 180 520 650 1,100 6,000 A or B
VII 1/2 ton 250 750 1000 1,700 9,000 A or B
VIII 1 ton 520 1,450 1,900 3,300 9,000 A or B
IX 2 ton 870 2,500 3,200 5,800 12,000 A
X 3 ton 1,350 4,000 5,200 9,300 18,000 A
XI 4 ton 1,800 5,000 6,800 12,200 24,000 A
NOTES:
(1) Rock grading and quality requirements per Standard Specifications.
(2) RSP-fabric Type of geotextile and quality requirements per Section 96 Rock Slope Protection Fabric of the Standard
Specifications. For RSP Classes I thru VIII, use Class 8 RSP-fabric which has lower weight per unit area and it also
has lower toughness (tensile x elongation, both at break) than Class 10 RSP-fabric. For RSP Classes IX thru XI, use
Class 10 RSP-fabric.
(3) Values shown are based on Table 873.3A dimensions and an assumed specific gravity of 2.65. Weight will vary
based on density of rock available for the project.
870-34 HIGHWAY DESIGN MANUAL
July 15, 2016

𝑊𝑊 = 0.85(𝛾𝛾𝑠𝑠 𝑑𝑑3 ) Based on the recommended


relationship between size and
Where:
weight, which assumes the volume
W = Weight of stone, lb; of the stone is 85% of a cube, Table
873.3B provides the equivalent
d = Size of intermediate ("B")
particle weights for the same eleven
axis, ft;
classes as Table 873.3A using a
γs = Density of stone, lb/ft3; specific gravity of 2.65 for the
= Sg γw particle density.

Where: (b) Stone Size. Where stream velocity


governs, rock size may be estimated
γw = 62.4 lb/ft3; from the following formula, which can
Sg = Specific gravity of be used with uniform or gradually
stone. varying flow. Coefficients are included
to account for the desired safety factor
Tables 873.3A and 873.3B provide for design, specific gravity of the riprap
recommended gradations for eleven stone, bank slope, and bendway
standard classes of riprap based on character;
median particle size d50 as
determined by the dimension of the 𝑑𝑑30
2.5
intermediate ("B") axis. The D or ⎡ ⎤
W refers to size or weight, 𝑉𝑉𝑑𝑑𝑑𝑑𝑑𝑑
= 𝑦𝑦�𝑆𝑆𝑓𝑓 𝐶𝐶𝑆𝑆 𝐶𝐶𝑉𝑉 𝐶𝐶𝑇𝑇 � ⎢ ⎥
respectively. The number is the ⎢ ⎥
�𝐾𝐾 �𝑆𝑆 − 1�𝑔𝑔𝑔𝑔
percent finer by weight. Tables ⎣ 1 𝑔𝑔 ⎦
873.3A and 873.3B are modified
versions of Tables 4.1 and 4.2 in Where:
HEC 23, Volume 2, Design d30 = Particle size for which
Guideline 4, which provide 30% is finer by weight, ft;
recommended gradations for ten
y = Local depth of flow, ft;
standard classes of riprap and
conform to those recommended in Sf = Safety factor (typically =
NCHRP Report 568 (Lagasse et al. 1.1);
2006). The gradation criteria in
CS = Stability coefficient (for
Table 873.3A are based on a
blanket thickness 1.5d50 or
nominal or "target" d50. See Index
d100, whichever is greater)
873.3(3)(a)(2)(b) for equations to
= 0.30 for angular rock;
calculate d30 and d50. The most
significant modifications to Tables CV = Velocity distribution
873.A and 873.B from the coefficient;
gradations shown in Tables 4.1 and = 1.0 for straight channels or
4.2 are to the d100max and W100max the inside of bends;
gradation for classes VIII through
XI, which have been truncated for = 1.283 – 0.2 log (Rc/W) for
practicality. An additional class XI the outside of bends (1.0
is included in Tables 873.3A and for Rc/W > 26);
873.3B. Contact the Headquarters = 1.25 downstream from
Hydraulic Engineer if more concrete channels;
information is needed on the
modification to the HEC 23 = 1.25 at the end of dikes;
gradations.
HIGHWAY DESIGN MANUAL 870-35
July 15, 2016

CT = Blanket thickness depth can be used. The smaller of


coefficient = 1.0; these values will result in a slightly
larger computed d30 size, since
Sg = Specific gravity of stone
riprap size is inversely proportional
(2.5 minimum);
to (y0.25). The blanket thickness
g = Acceleration due to coefficient (CT) is 1.0 for standard
2
gravity, 32.2 ft/s ; riprap applications where the
Vdes = Characteristic velocity for thickness is equal to 1.5d50 or d100,
design, defined as the whichever is greater. Because
depth-averaged velocity at limited data is available for
a point 20% upslope from selecting lower values of CT when
the toe of the revetment, greater thicknesses of riprap are
ft/s; used, a value of 1.0 is reasonable for
all applications. The recommended
For natural channels, Safety Factor Sf is 1.1 for bank
Vdes = Vavg (1.74 – 0.52 log (Rc/W)) revetment. Greater values should
Vdes = Vavg for Rc/W > 26 be considered where there is
significant potential for ice or
For trapezoidal channels, impact from large debris, freeze-
Vdes = Vavg (1.71 – 0.78 log (Rc/W)) thaw degradation that would
Vdes = Vavg for Rc/W > 8 significantly decrease particle size,
or large uncertainty in the design
Where: variables, especially velocity. The
Rc = Centerline radius of specific gravity (Sg) of stone is
curvature of channel commonly taken as 2.65 for
bend, ft; planning purposes, however, this
will result in a less conservative
W = Width of water design than utilizing a 2.5 specific
surface at upstream gravity assumption, which would
end of channel bend, be the minimum accepted in the
ft; field. Therefore, the designer
Vavg = Channel cross- should contact the District
sectional average Materials Engineer in the project’s
velocity, ft/s; area and determine if there is any
history of RSP materials used in
K1 = Side slope correction that region. Where such
factor; information or history is
1.6 unavailable, use of a 2.5 specific
sin(𝜃𝜃 − 14°) gravity within the design should be
𝐾𝐾1 = �1 − � �
sin 32° considered.
Where: The d30 size of the riprap is related
to the recommended median (d50)
θ = is the bank angle in size by:
degrees.
d50 = 1.20d30
The flow depth "y" used in the
above equation is defined as the Using standard sizes the
local flow depth. The flow depth at appropriate gradation can be
the toe of slope is typically used for achieved by selecting the next
bank revetment applications; larger size class, thereby creating a
alternatively, the average channel slightly over-designed structure,
870-36 HIGHWAY DESIGN MANUAL
July 15, 2016

but economically a less expensive resulting potential for damage to the


one. For example, if a riprap sizing bank, the potential for streambed
calculation results in a required d50 aggradation; and the confidence in
of 16.8 inches, Class V riprap data used to estimate design
should be specified because it has a highwater. Freeboard may also be
nominal d50 of 18 inches. See Table affected by regulatory or local
873.3A. agency requirements. Freeboard
may be more generous on the
A limitation to the rock size
outside bends of channels, or
equation above is that the
around critical bridges.
longitudinal slope of the channel
should not be steeper than 2.0% The 50-year design high water plus
(0.02 ft/ft). For steeper channels, freeboard goal should be followed
the riprap sizing approach for whenever possible, but the biggest
overtopping flows presented in exception to this goal occurs when
HEC 23, Volume 2, Design the design height exceeds the main
Guideline 5 should be considered channel top of bank. Because
and the results compared with the floodplain overbank areas can be
rock size equation above . wide and extensive, the footprint of
the RSP could grow exponentially
Where wave action is dominant,
if extended above and beyond the
design of rock slope protection
top of bank. This increased
should proceed as described for
footprint would bring higher costs
shore protection, see Chapter 880.
and permitting challenges that
(c) Design Height. The top of rock could make a project no longer
slope protection along a stream viable. Given this possibility, the
bank should be carried to the RSP vertical limit (height) should
elevation of the design high water typically end at the main channel
plus some allowance for freeboard. top of bank; however, a vegetation
Cost and severity of damage if component may extend above and
overtopped as well as the beyond the top of bank.
importance of the facility should
For cases where significant erosion
also be considered. The goal for the
has occurred above the main
design high water is based on the
channel top of bank into its
50-year (2% probability) flow, but
overbank(s), contact the District
can be modified using engineering
Hydraulic Engineer to discuss
judgment which may include
alternatives for repair and
consideration of historic high
protection.
water marks and climate change.
This stage may be exceeded during Design Example -- The following
infrequent floods, usually with little example reflects the HEC 23
or no damage to the upper slope. method for designing RSP. The
See Hybrid RSP cross section in designer is encouraged to review
Figure 873.3D for an example Design Guideline 4, Riprap
showing the top of rock slope Revetment from HEC 23, Volume
protection. 2. The following example assumes
that the designer has conducted the
When determining freeboard, or the
appropriate site assessments and
height above design high water
resulting calculations to establish
from which the RSP is to extend,
average stream velocity, flow depth
one should consider: the size and
at bank toe, estimated depth of
nature of debris in the flow; the
HIGHWAY DESIGN MANUAL 870-37
July 15, 2016

scour, stream alignment (i.e., 1.6


sin(26.6° − 14°)
parallel or impinging flow), width = �1 − � �
of channel, radius of bend (if sin 32°
impinging flow ), length and side
slope of stream bank to be protected = 0.87
and locations of natural hard points Step 2: Select the appropriate
(e.g., rock outcroppings). Field stability coefficient for riprap:
reviews and discussions with Cs (for blanket thickness 1.5d50 or
maintenance staff familiar with the d100, whichever is greater) = 0.30
site are critical to the success of the for angular rock
design.
Step 3: Compute the vertical
Given for example: velocity factor (Cv) for Rc /W = 5.0:
• Average stream velocity for Cv = 1.283 − 0.2 log (Rc/W)
design event of 9.8 feet per = 1.283 − 0.2 log (5.0)
second = 1.14

• Flow depth of 11.4 feet at bank Step 4: Compute local velocity on


toe the side slope (Vdes) for a natural
channel with Rc/W = 5.0:
• Estimated scour depth – Vdes = Vavg [1.74− 0.52 log (Rc /W)]
3.5 feet = 9.8[1.74 − 0.52 log (5.0)]
• Length of bank requiring = 13.5 ft/s
protection – 550 feet Step 5: Compute the d30 size using
• Bank slope – 2:1 stone size equation from Index
873.2(2)(a)(2)(b):
• Specific gravity of rock used 𝑉𝑉𝑑𝑑𝑑𝑑𝑑𝑑
2.5
for RSP – 2.54 (based on data 𝑑𝑑30 = 𝑆𝑆𝑓𝑓 𝐶𝐶𝑠𝑠 𝐶𝐶𝑣𝑣 𝑦𝑦 � �
from local quarry) �(𝑆𝑆𝑆𝑆 − 1)𝐾𝐾1 𝑔𝑔𝑔𝑔
= (1.2)(0.3)(1.14)(11.4)
• Embankment is on outside of 13.5
2.5
stream bend of 100 ft wide � �
natural channel on a bend that �(2.54 − 1)(0.87)(32.2)(11.4)
has a centerline radius (Rc) of = 1.35 ft
500 ft. The radius of curvature Step 6: Compute the d50 size =
divided by width (Rc/W) is 5.0. 1.2d30 = 1.2(1.35)
• A desired factor of safety (Sf) = 1.62 ft = 19 inches.
of 1.2. Note: Use next larger size class (see
Determine the target d50, select Table 873.3A)
appropriate RSP class from Table Step 7: Select Class VI riprap from
873.3A and determine the blanket Table 873.3A: d50 = 21 inches
thickness:
Step 8: Blanket thickness = 1.5d50
Step 1: Compute the side slope or d100, whichever is greater
correction factor: 1.5d50 = 1.5 (21 inches)
1.6
= 31.5 inches
sin(𝜃𝜃 − 14°) d100 = 42 inches, therefore, use
𝐾𝐾1 = �1 − � �
sin 32° 42 inches
Step 9: Determine the depth of
riprap embedment below the
870-38 HIGHWAY DESIGN MANUAL
July 15, 2016

streambed at the toe of the bank facility. As for the upstream and
slope: downstream ends, the given length
of revetment is 550 feet. Again, this
Since toe scour is expected to be
will typically be a minimum, as the
3.5 ft, the 2H:1V slope should be
designer should seek natural rock
extended below the ambient bed
outcroppings, areas of quiescent
level 7 ft horizontally out from the
stream flow, or other inherently
toe to accommodate this scour.
stable bank segments to end the
Alternatively, a mounded riprap toe
RSP.
3.5 ft high could be established at
the base of the slope and allowed to (d) Vegetated Rock Slope Protection.
self-launch when toe scour occurs, The use of vegetation in streambank
see Figure 873.3D. stabilization has positive attributes
on stream integrity, such as
Step 10: Assess Stream Impact Due
improving stream ecology,
to Revetment. In some cases, the
increasing soil strength, and
thickness of the completed RSP
providing flow resistance, but
revetment creates a narrowing of
vegetation can also have negative
the available stream channel width,
impacts on stream integrity by
to the extent that stream velocity or
altering conveyance characteristics
stage at the design event is
of the stream, affecting soil
increased to undesirable levels, or
characteristics, in addition to being
the opposite bank becomes
unpredictable in its long term
susceptible to attack. In these cases,
establishment and performance.
the bank upon which the RSP is to
be placed must be excavated such Streams with stable vegetation
that the constructed face of the typically have good water quality,
revetment is flush with the original as well as good biological and
embankment. chemical health due in part to the
ability of the vegetation to filter
Step 11: Exterior Edges of
pollutants including nitrates and
Revetment. The completed design
phosphates through their uptake of
must be compatible with existing
moisture in the soil. Vegetation
and future conditions. Freeboard
will also promote good fish,
and top edge of revetments were
wildlife, and aquatic organism
covered in Index 873.3(2)(a)(2)(c)
habitat by providing cover,
“Design Height.” For depth of toe,
reducing stream temperature and
the estimated scour was given as
controlling temperature
3.5 feet. This is the minimum toe
fluctuations, and supplying an
depth to be considered. Again,
organic food source. In addition to
based on site conditions and
ecological improvements,
discussions with maintenance staff
vegetation can strengthen the
and others, determine if any long-
underlying soils. It can create
term conditions need to be
additional cohesion and binding
addressed. These could include
properties through its roots. The
streambed degradation due to local
fibrous woody roots are strong in
aggregate mining or headcutting.
tension, but weak in compression,
Regardless of the condition, the toe
which is the opposite case for soil.
must be founded below the lowest
Therefore, roots and soil working in
anticipated elevation that could
tandem can complement the other
become exposed over the service
providing a material that has both
life of the embankment or roadway
tension and compression resistance.
HIGHWAY DESIGN MANUAL 870-39
July 15, 2016

Vegetation can also improve soil process, and the n-value and
strength by lowering pore-water velocity/flow resistance will also be
pressure through its soil moisture dynamic making revetment
extraction. performance unpredictable. Even
though the use of vegetation in bank
These benefits of the vegetation
stabilization may have negative
root system also carry some
effects, its ecological benefits
negative effects. Their additional
generally outweigh them.
mass and surcharge can increase
slope failure potential under The design premise is to use rock
saturated conditions where the and vegetation together in a
magnitude of saturation can streambank revetment in such a
actually be compounded because of way that will highlight their
root development. Another positive positive attributes while also
effect of vegetation use in addressing and managing their
revetments is its ability to improve negative impacts. In the design of
flow resistance creating higher hybrid revetments, mounded toes
roughness that will dissipate referenced in Index 873.3(3)(a)(1)
energy, shear stress, and velocity. are not recommended because of
The vegetation deflects velocity their encroachment into the middle
upwards away from the of the channel, which can impact
streambank, which reduces the cross-sectional area and capacity.
influence of drag and lift. For With the use of vegetation on the
example, willows planted on a bank and possible projection
streambank have the capacity to toward the middle of the channel,
deflect and resist velocities up to cross-sectional area could possibly
10 feet/second in their mature state, be impacted as well. A mounded
which would equate to a 12-inch to toe used with bank vegetation
18-inch rock (RSP Class III to IV) would only exacerbate this issue,
having similar permissive velocity. therefore an embedded toe is
To reach this point, it may take chosen for hybrid revetment
three to five years. In the first few application. See Figure 873.3D for
years after planting, the vegetation an example cross section of hybrid
is providing little resistance. RSP with an embedded toe. For
During this establishment period, hybrid revetment design, the
the streambanks can be subject to 50-year (2% probability) flood
scour and erosion because of the event should be used. Per Index
lack of flow resistance without 873.2, depending on the importance
some other means of protection. of the encroachment and level of
Even after vegetation reaches related risks, subsequent analysis
maturity and beyond, potential may consider historic high water
exists for it to succumb to drought marks and climate change for
conditions or to yield to large design. In order to manage possible
flows/velocities and break apart negative impacts from vegetation
rendering the vegetation ineffective use, planting needs to be performed
to dissipating velocity and in a controlled manner. Placement
hydraulic forces. Because the of vegetation within the bank-toe
stages of vegetation growth can be zone and the main channel is highly
dynamic as it is affected by drought discouraged to keep turbulence
or high flows, the vegetation may intensity in check that could cause
go through a reestablishment excessive sediment accumulation.
870-40 HIGHWAY DESIGN MANUAL
July 15, 2016

Plant mortality must be considered rock sizing, Index 7.1.1.2 should be


during the initial planting and substituted with Index
establishment period. Overplanting 873.3(3)(a)(2)(b) of this manual.
must be avoided so that high density
(e) Gabions. Gabion revetments
and projection does not occur
consist of rectangular wire mesh
causing increased sediment
baskets filled with stone. See
deposition and
Standard Plan D100A and D100B
capacity/conveyance reduction.
for gabion basket details and the
Given these issues, plant density in
Standard Specifications for
the design of a hybrid revetment
requirements.
and consideration of natural plant
density is critical to the Gabions are formed by filling
performance of the hybrid commercially fabricated and
revetment. The goal for design preassembled wire baskets with
should be medium density, where rock. There are two types of
horizontal projection and cross- gabions, wall type and mattress
sectional area reduction at maturity type. In wall type the empty cells
are minimal. See Figure 873.3B. are positioned and filled in place to
For woody vegetation, medium form walls in a stepped fashion.
density is described as mature trees Mattress type baskets are
or shrubs with full foliage on a positioned on the slope and filled.
streambank, where preferably See HEC 23, Volume II, Design
individual canopies or outer layers Guideline 10 and Figure 873.3B.
retain some free space between Wall type revetment is not fully
them, but may have minimal self-adjusting but has some
overlapping without being flexibility. The mattress type is
interwoven. very flexible and well suited for
man-made roadside channels (with
Figure 873.3B uniform flow) discussed in Chapter
Medium Density Vegetation 860 and as overside drains that are
constructed on steep, unstable
slopes. For some stream locations,
gabions may be more aesthetically
acceptable than rock riprap or may
be considered when larger stone
sizes are not readily available and
flows are nonabrasive. Due to
abrasion, corrosion and vandalism
concerns and difficulty of repairs,
caution is advised regarding in-
stream placement of gabions. In
addition, the California Department
of Fish and Wildlife recommends
against using gabions as weirs in
streams. If gabions are placed in-
Lower limit of medium vegetation density
stream, some form of abrasion
Pre-construction and post- protection in the form of wooden
construction hydraulic modelling planks or other facing will typically
and hybrid revetment design are be necessary for wall type, see
discussed in more detail in Design Figure 873.3C. Maintenance-free
Information Bulletin No. 87. For design service life in most
HIGHWAY DESIGN MANUAL 870-41
July 15, 2016

Figure 873.3D
Rock Slope Protection
Hybrid RSP with Embedded Toe

Rock Slope Protection

NOTES:
(1) Thickness "T" = 1.5 d50 or d100, whichever is greater.
(2) Face stone size is determined from Index 873.3(2)(a)(2)(a).
(3) RSP fabric not to extend more than 20 percent of the base width of the Mounded Toe past the Theoretical Toe.
870-42 HIGHWAY DESIGN MANUAL
July 15, 2016

environments is generally under Individual blocks are commonly


20 years. joined together with steel cable or
synthetic rope, to form articulated
Figure 873.3C block mattresses. Pre-assembled in
Gabion Lined Streambank sections to fit the site, the
mattresses can be used on slopes up
to 2:1. They are anchored at the top
of the revetment to secure the
system against slippage.
Pre-cast block revetments that are
formed by butting individual blocks
end to end, with no physical
connection, should not be used on
slopes steeper than 3:1. An
engineering fabric is normally used
on the slope to prevent the
migration of the underlying
embankment through the voids in
Gabion wall with timber facing to protect wires from the concrete blocks.
abrasive flow.
Refer to HEC 11, Design of Riprap
(f) Articulated Precast Concrete. This Revetment, Section 6.2, and HEC
type of revetment consists of pre- 23, Bridge Scour and Stream
cast concrete blocks which Instability Countermeasures,
interlock with each other, are Design Guideline 4, for further
attached to each other, or butted discussion on the use of articulated
together to form a continuous concrete blocks.
blanket or mat. A number of block
designs are commercially available. (4) Rigid Revetments.
They differ in shape and method of (a) Concreted-Rock Slope Protection.
articulation, but share common
features of flexibility and rapid (1) General Features. This type of
installation. Most provide for revetment consists of rock slope
establishment of vegetation within protection with interior voids filled with
the revetment. PCC to form a monolithic armor. A
typical section of this type of
The permeable nature of these installation is shown in Figure 873.3E.
revetments permits free draining of
the embankment and their It has application in areas where rock of
flexibility allows the mat to adjust sufficient size for ordinary rock slope
to minor changes in bank geometry. protection is not economically
Pre-cast concrete block revetments available.
may be economically justified (2) Design Concepts. Concreting of RSP is
where suitable rock for slope a common practice where availability of
protection is not readily available. large stones is limited, or where there is
They are generally more a need to reduce the total thickness of a
aesthetically pleasing than other RSP revetment. Inclusion of the
types of revetment, particularly concrete, and the labor required to place
after vegetation has become it, makes concreted RSP installations
established. more expensive per unit area than non-
concreted installations.
HIGHWAY DESIGN MANUAL 870-43
July 15, 2016

Figure 873.3E embankment are particularly important,


see Figure 873.3F. The concreted-rock
Concreted-Rock Slope Protection must be founded on solid rock or below
the depth of possible scour. Ends
should be protected by tying into stable
rock or forming smooth transitions with
embankment subjected to lower
velocities. As a precaution, cutoff stubs
may be provided. If the embankment
material is exposed at the top, freeboard
is warranted to prevent overtopping.

NOTES: Figure 873.3F


(1) If needed to relieve hydrostatic pressure. Toe Failure - Concreted RSP
(2) 1.5d50 or d100, whichever is greater from Table
873.3A for section thickness.
Dimensions and details should be modified as
required.
Design procedures for concreted RSP
revetments are similar to that of non-
concreted RSP. Start by following the
design example provided in Index
873.3(3)(a)(2)(c) to select a stable rock
class for a non-concreted design based
on the d50 and the next larger class in Toe of concreted RSP that has been undermined.
Table 873.3A. This non-concreted rock
size is divided by a factor of roughly The design intent is to place an adequate
four or five to arrive at the appropriate volume of concrete to tie the rock mass
d50 size rock for a concreted revetment. together, but leave the outer face
The factor is based on observations of roughened with enough rock projecting
previously constructed facilities and above the concrete to slow flow
represents the typical sized pieces that velocities to more closely approximate
stay together even after severe cracking natural conditions.
(i.e., failed revetments will still usually The volume of concrete required is
have segments of four to five rocks based on filling roughly two-thirds of
holding together). As with the non- the void space of the rock layer, as
concreted design procedures, use the shown in Figure 873.3E. The concrete
rock size derived from this calculation is rodded or vibrated into place leaving
to enter Table 873.3A (i.e., round up to the outer stones partially exposed. Void
the next larger d50 rock to select the space for the various RSP gradations
appropriate RSP Class. ranges from approximately 30 percent
As this type of protection is rigid to 35 percent for Method A placed rock
without high strength, support by the to 40 percent to 45 percent for Method
embankment must be maintained. B placed rock of the total volume
Slopes steeper than the angle of repose placed.
of the embankment are risky, but with Specifications. Quality specifications
rocks grouted in place, little is to be for rock used in concreted-rock slope
gained with slopes flatter than 1.5:1. protection are usually the same as for
Precautions to prevent undermining of
870-44 HIGHWAY DESIGN MANUAL
July 15, 2016

rock used in ordinary rock slope footprint than a non-grouted design. Both
protection. However, as the rocks are Headquarters Office of Highway Drainage
protected by the concrete which Design and District biologist staff should be
surrounds them, specifications for consulted early on during the planning
specific gravity and hardness may be phase for subject matter expertise relative to
lowered if necessary. The concrete used design and obtaining project specific
to fill the voids is normally 1 inch permits. For more guidance, see HEC 23,
maximum size aggregate minor Volume 2, Design Guideline 12.
concrete. Except for freeze-thaw
(c) Sacked-Concrete Slope Protection. This
testing of aggregates, which may be
method of protection consists of facing the
waived in the contract special
embankment with sacks filled with
provisions, the concrete should conform
concrete. It is expensive, but historically
to the provisions of Standard
was a much used type of revetment. Much
Specification Section 90.
hand labor is required but it is simple to
Size and grading of stone and concrete construct and adaptable to almost any
penetration depth are provided in embankment contour. Use of this method of
Standard Specification Section 72. slope protection is generally limited to
replacement or repair of existing sacked
(b) Partially Grouted Rock Slope Protection.
concrete facilities, or for small, unique
Partially grouted rock slope protection
situations that lend themselves to hand-
(PGRSP) is a viable alternative to larger
placed materials.
rock or concreted rock slope protection
where either the availability of large Tensile strength is low and as there is no
material is limited, or site limitations flexibility, the installation must depend
regarding placement of large material (e.g., almost entirely upon the stability of the
no excavation below spread footing base) embankment for support and therefore
would lead the designer to consider using should not be placed on face slopes much
some form of smaller rock held together steeper than the angle of repose of the
with a cementitious material. With partially embankment material. Slopes steeper than
grouted rock slope protection, there are no 1:1 are rare; 1.5:1 is common. The flatter
relationships per se for selecting the size of the slope, the less is the area of bond
rock, other than the practical considerations between sacks. From a construction
of proper void size, gradation, and adequate standpoint it is not practical to increase the
stone-to-stone contact area. The intent of area of bond between sacks; therefore for
partial grouting is to "glue" stones together slopes as flat as 2:1 all sacks should be laid
to create a conglomerate of particles. Each as headers rather than stretchers.
conglomerate is therefore significantly
Integrity of the revetment can be increased
larger than the d50 stone size, and typically
by embedding dowels in adjoining sacks to
is larger than the d100 size of the individual
reinforce intersack bond. A No. 3 deformed
stones in the matrix. The proposed
bar driven through a top sack into the
gradation criteria are based on a nominal or
underlying sack while the concrete is still
"target" d50 and only stones with a d50
fresh is effective. At cold joints, the first
ranging from 9 inches to 15 inches may be
course of sacks should be impaled on
used with the partial grouting technique.
projecting bars that were driven into the last
See rock classes II, III and IV in Table
previously placed course. The extra
873.3A. In HEC 23, PGRSP is presented as
strength may only be needed at the
a pier scour countermeasure, but it may be
perimeter of the revetment.
also used for bridge abutment protection, as
well as for bed/bank protection for short Most failures of sacked concrete are a result
localized areas with high velocities and of stream water eroding the embankment
shear stresses that require a smaller rock
HIGHWAY DESIGN MANUAL 870-45
July 15, 2016

material from the bottom, the ends, or the • Encroachment on a channel cannot be
top. tolerated.
The bottom should be founded on bedrock • Retreat of highway alignment is not viable.
or below the depth of possible scour. • Right of Way is restricted.
If the ends are not tied into rock or other • The force and direction of the stream can
nonerosive material, cutoff returns are to be best be redirected by a vertical structure.
provided and if the protection is long, cutoff
The foundation for bulkheads must be positive
stubs are built at 30-foot intervals, in order
and all terminals secure against erosive forces.
to prevent or retard a progressive failure.
The length of the structure should be the
Protection should be high enough to minimum necessary, with transitions to other
preclude overtopping. If the roadway grade less expensive types of slope protection when
is subject to flooding and the shoulder possible. Eddy currents can be extremely
material does not contain sufficient rock to damaging at the terminals and transitions. If
prevent erosion from the top, then pavement overtopping of the bulkheads is anticipated,
should be carried over the top of the slope suitable protection should be provided.
protection in order to prevent water entering
Along a stream bank, using a bulkhead
from this direction.
presumes a channel section so constricted as to
Class 8 RSP fabric as described in Standard prohibit use of a cheaper device on a natural
Specification Section 96 should be placed slope. Velocity will be unnaturally high along
behind all sacked concrete revetments. For the face of the bulkhead, which must have a
revetments over 4 feet in height, weep tubes fairly smooth surface to avoid compounding the
should also be placed, see Figure 873.3E. restriction. The high velocity will increase the
threat of scour at the toe and erosion at the
For good appearance, it is essential that the
downstream end. Allowance must be made for
sacks be placed in horizontal courses. If the
these threats in selecting the type of foundation,
foundation is irregular, corrective work
grade of footing, penetration of piling,
such as placement of entrenched concrete or
transition, and anchorage at downstream end.
sacked concrete is necessary to level up the
Transitions at both ends may appropriately taper
foundation. Refer to HDS No. 6, Section
the width of channel and slope of the bank.
6.6.5, for further discussion on the use of
Transition in roughness is desirable if attainable.
sacked concrete slope protection.
Refer to HDS No. 6, Section 6.4.8, for further
(5) Bulkheads. A bulkhead is a steep or vertical discussion on the use of bulkheads to prevent
structure supporting a natural slope or streambank erosion or failure.
constructed embankment. As bank protection
(a) Concrete or Masonry Walls. The expertise
structures, bulkheads serve to secure the bank
and coordination of several engineering
against erosion as well as retaining it against
disciplines is required to accomplish the
sliding. As a retaining structure, conventional
development of PS&E for concrete walls
design methods for retaining walls, cribs and
serving the dual purpose of slope protection
laterally loaded piles are used.
and support. The Division of Structures is
Bulkheads are usually expensive, but may be responsible for the structural integrity of all
economically justified in special cases where retaining walls, including bulkheads.
valuable riparian property or improvements are
(b) Crib walls. Timber and concrete cribs can
involved and foundation conditions are not
be used for bulkheads in locations where
satisfactory for less expensive types of slope
some flexibility is desirable or permissible.
protection. They may be used for toe protection
Metal cribs are limited to support of
in combination with other revetment types of
embankment and are not recommended for
slope protection. Some other considerations
use as protection because of vulnerability to
that may justify the use of bulkheads include:
corrosion and abrasion.
870-46 HIGHWAY DESIGN MANUAL
July 15, 2016

The design of crib walls is essentially a Erosion control and revegetation mats are
determination of line, foundation grade, and flexible three-dimensional mats or nets of
height with special attention given to natural or synthetic material that protect soil and
potential scour and possible loss of backfill seeds against water erosion prior to
at the base and along the toe. Design details establishment of vegetation. They permit
for concrete crib walls are shown on vegetation growth through the web of the mat
Standard Plans C7A through C7C. material and have been used as temporary
Concrete crib walls used as bulkheads and channel linings where ordinary seeding and
exposed to salt water require special mulching techniques will not withstand erosive
provisions specifying the use of coated flow velocities. The designer should recognize
rebars and special high density concrete. that flow velocity estimates and a particular soils
Recommendations from METS Corrosion resistance to erosion are parameters that must be
Technology Branch should be requested. based on specific site conditions. Using
arbitrarily selected values for design of
(c) Sheet Piling. Timber, concrete and steel
vegetative slope protection without consultation
sheet piling are used for bulkheads that
with the District Hydraulic Unit and/or the
depend on deep penetration of foundation
District Landscape Architect Unit is not
materials for all or part of their stability.
recommended. However, a suggested starting
High bulkheads are usually counterforted at
point of reference is Table 865.2 in which the
upper levels with batter piles or tie back
resistance of various unprotected soil
systems to deadmen. Any of the three
classifications to flow velocities are given.
materials is adaptable to sheet piling or a
Under near ideal conditions, ordinary seeding
sheathed system of post or column piles.
and mulching methods cannot reasonably be
Excluding structural requirements, design expected to withstand sustained flow velocities
of pile bulkheads is essentially as follows: above 4 feet per second. If velocities are in
excess of 4 feet per second, a lining maybe
• Recognition of foundation conditions
needed, see Table 865.2.
suitable to or demanding deep
penetration. Penetration of at least Temporary channel liners are used to establish
15 feet below scour level, or into soft vegetative growth in a drainage way or as slope
rock, should be assured. protection prior to the placement of a permanent
armoring. Some typical temporary channel
• Choice of material. Timber is suitable
liners presented in Table 865.2 are:
for very dry or very wet climates, for
other situations economic comparison • Single net straw
of preliminary designs and alternative
• Double net coconut/straw blend
materials should be made.
• Double net shredded wood
• Determination of line and grade. Fairly
smooth transitions with protection to Vegetative and temporary channel liners are
high-water level should be provided. suitable for conditions of uniform flow and
moderate shear stresses.
(6) Vegetation. Vegetation is the most natural
method for stabilization of embankments and Permanent soil reinforcing mats and rock riprap
channe bank protection. Vegetation can be may serve the dual purpose of temporary and
relatively easy to maintain, visually attractive permanent channel liner. Some typical
and environmentally desirable. The root system permanent channel liners are:
forms a binding network that helps hold the soil.
• Small rock slope protection
Grass and woody plants above ground provide
resistance to the near bank water flow causing it • Geosynthetic mats
to lose some of its erosive energy.
• Polyethelene cells or grids
HIGHWAY DESIGN MANUAL 870-47
July 15, 2016

• Gabion Mattresses (see Index culverts or other encroachments on the tributary


873.3(3)(a)(2)(e)) systems. In general, any increase in transported
materials from the tributaries to the main
However, geosynthetics and plastic
channel causes a reduction in the quality of the
(polyethylene, polypropylene, polyamide, etc.)
environment within the river.
based mats with no enhanced UV resistance
must be installed in a fashion where there will (a) Bendway Weirs. Bendway weirs, also
be no potential for long-term sunlight exposure, referred to as stream barbs, bank barbs, and
as these products will degrade due to UV reverse sills are low elevation stone sills
radiation. used to improve lateral stream stability and
flow alignment problems at river bends and
Composite designs are often used where there
highway crossings on streams and smaller
are sustained low flows of high to moderate
rivers.
velocities and intermediate high water flows of
low to moderate velocities. Brush layering is a They are placed at an angle with the
permanent type of erosion control technique that embankment in meandering streams for the
may also have application for channel purpose of directing or forcing the current
protection, particularly as a composite design. away from the embankment, see Figure
873.4A. They also encourage deposition of
Additional design information on vegetation,
bed material and growth of vegetation.
and temporary and permanent channel liners is
When the purpose is to deposit material and
given in Chapter IV, HEC 15, Design of
promote growth, the weirs are considered to
Roadside Channels and Flexible Linings and in
have fulfilled their function and are
Chapter 860 of this manual.
expendable when this occurs.
873.4 Training Systems
Figure 873.4A
(1) General. Training systems are structures,
usually within a channel, that act as Thalweg Redirection Using
countermeasures to control the direction, Bendway Weirs
velocity, or depth of flowing water. When
training systems are used, they generally
straighten the channel, shorten the flow line, and
increase the local velocity within the channel.
Any such changes made in the system that cause
an increase in the gradient may cause an
increase in local velocities. The increase in
velocity increases local and contraction scour
with subsequent deposition downstream, where
the channel takes on its normal characteristics.
If significant lengths of the river are trained and
straightened, there can be a noticeable decrease
in the elevation of the water surface profile for a Bendway weirs in conjunction with rock slope protection.
given discharge in the main channel. Tributaries
Bendway weirs are similar in appearance to
emptying into the main channel in such reaches stone spurs, but have significant functional
are significantly affected. Having a lower water differences. Spurs are typically visible
level in the main channel for a given discharge above the flow line and are designed so that
means that the tributary streams entering in that flow is either diverted around the structure,
vicinity are subjected to a steeper gradient and
or flow along the bank line is reduced as it
higher velocities which can cause degradation in passes through the structure. Bendway
the tributary streams. In extreme cases, weirs are normally not visible, especially at
degradation can be induced of such magnitude stages above low water, and are intended to
as to cause failure of structures such as bridges, redirect flow by utilizing weir hydraulics
870-48 HIGHWAY DESIGN MANUAL
July 15, 2016

over the structure. Flow passing over the moving the location of any scour away from
bendway weir is redirected such that it flows the bank, partial failure of the spur can often
perpendicular to the axis of the weir and is be repaired before damage is done to
directed towards the channel centerline. See structures along and across the stream.
Figure 873.4B for typical cross section and
In braided streams, the use of spurs to
layout. Similar to stone spurs, bendway
establish and maintain a well-defined
weirs reduce near bank velocities, reduce
channel location, cross section, and
the concentration of currents on the outer
alignment can decrease the required bridge
bank, and can produce a better alignment of
length, thus decreasing the cost of bridge
flow through the bend and downstream
construction and maintenance.
crossing. Experience with bendway weirs
has indicated that the structures do not Spur types are classified based upon their
perform well in degrading or sediment permeability as retarder spurs,
deficient reaches. retarder/deflector spurs, and deflector spurs.
The permeability of spurs is defined simply
Material sizing should be based on the
as the percentage of the spur surface area
Isbash equation plotted in Figure 873.4C.
facing the streamflow that is open.
Riprap stone size is designed using the
Deflector spurs are impermeable spurs
critical velocity near the boundary where the
which function by diverting the primary
riprap is placed. Typically the size ranges
flow currents away from the bank.
between 1 and 3 ft and should be
Retarder/deflector spurs are more
approximately 20% greater than that
permeable and function by retarding flow
computed from the rock sizing formula
velocities at the bank and diverting flow
presented in Index 873.3(3)(a)(2)(b). The
away from the bank. Retarder spurs are
minimum rock size should not be less than
highly permeable and function by retarding
the D100 of the streambed material. See
flow velocities near the bank.
Tables 873.3A and 873.3B to determine
rock class. These structures should be designed not to
overtop. Therefore, for permeable spurs,
See HEC 23 Volume 2, Design Guideline 1
the rock sizing formula presented in Index
for detailed guidance on weir height, length,
873.3(3)(a)(2)(b) may be used and a Cv
angle, location and spacing,
value of 1.25 is recommended. Where
(b) Spurs. A spur can be a pervious or overtopping the spur is unavoidable, the
impervious structure projecting from the riprap size may be determined by equations
streambank into the channel. Similar to 5.2 (for slopes > 25%) or 5.3 (for slopes
bendway weirs, spurs are used to halt < 25%) in HEC 23 Volume 2, Design
meander migration at a bend and channelize Guideline 5. Since these equations are for
wide, poorly defined streams into well- free flow down the slope, always check to
defined channels by reducing flow see if the structure is actually drowned
velocities in critical zones near the (submerged) by high tailwater. If that is the
streambank to prevent erosion and establish case, then use the rock sizing formula
a more desirable channel alignment or presented in Index 873.3(3)(a)(2)(b) for
width. The main function of spurs is to sizing riprap on a stream bank should be
reduce flow velocities near the bank, which used. See Tables 873.3A and 873.3B to
in turn, encourages sediment deposition due determine rock class.
to these reduced velocities. Increased
In general a top width equal to the width of
protection of banks can be achieved over
a dump truck can be used. The side slopes
time, as more sediment is deposited behind
of the spur should be 2H:1V or flatter. Rock
the spurs. Because of this, spurs may
riprap should be placed on the upstream and
protect a streambank more effectively and at
downstream faces as well as on the nose of
less cost than revetments. Furthermore, by
the spur to inhibit erosion of the spur.
HIGHWAY DESIGN MANUAL 870-49
July 15, 2016

Figure 873.4B
Bendway Weir Typical Cross Section and Layout
870-50 HIGHWAY DESIGN MANUAL
July 15, 2016

Figure 873.4C
Bendway Weir Rock Size Chart
HIGHWAY DESIGN MANUAL 870-51
July 15, 2016

Depending on the embankment material banks can be used on both sand and gravel-
being used, a gravel, sand, or geotextile bed streams.
filter may be required. It is recommended
that riprap be extended below the bed Figure 873.4E
elevation to the combined long-term Bridge Abutment Guide Banks
degradation and contraction scour depth.
Riprap should also extend to the crest of the
spur, in cases where the spur would be
submerged at design flow, or to 2 feet above
the design flow, if the spur crest is higher
than the design flow depth. Additional
riprap should be placed around the nose of
the spur, so that spur will be protected from
scour.
See Figure 873.4D for example of spur
design and HEC 23 Volume 2, Design
Guideline 2, for detailed guidance on spur
height, length, shape, angle, permeability, Guide banks are usually earthen
location and spacing. embankment faced with rock slope
protection. Optimum shape and length of
(c) Guide Dikes/Banks. Guide banks are
guide dikes will be different for each site.
appendages to the highway embankment at
Field experience has shown that an elliptical
bridge abutments, see Figure 873.4E. They
shape with a major to minor axis ratio of
are smooth extensions of the fill slope on the
2.5:1 is effective in reducing turbulence.
upstream side. When embankments
The length is dependent on the ratio of flow
encroach on wide floodplains to attain an
diverted from the floodplain to flow in the
economic length of bridge, the flows from
first 100 feet of waterway under the bridge.
these areas must flow parallel to the
If the use of another shape dike, such as a
approach embankment to the bridge
straight dike, is required for practical
opening. These flows can cause a severe
reasons more scour should be expected at
flow contraction at the abutment with
the upstream end of the dike. The bridge
damaging eddy currents that can scour away
end will generally not be immediately
abutment and pier foundations, erode the
threatened should a failure occur at the
approach embankment, and reduce the
upstream end of a guide dike.
effective bridge opening.
Toe dikes are sometimes needed
Guide banks can be used in these cases to
downstream of the bridge end to guide flow
prevent erosion of the approach
away from the structure so that
embankments by cutting off the flow
redistribution in the floodplain will not
adjacent to the embankment, guiding
cause erosion damage to the embankment
streamflow through a bridge opening, and
due to eddy currents. The shape of toe dikes
transferring scour away from abutments to
is of less importance than it is with upstream
prevent damage caused by abutment scour.
guide banks.
The two major enhancements guide banks
bring to bridge design are (1) reduce the Principal factors to be considered when
separation of flow at the upstream abutment designing guide banks, are their orientation
face and thereby maximize the use of the to the bridge opening, plan shape, upstream
total bridge waterway area, and (2) reduce and downstream length, cross-sectional
the abutment scour due to lessening shape, and crest elevation.
turbulence at the abutment face. Guide
It is apparent from the Figure 873.4E that
without this guide bank, overbank flows
870-52 HIGHWAY DESIGN MANUAL
July 15, 2016

Figure 873.4D
Example of Spur Design
HIGHWAY DESIGN MANUAL 870-53
July 15, 2016

would return to the channel at the bridge longitudinal dikes and bulkheads, see HEC
opening, which can increase the severity of 23 Volume 1, Chapter 8.
contraction and scour at the abutment. With
(e) Check Dams and Drop Structures. Drop
installation of guide banks the scour holes
structures or check dams are an effective
which normally would occur at the
means of gradient control. They may be
abutments of the bridge are moved upstream
constructed of rock, gabions, concrete,
away from the abutments. Guide banks may
treated timber, sheet piling or combinations
be designed at each abutment, as shown, or
of any of the above. They are most suited to
singly, depending on the amount of
locations where bed materials are relatively
overbank or floodplain flow directed to the
impervious otherwise underflow must be
bridge by each approach embankment.
prevented by cutoffs. Rock riprap and
The goal in the design of guide banks is to timber pile construction have been most
provide a smooth transition and contraction successful on channels having small drops
of the streamflow through the bridge and widths less than 100 ft. Sheet piles,
opening. Ideally, the flow lines through the gabions, and concrete structures are
bridge opening should be straight and generally used for larger drops on channels
parallel. As in the case with other with widths ranging up to 300 ft. Check
countermeasures, the designer should dams can initiate erosion of banks and the
consider the principles of river hydraulics channel bed downstream of the structure as
and morphology, and exercise sound a result of energy dissipation and turbulence
engineering judgment. at the drop. This local scour can undermine
the check dam and cause failure. The use of
The Division of Engineering Services
energy dissipators downstream of check
(DES) and Structures Maintenance and
dams can reduce the energy available to
Investigations (SMI) Hydraulics Branches
erode the channel bed and banks. In some
are responsible for the hydraulic design of
cases it may be better to construct several
bridges, therefore, for protection at bridge
consecutive drops of shorter height to
abutments and approaches, the District is
minimize erosion. Lateral erosion of
responsible for consulting with them to
channel banks just downstream of drop
verify the design parameters and also
structures is another adverse result of check
obtaining the bridge hydraulic model. See
dams and is caused by turbulence produced
Index 873.6 “Coordination with the
by energy dissipation at the drop, bank
Division of Engineering Services and
slumping from local channel bed erosion, or
Structures Maintenance and
eddy action at the banks. The usual solution
Investigations.”
to these problems is to place rock slope
For further detailed information on guide protection on the streambank adjacent to the
bank design procedures, refer to HEC 23, drop structure or check dam. Erosion of the
Volume 2, Design Guidelines 14 and 15. streambed can also be reduced by placing
See Tables 873.3A and 873.3B to determine rock riprap in a preformed scour hole
rock class. downstream of the drop structure. A row of
(d) Further Information and Other sheet piling with top set at or below
Countermeasures for Lateral Stream streambed elevation can keep the riprap
Instability. General design considerations from moving downstream. Because of the
and guidance for evaluating scour and problems associated with check dams, the
stream stability at highway bridges is design of these countermeasures requires
contained in HEC 18, HEC 20, and HEC 23. designing the check dams to resist scour by
providing for dissipation of excess energy
For further information on other and protection of areas of the bed and the
countermeasures such as retarder structures, bank which are susceptible to erosive
forces. Refer to HEC 23 Volume 2, Design
870-54 HIGHWAY DESIGN MANUAL
July 15, 2016

Guideline 3 and HDS No. 6, Section 6.4.11, 3. A typical cross section indicating dimensions,
for further discussion on the use of check slopes, arrangement and connections.
dams and drop structures. 4. Quantity of materials (per foot, per protection
873.5 Summary and Design Check List unit, or per job).
5. Relation of the foundation treatment with
The designer should anticipate the more significant respect to the existing ground.
problems that are likely to occur during the
construction and maintenance of channel protection 6. Relation of the top of the proposed protection to
facilities. So far as possible, the design should be design high water (historic, with date; or
adjusted to eliminate or minimize those potential predicted, with frequency).
problems. 7. The limits of excavation and backfill as they
may affect measurement and payment.
The logistics of the construction activity such as
access to the site, on-site storage of construction 8. Construction details such as weep holes, rock
materials, time of year restrictions, environmental slope protection fabrics, geocomposite drains
concerns, project specific permits and sequence of and associated materials.
construction should be carefully considered during 9. Location and details of construction joints, cut-
the project design. See Index 872.1, Planning, Index off stubs and end returns.
872.3(6), Construction, Easements, Access and 10. Restrictions to the placement of reinforcement.
Staging, and Index 872.3(7), Biodiversity. The 11. Connections and bracing for framing of timber
stream morphology and its response to construction or steel.
activities is an integral part of the planning process.
Communication between the designer and those 12. Splicing details for timber, pipe, rails and
responsible for construction administration as well structural shapes.
as maintenance are important. 13. Anchorage details, particularly size, type,
location, and method of connection.
Channel protection facilities require periodic
maintenance inspection and repair. Where 14. Size, shape, and special requirements of units
practicable, provisions should be made in the facility such as precast concrete shapes and other
design to provide access for inspection and manufactured items.
maintenance. 15. Number and arrangement of cables and details
of fastening devices.
The following check list has been prepared for both
the designer and reviewer. It will help assure that all 16. Size, mass per unit area, mesh spacing and
necessary information is included in the plans and fastening details for wire-fabric or geosynthetic
specifications. It is a comprehensive list for all types materials.
of protection. Items pertinent to any particular type 17. On timber pile construction the number of piles
can be selected readily and the rest ignored. per bent, number of bents, length of piling,
driving requirements, cut-off elevations, and
1. Location and staging of the planned work with framing details.
respect to:
18. The details of gabions and the filling material.
• The highway. See Standard Plan D100A and D100B and the
• The stream, its morphology, biodiversity Standard Specifications.
and project specific permits. 19. The size of articulated blocks, the placement of
• Right of way. See Index 872.1 and 872.3 steel, and construction details relating to
for construction easements and examination fabrication.
of stream behavior far upstream and 20. The corrosion considerations that may dictate
downstream. specialty concretes, coated reinforcing, or other
2. Datum control of the work, and relation of that special requirements.
datum to gage datum on streams.
HIGHWAY DESIGN MANUAL 870-55
July 15, 2016

873.6 Coordination with the Division of analyses, repair and monitoring of in-service
Engineering Services and Structures bridges. Typical maintenance challenges
Maintenance and Investigations include scour, flooding, and lateral migration.
Maintenance related impacts to a bridge will
(1) The Division of Engineering Services and trigger a hydraulic report for that specific
Structures Maintenance and Investigations bridge. The hydraulic report recommendations
Hydraulics Branches. The Division of are used by the District in determining the scope
Engineering Services (DES) and Structures of hydraulic improvements to the bridge
Maintenance and Investigations (SMI) projects. For countermeasure design at bridge
Hydraulics Branches are responsible for the abutments and piers (e.g., rock slope protection,
hydraulic design of bridges. Therefore, for guide banks, check dams, structural repairs etc.)
protection at bridge piers, abutments and the magnitude of the discharge used is the
approaches, the District is responsible for 100-year flood. This standard is independent of
consulting with them to verify the design the design flood used by the District for
parameters (i.e., water surface elevations, protecting the channel bank or the bridge
freeboard requirements, water velocities, scour approach embankment (see Index 873.2).
recommendations etc.) used and also obtaining
the bridge hydraulic model. Since the mid 1990’s, new bridges have been
designed so that the top of the pile cap is at the
Figure 873.6A bottom of anticipated scour (long-term
degradation, contraction and local scour) for the
Bridge Abutment Failure Example 100-year flood using the hypothesis that by
designing the foundations lower than
recommended in HEC 18 for the 100-year flood,
there would be ample safety factor inherent to
withstand the 200-year scour check flood.
Bridges that were designed prior to the first
edition of HEC 18 in 1991 may be more
vulnerable to the possible effects of climate
change or floods larger than the 100-year flood.
See Figure 873.6A.
Depending on location, site considerations may
include constructability and biodiversity, see
Index 872.3(4) and Index 872.3(5). During the
Bridge Abutment Failure at Tex Wash on I-10 after a planning and environmental phases on
Flood Larger Than the Design Flood environmentally sensitive projects (e.g., bridge
structures that require permits for fish passage
The DES Hydraulics branch performs all design under California Fish and Wildlife
hydraulic designs for new bridges or jurisdiction – see Figure 873.3B), the District
replacement bridges that meet the National should initiate contact with resource agencies
Bridge Inventory (NBI) bridge definition. early to propose conceptual design, identify
Modifications to an existing bridge or impacts and any necessary mitigation as part of
constructing a new bridge require obtaining the permitting process. The overriding issue of
permits from the regulatory agencies. The DES concern is the difference in timing of detailed
Hydraulics branch should coordinate with the analyses (e.g., hydraulics, geotechnical,
District to perform conceptual designs for foundation) that takes place on the District side
permit approval. The DES Hydraulics branch is of the project development process verses what
essentially a consultant/designer to the District takes place in DES prior to project approval
Design Offices. during the environmental phase.
The SMI Hydraulics branch within the Division
of Maintenance is responsible for the hydraulic
870-56 HIGHWAY DESIGN MANUAL
July 15, 2016

Prematurely approved projects and Coordination with Geotechnical Design and


environmental documents prior to permit Geology within DES may be initiated by the
approval can, and do, result in costly major re- designer when any of the following
work during the design phase. On determinations need to be made:
environmentally sensitive projects the District
• Scour potential of channel material.
should consider the need to shift resources to the
environmental phase so that a more advanced • Natural erosion potential of stream banks
bridge foundation design can be incorporated that may affect project features. See Figure
into the Advanced Planning Study (APS) and 873.6C.
the Environmental Document (ED) to facilitate
permit approval consistent with the Project • The performance of existing cut, fill and
Approval (PA) and to minimize rework. natural slopes including the slope soil/rock
composition.
Figure 873.6B • Slope stability analysis and need for earth
Habitat Enhancement Example retaining systems including crib walls and
gabion walls.
• Embankment constructability and impact to
nearby structures or bridge abutments. See
following link to the Geotechnical Manual
and Figure 873.6D:
http://www.dot.ca.gov/hq/esc/geotech/geo_
manual/page/Embankments_Dec2014.pdf

Figure 873.6C
Lateral Stream Migration Within a
Canyon Setting Example

Longitudinal Peaked Stone Toe Protection (LPSTP) with


Rock Vanes for Chinook Salmon Habitat Enhancement,
Route 128, Russian River Bridge in Geyserville
(2) Geotechnical Design and Geology. The Project
Engineer must review the Project Initiation
Document and Preliminary Geotechnical
Design Report, if any, to ascertain the scope of
geotechnical involvement for a project.
For all projects that involve designs for cut
slopes, embankments, earthwork, landslide
remediation, retaining walls, groundwater
studies, erosion control features, subexcavation Figure 873.6D
and any other studies involving geotechnical Conceptual Geotechnical Failures
investigations and engineering geology, a Resulting from Abutment Scour
Geotechnical Design Report (GDR) is to be
prepared by the Roadway Geotechnical
Engineering Branches of the Division of
Engineering Services, Geotechnical Services
(DES-GS).

You might also like