You are on page 1of 8

Cl/SfB (13)(23)

April 1997

uomestic floors:
'7
I construction, Part 1
insulation and
damp-proofing
c
This guide describes some recommendations floor construction for
ground floor construction apply equally to other replacement or repair, and
in new buildings and in types of building. how to repair them.
rehabilitation work where It is in five parts: the other This guide is of interest to
floors are being replaced. parts (which are listed on designers, building
It is concerned mainly with page 8) explain how to surveyors and builders.
domestic buildings but assess different types of

~~ ~ ~ _ _ _

This guide describes the types of ground floors This guide does not deal with:
commonly used in domestic properties: ground 0 structural requirements
supported concrete slab floors, suspended 0 specific values or thicknesses ofthermal
concrete floors (includingbeam and block) and insulation because they depend on
suspended timber floors. It tells you how to individual designs
construct each type and gives advice on the 0 requirements for the exclusion of radon and
positions of damp-proof membranes (dpm) methane - see BR 211 page 8
and thermal insulation. 0 heated screeds.
In particular, it gives details of:
0 damp-proofing
0 vapour control layers You must consult a chartered surveyor or Structural
0 drying times for concrete bases and screeds am* ~~~,~~~~~
0 positions for thermal insulation. requirmartm.

Floating screed - Flooring grade

7 Alternative
positions
for dprn

\V/
Figure 1Ground supported slabs: insulation above the structure (see page 2)
2
Ground supported concrete slabs
The most common type ofconstruction for Damp proofing
house floors in England and Wales is a concrete There should be a dpm either above or below
Recommended slab, not less than 100 mm thick, laid directly the concrete slab, complying with BS CP 102,
concretemixer on the ground. The concrete slab can be: Section 3, and Building RegulationsApproved
LkKsintwcedconcrete 0 reinforced or unreinforced Document C. Digest 54 also gives information
Readyinixed: 0 directly finished to receive flooring on damp proofing solid floors.
GEN 1
Site mixed. 0 topped with a bonded, unbonded or floating The main function ofthe dpm is to prevent
Standard mu: ST2
screed moisture from the ground reaching the inside
Rdnfonedconcrete
0 covered by wood-based sheets, such as ofthe building. It may have other functions:
Ready mixed:
RC 30
chipboard or plywood separating ground contaminants from the
S& mixed: 0 covered by a flooringbedded directly to it, concrete, reducing the risk of interstitial
Standard mix ST4
such as ceramic tiles. condensation, or retaining constructionai
water. It can be placed in different positions,
Thermal insulation but it must be below the slab ifit is to protect
Insulation can be incorporated within the floor. the concrete from contamination in the
It can be glass fibre or foamed or expanded ground.
plastics sheets of appropriate compressive Figures 1to 3 show how dpms and
strength. Insulation can be positioned: insulation are usually located in ground
0 above the structure; supported concrete floors.
0 below the structure, and/or
0 at the edge ofthe structure.

Directly finished slab Bonded screed -


25 - 40 mm thick
b*

/
Concrete finish to
w v e Rooring-
mav need latex

Unbonded screed - Flooring grade chipboard


minimum 50 mm thick L or Plywood

screed and slab

.Ailernative posltim
for dpm - upper OM
Alternative position prefer& ll i n w M a
for dpm if lime can be is moisture resistan
allowed for drying out

Figure 2 Ground supported slabs: insulation below the structure


3
A Horizontaledge insulation Vertical edge insulation
below slab

Bonded screed
-
25 40 mm thick
Dwng hme can be long
, to receive flooring

Figure 3 Ground supported slabs: insulation at the edge of the structure

Suspended concrete (beam and block)


This construction has become popular during Thermal insulation
the last 10 years; it can be topped with a Insulation may be incorporated within the
bonded, unbonded or floating screed or floor. It can be glass fibre or foamed or
covered by wood-based sheets, such as expanded plastics sheets ofappropriate
chipboard or plywood. It is particularly useful compressivestrength.
where significant depth offill is required for a Figures 4 and 5 show the insulation
ground supported base or where methane or positioned:
radon protection measures are needed. 0 above the structure
The NHBC requires a suspended floor 0 within the structure.
where the depth of fill exceeds 600 mm
because of possible settlement of ground
supported slabs.
Flooring grade chipboard Floating screed on insulation-
screed 65 mm minimum thick

Vapour Vapour
-control layer -control layer
c dpm cdpm

Figure 4 Suspended concrete: insulation above the structure

Flooring grade chipboard Unbonded screed -


r, OrPwOcd 50 mm minimum thick

Figure 5 Suspendedconcrete: insulation within the structure


4

Suspended timber
Damp-proofing In housing and small cellular-typebuildings,
A damp-proof membrane should be provided if three types of timber ground floor are
the ground beneath the floor is lower than the commonly used:
surrounding ground and will not be drained filly spanning: perimeter walls provide
effectively- see Building Regulations support
Approved Document C4. partially spanning: sleeper walls or beams
Because suspended concrete floors are reduce effective spans
constructed when the walls are at dpc level, the non-spanning: the floor deck is fmed to
blocks can get wet before the building is made battens resting on, or
watertight. The saturated blocks can then take partially set into, a concrete
a long time to dry out, and so delay the slab or screed or other solid
installation of moisture sensitive flooring and material. Not, strktly speakin8
hold up completion and occupation. If sqendedjloon, these are dealt
insufficient drying time is allowed, premature with in Digest 364.
floor failure can occur. It is therefore good
practice to install a dpm or vapour control layer Traditionally,floorjoists were supported by
above the structural floor or beneath any sleeper walls built in honeycomb bond. This
screed or board finish. allowed ventilation through to air bricks in the
A dpc must be placed below the ends ofthe external wall. Square-edged or tongued and
beams to prevent corrosion ofthe grooved floorboards were nailed to the joists.
reinforcement from moisture and soluble salts. Nowadays,joist hangers are being used
The underfloor space should be ventilated to increasingly instead of sleeper walls to support
keep the humidity low and reduce the the joists from perimeter walls. Chipboard,
possibility of transfer of moisture across the plywood or hardboard sheets are used instead
sub-floor void. of floorboards,fixed by screw nails, ring shank
If there is a risk of methane or radon from nails, divergent staples or countersunk screws.
the ground, the underfloor space must be Thejoist hangers must be specified to match
ventilated. See Radon:guidance onprotective the crushing strength of material in the
measuresfor new dwellings. supporting walls and must be installed correctly
- see Good Building Guide 21.
Between 1967 and 1985,Building Regulations
in England and Wales required a concrete
oversite laid under suspended timber ground
floors; since 1985 the guidance in support of the
regulations have instead allowed a layer of inert
gravel laid over polyethylene.

- -'wh 1--

Figure 6 Suspendedconcrete (beam and block) floor


5

Flooring grade
chlpboerd or plywood

to wall and flooring


-SeeBR262

L
\ ,Quilt insulation
. - Plastics board insulatlon
supported on battens
supported on
fine nettlng or
strips of breather
membrane

Figure 7 Suspended timber: insulation under suspendedtimber floors

Screeds for concrete bases


The performance of a traditional, suspended Most screeds are made from cement and sand.
single timber floor is measured by its stifhess Preferred mix proportions are 1:4 by weight
and deflection under load rather than collapse. (about 1:3l/2 by volume) but mix proportions
Using the timber sizes given in the tables in the between 1:3 and 1:4l/2 by weight are suitable.
England and Wales Building Regulations Proprietary screeds are based on
Approved Document A will provide sufficient cementitious systems and calcium sulfate
strength and stifhess for normal use in binders. Some are trowel applied; others are
domestic construction. self-levelling.Many are designed to be laid at
However, even if the joists are of adequate lesser thicknesses than conventional screeds.
section to bear the loads, rotation is still a
problem, sojoists must be blocked at bearings Bonded screeds
and strutted at intermediate points; at least: Before laying bonded screeds, scabble or
0 once in spans over 2.5m and under 4.5m shotblast the surface ofthe concrete base to
0 twice in spans 4.5m and over. remove laitance and to expose the aggregate.
Apply cementitious grout or bonding agent to
Thermal insulation the base, then lay the screed, which should be
There are two ways to install insulation under 25 mm to 40 mm thick. Any thicker, there is a
suspended timber ground floors - see Figure 7: risk of it debonding from the base.
0 foamed plastics rigid boards held by battens
or protruding nails on the sides of the joists Unbonded screeds
0 quilt on netting draped over the joists, but Unbonded screeds are not purposely bonded
held by battens to avoid sag. to the base. All screeds laid directly over dpms
(except for epoxy bonding dpms) must be
Damp-proofing treated as unbonded, and the minimum
S o h o o d timber is normally used; it must be thickness should be 50 mm.
kept dry to avoid rot. At ground level, the
timber joists are normally supported on Floating screeds
masonry or concrete and protected from rising Screeds laid immediately over compressible
damp by impervious dpcs or dpms. Ifthe layers, such as expanded polystyrene or glass
membranes are bridged or fractured, or have fibre, are classed as floating screeds. They
deteriorated, rising damp may reach the should be not less than 65 mm thick for
timber, particularly if the building is in an area domestic screeds and not less than 75 mm
ofhigh exposure to driving rain. This is thick for other applications.
covered in more detail in Digest 364.
Thermal insulation and membranes
for concrete bases
The position ofthe thermal insulation membrane. Allow excess constructional water
determines the thermal properties of the floor. in concrete bases and screeds to dry out before
Ifthe insulation is placed as a sandwich laying moisture sensitive floor coverings such
between the base and screed, the floor will as carpets, PVC or timber. A cement/sand
warm up quickly when the heating is switched screed, 50 mm thick, laid on a dpm needs about
on, because only the screed is heated. But the six weeks before it is dry enough to take
floor will also cool quickly when the heating is flooring. Some proprietary screed systems dry
switched off, because the screed has low considerably quicker than conventional
thermal capacity. screeds.
Ifthe insulation is placed below the slab, the Thick concrete bases, with the dpm below
floor will be slow to warm up when the heating the slab, take much longer to dry than do
is switched on because ofthe high thermal screeds laid directly on a dpm.
capacity ofthe concrete. But it will be slow to It is not uncommon for 150 mm-thick base
cool when the heating is switched OK to take up to a year to dry.
Insulating materials used in floors have some The table ofdrying times below is only for
resistance to moisture vapour but considerably guidance. The actual drying time ofa screed 01
less than that ofa dpm. Additional moisture slab depends on many factors, including:
barriers are needed in some forms of 0 the thickness
construction to control constructional water. 0 the amount of original mixing water
Use polyethylene sheet not less than 500 gauge 0 any admixtures
(125 pm). This is thinner than the sheet used 0 mix proportions
for dpms, but similar to that used for vapour 0 aggregate grading
control layers. Damp-proof membranes above 0 drying conditions.
or below the base must be continuous and
linked to the dpc in the walls. Polyethylene Always check the moisture condition of the
sheet below the base should be at least floor with a hygrometer before laying any
1200 gauge (300 pm) or 1000 gauge (250 pm) if moisture-sensitive floors, such as chipboard or
the product has a BBA certificate or is to the other wood-based materials, flexible PVC,
PIFA standard. linoleum, cork tiles or carpet - see BS 8203 and
Liquid membranes can be applied by brush Digest 364.
or hot poured on to the top ofthe base The timing oflaying the base slab is
concrete. When dry, the membrane should be important. Ifit is laid before the roofis in
at least 0.6 mm thick. Take care in selecting position, there is a chance that rain will saturate
these materials as some solvents may not be the slab and insulation. This can greatly extend
compatible with foamed plastics insulating the drying time ofthe slab, and reduce the
materials. Always allow sufficient time for any insulating properties ofsome types of
solvent to evaporate before covering the insulating material, such as glass fibre.

Thickness Con-struction Approximate


drying times

50 mm Screed 4 - 6 weeks
75 mm Screed 6 - 8 weeks
100 mm Concrete 4 - 6 months
150 mm Concrete
(or 100rnrn concrete
plus 50 m screed
with no dpm between) 6 - 12 months
200 mm Concrete 8 - 20 months
7

Chipboard
Use chipboard to BS 5669 Type C4 (M). Moisture
Where tongue and groove boards are Like all timber-based products, changes in the
supported continuously by the sub-base or the moisture condition of chipboard will change its
insulation underlay, all the joints must be glued dimensions. There must be a gap around the
continuously.Spot gluing is insufficient. perimeter of rigid upstands to accommodate
Where chipboard is laid over compressible any likely moisture-induced movement
insulation at thresholds, internal partitions and - see Figure 8. A gap of not less than 10 mm is
to battens supported by the sub-floor other recommended in normal house floors.
heavily loaded positions, fur the chipboard It is rarely possible to allow sufficient time
- see Figure 8. for concrete bases and screeds to dry to a state
which will not induce moisture movement in
Insulation chipboard. A moisture control layer is,
Ifchipboard (or insulation and chipboard) is to therefore, needed between the base and the
be laid on a concrete base, the surface ofthe chipboard. Where insulation is installed
base must be flat. Boards laid on an undulating between the base and the chipboard, place the
base may oscillate up and down under dynamic moisture control layer on the top (warm side)
loads, for example, when people walk across of the insulation.Some prefabricated panels
the floor. Surface deviations must be not more have the chipboard and insulation stuck
than 5 mm under a 3 m straight edge. Bases together at the factory. Ifyou are using these,
which do not meet this standard can be place the moisture control layer on the base.
levelled by applying a thin layer of Use polyethylene sheet of not less than
cemendsand mortar which should be allowed 500 gauge (125 pm). Ifthe base is laid directly
to set, harden and dry before proceeding on the ground, the moisture control layer is in
further. Do not use dry sand for levelling bases addition to the damp-proof membrane.
as it can move around under the effects of
pumping action induced by dynamic loads.

Figure 8 Extra support and allowance for movement of chipboard


8 Further information
1
British Standards Institution
BS 882: 1992 Specificationfor aggregates from natural sources for concrete
BS 5328:- Concrete
Part 1: 1991Guide to specifying concrete
Part 2: 1991Methods for specifying concrete mixes
BS 5669:- Particleboard
Part 5: 1993 Code of practice for the selection and applicationof particleboards for specific
purposes
BS 8000:- Workmanship on building sites
Part 9: 1989 Code of practice for cement/sand floor screeds and concrete floor toppings
BS 8203: 1996 Code of practice for installationof resilientfloor coverings
BS 8204:- Screeds, bases and in-situ floorings
Part 1: 1987 Code of practice for concrete bases and screeds to receive in-situ floorings
CP 102: 1973 Code of practice for protection of buildings against water from the ground

Building Regulations
Department of the Environment and the Welsh Office, HMSO, London, 1991.
Approved documents A and C4

Building Research Establishment


Reports
Radon: guidance on protective measures for new dwellings. BR 2 11, CRC, 1992.
Protecting dwellings with suspended timber floors: a BRE guide to radon remedial measures in
existing dwellings. BR 270. CRC, 1995.
Major alterations and conversions: a BRE guide to radon remedial measures in existing dwellings.
BR 267, CRC, 1994.
Sealing cracks in solid floors: a BRE guide to radon remedial measures in existing dwellings.
BR 239, CRC, 1993.
Thermal insulation: avoiding risks. BR 262. CRC, 1994.
Information Paper
IP 11/84 BRE Screed tester: classifications of screeds, sampling and acceptance limits
Digests
54 Damp-proofing solid floors
364 Design of timber floors to prevent decay
Good Building Guides
21 Joist hangers
28 Domestic floors:
Part 1 construction, insulation and damp-proofing
Part 2 assessingthem for replacementor repair: concrete floors, screeds and finishes
Part 3 assessingthem for replacementor repair: timber floors and decks
Part 4 repairing or replacing floors and flooring: rnagnesite, tiles, slabs and screeds
Part 5 repairing or replacing floors and flooring: wood blocks and suspended timber

BuildingGwdes have been with concise guidance Onw


gpw&sare desigmdta
diffmnttta&s and professions.
,and an on other r e W e sources, to
is made to ensure that the guidance given
s the most authoritativeat the date of issus.
,or through subscription to the BRE ProfessiQnal
EClRsQX

Technical enquiries to: Digests Construction Research Full detailsof all recent Publishedby Applicabonsto copy all or
BRE Advisory Service GoodBuildingGuldes CommunicabonsLtd, issuesof ERE publicabons Construction Research any part of this publicabon
Garston, Watford, Gwd Repair Guides 151 Rosebery Avenue are given in ERE News, CmmunicatlonsLtd by should be madeto
WD2 7JR lnformabonPapers London, EClR 4QX. Email. sent free to subscribers. permissionof the Controller ConstrucbonResearch
Telephone 01923 664664 are availableon crc@construct.emap CO uk of HMSO and the Building CommunicatKMsLtd,
Facsimile 01923 664098 subscription. For current Telephone 0171 505 6622 @Crowncopyright 1997 ResearchEstablishment PO Box 202, Watford,
prices pleasecontact‘ Facsimile 0171 5056606 ISBN 186081 140X He*, wD2 7QG

You might also like