You are on page 1of 66

BASEMENT

DCQ3043 CONSTRUCTION
TECHNOLOGY 3

TOPIC: BASEMENT

PREPARED BY: MOHD ANUWAR BIN SIMON


Mohd Anuwar Simon DCQ3043 Construction Technology 3 1
BASEMENT

Mohd Anuwar Simon DCQ3043 Construction Technology 3 2


BASEMENT
Syllabus Content :

2.1 Understand the construction of basement.


2.1.1 Explain methods of excavation for the construction of
deep and huge basement.
2.1.2 Explain usage of waterproofing system in basement
construction.
2.1.3 Identify clauses in Uniform Building By-Laws for
basement construction.
2.1.4 Describe construction of earthwork support system.
2.1.5 Justify the purpose of earthwork support system.

Mohd Anuwar Simon DCQ3043 Construction Technology 3 3


BASEMENT
INTRODUCTION
Definitions:

1. A storey with a floor that at


some point is more than 1.2m
below the highest level of
ground adjacent to the outside
wall.
2. A storey of a building
constructed wholly or partly
below ground level exposed to
soil, water and/or water
vapour pressure.
Mohd Anuwar Simon DCQ3043 Construction Technology 3 4
BASEMENT
Types of Basement:

1. Semi-basement
Single storey with only one, two or three
wall fully or partially below ground
level.

2. Residential basement
A shallow or semi-basement providing
space for storage and/or accommodation,
associated with housing.

3. Shallow basement
Not more than one storey wholly below
ground level.
Mohd Anuwar Simon DCQ3043 Construction Technology 3 5
BASEMENT
Types of Basement (cont’d):

4. Deep basement
More than one storey wholly
below ground level.

5. Cellar basement
Used for storage, heating plant
and for purpose other than
habitation.

Mohd Anuwar Simon DCQ3043 Construction Technology 3 6


BASEMENT
Basement Requirements:

 Primary functional requirements


of basement /wall below ground
may be summarized as follows:

1. Structural stability
2. Durability
3. Moisture exclusion
4. Buildability

Mohd Anuwar Simon DCQ3043 Construction Technology 3 7


BASEMENT
Basement Grades:

 Basements are graded according to BS8102 depending on their specific


performance requirements.

Mohd Anuwar Simon DCQ3043 Construction Technology 3 8


BASEMENT
METHOD OF EXCAVATION FOR THE
CONSTRUCTION OF DEEP & HUGE BASEMENT
Classification of Excavation:

Excavation may be classified in the following manner:


1. Shallow excavation – up to 1.5m deep.
2. Medium excavation – 1.5m to 3.0m deep.
3. Deep excavation – over 3.0m deep.

Factors that Affect Excavation Work:

Method of excavation depends on:


1. Nature of the subsoil - to determine the type of plant or hand tools and the type
of earthwork supports.
2. Purpose of the excavation - to determine the sizes, depth and volume of
excavation.
3. Presence of ground water - to determine dewatering techniques.
4. Location and surrounding condition - needs permit from local authorities such
as JKR, DBKL, etc. and impose certain restrictions and precautions.
Mohd Anuwar Simon DCQ3043 Construction Technology 3 9
BASEMENT
METHOD OF EXCAVATION FOR THE
CONSTRUCTION OF DEEP & HUGE BASEMENT
Method of Excavation:

There are 3 method of excavation for the construction of Deep and


Huge Basement that can be used:

1. Excavation with sloping sides / Open excavation.

2. Excavation with temporary support.

3. Excavation with permanent embedded retaining walls to deep


basements.

Mohd Anuwar Simon DCQ3043 Construction Technology 3 10


BASEMENT
1. Excavation with sloping sides /
Open excavation
 Excavation basement on an open site can
be carried out by cutting the perimeter
back to the natural angle of repose of the
soil.
 This method required sufficient site space
around for the over excavation and to
allow for the creation of a stable slope to
sides of the excavation.
 No temporary or permanent earth support
so saving the cost of excavation but
increase in volume of back filling.
 Suitable for small scale basement.

Mohd Anuwar Simon DCQ3043 Construction Technology 3 11


BASEMENT

Excavation with sloping sides / Open Excavation


Mohd Anuwar Simon DCQ3043 Construction Technology 3 12
BASEMENT
2. Excavation with temporary support
 Suitable where the space around the
excavation is insufficient for open excavation.
 Very economical compare with permanent
support such as contiguous piles, secant piles
or diaphragm walls.
 Temporary support elements such as Steel
Sheet Piles, Cross-lot bracing, Rakers and
Tiebacks.
 Temporary support are placed within the
ground around the perimeter of the intended
area to be excavated.
 When the earth is done excavate, the void will
become the basement area.
 Permanent basement walls are than
constructed and after completion the
temporary support is removed.
Mohd Anuwar Simon DCQ3043 Construction Technology 3 13
BASEMENT
Temporary Support Elements:- Hydraulic vibratory
a) Steel Sheet Pile hammer

 Sheet piling is an earth retention and


excavation support technique that retains
soil, using steel sheet sections with
interlocking edges.
 The interlocked sheet piles reduced
groundwater inflow.
 Vibratory hammers are used to install
sheet piles. If soils are too hard or dense,
an impact hammer can be used to
complete the installation. At certain sites
where vibrations are a concern, the sheets
Interlocking edges
can be hydraulically pushed into the
ground.
 Sheet piles are also a sustainable option
since recycled steel is used in their
construction, and the piles can often be
reused.
Mohd Anuwar Simon DCQ3043 Construction Technology 3 14
BASEMENT
b) Cross-lot Bracing
Steel sheet pile or
 Cross-lot bracing using steel sheet I-beam
piles or I-beam as waler that are
driven into the earth.
 As the earth is excavated down
around the sheeting (waler), tiers of
horizontal bracing struts, usually of
steel are added to support walers,
which are beams that span across the
face of the sheeting.
 Where the excavation is too wide
for cross-lot bracing, sloping rakers
are used instead, bearing against
heel blocks or other temporary
footings. Horizontal
bracing

Mohd Anuwar Simon DCQ3043 Construction Technology 3 15


BASEMENT

Sheet Pile

Horizontal Bracing
Support

A closer view of the cross-lot bracing supporting excavation.


Mohd Anuwar Simon DCQ3043 Construction Technology 3 16
BASEMENT
c) Raker

 For very wide excavations, raker bracing


is used.
 The support for the rakers are installed at
the bottom of the excavation.
 Construction of the soil support and
removal of the remainder of the
excavation then begins.
 The bottom ends of the rakers are braced
against the central part of the building
foundation slab.
 The excavation was carried to full depth
at the center first so that the foundation
slab could be placed.
 Prior to installation of the rakers, the
lower part of the slurry trench concrete
wall was supported by an earth berm.
 The earth berm remains at the far side of
the excavation.
Mohd Anuwar Simon DCQ3043 Construction Technology 3 17
BASEMENT

A closer view of the rakers supporting excavation.

Mohd Anuwar Simon DCQ3043 Construction Technology 3 18


BASEMENT
d) Tiebacks
 To minimize wall movement and ground
settlement, tieback anchors are designed to
achieve the highest stiffness.
 Tieback capacity depends on the vertical and
horizontal spacing of anchors and on surcharge
conditions.
 Typical tieback spacing ranges from 2m to 4m in
the vertical, and from 1.5m to 4.5m in the
horizontal direction.
 First drilling a hole with an auger and then
placing a bar (tendon) in the hole, concrete is
then poured in the hole and the connection with
wall is made.
 Different types of augers are used to drill the
tieback holes. The choice of the drilling method
depends on the soil/rock conditions on the site.
 Drilling should be done carefully since
inadequate procedures can cause significant soil
losses.
Mohd Anuwar Simon DCQ3043 Construction Technology 3 19
BASEMENT

A closer view of the tiebacks supporting excavation.

Mohd Anuwar Simon DCQ3043 Construction Technology 3 20


BASEMENT
3. Excavation with permanent embedded
retaining walls to deep basement

 The construction of deep basement walls


can be costly if traditional excavation and
construction techniques are used.
 Limitation on access to most commercials
sites also restrict the possibility of such an
approach.
 The most common options available for the
formation of deep basement wall
(permanent embedded retaining walls) are:
a) Contiguous piles
b) Secant piles
c) Diaphragm walls

Mohd Anuwar Simon DCQ3043 Construction Technology 3 21


BASEMENT

Mohd Anuwar Simon DCQ3043 Construction Technology 3 22


BASEMENT
a) Contiguous Bored Pile RW

• Piles are installed at centers generally 150mm greater


than their diameter therefore leaving gaps in the structural
wall where soil is exposed during excavation.
• This option is suitable where the retained soil is usually
firm to stiff (not generally granular) and where the
ground water table is below the level of the maximum
excavation.
• This is the most economic option and normally the fastest
method to construct.
Mohd Anuwar Simon DCQ3043 Construction Technology 3 23
BASEMENT

Contiguous piles for deep basements


Mohd Anuwar Simon DCQ3043 Construction Technology 3 24
BASEMENT
b) Secant Pile RW

• Similar to the contiguous bored pile wall but the gap


between piles is filled with an unreinforced
cement/bentonite mix (1 to 2N/mm2) for the hard/soft
wall and weak concrete (in the order of 10N/mm2) for
the hard/firm wall.
• Construction is carried out by installing the primary piles
(A) and then the secondary piles (B) are formed in
reinforced concrete, cutting into the primary piles.
• By using this form of construction the ingress of water to
any subsequent excavation can be substantially reduced.
Mohd Anuwar Simon DCQ3043 Construction Technology 3 25
BASEMENT

Mohd Anuwar Simon DCQ3043 Construction Technology 3 26


BASEMENT
c) Diaphragm Walling

 This method need to construct a R.C. retaining wall along the area
of work.
 The wall is designed to reach very great depth and sequence of
work includes:
a) Construct a guide wall
b) Excavation of the trench using bentonite slurry
c) Placement of reinforcements and pumped out bentonite slurry
d) Concrete casting

Mohd Anuwar Simon DCQ3043 Construction Technology 3 27


BASEMENT

Mohd Anuwar Simon DCQ3043 Construction Technology 3 28


BASEMENT
• The excavation of the deep trenches for segments of the
diaphragm wall can be achieved by means of hydraulic
grabs, by means of hydro fraise or by means of rotary
auguring.
• Overlapping holes are drilled to form a wall section as
opposed to individual pile holes.
• Traditionally, as the spoil is removed from the excavation
it is replaced by material called ‘bentonite’ slurry.
• This can be used to support the walls of the excavation
shaft in order to prevent collapse as the excavation
proceeds.

Mohd Anuwar Simon DCQ3043 Construction Technology 3 29


BASEMENT
• Once the excavation of a particular section of walling is
complete, a reinforcement cage may be placed into the
slurry and concrete placed using a tremie pipe.
• Diaphragm walls of 450mm to 1.0m thick can be formed
by hydraulic grabs and hydro fraise, whereas thicknesses
of up to 1.50m can be achieved using rotary methods.
• Diaphragm walls can be
constructed to depths of up to
50.00m.
• Once the diaphragm walls are
placed and completed, the deep
excavation work can proceed
virtually unobstructed.
Mohd Anuwar Simon DCQ3043 Construction Technology 3 30
BASEMENT
• Some degree of lateral support is normally required to
resist the bending stresses that are set up by soil and
water pressure as before since a diaphragm wall is not
normally intended to act as a pure retaining wall.

Mohd Anuwar Simon DCQ3043 Construction Technology 3 31


BASEMENT

Excavation of panel and


installation of rebar cage

Installation of rebar cage and


concreting of panel

Mohd Anuwar Simon DCQ3043 Construction Technology 3 32


BASEMENT
Diaphragm wall excavation using clamp shell.

Mohd Anuwar Simon DCQ3043 Construction Technology 3 33


BASEMENT
Waterproofing Work

 Apart from the structural design of


basement walls and floor,
waterproofing presents the greatest
problem in basement construction.
 There are 3 types of basement wall
structure:
1. Tanked / Membranes
2. Waterproof / Monolithic
Structures
3. Drained / Drained Cavities.

Mohd Anuwar Simon DCQ3043 Construction Technology 3 34


BASEMENT
Tanked / Membranes:

 Tanked / Tanking / Membranes is a thin


material placed either on the external or
internal face of a basement wall or floor to
provide the resistance to passage of moisture
to the inside of the basement.
 Membrane material can be applied
externally (external tanking) during
construction process meanwhile membrane
also can be applied to the interior face of the
walls after construction (internal tanking).
 Membrane materials such as fibre-reinforced
bituminous felt, polythene sheet,
polyisobutylene plastic, epoxy resin
compounds, bituminous compounds and
mastic asphalt.
Mohd Anuwar Simon DCQ3043 Construction Technology 3 35
BASEMENT

Internal Basement Tanking System


Mohd Anuwar Simon DCQ3043 Construction Technology 3 36
BASEMENT

External Basement Tanking System


Mohd Anuwar Simon DCQ3043 Construction Technology 3 37
BASEMENT

Mastic Asphalt Tanking

Asphalt in tanking work is laid in 3 coats to the total thickness of not less than 30mm on
horizontal surfaces and not less than 20mm on vertical faces. All internal angles (angle
fillet) are reinforced by means of a fillet 50mm on the face, formed in 2 coats.
Mohd Anuwar Simon DCQ3043 Construction Technology 3 38
BASEMENT
Waterproof / Monolithic Structures:

 Basement of dense reinforced concrete


using impervious aggregates for the wall
and floor to form the barrier to water
penetration.
 Its considered as ‘structurally integrated
protection’ where the waterproofing is
provided by the structural wall & floor
themselves.
 Shrinkage cracking can largely be
controlled by forming construction
joints at regular intervals.
 Structural joints normally incorporate
water stops made from materials such as
neoprene, rubber water bar, PVC etc.
Mohd Anuwar Simon DCQ3043 Construction Technology 3 39
BASEMENT

Rubber Waterstops
Mohd Anuwar Simon DCQ3043 Construction Technology 3 40
BASEMENT

PVC Waterstops
Mohd Anuwar Simon DCQ3043 Construction Technology 3 41
BASEMENT
Drained / Drained Cavities:

 Cavity drain structures make allowance for


the small amount of water that may pass
through the external wall.
 The basement is constructed with 2 wall
forming a void between the external and
internal wall and cavity is formed in the
walls around the basement and below the
floor.
 Traditionally cavities were formed with
floor tiles which created void and two
separate wall of masonry walling.
 Any water that penetrates through the
external wall or floor is guided to drainage
channels to a sump pit and remove by
pumps out of the building.
Mohd Anuwar Simon DCQ3043 Construction Technology 3 42
BASEMENT

Traditional Drained Cavities Basement


Mohd Anuwar Simon DCQ3043 Construction Technology 3 43
BASEMENT
In-situ Concrete:

Construct the basement using in-situ reinforced concrete and tradition


formwork system:

 The basement structure can be constructed upon the completion of the


excavation with the basement pit properly formed and supported.
 Usually this is done in a bottom-up arrangement using in-situ reinforced
concrete formed by traditional timber formwork.
 However, all the works are to be done in the congested underground
environment inside the basement pit with a lot of lateral supporting
frame and work in confined space.
 Special attention including accurate construction planning and spatial
design to allow room for the erection of the formwork as well as for the
placing in of the required materials and equipments, safe access etc.
should be provided.
Mohd Anuwar Simon DCQ3043 Construction Technology 3 44
BASEMENT
Sequence of Constructing Single Storey Basement

1. Before start of work 2. Prepare perimeter walling 3. Bulk excavation 4. Excavation almost complete

5. Complete excavation work 6. Waterproofing at basement 7. Placing basement flr reinf. 8. Concreting basement floor

9. Concreting wall & column 10. Placing grd flr reinf. 11. Concreting ground floor 12. Finish work
Mohd Anuwar Simon DCQ3043 Construction Technology 3 45
BASEMENT
Sequence of Constructing Huge Basement

1. Driven sheet pile & bulk 2. Excavation, ramming bottom of 3. Lean concrete & horizontal
excavation excavation & bracing earthwork tanking
support

4. Horizontal tanking 5. Horizontal tanking 6. Load rebar (bar reinforcement)

Mohd Anuwar Simon DCQ3043 Construction Technology 3 46


BASEMENT

7. Reinforcement & waterproofing 8. Reiforcement 9. Concreting

10. Preparing formwork for wall 11. Wall complete 12. Formwork & reinforcement for next
level

Mohd Anuwar Simon DCQ3043 Construction Technology 3 47


BASEMENT

13. Constructing the superstructure 14. Ditto 15. Ditto

16. Constructing the superstructure till


it gets finished

Mohd Anuwar Simon DCQ3043 Construction Technology 3 48


BASEMENT
CLAUSES IN UNIFORM BUILDING BY-LAWS FOR
BASEMENT CONSTRUCTION

72. (1) In the design of basement wall and similar underground


structures, provision shall be made for the lateral pressure of
adjacent soil due allowance being made for possible surcharge
from fixed on moving loads.
(2) When a portion, or the whole of the adjacent soil in below a
free water surface, computations shall be nased on the weight
of the soil diminished by bouyancy plus full hydrostatic
pressure.
(3) In the design of basement floors and similar structures
underground, the upward pressure of water, if any, shall be
taken as the full hydrostatic pressure applied over the entire
area.
(4) The hydrostatic head shall be measured from the underside of
Mohd Anuwarthe
Simonconstruction. DCQ3043 Construction Technology 3 49
BASEMENT
CONSTRUCTION OF EARTHWORK SUPPORT SYSTEM
 When applying the principles of
permanent embedded retaining
walls, two common construction of
earthwork support system, there are:
1. Bottom-up Construction
2. Top-down Construction

1. Bottom-up Construction
 Figure shown the sequence of
operation where the diaphragm
walls formed using bentonite.
 Retaining walls can from
contiguous pile, secant pile and steel
sheet pile.
Mohd Anuwar Simon DCQ3043 Construction Technology 3 50
BASEMENT
Bottom-up Construction (cont’d)

 First stage in this process is to form perimeter walls.


 This will become the structural walls of the basement.
 Bulk excavation then take place to the desired depth (lower level
of basement).
 The next stage is to form sub-structure such as foundation,
column, basement floor up to super-structure as work proceeds.
 Advantages using Bottom-up Construction Method are:
a) Speed construction
b) Save cost
c) Stability of the ground around
d) Reduce temporary supporting elements

Mohd Anuwar Simon DCQ3043 Construction Technology 3 51


BASEMENT

Sequence of operations for Bottom-up Construction


Mohd Anuwar Simon DCQ3043 Construction Technology 3 52
BASEMENT
Construction of basement using Bottom-up approach
 Suitable for basement of small to medium size.

Mohd Anuwar Simon DCQ3043 Construction Technology 3 53


BASEMENT
The overall excavation and lateral
support system for a typical large-scale
basement construction project (with
cut-off wall on the sides, lateral
supporting frame and other temporary
work stations/platform)

Excavation carried out using


excavator and rock breaker
within the work pit

Mohd Anuwar Simon DCQ3043 Construction Technology 3 54


BASEMENT
2. Top-down Construction
 Top-down construction attempts to
make use of the perimeter elements
of the construction works to
provide rigidity and bracing against
loadings from the ground.
 Figure shown the sequence of
operations for top-down
construction.
 First stage the formation of the
permanent retaining walls to the
perimeter of the basement area.
 Retaining walls can from either
contiguous pile, secant pile or
diaphragm wall.
Mohd Anuwar Simon DCQ3043 Construction Technology 3 55
BASEMENT
Top-down Construction (cont’d)

 Next stage is the creation of the foundation


that will support the columns of the
building structure at internal location.
 These columns will provide intermediate
support for the floors of the basement and
the building superstructure as work
proceeds.
 In the most cases the foundations to these
columns will take the form of CFA piles
with columns attached using pile caps or
increasingly in the case of steel framed
buildings, using the ‘plunge’ method.
 Excavation then take place to remove earth
from beneath the slab through appropriate
holes in the slab.
 The process is then repeated until the base
slab is reached.
Mohd Anuwar Simon DCQ3043 Construction Technology 3 56
BASEMENT

Construction of basement using Top-down


approach.
 Suitable for basement of very large size with
complex environment.

Mohd Anuwar Simon DCQ3043 Construction Technology 3 57


BASEMENT
Removal of Soil

 There will have great amount of excavated soil produced during the process of
excavation.
 Suitable planning for the removal of the excavated material should be made in
advance in order not to cause disruption to work and incur extra costs. Soil removal
can be done by the following ways.
i. Using manual method, by wheel barrow.
ii. Using bucket and lift to ground level by crane.
iii. Using hoist rack (opening has to be provided in the basement/excavation pit
first).
iv. Using gantry crane (opening has to be provided in the basement/excavation pit
first).
v. Using conveyor belt
vi. Using excavating machine to removal spoil, may be in stepped position in case
of very deep pit.
vii. Using dump truck but access provision has to be provided in advance (such as a
temporary ramp or the permanent vehicular access into a basement)

Mohd Anuwar Simon DCQ3043 Construction Technology 3 58


BASEMENT

Remove spoil by steel bucket

Excavating machine to take up


spoil from bottom

Mohd Anuwar Simon DCQ3043 Construction Technology 3 59


BASEMENT

Hoisting machine is provided for Using of a gantry crane for spoil


removing spoil from basement removal
Mohd Anuwar Simon DCQ3043 Construction Technology 3 60
BASEMENT

The use of a material hoist for the removal of


spoil from the basement interior

Mohd Anuwar Simon DCQ3043 Construction Technology 3 61


BASEMENT

Mohd Anuwar Simon DCQ3043 Construction Technology 3 62


BASEMENT

Mohd Anuwar Simon DCQ3043 Construction Technology 3 63


BASEMENT

Mohd Anuwar Simon DCQ3043 Construction Technology 3 64


BASEMENT

THANK YOU

Mohd Anuwar Simon DCQ3043 Construction Technology 3 65


BASEMENT
References:
http://personal.cityu.edu.hk/~bswmwong/contents/ebook/construction_technology/2e.pdf – Excavation & Basement Construction
http://www.cv.titech.ac.jp/~courses/atce2/Lesson5.pdf – Excavations and Excavation Supports
http://ebooks.narotama.ac.id/files/Deep%20Excavation;%20Theory%20and%20Practice/Chapter%203%20%20Excavation%20Method
s%20And%20Lateral%20Supporting%20Systems.pdf – Excavation Methods and Lateral Supporting System
http://constructionduniya.blogspot.my/2012/02/top-down-construction.html – Top Down Construction Part 1
http://constructionduniya.blogspot.my/2012/05/structural-members-required-for-top.html – Top Down Construction Part 2
https://www.youtube.com/watch?v=9DBNLAJ-bxk – Video Botton Up Construction
https://www.youtube.com/watch?v=vDvyOLD5n5w – Video Top Down Construction
https://www.youtube.com/watch?v=jRgxiQSw48U – Video Top Down Construction
https://www.youtube.com/watch?v=sboDavo84gc – Video Top Down Construction
https://www.youtube.com/watch?v=wUlQyiHfex0 – Diaphragm wall construction
https://www.youtube.com/watch?v=li6N6t09J-c – Diaphragm wall construction

Mohd Anuwar Simon DCQ3043 Construction Technology 3 66

You might also like