ID Task Name Duration Start Finish Predecessors01 June 11 October 21 February 01 July 11 November 21 March 01 August 11 December

27/07 28/09 30/11 01/02 04/04 06/06 08/08 10/10 12/12 13/02 17/04 19/06 21/08 23/10 25/12
1 Title: 499 days 07/12/15 02/11/17

2 Project Kick Off 0 days 07/12/15 07/12/15 07/12

3 Project Planning 499 days 07/12/15 02/11/17

4 Initiation 10 days 07/12/15 19/12/15

5 Feasibility Study 7 edays 07/12/15 14/12/15 2

6 Presentation to Management 0 days 14/12/15 14/12/15 5 14/12

7 Revised Feasi 3 days 14/12/15 16/12/15 6

8 Management Approval 3 edays 16/12/15 19/12/15 7

9 Accepted Feasi 0 days 19/12/15 19/12/15 8 19/12

10 Design Stage 489 days 21/12/15 02/11/17

11 Consultant Engagement 22 days 21/12/15 19/01/16

12 Architect 18 days 21/12/15 13/01/16

20 C&S Engineer 14 days 23/12/15 11/01/16

28 M&E Engineer 14 days 23/12/15 11/01/16

36 QS Consultant 14 days 25/12/15 13/01/16

44 Land Surveyor 16 days 25/12/15 15/01/16

52 TIA Consultant 16 days 25/12/15 15/01/16

60 EIA Consultant 18 days 25/12/15 19/01/16

68 Layout Planning 41 days 14/01/16 10/03/16

69 Architect Prepares Rough Layout 7 days 14/01/16 22/01/16 19


based on Design Brief
70 1st Meeting on Layout 0 days 22/01/16 22/01/16 69,27,35,43,51,59,67 22/01

71 Presentation to Management 0 days 27/01/16 27/01/16 70FS+3 days 27/01

72 Revision of Layout 7 days 28/01/16 05/02/16 71

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: Project Template-2007.m Split External Tasks Inactive Summary Manual Summary Progress
Date: 07/04/16 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 1
ID Task Name Duration Start Finish Predecessors01 June 11 October 21 February 01 July 11 November 21 March 01 August 11 December
27/07 28/09 30/11 01/02 04/04 06/06 08/08 10/10 12/12 13/02 17/04 19/06 21/08 23/10 25/12
73 2nd Meeting on Layout 0 days 05/02/16 05/02/16 72 05/02

74 Presentation to Management 0 days 10/02/16 10/02/16 73FS+3 days 10/02

75 Revision of Layout 7 days 11/02/16 19/02/16 74

76 Preparing LCP, Development Data & 14 days 22/02/16 10/03/16 75


KM Layout
77 Authorities Matter 469 days 18/01/16 02/11/17

78 Land Matter 454 days 18/01/16 12/10/17

79 Land ReZoning 90 days 18/01/16 20/05/16 51

80 Land Conversion 79 days 11/03/16 29/06/16

81 Prepare LCP 7 days 11/03/16 21/03/16 76

82 Review & Comment of LCP 3 days 22/03/16 24/03/16 81

83 Revision of LCP 5 days 25/03/16 31/03/16 82

84 Documents Compilation 5 days 22/03/16 28/03/16 81

85 Submission of LCP 0 days 31/03/16 31/03/16 83,84 31/03

86 Conversion Approval 0 days 29/06/16 29/06/16 85FS+90 edays 29/06

87 S&R 155 days 26/09/16 28/04/17

88 Document Preparation & 7 days 26/09/16 04/10/16 134


Compilation
89 Submission to Council 0 days 13/10/16 13/10/16 88,135 13/10

90 Approval from Council 0 days 24/11/16 24/11/16 89FS+30 days 24/11

91 Submission to Land Office 0 days 24/11/16 24/11/16 90 24/11

92 Approval from Land Office 0 days 30/03/17 30/03/17 91FS+90 days 30/03

93 Prepares Payment & QT 14 days 31/03/17 19/04/17 92

94 Obtained Approved QT 0 days 28/04/17 28/04/17 93FS+7 days 28/04

95 SiFUS 119 days 01/05/17 12/10/17

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: Project Template-2007.m Split External Tasks Inactive Summary Manual Summary Progress
Date: 07/04/16 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 2
ID Task Name Duration Start Finish Predecessors01 June 11 October 21 February 01 July 11 November 21 March 01 August 11 December
27/07 28/09 30/11 01/02 04/04 06/06 08/08 10/10 12/12 13/02 17/04 19/06 21/08 23/10 25/12
96 Application and Payment to LJTM 14 days 01/05/17 18/05/17 94

97 Obtained Payment Receipt 0 days 18/05/17 18/05/17 96 18/05

98 Application to JUPEM For Lot No 0 days 18/05/17 18/05/17 97 18/05

99 Obtained Lot No 0 days 07/06/17 07/06/17 98FS+14 days 07/06

100 Preparing Sijil Perhitungan 14 days 08/06/17 27/06/17 99

101 Submission to Land Office 0 days 27/06/17 27/06/17 100 27/06

102 Obtained Approved SiFUS 0 days 19/09/17 19/09/17 101FS+60 days 19/09

103 Send to Commissioner of 0 days 22/09/17 22/09/17 102FS+3 days 22/09


Building for Endorsement
104 Obtained Endorsement from CoB 0 days 12/10/17 12/10/17 103FS+14 days 12/10

105 KM Matter 430 days 11/03/16 02/11/17

106 Pre KM Submission 129 days 11/03/16 07/09/16

107 Water Enactment 19 days 11/03/16 06/04/16

108 Document Preparation & 5 days 11/03/16 17/03/16 51,76


Compilation
109 Submission to Land Office 0 days 17/03/16 17/03/16 108 17/03

110 Approval 0 days 06/04/16 06/04/16 109FS+14 days 06/04

111 IWK PDC1 24 days 11/03/16 13/04/16

112 Preparation of Payment 3 days 11/03/16 15/03/16 76,27

113 Document Preparation & 7 days 16/03/16 24/03/16 112


Compilation
114 Submission to IWK 0 days 24/03/16 24/03/16 113,112 24/03

115 Approval from IWK 0 days 13/04/16 13/04/16 114FS+14 days 13/04

116 SKMM/Telco 21 days 11/03/16 08/04/16

117 Document Preparation & 7 days 11/03/16 21/03/16 35,76


Compilation
118 Submission to Telco 0 days 21/03/16 21/03/16 117 21/03

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: Project Template-2007.m Split External Tasks Inactive Summary Manual Summary Progress
Date: 07/04/16 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 3
ID Task Name Duration Start Finish Predecessors01 June 11 October 21 February 01 July 11 November 21 March 01 August 11 December
27/07 28/09 30/11 01/02 04/04 06/06 08/08 10/10 12/12 13/02 17/04 19/06 21/08 23/10 25/12
119 SKMM Approval 0 days 08/04/16 08/04/16 118FS+14 days 08/04

120 EIA Submission 129 days 11/03/16 07/09/16

121 Pre EIA Report 14 days 11/03/16 30/03/16 67,76

122 Submission of PAT 0 days 20/05/16 20/05/16 132 20/05

123 Document Preparation & 14 days 23/05/16 09/06/16 122,121


Compilation
124 Submission to DOE 0 days 09/06/16 09/06/16 123 09/06

125 Approval from DOE 0 days 07/09/16 07/09/16 124FS+90 edays 07/09

126 TIA Submission 120 days 11/03/16 25/08/16

127 Prepare TIA Report 60 days 11/03/16 02/06/16 59,76

128 Submission of TIA Report 0 days 02/06/16 02/06/16 127,132 02/06

129 TIA Approval 0 days 25/08/16 25/08/16 128FS+60 days 25/08

130 KM Submission 155 days 11/03/16 13/10/16

131 Document preparation & 7 days 11/03/16 21/03/16 19,76


Compilation
132 Submission to OSC 0 days 20/05/16 20/05/16 119,115,110,131,79 20/05

133 OSC Tabling 0 days 05/09/16 05/09/16 132FS+108 edays 05/09

134 Compliance 14 days 06/09/16 23/09/16 133,86,129

135 Obtained C1 0 days 13/10/16 13/10/16 134FS+14 days 13/10

136 BP Submission 54 days 26/09/16 08/12/16

137 Document Preparation & 14 days 26/09/16 13/10/16 134


Compilation
138 Submission to OSC 0 days 13/10/16 13/10/16 135,137 13/10

139 Approval 0 days 08/12/16 08/12/16 138FS+40 days 08/12

140 EW Submission 74 days 26/09/16 05/01/17

141 Document Preparation & 7 days 26/09/16 04/10/16 134


Compilation

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: Project Template-2007.m Split External Tasks Inactive Summary Manual Summary Progress
Date: 07/04/16 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only

Page 4
ID Task Name Duration Start Finish Predecessors01 June 11 October 21 February 01 July 11 November 21 March 01 August 11 December
27/07 28/09 30/11 01/02 04/04 06/06 08/08 10/10 12/12 13/02 17/04 19/06 21/08 23/10 25/12
142 Submission to OSC 0 days 13/10/16 13/10/16 135,141 13/10

143 EW Approval 0 days 05/01/17 05/01/17 142FS+60 days 05/01

144 Application for Commencement of 34 days 09/12/16 25/01/17


Work (COW)

145 Building works 14 days 09/12/16 28/12/16 139

146 Obtained Building CoW 0 days 28/12/16 28/12/16 145 28/12

147 EarthWorks 14 days 06/01/17 25/01/17 143

148 Obtained EW CoW 0 days 25/01/17 25/01/17 147 25/01

149 Application for APDL 15 days 12/10/17 02/11/17

150 Submission Through BLESS 0 days 12/10/17 12/10/17 139,104 12/10


system
151 Obtained APDL 0 days 02/11/17 02/11/17 150FS+21 edays 02/11

152 Technical Submission 160 days 14/10/16 25/05/17

153 IWK PDC2 14 days 14/10/16 02/11/16 135

154 IWK PDC 3,4,5 14 days 03/11/16 22/11/16 153

155 IWK PDC 6 7 days 29/12/16 06/01/17 154,146

156 R&D - JKR 60 days 14/10/16 05/01/17 135

157 R&D - JPS 60 days 14/10/16 05/01/17 135

158 R&D - Council Kejuruteraan 60 days 14/10/16 05/01/17 135

159 Street Lighting 30 days 06/01/17 16/02/17 156,157,158

160 Int. Sanitary & Plumbing 60 days 09/12/16 02/03/17 139

161 External Water Reticulation 60 days 03/03/17 25/05/17 160

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: Project Template-2007.m Split External Tasks Inactive Summary Manual Summary Progress
Date: 07/04/16 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only