Professional Documents
Culture Documents
20% OH/P
Item Pay Unit Rate Rate
Description Qty Unit 20% OH/PROFFIT +2% NBT with Amount (Rs.)
No. Item (Rs.) LKR
rate
1.0 Allow for mobilisation & demobilisation 1.00 Item 1,000,000.00 1,200,000.00 1,224,489.80 1,224,489.80 -
2.0 Provide Office for the Engineer 12.00 Months 40,000.00 48,000.00 48,979.59 587,755.10 80,000.00 163%
3.0 Maintain Office for the Engineer Item PS 360,000.00 432,000.00 440,816.33 440,816.33 PS
4.0 Provide Furniture & equipment for the Engineer's Office Item PS 200,000.00 240,000.00 244,897.96 244,897.96 PS
2) Office Aide 12.00 Months 25,000.00 30,000.00 30,612.24 367,346.94 26,250.00 86%
3) Office Watcher (02 Nos.) 12.00 Months 50,000.00 60,000.00 61,224.49 734,693.88 52,500.00 86%
6.0 Provide and maintain Vehicle for the Engineer 12.00 Months 150,000.00 180,000.00 183,673.47 2,204,081.63 162,750.00 89%
9.00 Provide all necessary insurance Item Ps 200,000.00 240,000.00 244,897.96 244,897.96 Ps
10.00 Provide all Bonds & Securities Item Ps 300,000.00 360,000.00 367,346.94 367,346.94 Ps
BILL NO 02
20% OH/P
Item Pay Unit Rate Rate
Description Qty Unit 20% OH/PROFFIT +2% NBT with Amount (Rs.)
No. Item (Rs.) LKR
rate
B.1 Clearing & Grubbing 120.00 m2 247.50 297.00 303.06 36,367.35 75.00 25%
Piling -
B.10 Cross-hole sonic logging test for pile intergrity of bored pile. 32.00 nrs 40,000.00 48,000.00 48,979.59 1,567,346.94 9,500.00 19%
20% OH/P
Item Pay Unit Rate Rate
Description Qty Unit 20% OH/PROFFIT +2% NBT with Amount (Rs.)
No. Item (Rs.) LKR
rate
B.15 Class A concrete of Grade 25(20) in abutments & wingwalls. 181.00 m3 17,215.00 20,658.00 21,079.59 3,815,406.12 17,600.00 83%
Formwork
B.18 Smooth finish formwork for abutments & wingwalls 490.00 m2 3,416.00 4,099.20 4,182.86 2,049,600.00 1,700.00 41%
Reinforcement
Weep Holes
Sri Lanka Land Reclamation And Development Corporation ELS Construcitons
20% OH/P
Item Pay Unit Rate Rate
Description Qty Unit 20% OH/PROFFIT +2% NBT with Amount (Rs.)
No. Item (Rs.) LKR
rate
75mm. thick 40mm. stone filter layer behind dry stone lining
B.26 15.40 m3 2,609.00 3,130.80 3,194.69 49,198.29 2,750.00 86%
as per drawing.
C. SUPER STRUCTURE
Formwork
C.4 Smooth finish formwork for duct tie beams. 4.00 m2 3,392.00 4,070.40 4,153.47 16,613.88 1,700.00 41%
Reinforcement
Hot rolled mild steel bars of Grade 250 in deck, tie rods of
C.5 2.40 M.T 190,000.00 228,000.00 232,653.06 558,367.35 195,000.00 84%
deck.
Prestressed Concrete
Sri Lanka Land Reclamation And Development Corporation ELS Construcitons
20% OH/P
Item Pay Unit Rate Rate
Description Qty Unit 20% OH/PROFFIT +2% NBT with Amount (Rs.)
No. Item (Rs.) LKR
rate
Railings
Concrete Kerbs
Supplying and fixing of mild steel angle iron & hard rubber
C.13 52.00 L.m 7,282.00 8,738.40 8,916.73 463,670.20 3,000.00 34%
expansion joint as per drawing No. T/B/107 Rev.1
Bridge Bearings
Miscellaneous
20% OH/P
Item Pay Unit Rate Rate
Description Qty Unit 20% OH/PROFFIT +2% NBT with Amount (Rs.)
No. Item (Rs.) LKR
rate
20% OH/P
Item Pay Unit Rate Rate
Description Qty Unit 20% OH/PROFFIT +2% NBT with Amount (Rs.)
No. Item (Rs.) LKR
rate
Tack Coat
Medium curing cut back bitumen (10-20%) or emulsified
bitumen Grade CSS-1 or CSS-1h tack coat applied at the
C.26 510.00 m2 40.20 48.24 49.22 25,104.49 115.00 234%
rate of 0.5 litres/m² to concrete deck and approach slab
surface.
SUMMARY OF BILL NO 02
20% OH/P
Item Pay Unit Rate Rate
Description Qty Unit 20% OH/PROFFIT +2% NBT with Amount (Rs.)
No. Item (Rs.) LKR
rate
BILL NO 03
CONSTRUCTION OF IMMEDIATE APPROACHES FOR BRIDGE NO. 3/1 ON PELIYAGODA - PUTTALAM ROAD
(OLIYAMULLA BRIDGE) AS PER DRAWING NOS. SLLR & DC/WP/B/1295/1, 1B & 3 TO 6
A. SITE CLEARING
A.1 Clearing & Grubbing 200.00 m2 247.50 297.00 303.06 60,612.24 75.00 25%
B. EARTHWORKS
Roadway excavation
B.1 Roadway excavation in unclassified soil. 40.00 m3 1,432.00 1,718.40 1,753.47 70,138.78 220.00 13%
Embankment Construction
B.4 Trimming Levelling & Compacting of Original ground. 320.00 m2 78.40 94.08 96.00 30,720.00 95.00 99%
Shoulder Construction
Top Soiling
Sri Lanka Land Reclamation And Development Corporation ELS Construcitons
20% OH/P
Item Pay Unit Rate Rate
Description Qty Unit 20% OH/PROFFIT +2% NBT with Amount (Rs.)
No. Item (Rs.) LKR
rate
B.6 Top soil supplied, piled & spread. 30.00 m3 1,624.00 1,948.80 1,988.57 59,657.14 900.00 45%
Grassing
B.7 Solid sodding 270.00 m2 727.00 872.40 890.20 240,355.10 375.00 42%
Guard Stones
B.9 Grouted rip rap filled with 1:3 cement mortar as per drawing. 20.00 m3 7,377.00 8,852.40 9,033.06 180,661.22 10,000.00 111%
C. ROAD PAVEMENT
C.1 Soil sub base type I material compacted in position. 80.00 m3 4,426.00 5,311.20 5,419.59 433,567.35 2,650.00 49%
C.2 Scarifying existing surface as necessary. 400.00 m2 76.20 91.44 93.31 37,322.45 125.00 134%
Prime Coat
Tack coat
20% OH/P
Item Pay Unit Rate Rate
Description Qty Unit 20% OH/PROFFIT +2% NBT with Amount (Rs.)
No. Item (Rs.) LKR
rate
SUMMARY OF BILL NO 03
01 LABOUR
1.0 Unskilled labour 10.00 Days 1,516.60 1,819.92 1,857.06 18,570.61 1,000.00 54%
2.0 Semi skilled labour 10.00 Days 1,555.06 1,866.07 1,904.16 19,041.55 900.00 47%
3.0 Skilled labour 5.00 Days 1,627.40 1,952.88 1,992.73 9,963.67 750.00 38%
4.0 Mechanic 2.00 Days 1,627.40 1,952.88 1,992.73 3,985.47 1,200.00 60%
5.0 Driver 3.00 Days 1,627.40 1,952.88 1,992.73 5,978.20 1,350.00 68%
6.0 Operator 5.00 Days 1,627.40 1,952.88 1,992.73 9,963.67 1,200.00 60%
7.0 Surveyor 1.00 Days 4,500.00 5,400.00 5,510.20 5,510.20 1,800.00 33%
LABOUR 73,013.39
Sri Lanka Land Reclamation And Development Corporation ELS Construcitons
20% OH/P
Item Pay Unit Rate Rate
Description Qty Unit 20% OH/PROFFIT +2% NBT with Amount (Rs.)
No. Item (Rs.) LKR
rate
02 EQUIPMENT
1.0 Poker vibrator 10.00 Hrs 240.06 288.07 293.95 2,939.51 100.00 34%
2.0 Tractor with Trailer 12.00 Hrs 745.41 894.49 912.75 10,952.96 150.00 16%
3.0 Wheel Loader 4.00 Hrs 3,960.73 4,752.88 4,849.87 19,399.49 150.00 3%
4.0 Hand Rammers 10.00 Hrs 425.42 510.50 520.92 5,209.22 250.00 48%
5.0 Smooth Roller 8.00 Hrs 1,366.48 1,639.78 1,673.24 13,385.93 200.00 12%
6.0 Concrete Mixer 8.00 Hrs 1,357.17 1,628.60 1,661.84 13,294.73 250.00 15%
7.0 Steel Wheel Roller self - Propelled Static 8.00 Hrs 2,596.47 3,115.76 3,179.35 25,434.81 750.00 24%
8.0 Water pump 50.00 Hrs 226.48 271.78 277.32 13,866.12 500.00 180%
9.0 Bitumen Distributor 3.00 Hrs 1,562.30 1,874.76 1,913.02 5,739.06 500.00 26%
10.0 Water Bowser 10.00 Hrs 2,429.42 2,915.30 2,974.80 29,748.00 600.00 20%
11.0 Backhoe loader 8.00 Hrs 2,951.67 3,542.00 3,614.29 28,914.32 800.00 22%
12.0 Dump Truck 4.00 Hrs 9,194.00 11,032.80 11,257.96 45,031.84 1,250.00 11%
13.0 Van or similar utility vehicle 125.00 km 80.48 96.58 98.55 12,318.37 40.00 41%
14.0 Tipper Truck (Inclusive of return trip) 125.00 km 163.73 196.48 200.49 25,060.71 55.00 27%
15.0 Welding plant engine driven 20.00 Hrs 1,616.18 1,939.42 1,979.00 39,579.92 900.00 45%
16.0 Extractor (sheet pile) 10.00 Hrs 114.74 137.69 140.50 1,404.98 900.00 641%
17.0 Hammer (Vibro electric) 5.00 Hrs 3,714.64 4,457.57 4,548.54 22,742.69 500.00 11%
18.0 Generator 5.00 Hrs 814.66 977.59 997.54 4,987.71 350.00 35%
19.0 Compressor 10.00 Hrs 5,900.20 7,080.24 7,224.73 72,247.35 700.00 10%
20.0 Hand held breaker demolition 10.00 Days 468.65 562.38 573.86 5,738.57 250.00 44%
Sri Lanka Land Reclamation And Development Corporation ELS Construcitons
20% OH/P
Item Pay Unit Rate Rate
Description Qty Unit 20% OH/PROFFIT +2% NBT with Amount (Rs.)
No. Item (Rs.) LKR
rate
21.0 Mobile Crane 5.00 Hrs 9,591.32 11,509.58 11,744.47 58,722.37 1,000.00 9%
22.0 Excavator (Crawler with breaker) 5.00 Hrs 6,114.10 7,336.92 7,486.65 37,433.27 900.00 12%
EQUIPMENT 494,151.93
Sri Lanka Land Reclamation And Development Corporation ELS Construcitons
20% OH/P
Item Pay Unit Rate Rate
Description Qty Unit 20% OH/PROFFIT +2% NBT with Amount (Rs.)
No. Item (Rs.) LKR
rate
03 MATERIAL
1.0 Cement ordinary (50 kg bag) 10.00 Nos 816.80 980.16 1,000.16 10,001.63 920.00 92%
2.0 Aggregate (19 mm) 5.00 Cu.m 2,004.53 2,405.44 2,454.53 12,272.63 2,500.00 102%
3.0 Aggregate (37.5 mm) 5.00 Cu.m 1,711.53 2,053.84 2,095.75 10,478.76 1,500.00 72%
4.0 Sand 5.00 Cu.m 4,919.00 5,902.80 6,023.27 30,116.33 2,500.00 42%
5.0 Bitumen 80/100 200.00 Liter 55.00 66.00 67.35 13,469.39 75.00 111%
6.0 Bituminous emulsion CRS-1 200.00 Liter 52.35 62.82 64.10 12,820.41 75.00 117%
8.0 Aggregate Base Course (37.5 mm down graded) 5.00 Cu.m 1,711.19 2,053.43 2,095.33 10,476.67 1,500.00 72%
9.0 Random Rubble (150-225 mm) 5.00 Cu.m 1,402.30 1,682.76 1,717.10 8,585.51 1,000.00 58%
(Excluding piling)
10.0 Reinforcement in bars Grade 250 0.25 Mt 100,620.00 120,744.00 123,208.16 30,802.04 85,000.00 69%
11.0 Reinforcement in bars Grade 460 0.25 Mt 100,980.00 121,176.00 123,648.98 30,912.24 85,000.00 69%
13.0 Plywood (15 mm thick) 25.00 Sq.m 1,207.90 1,449.48 1,479.06 36,976.53 150.00 10%
14.0 Diesel 80.00 Liter 95.00 114.00 116.33 9,306.12 95.00 82%
MATERIAL 403,834.59
03.Material 403,834.59
Sri Lanka Land Reclamation And Development Corporation ELS Construcitons
20% OH/P
Item Pay Unit Rate Rate
Description Qty Unit 20% OH/PROFFIT +2% NBT with Amount (Rs.)
No. Item (Rs.) LKR
rate
Calculation error
Calculation error
Calculation error
Calculation error
Calculation error
2,242,500.00 253,245.91 2,912,327.97 220,000.00 2,530,000.00 248,120.00 2,853,380.00
Calculation error
ucitons Access Engineering Sunbeam Construction Sierra Cons
Calculation error
-
100,300.00 2,891.35 170,589.65 3,000.00 177,000.00 3,765.00 222,135.00
Calculation error
468,000.00 253,245.91 607,790.18 220,000.00 528,000.00 248,120.00 595,488.00
Calculation error
-
ucitons Access Engineering Sunbeam Construction Sierra Cons
-
Calculation error
Calculation error
Calculation Error
Calculation error
Calculation error
Calculation error
Calculation error
- Calculation error -
Calculation error
Calculation error
A.1 202(1b) Removal and disposal of parts of existing bridge Item L.S.
as and when necessary for the construction of
the new bridge inclusive of necessary repairs to
existing bridge in order to maintain free flow of
traffic.
Piling
B.5 1004(1b) Provide 300 x 250mm. reinforced concrete sheet 968.00 L.m.
piles in Class A Grade 30(20) concrete as per
drawing.
B.6 1004(3a) Cast insitu 1000mm dia. bored piles in Grade 480.00 L.m.
30(20) concrete inclusive of reinforcement &
50mm dia. G.I. pipe and accessories for sonic
logging tests as per drawing for foundations of
abutments & wingwalls.
B.8 1004(3c) Temporary filling of holes of bored pile (1000 mm Item P.S.
dia.) above pile cap top level to existing road
level to maintain a free flow of traffic during
construction as directed by the Engineer.
B.9 1004(2b) Drive 300 x 250mm. reinforced concrete sheet 968.00 L.m.
piles as per drawing.
B.10 1004(6a) Cross-hole sonic logging test for pile intergrity of 32 Nos.
bored pile.
B.11 1004(6b) Supply & pumping of grouting material to the 1850.00 L.m.
50mm dia. G.I. pipes.
Formwork
Reinforcement
B.21 1002(1a) Cold worked deformed high yield steel bars of 16.40 M.T.
Grade 460 in abutments & wingwalls.
B.22 1002(1b) Hot rolled mild steel bars of Grade 250 in 0.16 M.T.
abutment capping beams, curtain walls, ballast
walls, bearing pads and approach slabs.
B.23 1002(1a) Cold worked deformed high yield steel bars of 3.00 M.T.
Grade 460 in approach slabs.
Weep Holes
B.24 706(1) Forming weep holes in abutments & wingwalls 107.00 L.m.
using 110mm dia. P.V.C. pipes and finished
smooth with dripledge and surround complete as
per drawing.
B.25 705(1) 50-200mm. dry stone lining behind abutment & 204.00 m3
wingwalls as per drawing.
B.26 705(2) 75mm. thick 40mm. stone filter layer behind dry 15.40 m3
stone lining as per drawing.
B.27 705(3) Clay puddled & laid behind abutments & 58.00 m2
wingwalls to form the impervious layer as per
drawing.
C. SUPER STRUCTURE
Formwork
C.3 1008(1b) Smooth finish formwork on sides for deck & foot 59.00 m2
walk concreting.
C.4 1008(1c) Smooth finish formwork for duct tie beams. 4.00 m2
Reinforcement
C.5 1002(1b) Hot rolled mild steel bars of Grade 250 in deck, 2.40 M.T.
tie rods of deck.
C.6 1002(1a) Cold worked deformed high yield steel bars 4.60 M.T.
Grade 460 in deck & foot walks.
Prestressed Concrete
Railings
C.9 1018(1) Precast reinforced concrete railing & uprights in 38.00 L.m.
Class A Grade 25(20) concrete inclusive of light
reinforcement & mould as per drawing No.
T/B/102 A & B.
C.11 807(1) Precast kerb in Class B Grade 25(20) concrete 88.00 L.m.
with light reinforcement & mould as per drawing
No. T/B/106 Rev. 1
C.12 807(4) Lower kerbs in Class B Grade 20(14) concrete 88.00 L.m.
cast insitu as per drawing.
Expansion joints
C.13 1009(1) Supplying and fixing of mild steel angle iron & 52.00 L.m.
hard rubber expansion joint as per drawing No.
T/B/107 Rev.1
Bridge Bearings
C.14 1010(2) 75x12mm. hard rubber bearing pads supplied & 98.00 L.m.
laid over capping beam as per drawing.
Miscellaneous
C.15 1012(1) 20mm Dia. 200mm long stainless steel dowels 43 Nos.
supplied fixed and grouted at fixed ends as per
drawing.
C.16 1011(1) 25mm Dia. 200mm long hot rolled mild steel 92 Nos.
dowels supplied fixed and grouted for the
approach slab as per drawing.
C.17 1013(1) Bituminous sealing felt under beams at ends to 52.00 L.m.
prevent grout leak on to capping beam as per
drawing.
C.18 1014(1) Bituminous sealing felt under approach slabs at 46.00 L.m.
capping beam ends to prevent bitumen running
on capping beam as per drawing.
C.19 1015(1b) 225mm. dia. Polythene displacers supplied and 630.00 L.m.
filled with saw dust or similar light material in deck
as per drawing.
C.20 1016(1c) Service duct of size 350x600mm. formed in deck 88.00 L.m.
as per drawing.
C.21 1017(1a) 500x450x100mm. thick cover slabs for service 180 Nos.
ducts in Class B Grade 25(20) concrete inclusive
of light reinforcement and smooth shuttering
provided as per drawing.
C.24 1020(1c) 50mm. dia. P.V.C. drain pipes supplied and fixed 12 Nos.
through deck as per drawing.
C.25 812(2) 12 m high steel lamp post with duble arm 2 Nos.
bracket, supplied & fixed at the centre median as
per drawing. (Drg. No. T/0041/A) This includes
installation of electirc cables, fixing of lamps and
other necessary appliances.
Tack Coat
SUMMARY OF BILL NO 02
C. Super Structure
TOTAL
#REF!
1,500,000.00
A.1 202(1b) Removal and disposal of parts of existing bridge Item L.S.
as and when necessary for the construction of
the new bridge inclusive of necessary repairs to
existing bridge in order to maintain free flow of
traffic.
Piling
B.5 1004(1b) Provide 300 x 250mm. reinforced concrete sheet 968.00 L.m.
piles in Class A Grade 30(20) concrete as per
drawing.
B.6 1004(3a) Cast insitu 1000mm dia. bored piles in Grade 480.00 L.m.
30(20) concrete inclusive of reinforcement &
50mm dia. G.I. pipe and accessories for sonic
logging tests as per drawing for foundations of
abutments & wingwalls.
B.8 1004(3c) Temporary filling of holes of bored pile (1000 mm Item P.S.
dia.) above pile cap top level to existing road
level to maintain a free flow of traffic during
construction as directed by the Engineer.
B.9 1004(2b) Drive 300 x 250mm. reinforced concrete sheet 968.00 L.m.
piles as per drawing.
B.10 1004(6a) Cross-hole sonic logging test for pile intergrity of 32 Nos.
bored pile.
B.11 1004(6b) Supply & pumping of grouting material to the 1850.00 L.m.
50mm dia. G.I. pipes.
Formwork
Reinforcement
B.21 1002(1a) Cold worked deformed high yield steel bars of 16.40 M.T.
Grade 460 in abutments & wingwalls.
B.22 1002(1b) Hot rolled mild steel bars of Grade 250 in 0.16 M.T.
abutment capping beams, curtain walls, ballast
walls, bearing pads and approach slabs.
B.23 1002(1a) Cold worked deformed high yield steel bars of 3.00 M.T.
Grade 460 in approach slabs.
Weep Holes
B.24 706(1) Forming weep holes in abutments & wingwalls 107.00 L.m.
using 110mm dia. P.V.C. pipes and finished
smooth with dripledge and surround complete as
per drawing.
B.25 705(1) 50-200mm. dry stone lining behind abutment & 204.00 m3
wingwalls as per drawing.
B.26 705(2) 75mm. thick 40mm. stone filter layer behind dry 15.40 m3
stone lining as per drawing.
B.27 705(3) Clay puddled & laid behind abutments & 58.00 m2
wingwalls to form the impervious layer as per
drawing.
C. SUPER STRUCTURE
Formwork
C.3 1008(1b) Smooth finish formwork on sides for deck & foot 59.00 m2
walk concreting.
C.4 1008(1c) Smooth finish formwork for duct tie beams. 4.00 m2
Reinforcement
C.5 1002(1b) Hot rolled mild steel bars of Grade 250 in deck, 2.40 M.T.
tie rods of deck.
C.6 1002(1a) Cold worked deformed high yield steel bars 4.60 M.T.
Grade 460 in deck & foot walks.
Prestressed Concrete
Railings
C.9 1018(1) Precast reinforced concrete railing & uprights in 38.00 L.m.
Class A Grade 25(20) concrete inclusive of light
reinforcement & mould as per drawing No.
T/B/102 A & B.
C.11 807(1) Precast kerb in Class B Grade 25(20) concrete 88.00 L.m.
with light reinforcement & mould as per drawing
No. T/B/106 Rev. 1
C.12 807(4) Lower kerbs in Class B Grade 20(14) concrete 88.00 L.m.
cast insitu as per drawing.
Expansion joints
C.13 1009(1) Supplying and fixing of mild steel angle iron & 52.00 L.m.
hard rubber expansion joint as per drawing No.
T/B/107 Rev.1
Bridge Bearings
C.14 1010(2) 75x12mm. hard rubber bearing pads supplied & 98.00 L.m.
laid over capping beam as per drawing.
Miscellaneous
C.15 1012(1) 20mm Dia. 200mm long stainless steel dowels 43 Nos.
supplied fixed and grouted at fixed ends as per
drawing.
C.16 1011(1) 25mm Dia. 200mm long hot rolled mild steel 92 Nos.
dowels supplied fixed and grouted for the
approach slab as per drawing.
C.17 1013(1) Bituminous sealing felt under beams at ends to 52.00 L.m.
prevent grout leak on to capping beam as per
drawing.
C.18 1014(1) Bituminous sealing felt under approach slabs at 46.00 L.m.
capping beam ends to prevent bitumen running
on capping beam as per drawing.
C.19 1015(1b) 225mm. dia. Polythene displacers supplied and 630.00 L.m.
filled with saw dust or similar light material in deck
as per drawing.
C.20 1016(1c) Service duct of size 350x600mm. formed in deck 88.00 L.m.
as per drawing.
C.21 1017(1a) 500x450x100mm. thick cover slabs for service 180 Nos.
ducts in Class B Grade 25(20) concrete inclusive
of light reinforcement and smooth shuttering
provided as per drawing.
C.24 1020(1c) 50mm. dia. P.V.C. drain pipes supplied and fixed 12 Nos.
through deck as per drawing.
C.25 812(2) 12 m high steel lamp post with duble arm 2 Nos.
bracket, supplied & fixed at the centre median as
per drawing. (Drg. No. T/0041/A) This includes
installation of electirc cables, fixing of lamps and
other necessary appliances.
Tack Coat
SUMMARY OF BILL NO 02
C. Super Structure
TOTAL
20/January/2018
1,500,000.00
A. SITE CLEARING
B. EARTHWORKS
Roadway excavation
Embankment Construction
Shoulder Construction
Top Soiling
Grassing
Guard Stones
B.9 804(1) Grouted rip rap filled with 1:3 cement mortar as 20.00 m3
per drawing.
C. ROAD PAVEMENT
Prime Coat
Tack coat
SUMMARY OF BILL NO 03
A. SITE CLEARING
B. EARTH WORK
C. ROAD PAVEMENT
Page 52 of Pages 62 377035495.xlsx : BOQ3
Item Pay Item Description Quantity Unit Rate
TOTAL
20/January/2018
The rate entered in this Schedule shall form the schedule of Materials on Site for the purpose
of the Contract.
The rates shall be the cost of purchase including any customs duty demurrage
or other freight charges, loading and off loading, haulage and any other expenses in
connection with bringing of the material of site. The rate given must be supported by
quotations and other documentary evidence.
Additional items may be written in with the prior agreement of the Engineer. The rates
entered in this Schedule shall also be used for works ordered to be carried out as Day works.
01. LABOUR
4 Mechanic 2 Days
5 Driver 3 Days
6 Operator 5 Days
7 Surveyor 1 Days
Total
A081BBOQ
03.07.2017
La/W/2017
02. EQUIPMENT
The rates are exclusive of Driver, Operator or Attendant, but inclusive of fuel
and Consumable stores.
Total
Eq/W/2017
A081BBOQ 03.07.2017
03. MATERIAL
4 Sand 5 Cu.m.
14 Diesel 80 Liter
Total
01. Labour -
02. Equipment -
03. Material -
TOTAL -
A081BBOQ Ma/W/2017
03.07.2017
Estimate ELS Sunbeam
B5 9,715,954.29 4,259,200.00 9,680,000.00
B6 58,775,510.20 33,360,000.00 52,800,000.00 63,869,387.76 38,960,000.00
B7 5,093,877.55 5,600,000.00 7,040,000.00