ID Task Name Duration Start2017

November Finish January 2018 March 2018 May 2018 July 2018 September 2018
December 1 January 1 February 1 March 1 April 1 May 1 June 1 July 1 August 1 September 1 October 1
W40 W38 W36 W34 W32 W30 W28 W26 W24 W22 W20 W18 W16 W14 W12 W10 W8 W6 W4 W2 W-1 W-3
1 FUEL GAS SYSTEM - HOLD1-9 & 172 days Thu 2/1/18 Fri 9/28/18
HOLD200
2 Preparation 21 days Thu 2/1/18 Thu 3/1/18
3 Mob & Demob 7 days Thu 2/1/18 Fri 2/9/18
4 Mess & Shop Facilities 14 days Mon 2/12/18Thu 3/1/18
5 Engineering 17 days Fri 3/2/18 Mon 3/26/18
6 Survey 3 days Fri 3/2/18 Tue 3/6/18
7 Mark Up Detail Drawing 14 days Wed 3/7/18 Mon 3/26/18
8 Procurement 90 days Fri 3/2/18 Thu 7/5/18
9 Pipe Seamless 45 days Fri 3/2/18 Thu 5/3/18
10 Pipe & Fittings Stainless 60 days Fri 3/2/18 Thu 5/24/18
11 Fittings 30 days Fri 3/2/18 Thu 4/12/18
12 Valve 90 days Fri 3/2/18 Thu 7/5/18
13 Cable 30 days Fri 3/2/18 Thu 4/12/18
14 Construction 132 days Fri 3/9/18 Mon 9/10/18
15 Fabrication 90 days Tue 4/3/18 Tue 8/7/18
16 NDT 90 days Fri 4/20/18 Thu 8/23/18
17 Sand Blast & Painting 90 days Tue 4/24/18Mon 8/27/18
18 Erection 90 days Tue 5/8/18 Mon 9/10/18
19 Termination & Interconnection 7 days Fri 3/9/18 Mon 3/19/18
20 Pre-Commissioning 30 days Wed 8/15/18 Tue 9/25/18
21 Cleaning, Hydrotest & Purging 30 days Wed 8/15/18Tue 9/25/18
22 Commissioning & Hand Over 3 days Wed 9/26/18 Fri 9/28/18
23 Finishing 120 days Fri 4/13/18 Thu 9/27/18
24 Final Report & Documentation 120 days Fri 4/13/18 Thu 9/27/18
25 As Built Drawing 30 days Fri 8/3/18 Thu 9/13/18

Task Milestone External Milestone Manual Task Start-only

Project: Fuel Gas System Project Critical Summary Inactive Task Duration-only Finish-only
Date: Tue 1/16/18 Baseline Project Summary Inactive Milestone Manual Summary Rollup Deadline
Split External Tasks Inactive Summary Manual Summary Progress