S10 Página 1

Presupuesto
Presupuesto 0502004 “INSTALACIÓN DEL SISTEMA DE RIEGO EN LA COMUNIDAD DE CHAUPI AYLLU Y CERCADO DE PATAMBUCO,
DISTRITO PATAMBUCO - PROVINCIA DE SANDIA - PUNO”
Subpresupuesto 001 “INSTALACIÓN DEL SISTEMA DE RIEGO EN LA COMUNIDAD DE CHAUPI AYLLU Y CERCADO DE PATAMBUCO,
DISTRITO PATAMBUCO - PROVINCIA DE SANDIA - PUNO”
Cliente MUNICIPALIDAD DISTRITAL DE PATAMBUCO Costo al 24/12/2017
Lugar PUNO - SANDIA - PATAMBUCO

Item Descripción Und. Metrado Precio S/. Parcial S/.

01 OBRAS PRELIMINARES 1,500.00


01.01 CARTEL DE OBRA und 1.00 1,500.00 1,500.00
02 ESTRUCTURA CAPTACION DE RIO (01UND) 16,142.79
02.01 LIMPIEZA DE TERRENO MANUAL m2 48.50 0.88 42.68
02.02 TRAZO NIVEL Y REPLANTEO m2 48.50 3.92 190.12
02.03 EXCAVACION DE TERRENO SUELTO m3 55.50 12.57 697.64
02.04 REFINE Y NIVELACION EN TERRENO NORMAL m2 24.54 2.20 53.99
02.05 ACARREO DE MATERIAL EXCEDENTE - DIST. PROMED. D=30M m3 22.52 5.50 123.86
02.06 CONCRETO CICLOPEO FC=175 KG/CM2 + 30 % P.M. m3 22.48 261.24 5,872.68
02.07 CONCRETO FC = 175 KG/CM2 m3 5.28 313.13 1,653.33
02.08 ACERO FY=4200 KG/CM2 kg 225.00 0.71 159.75
02.09 ENCOFRADO Y DESENCOFRADO m2 158.00 20.24 3,197.92
02.10 TARRAJEO CON MORTERO CEMENTO-ARENA 1:3 m2 59.50 14.77 878.82
02.11 SUM. Y COLOC. DE ACCESORIOS CAPTACION GLB 1.00 3,272.00 3,272.00
03 ESTRUCTURA DESARENADOR (01 UND) 4,356.60
03.01 LIMPIEZA DE TERRENO MANUAL m2 8.45 0.88 7.44
03.02 TRAZO NIVEL Y REPLANTEO m2 8.45 3.92 33.12
03.03 EXCAVACION DE TERRENO SUELTO m3 8.50 12.57 106.85
03.04 REFINE Y NIVELACION EN TERRENO NORMAL m2 8.43 2.20 18.55
03.05 ACARREO DE MATERIAL EXCEDENTE - DIST. PROMED. D=30M m3 10.50 8.40 88.20
03.06 CONCRETO CICLOPEO FC=175 KG/CM2 + 30 % P.M. m3 8.50 261.24 2,220.54
03.07 ENCOFRADO Y DESENCOFRADO m2 15.06 20.24 304.81
03.08 TARRAJEO CON MORTERO CEMENTO-ARENA 1:3 m2 10.50 14.77 155.09
03.09 SUM. Y COLOC. DE ACCESORIOS DESARENADOR GLB 1.00 1,422.00 1,422.00
04 LINEA DE CONDUCCION (L=9,100.00 ML) 1,131,851.05
04.01 TRAZO, NIVELACION Y REPLANTEO m 9,100.00 1.49 13,559.00
04.02 EXCAVACION DE ZANJAS MAT.COMPACTO,MANUAL m 4,850.00 7.33 35,550.50
04.03 EXCAVACION DE ZANJAS ROCA SUELTA m 4,250.00 14.40 61,200.00
04.04 REFINE Y NIVELACION DE ZANJAS m 9,100.00 2.20 20,020.00
04.05 CAMA DE APOYO m 9,100.00 1.40 12,740.00
04.06 RELLENO Y APISONADO DE ZANJAS m 9,100.00 0.83 7,553.00
04.07 TUBERIA PVC UF, D=200MM; CLASE 7.5 C/ANILLO m 7,150.00 92.61 662,161.50
04.08 TUBERIA FIERRO GALVANIZADO 6" NSTAL.INC.PRUEBA HIDR. m 1,950.00 155.27 302,776.50
04.09 PRUEBA HIDRAULICA m 9,100.00 0.87 7,917.00
04.10 CAJAS Cº PREF. 0.50M X 0.50M Y VALVULA PURGA CONDUC. 6"x3" und 8.00 457.15 3,657.20
04.11 CAJAS Cº PREF. 0.50M X 0.50M Y VALVULA PURGA CONDUC. 4"x3" und 9.00 447.15 4,024.35
04.12 SUM. Y COLOC. ACCESORIOS LINEA DE CONDUCCION GLB 1.00 692.00 692.00
05 CRUCE DE RIO ACUEDUCTO METALICO (02 UND.) 24,759.59
05.01 TRABAJOS PRELIMINARES 91.11
05.01.01 TRAZO Y REPLANTEO m2 48.72 1.87 91.11
05.02 MOVIMIENTO DE TIERRAS 528.07
05.02.01 EXCAVACION PARA ESTRUCTURA m3 4.58 18.13 83.04
05.02.02 EXCAVACION PARA ESTRUCTURA EN ROCA m 4.58 14.40 65.95
05.02.03 COMPACTACION C/ 0.15m POR CAPA m3 19.92 19.03 379.08
05.03 CONCRETO SIMPLE 3,134.64
05.03.01 CONCRETO F'C=175 KG/CM2 +30% P.G. m3 10.20 277.95 2,835.09
05.03.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURA DE CONCRETO (OBRAS m2 14.80 20.24 299.55
DE ARTE)
05.04 CONCRETO ARMADO 1,961.99
05.04.01 CONCRETO F'C=210 KG/CM2 S/M PARA CAMARAS DE INCRESO Y SALIDA m3 5.12 278.61 1,426.48
05.04.02 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURA m2 20.76 20.24 420.18
05.04.03 ACERO FY=4200 KG/CM2 kg 162.43 0.71 115.33
05.05 JUNTA WATER STOP 6" 93.20

Fecha : 09/01/2018 04:48:55p.m.


S10 Página 2

Presupuesto
Presupuesto 0502004 “INSTALACIÓN DEL SISTEMA DE RIEGO EN LA COMUNIDAD DE CHAUPI AYLLU Y CERCADO DE PATAMBUCO,
DISTRITO PATAMBUCO - PROVINCIA DE SANDIA - PUNO”
Subpresupuesto 001 “INSTALACIÓN DEL SISTEMA DE RIEGO EN LA COMUNIDAD DE CHAUPI AYLLU Y CERCADO DE PATAMBUCO,
DISTRITO PATAMBUCO - PROVINCIA DE SANDIA - PUNO”
Cliente MUNICIPALIDAD DISTRITAL DE PATAMBUCO Costo al 24/12/2017
Lugar PUNO - SANDIA - PATAMBUCO

Item Descripción Und. Metrado Precio S/. Parcial S/.

05.05.01 WATER STOP DE NEOPRENE DE 6". PROVISION Y COLOCADO DE JUNTA m 4.00 23.30 93.20
05.06 REVESTIMIENTO 688.98
05.06.01 SOLAQUEADO EN OBRAS DE ARTE m2 33.84 20.36 688.98
05.07 CURADO DE CONCRETO 63.63
05.07.01 CURADO DE CONCRETO m2 10.38 6.13 63.63
05.08 MARCO-TAPA METALICA 68.19
05.08.01 SUMINISTRO Y COLOCACION DE TAPAS METALICAS und 1.00 68.19 68.19
05.09 SUMINISTRO E INSTALACION DE COMPUERTA 404.48
05.09.01 COMPUERTAS FIERRO CON VOLANTE DE 0.40*0.30m CON JALADOR und 2.00 202.24 404.48
05.10 ESTRUCTURA METALICAS 13,498.80
05.10.01 SUMINISTRO Y COLOCACION DE PERFIL METALICO L=12mts. GLB 1.00 3,748.30 3,748.30
05.10.02 ACCESORIO9 VARIOS PARA ACUEDUCTO METALICOS GLB 1.00 8,532.50 8,532.50
05.10.03 ABRAZADERAS PREFABRICADAS PARA TUBERIA EN PUENTE und 8.00 152.25 1,218.00
05.11 PINTURA 943.54
05.11.01 PINTURA ESMALTE EN ESTRUCTURAS m 95.50 9.88 943.54
05.12 TUBERIA Y ACCESORIOS 3,282.96
05.12.01 SUMINISTRO E INSTALACION DE TUBERIA HDPE m 12.00 273.58 3,282.96
06 RESERVORIO CON GEOMENBRANA DE 80 M3 (03UND) 101,501.70
06.01 LIMPIEZA DE TERRENO MANUAL m2 765.00 1.26 963.90
06.02 TRAZO NIVEL Y REPLANTEO m2 765.00 3.92 2,998.80
06.03 EXCAVACION DE TERRENO SUELTO m3 579.95 12.57 7,289.97
06.04 EXCAVACION EN ROCA m3 97.20 56.91 5,531.65
06.05 REFINE Y NIVELACION EN TERRENO NORMAL m2 636.48 2.20 1,400.26
06.06 RELLENO Y COMP. MANUAL- MAT. PROPIO A MANO m3 743.41 16.68 12,400.08
06.07 ENCOFRADO Y DESENCOFRADO m2 8.49 20.24 171.84
06.08 CONCRETO SIMPLE FC=140 KG/CM2 m3 12.70 242.01 3,073.53
06.09 TARRAJEO MEZCLA 1:5 m2 8.04 27.64 222.23
06.10 SUMINISTRO E INSTALACION DE GEOTEXTIL m2 696.00 17.56 12,221.76
06.11 SUMINISTRO E INSTALACION DE GEOMENBRANA PVC e=1.00mm m2 696.00 28.63 19,926.48
06.12 ENROCADO DE PROTECCION EN TALUD m2 126.72 217.44 27,554.00
06.13 CERCO CON ALAMBRE DE PUAS Y MADERA (BASE DE CONCRETO 1:10) m 180.00 13.97 2,514.60
06.14 SUMINISTRO E INSTALACION DE ACCESORIOS DE RESERVORIO GLB 3.00 1,744.20 5,232.60
07 LINEA DE ADUCCION Y RED DE DISTRIBUCION (L=69,970.24 M) 7,239,368.05
07.01 TRAZO, NIVELACION Y REPLANTEO m 69,970.00 1.49 104,255.30
07.02 EXCAVACION DE ZANJAS MAT.COMPACTO,MANUAL m 69,970.24 7.33 512,881.86
07.03 REFINE Y NIVELACION DE ZANJAS m 69,970.24 2.20 153,934.53
07.04 CAMA DE APOYO m 69,970.24 1.40 97,958.34
07.05 RELLENO Y APISONADO DE ZANJAS m 69,970.24 0.83 58,075.30
07.06 TUBERIA PVC UF, D=25MM; CLASE 7.5 C/ANILLO m 293.42 24.30 7,130.11
07.07 TUBERIA PVC UF, D=32MM; CLASE 7.5 C/ANILLO m 108.00 28.12 3,036.96
07.08 TUBERIA PVC UF, D=40MM; CLASE 7.5 C/ANILLO m 1,019.96 28.64 29,211.65
07.09 TUBERIA PVC UF, D=50MM; CLASE 7.5 C/ANILLO m 1,294.98 34.33 44,456.66
07.10 TUBERIA PVC UF, D=63MM; CLASE 7.5 C/ANILLO m 4,063.27 35.34 143,595.96
07.11 TUBERIA PVC UF, D=75MM; CLASE 7.5 C/ANILLO m 3,630.78 38.57 140,039.18
07.12 TUBERIA PVC UF, D=90MM; CLASE 7.5 C/ANILLO m 6,882.63 65.64 451,775.83
07.13 TUBERIA PVC UF, D=110MM; CLASE 7.5 C/ANILLO m 9,841.23 68.92 678,257.57
07.14 TUBERIA PVC UF, D=160MM; CLASE 7.5 C/ANILLO m 17,478.44 85.24 1,489,862.23
07.15 TUBERIA PVC UF, D=200MM; CLASE 7.5 C/ANILLO m 5,135.43 92.61 475,592.17
07.16 TUBERIA PVC UF, D=250MM; CLASE 7.5 C/ANILLO m 6,408.74 91.41 585,822.92
07.17 TUBERIA PVC UF, D=315MM; CLASE 7.5 C/ANILLO m 3,273.05 116.99 382,914.12
07.18 TUBERIA PVC UF, D=355MM; CLASE 7.5 C/ANILLO m 1,176.85 120.14 141,386.76
07.19 TUBERIA PVC UF, D=400MM; CLASE 7.5 C/ANILLO m 5,291.53 128.49 679,908.69
07.20 TUBERIA PVC UF, D=450MM; CLASE 7.5 C/ANILLO m 1,822.73 132.24 241,037.82

Fecha : 09/01/2018 04:48:55p.m.


S10 Página 3

Presupuesto
Presupuesto 0502004 “INSTALACIÓN DEL SISTEMA DE RIEGO EN LA COMUNIDAD DE CHAUPI AYLLU Y CERCADO DE PATAMBUCO,
DISTRITO PATAMBUCO - PROVINCIA DE SANDIA - PUNO”
Subpresupuesto 001 “INSTALACIÓN DEL SISTEMA DE RIEGO EN LA COMUNIDAD DE CHAUPI AYLLU Y CERCADO DE PATAMBUCO,
DISTRITO PATAMBUCO - PROVINCIA DE SANDIA - PUNO”
Cliente MUNICIPALIDAD DISTRITAL DE PATAMBUCO Costo al 24/12/2017
Lugar PUNO - SANDIA - PATAMBUCO

Item Descripción Und. Metrado Precio S/. Parcial S/.

07.21 TUBERIA PVC UF, D=500MM; CLASE 7.5 C/ANILLO m 279.55 144.76 40,467.66
07.22 TUBERIA PVC UF, D=630MM; CLASE 7.5 C/ANILLO m 1,949.93 163.81 319,418.03
07.23 PRUEBA HIDRAULICA m 69,970.00 0.87 60,873.90
07.24 CAJAS Cº PREF. 0.50M X 0.50M Y VALVULA DE CONTROL . und 48.00 2,525.50 121,224.00
07.25 SUM. Y COLOC. ACCESORIOS RED DE DISTRIBUCION GLB 1.00 8,750.50 8,750.50
07.26 CAMARAS DE ROMPE PRESION und 107.00 2,500.00 267,500.00
08 HIDRANTES (750 UND) 203,062.55
08.01 LIMPIEZA DE TERRENO MANUAL m2 151.88 1.26 191.37
08.02 TRAZO NIVEL Y REPLANTEO m2 151.88 3.92 595.37
08.03 EXCAVACION DE TERRENO SUELTO m3 92.14 12.57 1,158.20
08.04 REFINE Y NIVELACION EN TERRENO NORMAL m2 16.00 2.20 35.20
08.05 ACARREO DE MATERIAL EXCEDENTE - DIST. PROMED. D=30M m3 14.00 8.40 117.60
08.06 CONCRETO FC = 175 KG/CM2 -MUROS m3 30.32 313.13 9,494.10
08.07 ENCOFRADO Y DESENCOFRADO m2 152.32 20.24 3,082.96
08.08 TARRAJEO CON MORTERO CEMENTO-ARENA 1:3 m2 1,575.00 14.77 23,262.75
08.09 SUM. Y COLOC. DE ACCES. HIDRANTES 1" GLB 650.00 218.50 142,025.00
08.10 SUM. Y COLOC. DE ACCES. HIDRANTES 1 1/2" GLB 50.00 230.00 11,500.00
08.11 SUM. Y COLOC. DE ACCES. HIDRANTES 2" GLB 50.00 232.00 11,600.00
09 MODULO DE RIEGO POR ASPERSION 77,973.00
09.01 INSTALACION MODULO ASPERSION (LINEA MOVIL 03 ASPER.) und 45.00 752.60 33,867.00
09.02 INSTALACION MODULO ASPERSION (LINEA MOVIL 04 ASPER.) und 45.00 931.80 41,931.00
09.03 PRUEBA HIDRAULICA m 2,500.00 0.87 2,175.00
10 PRUEBAS DE LABORATORIO 2,085.00
10.01 DISEÑO DE MEZCLA DEL CONCRETO GLB 3.00 350.00 1,050.00
10.02 PRUEBAS DE RESISTENCIA, COMPRESION CONCRETO und 45.00 23.00 1,035.00
11 PROGRAMA DE CAPACITACION 182,100.00
11.01 CAPACITACION Y SENCIBILAZACION GLB 1.00 45,000.00 45,000.00
11.02 PARCELAS DEMOSTRATIVAS GLB 1.00 12,500.00 12,500.00
11.03 FORTALECIMIIENTO DE LA ORGANIZACION DE REGANTES GLB 1.00 15,000.00 15,000.00
11.04 ASISTENCIA TECNICA A BENEFICIARIOS mes 6.00 10,000.00 60,000.00
11.05 PASANTIAS A SISTEMA DE RIEGO GLB 2.00 24,800.00 49,600.00
12 MEDIDAS DE MITIGACION AMBIENTAL 57,350.48
12.01 PROGRAMA DE MITIGACION Y/O PREVENTIVO 19,139.80
12.01.01 EDUCACION AMBIENTAL Y CAPACITACION GLB 6.00 2,500.00 15,000.00
12.01.02 SEÑALIZACIONES AMBIENTALES und 25.00 100.00 2,500.00
12.01.03 CONTROL DE PARTICULAS -RIEGO AREAS DE TRABAJO GLB 6.00 273.30 1,639.80
12.02 PROGRAMA DE MANEJO DE RESIDUOS SOLIDOS Y EFLUENTES 4,800.00
12.02.01 INSTALACION DE CONTENEDORES DE RESIDUOS SOLIDOS und 12.00 400.00 4,800.00
12.03 PROGRAMA DE CONTINGENCIA 2,000.00
12.03.01 EQUIPOS DE EMERGENCIAS GLB 1.00 2,000.00 2,000.00
12.04 PROGRAMA DE MONITOREO Y SEGUIMIENTO AMBIENTAL 15,000.00
12.04.01 MONITOREO DE LA CLAIDAD DEL AGUA und 3.00 2,000.00 6,000.00
12.04.02 MONITOREO DE LA CALIDAD DEL AIRE und 3.00 2,000.00 6,000.00
12.04.03 MONITOREO DE RUIDO AMBIENTAL und 3.00 1,000.00 3,000.00
12.05 PROGRAMA DE CIERRE 16,410.68
12.05.01 RETIRO DE EQUIPO, MATERIALES E INSTALACIONES TEMPORALES Y m2 450.00 3.99 1,795.50
RESTAURACION
12.05.02 LIMPIEZA Y MANEJO DE RESIDUOS PELIGROSOS Y NO PELIGROSOS mes 1.00 2,500.00 2,500.00
12.05.03 ACOPIO DEL TOP SOIL Y MATERIALES INERTES m3 100.00 6.81 681.00
12.05.04 REACONDICIONAMIENTO DEL AREA DE CAMPAMENTO Y PATIO DE HA 1.50 2,082.00 3,123.00
MAQUINAROA
12.05.05 REACONDICIONAMIENTO DE CANTERAS Y ACCESOS HA 3.50 1,907.30 6,675.55
12.05.06 REVEGETACION Y/O REFORESTACION HA 2.50 654.25 1,635.63
13 FLETE 185,000.00

Fecha : 09/01/2018 04:48:55p.m.


S10 Página 4

Presupuesto
Presupuesto 0502004 “INSTALACIÓN DEL SISTEMA DE RIEGO EN LA COMUNIDAD DE CHAUPI AYLLU Y CERCADO DE PATAMBUCO,
DISTRITO PATAMBUCO - PROVINCIA DE SANDIA - PUNO”
Subpresupuesto 001 “INSTALACIÓN DEL SISTEMA DE RIEGO EN LA COMUNIDAD DE CHAUPI AYLLU Y CERCADO DE PATAMBUCO,
DISTRITO PATAMBUCO - PROVINCIA DE SANDIA - PUNO”
Cliente MUNICIPALIDAD DISTRITAL DE PATAMBUCO Costo al 24/12/2017
Lugar PUNO - SANDIA - PATAMBUCO

Item Descripción Und. Metrado Precio S/. Parcial S/.

13.01 FLETE TERRESTRE GLB 1.00 120,000.00 120,000.00


13.02 FLETE RURAL GLB 1.00 65,000.00 65,000.00
COSTO DIRECTO 9,227,050.81

GASTOS GENERALES 11.16% 1,029,914.18

UTILIDAD 10.0000% 922,705.08


_____________________

SUB TOTAL 11,179,670.07

IGV 18% 2,012,340.61


_____________________

PRESUPUESTO VALOR REFERENCIAL 13,192,010.68

SUPERVISION 5% 461,352.54
====================

PRESUPUESTO TOTAL 13,653,363.22

SON : TRECE MILLONES SEISCIENTOS CINCUENTITRES MIL TRESCIENTOS SESENTITRES Y 22/100 NUEVOS SOLES

Fecha : 09/01/2018 04:48:55p.m.