You are on page 1of 2

METEC 137.

5MW SIDDICA FAAGE BIOMASS POWER PLANT

Engineering Design Schedule

COMPLETION
TARGET NAME DURATION START DATE
DATE
Remark:
The official start date of design is the same with the date of effective date of contract.
For the tentative effective date is May 1, 2018. And the total project schedule duration is 22
months. And it will be adjusted based on actual need.
Engineering Design 277 d 2018-5-2- 2019-2-13-
Preliminary Design 77 d 2018-5-17- 2018-8-1-
General Layout & Transportation 10 d 2018-7-16- 2018-7-25-
Mechanical System 30 d 2018-5-17- 2018-6-15-
Chemical System 30 d 2018-6-16- 2018-7-15-
Ash&Slag Handling System 29 d 2018-6-17- 2018-7-15-
Fuel System 25 d 2018-6-21- 2018-7-15-
Electrical System 35 d 2018-5-27- 2018-6-30-
I&C 25 d 2018-7-1- 2018-7-25-
Construction Structure 15 d 2018-7-1- 2018-7-15-
HVAC 10 d 2018-7-16- 2018-7-25-
Hydraulic&Fire fighting system 15 d 2018-7-1- 2018-7-15-
Preliminary Design Review and Approved 7d 2018-7-26- 2018-8-1-

Equipment(material) Technical
277 d 2018-5-2- 2019-2-13-
Specification
Boiler Technical Specification 15 d 2018-5-2- 2018-5-16-
Boiler document submit for construction
15 d 2018-5-17- 2018-5-31-
design
STG Technical Specification(already supply to
1d 2018-5-2- 2018-5-2-
site )
Technical specification of the first batch of
7d 2018-6-4- 2018-6-10-
auxiliaries
Technical specification of the second batch of
7d 2018-7-1- 2018-7-7-
auxiliaries
Technical specification of the third batch of
7d 2018-8-22- 2018-8-28-
auxiliaries
Technical specification of the fourth batch of
7d 2018-10-13- 2018-10-19-
auxiliaries
Technical specification of the fifth batch of
7d 2019-11-10- 2019-11-16-
auxiliaries
Technical specification of HP pipe 7d 2018-11-10- 2018-11-16-
Technical specification of LP pipe 15 d 2019-12-5- 2019-12-19-
Technical specification of electric cable 15 d 2018-12-14- 2018-12-28-
Technical specification of other material 15 d 2019-1-19- 2019-2-2-

Detailed Construction Design 177 d 2018-7-26- 2019-1-31-


Main building foundation excavation drawing 10 d 2018-8-2- 2018-8-11-
Foundation treatment drawing 15 d 2018-8-10- 2018-8-24-
Main building foundation drawing 30 d 2018-8-2- 2018-8-31-
Main building superstructure & architecture
80 d 2018-8-2- 2018-10-20-
drawing
Chimney foundation construction drawing 30 d 2018-8-18- 2018-9-16-
Architecture drawing of fuel supply system 30 d 2018-7-28- 2018-8-26-
Architecture drawing of chemical treatment
30 d 2018-7-28- 2018-8-26-
building
Auxiliary buildings & road construction
45 d 2018-10-11- 2018-11-24-
drawing
Thermal system installation drawing 90 d 2018-9-21- 2018-12-19-
Fuel handling system installation drawing 30 d 2018-8-17- 2018-9-15-
Chemical&water supply system installation
60 d 2018-9-23- 2019-11-21-
drawing
Electric system construction drawing 120 d 2018-7-26- 2018-11-22-
I&C construction drawing 120 d 2018-9-6- 2019-1-3-
Other construction drawing 15 d 2019-1-4- 2019-1-18-

You might also like