Which of the following tools is used when there is uncertainty in activity duration's?
Gantt Chart
Critical Path Method
Milestone chart
Program Evaluation and Review Technique
Question #11 to 15: Use the following data. The cost expenditure for performing the
seven activities, start date, the duration is given in Table 1.
Table 1
Activity Start Date Duration Cost (Rs.)/Day
X 1 1 0
A 2 2 4550
B 3 3 3175
C 4 2 6995
D 5 3 1556
E 5 4 789
F 9 1 9000
1 point
What is the total duration of the project?.
9 days
8 days
10 days
7 days
1 point
The cumulative budget of the project reaches 80% of the total budget on____day.
8th
9th
6th
7th
1 point
If activities ‘D’ and ‘E’ start on day 6 instead of day 5 as planned, due to the shortage of
manpower, 80% of project budget reaches on___day.
8th
9th
6th
7th
1 point
Which day has the highest cost budget (baseline schedule)?
3
4
5
6
1 point
Draw a bar chart and find the cumulative total cost on day 3, day 5 and day 6.
Rs. 22445, Rs. 34960, Rs. 37305
Rs. 12275, Rs. 34960, Rs. 37305
Rs. 4550, Rs. 12275, Rs. 34960
Rs. 34960, Rs. 37305, Rs. 39650
You may submit any number of times before the due date. The final submission will be
considered for grading.