You are on page 1of 15

FIRST DIVISION ‘NAGSASALAYSAY: [respondents] to pay the balance of the purchase price

constitutes a violation of the contract which entitles her to


G.R. No. 137909 December 11, 2003 ‘Na ang NAGBIBILI ay nagmamay-aring tunay at rescind the same; that [respondents] have been in
FIDELA DEL CASTILLO Vda. DE naghahawak ng isang lagay na lupa na nasa Nayon ng possession of the subject portion and they should be
MISTICA, petitioner, Malhacan, Bayan ng Meycauayan, Lalawigan ng Bulacan, ordered to vacate and surrender possession of the same to
vs. na ang kabuuan sukat at mga kahangga nito gaya ng [petitioner] ; that the reasonable amount of rental for the
Spouses BERNARDINO NAGUIAT and MARIA sumusunod:x x x subject land is ₱200.00 a month; that on account of the
PAULINA GERONA-NAGUIAT, respondents. unjustified actuations of [respondents], [petitioner] has
DECISION been constrained to litigate where she incurred expenses
‘Na alang-alang sa halagang DALAWANG PUNG LIBONG for attorney’s fees and litigation expenses in the sum of
PANGANIBAN, J.: PISO (₱20,000.00) Kualtang Pilipino, ang NAGBIBILI ay ₱20,000.00.
nakipagkasundo ng kanyang ipagbibili ang isang bahagi o
The failure to pay in full the purchase price stipulated in a sukat na DALAWANG DAAN (200) METROS
deed of sale does not ipso facto grant the seller the right to PARISUKAT, sa lupang nabanggit sa itaas, na ang mga "In their answer and amended answer, [respondents]
rescind the agreement. Unless otherwise stipulated by the kahangga nito ay gaya ng sumusunod:x x x contended that the contract cannot be rescinded on the
parties, rescission is allowed only when the breach of the ground that it clearly stipulates that in case of failure to
contract is substantial and fundamental to the fulfillment pay the balance as stipulated, a yearly interest of 12% is to
‘Na magbibigay ng paunang bayad ang BUMIBILI SA be paid. [Respondent Bernardino Naguiat] likewise alleged
of the obligation. NAGBIBILI na halagang DALAWANG LIBONG PISO that sometime in October 1986, during the wake of the late
(₱2,000.00) Kualtang Pilipino, sa sandaling lagdaan ang Eulalio Mistica, he offered to pay the remaining balance to
The Case kasulatang ito. [petitioner] but the latter refused and hence, there is no
breach or violation committed by them and no damages
Before us is a Petition for Review1 under Rule 45 of the ‘Na ang natitirang halagang LABING WALONG LIBONG could yet be incurred by the late Eulalio Mistica, his heirs
Rules of Court, seeking to nullify the October 31, 1997 PISO (₱18,000.00) Kualtang Pilipino, ay babayaran ng or assigns pursuant to the said document; that he is
Decision2 and the February 23, 1999 Resolution3 of the BUM[I]BILI sa loob ng Sampung (10) taon, na presently the owner in fee simple of the subject lot having
Court of Appeals (CA) in CA-GR CV No. 51067. The magsisimula sa araw din ng lagdaan ang kasulatang ito. acquired the same by virtue of a Free Patent Title duly
assailed Decision disposed as follows: awarded to him by the Bureau of Lands; and that his title
and ownership had already become indefeasible and
‘Sakaling hindi makakabayad ang Bumibili sa loob ng
incontrovertible. As counterclaim, [respondents] pray for
"WHEREFORE, modified as indicated above, the decision panahon pinagkasunduan, an[g] BUMIBILI ay
of the Regional Trial Court is hereby AFFIRMED."4 moral damages in the amount of ₱50,000.00; exemplary
magbabayad ng pakinabang o interes ng 12% isang taon,
damages in the amount of ₱30,000.00; attorney’s fees in
sa taon nilakaran hanggang sa ito’y mabayaran tuluyan ng
the amount of ₱10,000.00 and other litigation expenses.
The assailed Resolution denied petitioner’s Motion for Bumibili:
Reconsideration.
"On 8 July 1992, [respondents] also filed a motion to
‘Sa katunayan ng lahat ay nilagdaan ng Magkabilang Panig
dismiss which was denied by the court on 29 July 1992.
The Facts ang kasulatang ito, ngayon ika 5 ng Abril, 1979, sa Bayan
ng Meycauayan. Lalawigan ng Bulacan, Pilipinas. The motion for reconsideration was likewise denied per its
Order of 17 March 1993.
The facts of the case are summarized by the CA as follows:
(signed) (signed) "After the presentation of evidence, the court on 27
"Eulalio Mistica, predecessor-in-interest of herein BERNARDINO EULALIO MISTICA January 1995 rendered the now assailed judgment, the
[petitioner], is the owner of a parcel of land located at NAGUIAT Nagbibili' dispositive portion of which reads:
Malhacan, Meycauayan, Bulacan. A portion thereof was Bumibili
leased to [Respondent Bernardino Naguiat] sometime in ‘WHEREFORE, premises considered, judgment is hereby
1970. rendered:
"Pursuant to said agreement, [Respondent Bernardino
Naguiat] gave a downpayment of ₱2,000.00. He made
"On 5 April 1979, Eulalio Mistica entered into a contract to another partial payment of ₱1,000.00 on 7 February 1980. ‘1. Dismissing the complaint and ordering the [petitioner]
sell with [Respondent Bernardino Naguiat] over a portion He failed to make any payments thereafter. Eulalio Mistica to pay the [respondents] attorney’s fee in the amount of
of the aforementioned lot containing an area of 200 square died sometime in October 1986. ₱10,000.00 and costs of the suit;
meters. This agreement was reduced to writing in a
document entitled ‘Kasulatan sa Pagbibilihan’ which reads
as follows: "On 4 December 1991, [petitioner] filed a complaint for ‘2. Ordering the [respondents]:
rescission alleging inter alia: that the failure and refusal of
‘a. To pay [petitioner] and the heirs of Eulalio Mistica the lapse of the stipulated period and the failure of the private In the present case, the failure of respondents to pay the
balance of the purchase price in the amount of respondents to pay. balance of the purchase price within ten years from the
₱17,000.00, with interest thereon at the rate of 12% per execution of the Deed did not amount to a substantial
annum computed from April 5, 1989 until full payment is "2. Whether or not the Honorable Court of Appeals [e]rred breach. In the Kasulatan, it was stipulated that payment
made, subject to the application of the consigned amount in ruling that rescission of the contract is no longer could be made even after ten years from the execution of
to such payment; feasible considering that a certificate of title had been the Contract, provided the vendee paid 12 percent interest.
issued in favor of the private respondents. The stipulations of the contract constitute the law between
‘b. To return to [petitioner] and the heirs of Eulalio Mistica the parties; thus, courts have no alternative but to enforce
the extra area of 58 square meters from the land covered them as agreed upon and written.13
"3. Whether or not the Honorable Court of Appeals erred
by OCT No. 4917 (M), the corresponding price therefor in ruling that since the 58 sq. m. portion in question is
based on the prevailing market price thereof.’"5 (Citations covered by a certificate of title in the names of private Moreover, it is undisputed that during the ten-year period,
omitted) respondents reconveyance is no longer feasible and petitioner and her deceased husband never made any
proper."8 demand for the balance of the purchase price. Petitioner
CA’s Decision even refused the payment tendered by respondents during
her husband’s funeral, thus showing that she was not
The Court’s Ruling exactly blameless for the lapse of the ten-year period. Had
Disallowing rescission, the CA held that respondents did she accepted the tender, payment would have been made
not breach the Contract of Sale. It explained that the The Petition is without merit. well within the agreed period.
conclusion of the ten-year period was not a resolutory
term, because the Contract had stipulated that payment --
with interest of 12 percent -- could still be made if First Issue: If petitioner would like to impress upon this Court that the
respondents failed to pay within the period. According to parties intended otherwise, she has to show competent
the appellate court, petitioner did not disprove the proof to support her contention. Instead, she argues that
Rescission in Article 1191
allegation of respondents that they had tendered payment the period cannot be extended beyond ten years, because
of the balance of the purchase price during her husband’s to do so would convert the buyer’s obligation to a purely
Petitioner claims that she is entitled to rescind the potestative obligation that would annul the contract under
funeral, which was well within the ten-year period.
Contract under Article 1191 of the Civil Code, because Article 1182 of the Civil Code.
respondents committed a substantial breach when they
Moreover, rescission would be unjust to respondents, did not pay the balance of the purchase price within the
because they had already transferred the land title to their This contention is likewise untenable. The Code prohibits
ten-year period. She further avers that the proviso on the
names. The proper recourse, the CA held, was to order purely potestative, suspensive, conditional obligations that
payment of interest did not extend the period to pay. To
them to pay the balance of the purchase price, with 12 depend on the whims of the debtor, because such
interpret it in that way would make the obligation purely
percent interest. obligations are usually not meant to be fulfilled.14 Indeed,
potestative and, thus, void under Article 1182 of the Civil
to allow the fulfillment of conditions to depend exclusively
Code.
on the debtor’s will would be to sanction illusory
As to the matter of the extra 58 square meters, the CA held obligations.15 The Kasulatan does not allow such thing.
that its reconveyance was no longer feasible, because it We disagree. The transaction between Eulalio Mistica and First, nowhere is it stated in the Deed that payment of the
had been included in the title issued to them. The respondents, as evidenced by the Kasulatan, was clearly a purchase price is dependent upon whether respondents
appellate court ruled that the only remedy available was to Contract of Sale. A deed of sale is considered absolute in want to pay it or not. Second, the fact that they already
order them to pay petitioner the fair market value of the nature when there is neither a stipulation in the deed that made partial payment thereof only shows that the parties
usurped portion. title to the property sold is reserved to the seller until the intended to be bound by the Kasulatan.
full payment of the price; nor a stipulation giving the
Hence, this Petition.6 vendor the right to unilaterally resolve the contract the
Both the trial and the appellate courts arrived at this
moment the buyer fails to pay within a fixed period.9
finding.1âwphi1 Well-settled is the rule that findings of
Issues fact by the CA are generally binding upon this Court and
In a contract of sale, the remedy of an unpaid seller is will not be disturbed on appeal, especially when they are
either specific performance or rescission.10 Under Article the same as those of the trial court.16 Petitioner has not
In her Memorandum,7 petitioner raises the following 1191 of the Civil Code, the right to rescind an obligation is given us sufficient reasons to depart from this rule.
issues: predicated on the violation of the reciprocity between
parties, brought about by a breach of faith by one of
Second Issue:
"1. Whether or not the Honorable Court of Appeals erred them.11 Rescission, however, is allowed only where the
in the application of Art. 1191 of the New Civil Code, as it breach is substantial and fundamental to the fulfillment of
ruled that there is no breach of obligation inspite of the the obligation.12 Rescission Unrelated to Registration
The CA further ruled that rescission in this case would be such action is tantamount to allowing a collateral attack on $60,000.00 on January 5, 1985. On January 25, 1985,
unjust to respondents, because a certificate of title had the title. although the period of payment had already expired,
already been issued in their names. Petitioner nonetheless plaintiff paid to the defendant Melody Co in the United
argues that the Court is still empowered to order It appears that an action for cancellation/annulment of States, the sum of $30,000.00, as partial payment of the
rescission. patent and title and for reversion was already filed by the purchase price. Defendants counsel, Atty. Leopoldo
State in favor of petitioner and the heirs of her Cotaco, wrote a letter to the plaintiff dated March 15, 1985,
We clarify. The issuance of a certificate of title in favor of husband.24 Hence, there is no need in this case to pass demanding that she pay the balance of $70,000.00 and
respondents does not determine whether petitioner is upon the right of respondents to the registration of the not receiving any response thereto, said lawyer wrote
entitled to rescission. It is a fundamental principle in land subject land under their names. For the same reason, there another letter to plaintiff dated August 8, 1986, informing
registration that such title serves merely as an evidence of is no necessity to order them to pay petitioner the fair her that she has lost her option to purchase the property
an indefeasible and incontrovertible title to the property in market value of the extra 58-square meter lot subject of this case and offered to sell her another
favor of the person whose name appears therein.17 importunately included in the title. property.

While a review of the decree of registration is no longer WHEREFORE, the assailed Decision and Resolution are Under date of September 5 (1986), Atty. Estrella O. Laysa,
possible after the expiration of the one-year period from AFFIRMED with the MODIFICATION that the payment counsel for plaintiff, wrote a letter to Atty. Leopoldo
entry, an equitable remedy is still available to those for the extra 58-square meter lot included in respondents’ Cotaco informing him that plaintiff is now ready to pay the
wrongfully deprived of their property.18 A certificate of title title is DELETED. remaining balance to complete the sum of $100,000.00,
cannot be subject to collateral attack and can only be the agreed amount as selling price and on October 24,
altered, modified or canceled in direct proceedings in 1986, plaintiff filed the instant complaint.[2]
SO ORDERED
accordance with law.19 Hence, the CA correctly held that
the propriety of the issuance of title in the name of The Regional Trial Court (RTC) ruled in favor of
respondents was an issue that was not determinable in THIRD DIVISION private respondent Adoracion Custodio (CUSTODIO) and
these proceedings. [G.R. No. 112330. August 17, 1999] ordered the petitioner spouses Henry and Elizabeth Co
SPS. HENRY CO AND ELIZABETH CO AND (COS) to refund the amount of $30,000.00 in
MELODY CO, petitioners, vs. COURT OF CUSTODIOs favor. The dispositive portion of the RTCs
Third Issue: APPEALS AND MRS. ADORACION CUSTODIO, decision reads:
represented by her Attorney-in-fact, TRINIDAD
Reconveyance of the Portion Importunately Included KALAGAYAN, respondents. WHEREFORE, the Court hereby orders:
DECISION
Petitioner argues that it would be reasonable for GONZAGA-REYES, J.: 1. that the earnest money of $1,000.00 and
respondents to pay her the value of the lot, because the CA Before us is a Petition for Review on Certiorari of the P40,000.00 is hereby forfeited in favor of
erred in ruling that the reconveyance of the extra 58- decision of the Court of Appeals[1] in CA-G.R. CV No. the defendants, and
square meter lot, which had been included in the 32972 entitled MRS. ADORACION CUSTODIO,
certificate of title issued to them, was no longer feasible. represented by her Attorney-in-fact, TRINIDAD 2. the defendants are ordered to remit to
KALAGAYAN vs. SPS. HENRY CO AND ELIZABETH CO plaintiff the peso equivalent of THIRTY
AND MELODY CO. THOUSAND ($30,000.00) U.S. DOLLARS,
In principle, we agree with petitioner. Registration has at the prevailing rate of exchange at the
never been a mode of acquiring ownership over The following facts as found by the lower court and time of payment.
immovable property, because it does not create or vest adopted by the Court of Appeals are undisputed:
title, but merely confirms one already created or Costs against plaintiff.
vested.20 Registration does not give holders any better title xxx sometime on October 9, 1984, plaintiff entered into a
than what they actually have.21 Land erroneously included verbal contract with defendant for her purchase of the
latters house and lot located at 316 Beata St., New Alabang SO ORDERED.[3]
in the certificate of title of another must be reconveyed in
favor of its true and actual owner.22 Village, Muntinlupa, Metro Manila, for and in
consideration of the sum of $100,000.00. One week Not satisfied with the decision, the COS appealed to
thereafter, and shortly before she left for the United States, the Court of Appeals which affirmed the decision of the
Section 48 of Presidential Decree 1529, however, provides plaintiff paid to the defendants the amounts of $1,000.00 RTC. Hence, this appeal where the COS assign as sole
that the certificate of title shall not be subject to collateral and P40,000.00 as earnest money, in order that the same error the following:
attack, alteration, modification, or cancellation except in a may be reserved for her purchase, said earnest money to
direct proceeding.23 The cancellation or removal of the be deducted from the total purchase price. The purchase PETITIONER RESPECTFULLY SUBMITS THAT
extra portion from the title of respondents is not price of $100,000.00 is payable in two payments RESPONDENT COURT OF APPEALS HAS
permissible in an action for rescission of the contract of $40,000.00 on December 4, 1984 and the balance of DECIDED A QUESTION OF SUBSTANCE NOT IN
sale between them and petitioner’s late husband, because
ACCORD WITH LAW AND THE APPLICABLE by CUSTODIO pursuant to the option granted to her over Despite the fact that CUSTODIOs failure to pay the
DECISIONS OF THE SUPREME COURT.[4] the Beata property? amounts of US$ 40,000.00 and US$ 60,000.00 on or
before December 4, 1984 and January 5, 1985 respectively
We rule in the negative. was a breach of her obligation under Article 1191[16] of the
The COS argue that the Court of Appeals erred in
ruling that CUSTODIO could still exercise her option to The COS main argument is that CUSTODIO lost her Civil Code, the COS did not sue for either specific
pay the balance of the purchase price of the property. The option over the Beata property and her failure to exercise performance or rescission of the contract. The COS were of
COS claim that CUSTODIO was in default since she failed said option resulted in the forfeiture of any amounts paid the mistaken belief that CUSTODIO had lost her option
to pay after a demand was made by the petitioners in their by her pursuant to the August letter. over the Beata property when she failed to pay the
March 15, 1985 letter[5]. The COS claim that they never remaining balance of $70,000.00 pursuant to their August
granted CUSTODIO an extension of time to exercise the An option is a contract granting a privilege to buy or 8, 1986 letter. In the absence of an express stipulation
option contrary to the finding of the Court of Appeals that sell within an agreed time and at a determined price. It is a authorizing the sellers to extrajudicially rescind the
a thirty (30) day period of time was granted to her in their separate and distinct contract from that which the parties contract of sale, the COS cannot unilaterally and
August 8, 1986 letter[6]. Said period refers to another may enter into upon the consummation of the option. It extrajudicially rescind the contract of sale.[17] Accordingly,
option which the COS gave CUSTODIO to buy another must be supported by consideration.[9] An option contract CUSTODIO acted well within her rights when she
piece of property and not the Beata property as they could conforms with the second paragraph of Article 1479 of the attempted to pay the remaining balance of $70,000.00 to
no longer hold the Beata property for CUSTODIO. In fact, Civil Code[10] which reads: complete the sum owed of $100,000.00 as the contract
said letter specifically states that CUSTODIO lost her was still subsisting at that time. When the COS refused to
Article 1479. xxx accept said payment and to deliver the Beata property,
option to purchase the subject property; that the COS were
willing to apply the payments already made to the CUSTODIO immediately sued for the rescission of the
payment of the second property; and that if CUSTODIO An accepted unilateral promise to buy or to sell a contract of sale and prayed for the return of the
failed to purchase the second property within thirty (30) determinate thing for a price certain is binding upon the $30,000.00 she had initially paid.
days, she would forfeit her previous payments. Since promissor if the promise is supported by a consideration
Under Article 1385[18] of the Civil Code, rescission
CUSTODIO manifested her readiness to exercise her distinct from the price.
creates the obligation to return the things which were the
option to pay the balance of the purchase price of the object of the contract but such rescission can only be
Beata property and not the second property, her However, the March 15, 1985 letter[11] sent by the carried out when the one who demands rescission can
manifestation was no longer of any legal effect as this COS through their lawyer to the CUSTODIO reveals that return whatever he may be obliged to restore. This
option was no longer available to her. This being the case, the parties entered into a perfected contract of sale and not principle has been applied to rescission of reciprocal
the Court of Appeals should have ruled that the COS an option contract. obligations under Article 1191 of the Civil Code.[19] The
properly rescinded their contract with CUSTODIO over Court of Appeals therefore did not err in ordering the COS
the Beata property pursuant to Article 1191[7] of the Civil A contract of sale is a consensual contract and is
to return the amount of $30,000.00 to CUSTODIO after
Code and should have further ordered her to pay them perfected at the moment there is a meeting of the minds
ordering the rescission of the contract of sale over the
damages consequent to the rescission. Moreover, even upon the thing which is the object of the contract and upon
Beata property. We quote with approval the Court of
assuming that they waived the deadline by accepting the the price. From that moment the parties may reciprocally
Appeals decision to wit:
payment of $30,000.00 on January 26, 1986, CUSTODIO demand performance subject to the provisions of the law
still failed to pay the remaining balance of governing the form of contracts.[12] The elements of a valid Since it has been shown that the appellee who was not in
$70,000.00. Her offer to pay the remaining balance came contract of sale under Article 1458 of the Civil Code are (1) default, was willing to perform part of the contract while
too late as the option given to her had already been lost. In consent or meeting of the minds; (2) determinate subject the appellants were not, rescission of the contract is in
addition, the Court of Appeals also erred in ordering the matter; and (3) price certain in money or its order. The power to rescind obligations is implied in
COS to return the $30,000.00 dollars since the August 8, equivalent.[13] As evidenced by the March 15, 1985 letter, reciprocal ones, in case one of the obligors should not
1986 letter warned CUSTODIO that if the she did not all three elements of a contract of sale are present in the comply with what is incumbent upon him, (Article 1191,
exercise her option within thirty days, she would lose her transaction between the petitioners and same Code). Rescission creates the obligation to return the
option and other rights and any payments made shall be respondent. CUSTODIOs offer to purchase the Beata things which were the object of the contract, together with
forfeited. Finally, the COS claim that the Court of Appeals property, subject of the sale at a price of $100,000.00 was their fruits, and the price with its interest x x x x (Article
erred in not granting them attorneys fees when the law accepted by the COS. Even the manner of payment of the 1385, same Code).
allows recovery therefor considering that by the price was set forth in the letter. Earnest money in the
defendants act or omission, the plaintiff is compelled to amounts of US$1,000.00 and P40,000.00 was already
In the case at bar, the property involved has not been
litigate with third persons or to incur expenses to protect received by the COS. Under Article 1482[14] of the Civil
delivered to the appellee. She has therefore nothing to
his rights.[8] Code, earnest money given in a sale transaction is
return to the appellants. The price received by the
considered part of the purchase price and proof of the
The core issue is whether or not the Court of Appeals appellants has to be returned to the appellee as aptly ruled
perfection of the sale.[15]
erred in ordering the COS to return the $30,000.00 paid by the lower court, for such is a consequence of rescission,
which is to restore the parties in their former situations.
No error was committed by the lower court when it did not their favor and the tax declaration transferred in their which to file a motion for its reconsideration or a notice of
award attorneys fees to the appellants for as has been names, the Funcions mortgaged the lot with the DBP. appeal from it. But the DBP failed to appeal supposedly
shown, the appellees complaint is not unfounded.[20] because of excusable negligence and the withdrawal of its
On February 12, 1979, after the Funcions failed to pay their previous counsel of record.8
We cannot uphold the forfeiture clause contained in loan, the DBP foreclosed the mortgage on the lot and
the petitioners August 8, 1986 letter. It appears that such consolidated ownership in its name on June 17, 1981.3 When the RTC judgment became final and the court issued
condition was unilaterally imposed by the COS and was a writ of execution, the DBP resisted the writ by motion to
not agreed to by CUSTODIO. It cannot therefore be Four years later or on September 20, 1983 the DBP quash, claiming that the decision could not be enforced
considered as part of the contract of sale as it lacks the conditionally sold the lot to Sofia Quirong4 for the price of because it failed to state by metes and bounds the
consent of CUSTODIO.[21] P78,000.00. In their contract of sale, Sofia Quirong particular portions of the lot that would be assigned to the
waived any warranty against eviction. The contract different parties in the case. The RTC denied the DBP’s
Finally, the Court of Appeals did not err in not motion, prompting the latter to seek recourse by special
awarding the COS attorneys fees. Although attorneys fees provided that the DBP did not guarantee possession of the
property and that it would not be liable for any lien or civil action of certiorari directly with this Court in G.R.
may be awarded if the claimant is compelled to litigate 116575, Development Bank of the Philippines v. Fontanilla.
with third persons or to incur expenses to protect his encumbrance on the same. Quirong gave a down payment
of P14,000.00. On September 7, 1994 the Court issued a resolution,
interest by reason of an unjustified act or omission of the denying the petition for failure of the DBP to pay the
party from whom it is sought[22], we find that CUSTODIOs prescribed fees. This resolution became final and
act clearly was not unjustified. Two months after that sale or on November 28, 1983 executory on January 17, 1995.9
Felisa and her eight children (collectively, the
WHEREFORE, the instant petition is hereby Dalopes)5 filed an action for partition and declaration of
DENIED, and the appealed decision of the Court of nullity of documents with damages against the DBP and On June 10, 1998 the Quirong heirs filed the present
Appeals is AFFIRMED. the Funcions before the Regional Trial Court (RTC) of action10 against the DBP before the RTC of Dagupan City,
Dagupan City, Branch 42, in Civil Case D-7159. Branch 44, in Civil Case CV-98-02399-D for rescission of
SO ORDERED. the contract of sale between Sofia Quirong, their
predecessor, and the DBP and praying for the
On December 27, 1984, notwithstanding the suit, the DBP reimbursement of the price of P78,000.00 that she paid
SECOND DIVISION executed a deed of absolute sale of the subject lot in Sofia the bank plus damages. The heirs alleged that they were
G.R. No. 173441 December 3, 2009 Quirong’s favor. The deed of sale carried substantially the entitled to the rescission of the sale because the decision in
HEIRS OF SOFIA QUIRONG, Represented by same waiver of warranty against eviction and of any Civil Case D-7159 stripped them of nearly the whole of the
ROMEO P. QUIRONG, Petitioners, adverse lien or encumbrance. lot that Sofia Quirong, their predecessor, bought from the
vs.
DBP. The DBP filed a motion to dismiss the action on
DEVELOPMENT BANK OF THE
On May 11, 1985, Sofia Quirong having since died, her ground of prescription and res judicata but the RTC
PHILIPPINES, Respondent.
heirs (petitioner Quirong heirs) filed an answer in denied their motion.
DECISION
ABAD, J.: intervention6 in Civil Case D-7159 in which they asked the
RTC to award the lot to them and, should it instead be On June 14, 2004, after hearing the case, the RTC
given to the Dalopes, to allow the Quirong heirs to recover rendered a decision,11 rescinding the sale between Sofia
This case is about the prescriptive period of an action for the lot’s value from the DBP. But, because the heirs failed Quirong and the DBP and ordering the latter to return to
rescission of a contract of sale where the buyer is evicted to file a formal offer of evidence, the trial court did not rule the Quirong heirs the P78,000.00 Sofia Quirong paid the
from the thing sold by a subsequent judicial order in favor on the merits of their claim to the lot and, alternatively, to bank.12 On appeal by the DBP, the Court of Appeals (CA)
of a third party. relief from the DBP.7 reversed the RTC decision and dismissed the heirs’ action
on the ground of prescription. The CA concluded that,
The Facts and the Case On December 16, 1992 the RTC rendered a decision, reckoned from the finality of the December 16, 1992
declaring the DBP’s sale to Sofia Quirong valid only with decision in Civil Case D-7159, the complaint filed on June
The facts are not disputed. When the late Emilio Dalope respect to the shares of Felisa and Rosa Funcion in the 10, 1998 was already barred by the four-year prescriptive
died, he left a 589-square meter untitled lot1 in Sta. property. It declared Felisa’s sale to the Funcions, the period under Article 1389 of the Civil Code.13 The Quirong
Barbara, Pangasinan, to his wife, Felisa Dalope (Felisa) latter’s mortgage to the DBP, and the latter’s sale to Sofia heirs filed a motion for reconsideration of the decision but
and their nine children, one of whom was Rosa Dalope- Quirong void insofar as they prejudiced the shares of the the appellate court denied it,14 thus, this petition.
Funcion.2 To enable Rosa and her husband Antonio eight other children of Emilio and Felisa who were each
Funcion (the Funcions) get a loan from respondent entitled to a tenth share in the subject lot. The Issues Presented
Development Bank of the Philippines (DBP), Felisa sold
the whole lot to the Funcions. With the deed of sale in The DBP received a copy of the decision on January 13, The issues presented in this case are:
1993 and, therefore, it had until January 28, 1993 within
1. Whether or not the Quirong heirs’ action for rescission Now, was the action of the Quirong heirs "for rescission" rescission? Apparently, that contract of sale had already
of respondent DBP’s sale of the subject property to Sofia or "upon a written contract"? There is no question that been fully performed when Sofia Quirong paid the full
Quirong was already barred by prescription; and their action was for rescission, since their complaint in price for the lot and when, in exchange, the DBP executed
Civil Case CV-98-02399-D asked for the rescission of the the deed of absolute sale in her favor. There was a turnover
2. In the negative, whether or not the heirs of Quirong contract of sale between Sofia Quirong, their predecessor, of control of the property from DBP to Sofia Quirong since
were entitled to the rescission of the DBP’s sale of the and the DBP and the reimbursement of the price of she assumed under their contract, "the ejectment of
subject lot to the late Sofia Quirong as a consequence of P78,000.00 that Sofia Quirong paid the bank plus squatters and/or occupants" on the lot, at her own
her heirs having been evicted from it. damages. The prescriptive period for rescission is four expense.19
years.
The Court’s Rulings Actually, the cause of action of the Quirong heirs stems
But it is not that simple. The remedy of "rescission" is not from their having been ousted by final judgment from the
confined to the rescissible contracts enumerated under ownership of the lot that the DBP sold to Sofia Quirong,
The CA held that the Quirong heirs’ action for rescission of Article 1381.17 Article 1191 of the Civil Code gives the their predecessor, in violation of the warranty against
the sale between DBP and their predecessor, Sofia injured party in reciprocal obligations, such as what eviction that comes with every sale of property or thing.
Quirong, is barred by prescription reckoned from the date contracts are about, the option to choose between Article 1548 of the Civil Code provides:
of finality of the December 16, 1992 RTC decision in Civil fulfillment and "rescission." Arturo M. Tolentino, a well-
Case D-7159 and applying the prescriptive period of four known authority in civil law, is quick to note, however,
years set by Article 1389 of the Civil Code. Article 1548. Eviction shall take place whenever by a final
that the equivalent of Article 1191 in the old code actually judgment based on a right prior to the sale or an act
uses the term "resolution" rather than the present imputable to the vendor, the vendee is deprived of the
Unfortunately, the CA did not state in its decision the date "rescission."18 The calibrated meanings of these terms are whole or of a part of thing purchased.
when the RTC decision in Civil Case D-7159 became final distinct.
and executory, which decision resulted in the Quirong
heirs’ loss of 80% of the lot that the DBP sold to Sofia xxxx
"Rescission" is a subsidiary action based on injury to the
Quirong. Petitioner heirs claim that the prescriptive period plaintiff’s economic interests as described in Articles 1380
should be reckoned from January 17, 1995, the date this and 1381. "Resolution," the action referred to in Article With the loss of 80% of the subject lot to the Dalopes by
Court’s resolution in G.R. 116575 became final and 1191, on the other hand, is based on the defendant’s breach reason of the judgment of the RTC in Civil Case D-7159,
executory.15 of faith, a violation of the reciprocity between the parties. the Quirong heirs had the right to file an action for
As an action based on the binding force of a written rescission against the DBP pursuant to the provision of
But the incident before this Court in G.R. 116575 did not contract, therefore, rescission (resolution) under Article Article 1556 of the Civil Code which provides:
deal with the merit of the RTC decision in Civil Case D- 1191 prescribes in 10 years. Ten years is the period of
7159. That decision became final and executory on January prescription of actions based on a written contract under Article 1556. Should the vendee lose, by reason of the
28, 1993 when the DBP failed to appeal from it within the Article 1144. eviction, a part of the thing sold of such importance, in
time set for such appeal. The incident before this Court in relation to the whole, that he would not have bought it
G.R. 116575 involved the issuance of the writ of execution The distinction makes sense. Article 1191 gives the injured without said part, he may demand the rescission of the
in that case. The DBP contested such issuance supposedly party an option to choose between, first, fulfillment of the contract; but with the obligation to return the thing
because the dispositive portion of the decision failed to contract and, second, its rescission. An action to enforce a without other encumbrances than those which it had when
specify details that were needed for its implementation. written contract (fulfillment) is definitely an "action upon he acquired it. x x x
Since this incident did not affect the finality of the decision a written contract," which prescribes in 10 years (Article
in Civil Case D-7159, the prescriptive period remained to 1144). It will not be logical to make the remedy of And that action for rescission, which is based on a
be reckoned from January 28, 1993, the date of such fulfillment prescribe in 10 years while the alternative subsequent economic loss suffered by the buyer, was
finality. remedy of rescission (or resolution) is made to prescribe precisely the action that the Quirong heirs took against the
after only four years as provided in Article 1389 when the DBP. Consequently, it prescribed as Article 1389 provides
The next question that needs to be resolved is the injury from which the two kinds of actions derive is the in four years from the time the action accrued. Since it
applicable period of prescription. The DBP claims that it same. accrued on January 28, 1993 when the decision in Civil
should be four years as provided under Article 1389 of the Case D-7159 became final and executory and ousted the
Civil Code.16 Article 1389 provides that "the action to claim Here, the Quirong heirs alleged in their complaint that heirs from a substantial portion of the lot, the latter had
rescission must be commenced within four years." The they were entitled to the rescission of the contract of sale only until January 28, 1997 within which to file their
Quirong heirs, on the other hand, claim that it should be of the lot between the DBP and Sofia Quirong because the action for rescission. Given that they filed their action on
10 years as provided under Article 1144 which states that decision in Civil Case D-7159 deprived her heirs of nearly June 10, 1998, they did so beyond the four-year period.
actions "upon a written contract" must be brought "within the whole of that lot. But what was the status of that
10 years from the date the right of action accrues." contract at the time of the filing of the action for
With the conclusion that the Court has reached respecting On July 16, 1980, The Plaza, Inc. (The Plaza), a On September 19, 1980, the Project Manager (Tayzon) in
the first issue presented in this case, it would serve no corporation engaged in the restaurant business, through his Construction Memo #23 reported on his evaluation of
useful purpose for it to further consider the issue of its President, Jose C. Reyes, entered into a contract4 with Progress Billing #1 submitted by Rhogen. Tayzon stated
whether or not the heirs of Quirong would have been Rhogen Builders (Rhogen), represented by Ramon C. that actual jobsite assessment showed that the finished
entitled to the rescission of the DBP’s sale of the subject lot Gaite, for the construction of a restaurant building in works fall short of Rhogen’s claimed percentage of
to Sofia Quirong as a consequence of her heirs having been Greenbelt, Makati, Metro Manila for the price of accomplishment and Rhogen was entitled to only
evicted from it. As the Court has ruled above, their action ₱7,600,000.00. On July 18, 1980, to secure Rhogen’s ₱32,684.16 and not ₱260,649.91 being demanded by
was barred by prescription. The CA acted correctly in compliance with its obligation under the contract, Gaite Rhogen. Further, he recommended that said amount
reversing the RTC decision and dismissing their action. and FGU Insurance Corporation (FGU) executed a surety payable to Rhogen be withheld pending compliance with
bond in the amount of ₱1,155,000.00 in favor of The Plaza. Construction Memo #18, resolution of cases regarding
Parenthetically, the Quirong heirs were allowed by the On July 28, 1980, The Plaza paid ₱1,155,000.00 less unauthorized withdrawal of materials from jobsite and
RTC to intervene in the original action for annulment of withholding taxes as down payment to Gaite. Thereafter, stoppage of work by the Municipal Engineer’s Office of
sale in Civil Case D-7159 that the Dalopes filed against the Rhogen commenced construction of the restaurant Makati.8
DBP and the Funcions. Not only did the heirs intervene in building.
defense of the sale, they likewise filed a cross claim against On October 7, 1980, Gaite wrote Mr. Jose C. Reyes,
the DBP. And they were apparently heard on their defense In a letter dated September 10, 1980, Engineer Angelito Z. President of The Plaza regarding his actions/observations
and cross claim but the RTC did not adjudicate their claim Gonzales, the Acting Building Official of the Municipality on the stoppage order issued. On the permit for temporary
for the reason that they failed to make a formal offer of of Makati, ordered Gaite to cease and desist from structure, Gaite said the plans were being readied for
their documentary exhibits. Yet, they did not appeal from continuing with the construction of the building for submission to the Engineering Department of the
this omission or from the judgment of the RTC, annulling violation of Sections 301 and 302 of the National Building Municipality of Makati and the application was being
the DBP’s sale of the subject lot to Sofia Quirong. This Code (P.D. 1096) and its implementing rules and resent to Reyes for his appropriate action. As to the notice
point is of course entirely academic but it shows that the regulations.5 The letter was referred to The Plaza’s Project for concrete pouring, Gaite said that their construction set-
Quirong heirs have themselves to blame for the loss of Manager, Architect Roberto L. Tayzon. up provides for a Project Manager to whom the Pouring
whatever right they may have in the case. Request is first submitted and whose job is to clear to
On September 15, 1980, Engr. Gonzales informed Gaite whoever parties are involved (this could still be worked out
WHEREFORE, the Court DENIES the petition that the building permit for the construction of the with the Building Inspector). Regarding the safety devices
and AFFIRMS the November 30, 2005 decision of the restaurant was revoked for non-compliance with the for workers, Gaite averred that he had given strict rules on
Court of Appeals in CA-G.R. CV 83897. provisions of the National Building Code and for the this but in the course of construction some workers have
additional temporary construction without permit.6 The personal preferences. On the refusal of the secretary and
Memorandum Report of Building Inspector Victor Gregory construction foreman to receive the stoppage order dated
SO ORDERED. September 10, 1980, Gaite took responsibility but insisted
enumerated the following violations of Rhogen in the
construction of the building: it was not a violation of the National Building Code.
THIRD DIVISION Likewise, questioning the authority of the Building
G.R. No. 177685 January 26, 2011 Inspector is not a violation of the Code although Gaite
HEIRS OF RAMON C. GAITE, CYNTHIA 1) No permit for Temporary Structure. denied he ever did so. Lastly, on the construction plans
GOROSTIZA GAITE and RHOGEN used in the jobsite not being in accordance with the
BUILDERS, Petitioners, 2) No notice of concrete pouring. approved plan, Gaite said he had sent Engr. Cristino V.
vs. Laurel on October 3, 1980 to Reyes’ office and make a copy
THE PLAZA, INC. and FGU INSURANCE of the only approved plan which was in the care of Reyes,
CORPORATION, Respondents. 3) Some workers have no safety devices.
but the latter did not give it to Engr. Laurel. Gaite thus
DECISION thought that Reyes would handle the matter by himself.9
VILLARAMA, JR., J.: 4) The Secretary and Construction Foreman
This is a petition for review under Rule 45 of the 1997 refused to [receive] the Letter of Stoppage dated
Rules of Civil Procedure, as amended, which seeks to On the same day, Gaite notified Reyes that he is
September 10, 1980.
reverse and set aside the Decision1 dated June 27, 2006 suspending all construction works until Reyes and the
and Resolution2 dated April 20, 2007 of the Court of Project Manager cooperate to resolve the issue he had
5) Mr. Ramon Gaite [is] questioning the authority raised to address the problem.10 This was followed by
Appeals (CA) in CA-G.R. CV No. 58790. The CA affirmed
of the Building Official’s Inspector. another letter dated November 18, 1980 in which Gaite
with modification the Decision3 dated July 3, 1997 of the
Regional Trial Court (RTC) of Makati City, Branch 63, in expressed his sentiments on their aborted project and
Civil Case Nos. 1328 (43083) and 40755. 6) Construction plans use[d] on the job site is not reiterated that they can still resolve the matter with
in accordance to the approved plan.7 cooperation from the side of The Plaza.11 In his reply-letter
dated November 24, 1980, Reyes asserted that The Plaza is
The facts are as follows: not the one to initiate a solution to the situation, especially
after The Plaza already paid the agreed down payment of but will charge Rhogen for liquidated damages as Plaza withhold payment on the progress billings submitted
₱1,155,000.00, which compensation so far exceeds the stipulated in Article VIII of the Contract. After proper by Rhogen based on his evaluation that The Plaza is liable
work completed by Rhogen before the municipal evaluation of the works completed by Rhogen, The Plaza to pay only ₱32,684.16 and not ₱260,649.91. The other
authorities stopped the construction for several violations. shall then resume the construction and charge Rhogen for valid grounds for the withholding of payment were the
Reyes made it clear they have no obligation to help Rhogen all the costs and expenses incurred in excess of the pending estafa case against Gaite, non-compliance by
get out of the situation arising from non-performance of contract price. In the meantime that The Plaza is still Rhogen with Construction Memorandum No. 18 and the
its own contractual undertakings, and that The Plaza has evaluating the extent and condition of the works non-lifting of the stoppage order.22
its rights and remedies to protect its interest.12 performed by Rhogen to determine whether these are
done in accordance with the approved plans, Reyes Regarding the non-lifting of the stoppage order, which the
Subsequently, the correspondence between Gaite and demanded from Gaite the reimbursement of the balance of trial court said was based on simple infractions, the same
Reyes involved the custody of remaining bags of cement in their initial payment of ₱1,155,000.00 from the value of was held to be solely attributable to Rhogen’s willful
the jobsite, in the course of which Gaite was charged with the works correctly completed by Rhogen, or if none, to inaction. Instead of readily rectifying the violations,
estafa for ordering the removal of said items. Gaite reimburse the entire down payment plus expenses of Rhogen continued with the construction works thereby
complained that Reyes continued to be uncooperative in removal and replacement. Rhogen was also asked to turn causing more damage. The trial court pointed out that
refusing to meet with him to resolve the delay. Gaite over the jobsite premises as soon as possible.16 The Plaza Rhogen is not only expected to be aware of standard
further answered the estafa charge by saying that he only sent copy of said letter to FGU but the latter replied that it requirements and pertinent regulations on construction
acted to protect the interest of the owner (prevent has no liability under the circumstances and hence it could work, but also expressly bound itself under the General
spoilage/hardening of cement) and that Reyes did not not act favorably on its claim against the bond.17 Construction Contract to comply with all the laws, city and
reply to his request for exchange.13 municipal ordinances and all government regulations.
On March 3, 1981, The Plaza notified Gaite that it could no Having failed to complete the project within the stipulated
On January 9, 1981, Gaite informed The Plaza that he is longer credit any payment to Rhogen for the work it had period and comply with its obligations, Rhogen was thus
terminating their contract based on the Contractor’s Right completed because the evaluation of the extent, condition, declared guilty of breaching the Construction Contract and
to Stop Work or Terminate Contracts as provided for in and cost of work done revealed that in addition to the is liable for damages under Articles 1170 and 1167 of
the General Conditions of the Contract. In his letter, Gaite violations committed during the construction of the the Civil Code.23
accused Reyes of not cooperating with Rhogen in solving building, the structure was not in accordance with plans
the problem concerning the revocation of the building approved by the government and accepted by Ayala. The dispositive portion of the trial court’s decision reads:
permits, which he described as a "minor problem." Hence, The Plaza demanded the reimbursement of the
Additionally, Gaite demanded the payment of ₱63,058.50 down payment, the cost of uprooting or removal of the
defective structures, the value of owner-furnished WHEREFORE, in Civil Case No. 40755, defendants
from The Plaza representing the work that has already Ramon Gaite, Cynthia Gaite and Rhogen Builders are
been completed by Rhogen.14 materials, and payment of liquidated damages.18
jointly and severally ordered to pay plaintiff:

On January 13, 1981, The Plaza, through Reyes, countered On March 26, 1981, The Plaza filed Civil Case No.
40755 for breach of contract, sum of money and damages 1. the amount of ₱525,422.73 as actual damages
that it will hold Gaite and Rhogen fully responsible for representing owner-furnished materials with legal interest
failure to comply with the terms of the contract and to against Gaite and FGU in the Court of First Instance (CFI)
of Rizal.19 The Plaza later amended its complaint to from the time of filing of the complaint until full payment;
deliver the finished structure on the stipulated date. Reyes
argued that the down payment made by The Plaza was include Cynthia G. Gaite and Rhogen.20 The Plaza likewise
more than enough to cover Rhogen’s expenses.15 filed Civil Case No. 1328 (43083) against Ramon C. Gaite, 2. the amount of ₱14,504.66 as actual damages
Cynthia G. Gaite and/or Rhogen Builders also in the CFI of representing expenses for uprooting with interest from the
Rizal for nullification of the project development contract time of filing the complaint until full payment;
In a subsequent letter dated January 20, 1981, Reyes executed prior to the General Construction Contract
adverted to Rhogen’s undertaking to complete the subject of Civil Case No. 40755, which was allegedly in
construction within 180 calendar days from July 16, 1980 3. the amount of ₱1,155,000.00 as actual damages
violation of the provisions of R.A. No. 545 (Architectural
or up to January 12, 1981, and to pay the agreed payment representing the downpayment with legal interest from the
Law of the Philippines).21 After the reorganization of the
of liquidated damages for every month of delay, chargeable time of filing the complaint until full payment;
Judiciary in 1983, the cases were transferred to the RTC of
against the performance bond posted by FGU. Reyes Makati and eventually consolidated.
invoked Section 121 of the Articles of General Conditions 4. the amount of ₱150,000.00 for moral damages;
granting the owner the right to terminate the contract if
the contractor fails to execute the work properly and to On July 3, 1997, Branch 63 of the RTC Makati rendered its
decision granting the claims of The Plaza against Rhogen, 5. the amount of ₱100,000.00 for exemplary damages;
make good such deficiencies and deducting the cost from
the payment due to the contractor. Reyes also informed the Gaites and FGU, and the cross-claim of FGU against
Gaite that The Plaza will continue the completion of the Rhogen and the Gaites. The trial court ruled that the 6. the amount of ₱500,000.00 as liquidated damages;
structure utilizing the services of a competent contractor Project Manager was justified in recommending that The
7. the amount of ₱100,000.00 as reasonable attorney’s LIQUIDATED DAMAGES AND ATTORNEY’S FEES IX. THE REGIONAL TRIAL COURT ERRED IN
fees; and, SINCE THERE WERE NO FACTUAL AND LEGAL BASES AWARDING ATTORNEY’S FEES TO PLAINTIFF-
THEREFOR; AND APPELLEE.
8. the cost of suit.
V. THE TRIAL COURT ERRED IN FAILING TO AWARD X. THE REGIONAL TRIAL COURT ERRED IN HOLDING
Under the surety bond, defendants Rhogen and FGU are ACTUAL, MORAL AND EXEMPLARY DAMAGES AND DEFENDANT-APPELLANT FGU INSURANCE
jointly and severally ordered to pay plaintiff the amount of ATTORNEY’S FEES IN FAVOR OF DEFENDANTS- CORPORATION LIABLE TO PLAINTIFF-APPELLEE.28
₱1,155,000.00 with legal interest from the time of filing APPELLANTS.27
the complaint until full payment. In the event [that] FGU On June 27, 2006, the CA affirmed the Decision of the trial
pays the said amount, third-party defendants are jointly For its part, FGU interposed the following assignment of court but modified the award of damages as follows:
and severally ordered to pay the same amount to FGU plus errors:
₱50,000.00 as reasonable attorney’s fees, the latter having WHEREFORE, the Decision dated July 3, 1997 rendered
been forced to litigate, and the cost of suit. I. THE REGIONAL TRIAL COURT ERRED IN NOT by the Regional Trial Court of Makati City, Branch 63 in
RULING THAT DEFENDANT-APPELLANT RAMON Civil Case Nos. 40755 and 1328 is AFFIRMED with
Civil Case No. 1328 is hereby ordered dismissed with no GAITE VALIDLY TERMINATED THE CONTRACT the modification that: (a) the award for actual damages
pronouncement as to cost. BETWEEN HIM AND PLAINTIFF-APPELLEE. representing the owner-furnished materials and the
expenses for uprooting are deleted, and in lieu thereof, the
SO ORDERED.24 II. THE REGIONAL TRIAL COURT ERRED IN HOLDING amount of P300,000.00 as temperate damages is
DEFENDANT-APPELLANT RAMON GAITE awarded; and (b) the awards for moral, exemplary,
RESPONSIBLE FOR THE STOPPAGE OF THE liquidated and attorney’s fees are likewise deleted.
Dissatisfied, Ramon and Cynthia Gaite, Rhogen and FGU
appealed to the CA.25 In view of the death of Ramon C. CONSTRUCTION.
Gaite on April 21, 1999, the CA issued a Resolution dated SO ORDERED.29
July 12, 2000 granting the substitution of the former by III. THE REGIONAL TRIAL COURT ERRED IN
his heirs Cynthia G. Gaite, Rhoel Santiago G. Gaite, ORDERING DEFENDANT-APPELLANT RAMON GAITE According to the CA, The Plaza cannot now be demanded
Genevieve G. Gaite and Roman Juan G. Gaite.26 TO PAY THE AMOUNT OF P525,422.73 FOR THE to comply with its obligation under the contract since
OWNER FURNISHED MATERIALS. Rhogen has already failed to comply with its own
In their appeal, the heirs of Ramon C. Gaite, Cynthia G. contractual obligation. Thus, The Plaza had every reason
Gaite and Rhogen assigned the following errors, to wit: IV. THE REGIONAL TRIAL COURT ERRED IN not to pay the progress billing as a result of Rhogen’s
ORDERING DEFENDANT-APPELLANT RAMON GAITE inability to perform its obligations under the contract.
TO PAY PLAINTIFF-APPELLEE THE AMOUNT OF Further, the stoppage and revocation orders were issued
I. THE TRIAL COURT ERRED IN DECLARING THAT on account of Rhogen’s own violations involving the
THE GROUNDS RELIED UPON BY DEFENDANT- P14,504.66 AS ALLEGED EXPENSES FOR UPROOTING
THE WORK HE PERFORMED. construction as found by the local building official. Clearly,
APPELLANT RHOGEN BUILDERS IN TERMINATING Rhogen cannot blame The Plaza for its own failure to
THE CONTRACT ARE UNTENABLE; comply with its contractual obligations. The CA stressed
V. THE REGIONAL TRIAL COURT ERRED IN that Rhogen obliged itself to comply with "all the laws, city
II. THE TRIAL COURT ERRED IN DECLARING THAT ORDERING DEFENDANT-APPELLANT RAMON GAITE and municipal ordinances and all government regulations
THE NON-LIFTING OF THE STOPPAGE ORDER OF TO REFUND THE DOWN PAYMENT OF P1,155,000.00 insofar as they are binding upon or affect the parties [to
THE THEN MUNICIPAL GOVERNMENT OF MAKATI PLAINTIFF-APPELLEE PAID HIM. the contract] , the work or those engaged thereon."30 As
WAS SOLELY ATTRIBUTABLE TO DEFENDANT- such, it was responsible for the lifting of the stoppage and
APPELLANT RHOGEN’S WILLFUL INACTION; VI. THE REGIONAL TRIAL COURT ERRED IN revocation orders. As to Rhogen’s act of challenging the
AWARDING MORAL DAMAGES TO PLAINTIFF- validity of the stoppage and revocation orders, the CA held
APPELLEE. that it cannot be done in the present case because under
III. THE TRIAL COURT ERRED IN FAILING TO
Section 307 of the National Building Code, appeal to the
CONSIDER THAT IT WAS THE WILLFUL INACTION OF
Secretary of the Department of Public Works and
PLAINTIFF-APPELLEE WHICH MADE IT IMPOSSIBLE VII. THE REGIONAL TRIAL COURT ERRED IN
Highways (DPWH) – whose decision is subject to review
FOR DEFENDANT–APPELLANT RHOGEN TO AWARDING EXEMPLARY DAMAGES TO PLAINTIFF-
by the Office of the President -- is available as remedy for
PERFORM ITS OBLIGATIONS UNDER THE APPELLEE.
Rhogen.31
CONTRACT;
VIII. THE REGIONAL TRIAL [COURT] ERRED IN
However, the CA modified the award of damages holding
IV. THE TRIAL COURT ERRED IN AWARDING ACTUAL AWARDING LIQUIDATED DAMAGES TO PLAINTIFF-
that the claim for actual damages of ₱525,422.73
DAMAGES AS WELL AS MORAL, EXEMPLARY, AND APPELLEE.
representing the damaged owner-furnished materials was Whether or not the Court of Appeals acted without or in agreed down payment. It also exercised the option of
not supported by any evidence. Instead, the CA granted excess of jurisdiction, or with grave abuse of discretion furnishing and delivering construction materials at the
temperate damages in the amount of ₱300,000.00. As to amounting to lack of or excess of jurisdiction, when it jobsite pursuant to Article III of the Construction
moral damages, no specific finding for the factual basis of failed to award damages in favor of Petitioners.33 Contract. However, just two months after commencement
said award was made by the trial court, and hence it of the project, construction works were ordered stopped by
should be deleted. Likewise, liquidated damages is not Petitioners contend that the CA gravely erred in not the local building official and the building permit
proper considering that this is not a case of delay but non- holding that there were valid and legal grounds for Rhogen subsequently revoked on account of several violations of
completion of the project. The Plaza similarly failed to to terminate the contract pursuant to Article 1191 of the National Building Code and other regulations of the
establish that Rhogen and Gaite acted with malice or bad the Civil Code and Article 123 of the General Conditions of municipal authorities.
faith; consequently, the award of exemplary damages must the Construction Contract. Petitioners claim that Rhogen
be deleted. Finally, there being no bad faith on the part of sent Progress Billing No. 1 dated September 10, 1980 and Petitioners reiterate their position that the stoppage order
the defendants, the award of attorneys’ fees cannot be demanded payment from The Plaza in the net amount of was unlawful, citing the fact that when the new contractor
sustained.32 ₱473,554.06 for the work it had accomplished from July (ACK Construction, Inc.) took over the project, the local
28, 1980 until September 7, 1980. The Plaza, however, government of Makati allowed the construction of the
The motion for reconsideration of the aforesaid Decision failed to pay the said amount. According to petitioners, building using the old building permit; moreover, the
was denied in the Resolution dated April 20, 2007 for lack Article 123 of the General Conditions of the Construction basement depth of only two meters was retained, with no
of merit. Hence, this appeal. Contract gives The Plaza seven days from notice within further excavation made. They cite the testimony of the
which to pay the Progress Billing; otherwise, Rhogen may late Ramon Gaite before the trial court that at the time, he
Before us, petitioners submit the following issues: terminate the contract. Petitioners also invoke Article 1191 had incurred the ire of then Mayor of Makati because his
of the Civil Code, which states that the power to rescind (Gaite) brother was the Mayor’s political opponent; hence,
obligations is implied in reciprocal ones, in case one of the they sought to file whatever charge they could against him
I. obligors should not comply with what is incumbent upon in order to call the attention of his brother. This "political
him. harassment" defense was raised by petitioners in their
Whether or not the Court of Appeals acted without or in Amended Answer. Gaite’s testimony was intended to
excess of jurisdiction, or with grave abuse of discretion We deny the petition. explain the circumstances leading to his decision to
amounting to lack of or excess of jurisdiction, when it terminate the construction contract and not to question
found that Petitioner Rhogen had no factual or legal basis the revocation of the building permit. As the available
to terminate the General Construction Contract. Reciprocal obligations are those which arise from the same remedy was already foreclosed, it was thus error for the CA
cause, and in which each party is a debtor and a creditor of to suggest that Rhogen should have appealed the stoppage
the other, such that the obligation of one is dependent and revocations orders issued by the municipal authorities
II. upon the obligation of the other. They are to be performed to the DPWH and then to the OP.36
simultaneously such that the performance of one is
Whether or not the Court of Appeals acted without or in conditioned upon the simultaneous fulfillment of the
other. Respondent The Plaza predicated its action on Article 123 of the Articles of General Conditions states the
excess of jurisdiction, or with grave abuse of discretion
Article 119134 of the Civil Code, which provides for the grounds for the termination of the work or contract by the
amounting to lack of or excess of jurisdiction, when, as a
remedy of "rescission" or more properly resolution, a Contractor:
consequence of its finding that Petitioners did not have
valid grounds to terminate the Construction Contract, it principal action based on breach of faith by the other party
directed Petitioners to return the downpayment paid by who violates the reciprocity between them. The breach 123. CONTRACTOR’S RIGHT TO STOP WORK OR
The Plaza, with legal interest. contemplated in the provision is the obligor’s failure to TERMINATE
comply with an existing obligation. Thus, the power to
rescind is given only to the injured party. The injured party CONTRACT
III.
is the party who has faithfully fulfilled his obligation or is
ready and willing to perform his obligation.35
Whether or not the Court of Appeals acted without or in If work should be stopped under order of any court, or
excess of jurisdiction, or with grave abuse of discretion other public authority, for period of three (3) months
The construction contract between Rhogen and The Plaza through no act or fault of Contractor or of anyone
amounting to lack of or excess of jurisdiction, when, in
provides for reciprocal obligations whereby the latter’s employed by him, or if Owner’s Representative should fail
addition thereto, it awarded temperate damages to The
obligation to pay the contract price or progress billing is to issue any certificate of payment within seven (7) days
Plaza.
conditioned on the former’s performance of its after its maturity and presentation of any sum certified by
undertaking to complete the works within the stipulated Owner’s Representative or awarded arbitrator, then
IV. period and in accordance with approved plans and other contractor, may, stop work or terminate Contract, recover
specifications by the owner. Pursuant to its contractual from Owner payment for work executed, loss sustained
obligation, The Plaza furnished materials and paid the
upon any plant or materials, reasonable profit, “A. If Contractor should be adjudged bankrupt, or if he that in an action for work and labor, payment shall be
damages.37 (Emphasis supplied.) should make general assignment for benefit of his made in such amount as the plaintiff reasonably deserves.
creditors, or if receiver should be appointed on account of To deny payment for a building almost completed and
Petitioners may not justify Rhogen’s termination of the his insolvency, or if he should persistently or repeatedly already occupied would be to permit unjust enrichment at
contract upon grounds of non-payment of progress billing refuse or should fail, except in cases for which extension of the expense of the contractor.41
and uncooperative attitude of respondent The Plaza and time is provided, to supply enough properly skilled
its employees in rectifying the violations which were the workmen or proper materials, or if he should fail to make Rhogen failed to finish even a substantial portion of the
basis for issuance of the stoppage order. Having breached prompt payment to Sub-Contractors or for materials of works due to the stoppage order issued just two months
the contractual obligation it had expressly assumed, i.e., to labor, or persistently disregard laws, ordinances, or from the start of construction. Despite the down payment
comply with all laws, rules and regulations of the local instructions of Owner’s Representative or otherwise be received from The Plaza, Rhogen, upon evaluation of the
authorities, Rhogen was already at fault. Respondent The guilty of substantial violation of any provision of [the] Project Manager, was able to complete a meager
Plaza, on the other hand, was justified in withholding Contract, then Owner, upon certification by Owner’s percentage much lower than that claimed by it under the
payment on Rhogen’s first progress billing, on account of Representative that sufficient cause exists to justify such first progress billing between July and September 1980.
the stoppage order and additionally due to disappearance action, may, without prejudice to any right or remedy, Moreover, after it relinquished the project in January
of owner-furnished materials at the jobsite. In failing to after giving Contractor seven days written notice, 1981, the site inspection appraisal jointly conducted by the
have the stoppage and revocation orders lifted or recalled, terminate contract with Contractor, take possession of Project Manager, Building Inspector Engr. Gregory and
Rhogen should take full responsibility in accordance with premises, materials, tools, appliances, thereon, finish work representatives from FGU and Rhogen, Rhogen was found
its contractual undertaking, thus: by whatever method he may deem expedient. In such to have executed the works not in accordance with the
cases, Contractor shall not be entitled to receive any approved plans or failed to seek prior approval of the
further payment until work is finished. Municipal Engineer. Article 1167 of the Civil Code is
In the performance of the works, services, and obligations
subject of this Contract, the CONTRACTOR binds itself to explicit on this point that if a person obliged to do
observe all pertinent and applicable laws, rules and B. If unpaid balance of Contract sum shall exceed expense something fails to do it, the same shall be executed at his
regulations promulgated by duly constituted authorities of finishing work including compensation for additional cost.
and to be personally, fully and solely liable for any and all managerial and administrative services, such excess, paid
violations of the same.38 (Emphasis supplied.) to Contractor. Refund the difference to Owner if such Art. 1167. If a person obliged to do something fails to do it,
expense shall exceed unpaid balance.40 (Emphasis the same shall be executed at his cost.
supplied.)”
Significantly, Rhogen did not mention in its
communications to Reyes that Gaite was merely a victim of This same rule shall be observed if he does it in
abuse by a local official and this was the primary reason Upon the facts duly established, the CA therefore did not contravention of the tenor of the obligation. Furthermore,
for the problems besetting the project. On the contrary, err in holding that Rhogen committed a serious breach of it may be decreed that what has been poorly done be
the site appraisal inspection conducted on February 12 and its contract with The Plaza, which justified the latter in undone.
13, 1981 in the presence of representatives from The Plaza, terminating the contract. Petitioners are thus liable for
Rhogen, FGU and Municipal Engineer Victor Gregory, damages for having breached their contract with
respondent The Plaza. Article 1170 of the Civil In addition, Article 122 of the Articles of General
disclosed that in addition to the violations committed by Conditions provides that the contractor shall not be
Rhogen which resulted in the issuance of the stoppage Code provides that those who in the performance of their
obligations are guilty of fraud, negligence or delay and entitled to receive further payment "until the work is
order, Rhogen built the structure not in accordance with finished." As the works completed by Rhogen were not in
government approved plans and/or without securing the those who in any manner contravene the tenor thereof are
liable for damages. accordance with approved plans, it should have been
approval of the Municipal Engineer before making the executed at its cost had it not relinquished the project in
changes thereon.39 January 1981. The CA thus did not err in sustaining the
Petitioners assail the order for the return of down trial court’s order for the return of the down payment
Such non-observance of laws and regulations of the local payment, asserting that the principle of quantum meruit given by The Plaza to Rhogen.
authorities affecting the construction project constitutes a demands that Rhogen as contractor be paid for the work
substantial violation of the Construction Contract which already accomplished.
As to temperate damages, Article 2224 of the Civil
entitles The Plaza to terminate the same, without Code provides that temperate or moderate damages, which
obligation to make further payment to Rhogen until the We disagree. are more than nominal but less than compensatory
work is finished or subject to refund of payment exceeding damages, may be recovered when the court finds that
the expenses of completing the works. This is evident from Under the principle of quantum meruit, a contractor is some pecuniary loss has been suffered but its amount
a reading of Article 122 which states: allowed to recover the reasonable value of the thing or cannot, from the nature of the case, be proved with
services rendered despite the lack of a written contract, in certainty. The rationale behind temperate damages is
122. OWNER’S RIGHT TO TERMINATE CONTRACT order to avoid unjust enrichment. Quantum meruit means precisely that from the nature of the case, definite proof of
pecuniary loss cannot be offered. When the court is In the first quarter of 1998, petitioner, Solar Harvest, Inc., made an additional order of 24,000 boxes, out of which,
convinced that there has been such loss, the judge is entered into an agreement with respondent, Davao 14,000 had been completed without waiting for
empowered to calculate moderate damages, rather than let Corrugated Carton Corporation, for the purchase of petitioner’s payment. Respondent stated that petitioner
the complainant suffer without redress from the corrugated carton boxes, specifically designed for was to pick up the boxes at the factory as agreed upon, but
defendant’s wrongful act.42Petitioners’ contention that petitioner’s business of exporting fresh bananas, at petitioner failed to do so. Respondent averred that, on
such award is improper because The Plaza could have US$1.10 each. The agreement was not reduced into October 8, 1998, petitioner’s representative, Bobby Que
presented receipts to support the claim for actual writing. To get the production underway, petitioner (Que), went to the factory and saw that the boxes were
damages, must fail considering that Rhogen never denied deposited, on March 31, 1998, US$40,150.00 in ready for pick up. On February 20, 1999, Que visited the
the delivery of the owner-furnished materials which were respondent’s US Dollar Savings Account with Westmont factory again and supposedly advised respondent to sell
under its custody at the jobsite during the work stoppage Bank, as full payment for the ordered boxes. the boxes as rejects to recoup the cost of the unpaid
and before it terminated the contract. Since Rhogen failed 14,000 boxes, because petitioner’s transaction to ship
to account either for those items which it had caused to be Despite such payment, petitioner did not receive any boxes bananas to China did not materialize. Respondent claimed
withdrawn from the premises, or those considered from respondent. On January 3, 2001, petitioner wrote a that the boxes were occupying warehouse space and that
damaged or lost due spoilage, or disappeared for whatever demand letter for reimbursement of the amount paid.3 On petitioner should be made to pay storage fee at ₱60.00 per
reason – there was no way of determining the exact February 19, 2001, respondent replied that the boxes had square meter for every month from April 1998. As
quantity and cost of those materials.1âwphi1 Hence, The been completed as early as April 3, 1998 and that counterclaim, respondent prayed that judgment be
Plaza was correctly allowed to recover temperate damages. petitioner failed to pick them up from the former’s rendered ordering petitioner to pay $15,400.00, plus
warehouse 30 days from completion, as agreed upon. interest, moral and exemplary damages, attorney’s fees,
Upon the foregoing, we find petitioners’ claim for actual, Respondent mentioned that petitioner even placed an and costs of the suit.
moral and exemplary damages and attorney’s fees lacking additional order of 24,000 boxes, out of which, 14,000 had
in legal basis and undeserving of further discussion. been manufactured without any advanced payment from In reply, petitioner denied that it made a second order of
petitioner. Respondent then demanded petitioner to 24,000 boxes and that respondent already completed the
WHEREFORE, the petition is DENIED. The Decision remove the boxes from the factory and to pay the balance initial order of 36,500 boxes and 14,000 boxes out of the
dated June 27, 2006 and the Resolution dated April 20, of US$15,400.00 for the additional boxes and second order. It maintained that
2007 of the Court of Appeals in CA-G.R. CV No. 58790 ₱132,000.00 as storage fee.
are AFFIRMED. respondent only manufactured a sample of the ordered
On August 17, 2001, petitioner filed a Complaint for sum boxes and that respondent could not have produced
With costs against petitioners. of money and damages against respondent. The Complaint 14,000 boxes without the required pre-payments.6
averred that the parties agreed that the boxes will be
delivered within 30 days from payment but respondent During trial, petitioner presented Que as its sole witness.
SO ORDERED. failed to manufacture and deliver the boxes within such Que testified that he ordered the boxes from respondent
time. It further alleged and deposited the money in respondent’s account.7 He
SECOND DIVISION specifically stated that, when he visited respondent’s
G.R. No. 176868 July 26, 2010 6. That repeated follow-up was made by the plaintiff for factory, he saw that the boxes had no print of petitioner’s
SOLAR HARVEST, INC., Petitioner, the immediate production of the ordered boxes, but every logo.8 A few months later, he followed-up the order and
vs. time, defendant [would] only show samples of boxes and was told that the company had full production, and thus,
DAVAO CORRUGATED CARTON ma[k]e repeated promises to deliver the said ordered was promised that production of the order would be
CORPORATION, Respondent. boxes. rushed. He told respondent that it should indeed rush
DECISION production because the need for the boxes was urgent.
NACHURA, J.: Thereafter, he asked his partner, Alfred Ong, to cancel the
Petitioner seeks a review of the Court of Appeals (CA) 7. That because of the failure of the defendant to deliver
the ordered boxes, plaintiff ha[d] to cancel the same and order because it was already late for them to meet their
Decision1 dated September 21, 2006 and Resolution2 dated commitment to ship the bananas to China.9 On cross-
February 23, 2007, which denied petitioner’s motion for demand payment and/or refund from the defendant but
the latter refused to pay and/or refund the US$40,150.00 examination, Que further testified that China Zero Food,
reconsideration. The assailed Decision denied petitioner’s the Chinese company that ordered the bananas, was
claim for reimbursement for the amount it paid to payment made by the former for the ordered
boxes.41avvphi1 sending a ship to Davao to get the bananas, but since there
respondent for the manufacture of corrugated carton were no cartons, the ship could not proceed. He said that,
boxes. at that time, bananas from Tagum Agricultural
In its Answer with Counterclaim,5 respondent insisted Development Corporation (TADECO) were already there.
The case arose from the following antecedents: that, as early as April 3, 1998, it had already completed He denied that petitioner made an additional order of
production of the 36,500 boxes, contrary to petitioner’s 24,000 boxes. He explained that it took three years to
allegation. According to respondent, petitioner, in fact,
refer the matter to counsel because respondent promised boxes. According to the CA, it was unthinkable that, over a extrajudicially demands from them the fulfillment of their
to pay.10 period of more than two years, petitioner did not even obligation.
demand for the delivery of the boxes. The CA added that
For respondent, Bienvenido Estanislao (Estanislao) even assuming that the agreement was for respondent to However, the demand by the creditor shall not be
testified that he met Que in Davao in October 1998 to deliver the boxes, respondent would not be liable for necessary in order that delay may exist:
inspect the boxes and that the latter got samples of them. breach of contract as petitioner had not yet demanded
In February 2000, they inspected the boxes again and Que from it the delivery of the boxes.16
(1) When the obligation or the law expressly so declares; or
got more samples. Estanislao said that petitioner did not
pick up the boxes because the ship did not arrive.11 Jaime Petitioner moved for reconsideration,17but the motion was
Tan (Tan), president of respondent, also testified that his denied by the CA in its Resolution of February 23, 2007.18 (2) When from the nature and the circumstances of the
company finished production of the 36,500 boxes on April obligation it appears that the designation of the time when
3, 1998 and that petitioner made a second order of 24,000 the thing is to be delivered or the service is to be rendered
In this petition, petitioner insists that respondent did not was a controlling motive for the establishment of the
boxes. He said that the agreement was for respondent to completely manufacture the boxes and that it was
produce the boxes and for petitioner to pick them up from contract; or
respondent which was obliged to deliver the boxes to
the warehouse.12 He also said that the reason why TADECO.
petitioner did not pick up the boxes was that the ship that (3) When demand would be useless, as when the obligor
was to carry the bananas did not arrive.13 According to has rendered it beyond his power to perform.
him, during the last visit of Que and Estanislao, he asked We find no reversible error in the assailed Decision that
them to withdraw the boxes immediately because they would justify the grant of this petition.
In reciprocal obligations, neither party incurs in delay if
were occupying a big space in his plant, but they, instead,
the other does not comply or is not ready to comply in a
told him to sell the cartons as rejects. He was able to sell Petitioner’s claim for reimbursement is actually one for proper manner with what is incumbent upon him. From
5,000 boxes at ₱20.00 each for a total of ₱100,000.00. rescission (or resolution) of contract under Article 1191 of the moment one of the parties fulfills his obligation, delay
They then told him to apply the said amount to the unpaid the Civil Code, which reads: by the other begins.
balance.
Art. 1191. The power to rescind obligations is implied in In reciprocal obligations, as in a contract of sale, the
In its March 2, 2004 Decision, the Regional Trial Court reciprocal ones, in case one of the obligors should not general rule is that the fulfillment of the parties’ respective
(RTC) ruled that respondent did not commit any breach of comply with what is incumbent upon him. obligations should be simultaneous. Hence, no demand is
faith that would justify rescission of the contract and the
generally necessary because, once a party fulfills his
consequent reimbursement of the amount paid by
The injured party may choose between the fulfillment and obligation and the other party does not fulfill his, the latter
petitioner. The RTC said that respondent was able to
the rescission of the obligation, with the payment of automatically incurs in delay. But when different dates for
produce the ordered boxes but petitioner failed to obtain
damages in either case. He may also seek rescission, even performance of the obligations are fixed, the default for
possession thereof because its ship did not arrive. It thus
after he has chosen fulfillment, if the latter should become each obligation must be determined by the rules given in
dismissed the complaint and respondent’s counterclaims,
impossible. the first paragraph of the present article,19 that is, the
disposing as follows:
other party would incur in delay only from the moment the
The court shall decree the rescission claimed, unless there other party demands fulfillment of the former’s obligation.
WHEREFORE, premises considered, judgment is hereby Thus, even in reciprocal obligations, if the period for the
be just cause authorizing the fixing of a period.
rendered in favor of defendant and against the plaintiff fulfillment of the obligation is fixed, demand upon the
and, accordingly, plaintiff’s complaint is hereby ordered obligee is still necessary before the obligor can be
DISMISSED without pronouncement as to cost. This is understood to be without prejudice to the rights of considered in default and before a cause of action for
Defendant’s counterclaims are similarly dismissed for lack third persons who have acquired the thing, in accordance rescission will accrue.
of merit. with Articles 1385 and 1388 and the Mortgage Law.
Evident from the records and even from the allegations in
SO ORDERED.14 The right to rescind a contract arises once the other party the complaint was the lack of demand by petitioner upon
defaults in the performance of his obligation. In respondent to fulfill its obligation to manufacture and
determining when default occurs, Art. 1191 should be deliver the boxes. The Complaint only alleged that
Petitioner filed a notice of appeal with the CA.
taken in conjunction with Art. 1169 of the same law, which petitioner made a "follow-up" upon respondent, which,
provides: however, would not qualify as a demand for the fulfillment
On September 21, 2006, the CA denied the appeal for lack of the obligation. Petitioner’s witness also testified that
of merit.15 The appellate court held that petitioner failed to they made a follow-up of the boxes, but not a demand.
Art. 1169. Those obliged to deliver or to do something
discharge its burden of proving what it claimed to be the Note is taken of the fact that, with respect to their claim for
incur in delay from the time the obligee judicially or
parties’ agreement with respect to the delivery of the reimbursement, the Complaint alleged and the witness
testified that a demand letter was sent to respondent. due to petitioner’s fault that the boxes were not delivered Q. Did you give authority to Mr. Tan to deliver these boxes
Without a previous demand for the fulfillment of the to TADECO. to TADECO?
obligation, petitioner would not have a cause of action for
rescission against respondent as the latter would not yet be Petitioner had the burden to prove that the agreement A. No, sir. As I have said, before the delivery, we must have
considered in breach of its contractual obligation. was, in fact, for respondent to deliver the boxes within 30 to check the carton, the quantity and quality. But I have
days from payment, as alleged in the Complaint. Its sole not seen a single carton.
Even assuming that a demand had been previously made witness, Que, was not even competent to testify on the
before filing the present case, petitioner’s claim for terms of the agreement and, therefore, we cannot give Q. Are you trying to impress upon the [c]ourt that it is only
reimbursement would still fail, as the circumstances would much credence to his testimony. It appeared from the after the boxes are completed, will you give authority to
show that respondent was not guilty of breach of contract. testimony of Que that he did not personally place the order Mr. Tan to deliver the boxes to TADECO[?]
with Tan, thus:
The existence of a breach of contract is a factual matter not A. Sir, because when I checked the plant, I have not seen
usually reviewed in a petition for review under Rule “Q. No, my question is, you went to Davao City and placed any carton. I asked Mr. Tan to rush the carton but not…26
45.20 The Court, in petitions for review, limits its inquiry your order there?
only to questions of law. After all, it is not a trier of facts,
and findings of fact made by the trial court, especially Q. Did you give any authority for Mr. Tan to deliver these
A. I made a phone call. boxes to TADECO?
when reiterated by the CA, must be given great respect if
not considered as final.21 In dealing with this petition, we
will not veer away from this doctrine and will thus sustain Q. You made a phone call to Mr. Tan? A. Because I have not seen any of my carton.
the factual findings of the CA, which we find to be
adequately supported by the evidence on record. A. The first time, the first call to Mr. Alf[re]d Ong. Alfred Q. You don’t have any authority yet given to Mr. Tan?
Ong has a contact with Mr. Tan.
As correctly observed by the CA, aside from the pictures of
A. None, your Honor.27
the finished boxes and the production report thereof, there Q. So, your first statement that you were the one who
is ample showing that the boxes had already been placed the order is not true?
manufactured by respondent. There is the testimony of Surely, without such authority, TADECO would not have
Estanislao who accompanied Que to the factory, attesting allowed respondent to deposit the boxes within its
A. That’s true. The Solar Harvest made a contact with Mr. premises.
that, during their first visit to the company, they saw the
Tan and I deposited the money in the bank.
pile of petitioner’s boxes and Que took samples thereof.
Que, petitioner’s witness, himself confirmed this incident. In sum, the Court finds that petitioner failed to establish a
He testified that Tan pointed the boxes to him and that he Q. You said a while ago [t]hat you were the one who called cause of action for rescission, the evidence having shown
got a sample and saw that it was blank. Que’s absolute Mr. Tan and placed the order for 36,500 boxes, isn’t it? that respondent did not commit any breach of its
assertion that the boxes were not manufactured is, contractual obligation. As previously stated, the subject
therefore, implausible and suspicious. A. First time it was Mr. Alfred Ong. boxes are still within respondent’s premises. To put a rest
to this dispute, we therefore relieve respondent from the
In fact, we note that respondent’s counsel manifested in Q. It was Mr. Ong who placed the order[,] not you? burden of having to keep the boxes within its premises
court, during trial, that his client was willing to shoulder and, consequently, give it the right to dispose of them,
expenses for a representative of the court to visit the plant after petitioner is given a period of time within which to
and see the boxes.22 Had it been true that the boxes were A. Yes, sir.24 remove them from the premises.
not yet completed, respondent would not have been so
bold as to challenge the court to conduct an ocular Q. Is it not a fact that the cartons were ordered through WHEREFORE, premises considered, the petition is
inspection of their warehouse. Even in its Comment to this Mr. Bienvenido Estanislao? DENIED. The Court of Appeals Decision dated September
petition, respondent prays that petitioner be ordered to 21, 2006 and Resolution dated February 23, 2007 are
remove the boxes from its factory site,23 which could only A. Yes, sir.” AFFIRMED. In addition, petitioner is given a period of 30
mean that the boxes are, up to the present, still in days from notice within which to cause the removal of the
respondent’s premises. 36,500
Moreover, assuming that respondent was obliged to
deliver the boxes, it could not have complied with such
We also believe that the agreement between the parties obligation. Que, insisting that the boxes had not been boxes from respondent’s warehouse. After the lapse of said
was for petitioner to pick up the boxes from respondent’s manufactured, admitted that he did not give respondent period and petitioner fails to effect such removal,
warehouse, contrary to petitioner’s allegation. Thus, it was the authority to deliver the boxes to TADECO:
respondent shall have the right to dispose of the boxes in
any manner it may deem fit.

SO ORDERED.

You might also like