You are on page 1of 2

Federal Acquisition Regulation 52.

236–15

or hazardous nature, or (b) perform- used for the purpose of determining charges.
ance on a Government facility that on Before final acceptance of the work by the
the advice of technical representatives Government, the Contractor shall remove all
the temporary connections, distribution
involves hazardous materials or oper- lines, meters, and associated paraphernalia.
ations that might endanger the safety
of the public and/or Government per- (End of clause)
sonnel or property, add the following
paragraph (f) to the basic clause: 52.236–15 Schedules for Construction
Contracts.
(f) Before commencing the work, the Con-
tractor shall— As prescribed in 36.515, insert the fol-
(1) Submit a written proposed plan for im- lowing clause:
plementing this clause. The plan shall in-
clude an analysis of the significant hazards SCHEDULES FOR CONSTRUCTION CONTRACTS
to life, limb, and property inherent in con- (APR 1984)
tract work performance and a plan for con- (a) The Contractor shall, within five days
trolling these hazards; and after the work commences on the contract or
(2) Meet with representatives of the Con- another period of time determined by the
tracting Officer to discuss and develop a mu- Contracting Officer, prepare and submit to
tual understanding relative to administra- the Contracting Officer for approval three
tion of the overall safety program. copies of a practicable schedule showing the
[56 FR 55376, Oct. 25, 1991] order in which the Contractor proposes to
perform the work, and the dates on which
52.236–14 Availability and Use of Util- the Contractor contemplates starting and
ity Services. completing the several salient features of
the work (including acquiring materials,
As prescribed in 36.514, insert the fol- plant, and equipment). The schedule shall be
lowing clause in solicitations and con- in the form of a progress chart of suitable
tracts when a fixed-price construction scale to indicate appropriately the percent-
contract or a fixed-price dismantling, age of work scheduled for completion by any
demolition, or removal of improve- given date during the period. If the Con-
tractor fails to submit a schedule within the
ments contract is contemplated, the
time prescribed, the Contracting Officer may
contract is to be performed on Govern- withhold approval of progress payments
ment sites when the contracting officer until the Contractor submits the required
decides (a) that the existing utility schedule.
system is adequate for the needs of (b) The Contractor shall enter the actual
both the Government and the con- progress on the chart as directed by the Con-
tractor, and (b) furnishing it is in the tracting Officer, and upon doing so shall im-
Government’s interest. When this mediately deliver three copies of the anno-
tated schedule to the Contracting Officer. If,
clause is used, the contracting officer in the opinion of the Contracting Officer, the
shall list the available utilities in the Contractor falls behind the approved sched-
contract. ule, the Contractor shall take steps nec-
essary to improve its progress, including
AVAILABILITY AND USE OF UTILITY SERVICES
those that may be required by the Con-
(APR 1984)
tracting Officer, without additional cost to
(a) The Government shall make all reason- the Government. In this circumstance, the
ably required amounts of utilities available Contracting Officer may require the Con-
to the Contractor from existing outlets and tractor to increase the number of shifts,
supplies, as specified in the contract. Unless overtime operations, days of work, and/or
otherwise provided in the contract, the the amount of construction plant, and to
amount of each utility service consumed submit for approval any supplementary
shall be charged to or paid for by the Con- schedule or schedules in chart form as the
tractor at prevailing rates charged to the Contracting Officer deems necessary to dem-
Government or, where the utility is produced onstrate how the approved rate of progress
by the Government, at reasonable rates de- will be regained.
termined by the Contracting Officer. The (c) Failure of the Contractor to comply
Contractor shall carefully conserve any util- with the requirements of the Contracting Of-
ities furnished without charge. ficer under this clause shall be grounds for a
(b) The Contractor, at its expense and in a determination by the Contracting Officer
workmanlike manner satisfactory to the that the Contractor is not prosecuting the
Contracting Officer, shall install and main- work with sufficient diligence to ensure
tain all necessary temporary connections completion within the time specified in the
and distribution lines, and all meters re- contract. Upon making this determination,
quired to measure the amount of each utility the Contracting Officer may terminate the

277

VerDate Aug<31>2005 10:43 Nov 14, 2006 Jkt 208202 PO 00000 Frm 00287 Fmt 8010 Sfmt 8010 Y:\SGML\208202.XXX 208202
52.236–16 48 CFR Ch. 1 (10–1–06 Edition)
Contractor’s right to proceed with the work, instance. The Government shall make such
or any separable part of it, in accordance computations as are necessary to determine
with the default terms of this contract. the quantities of work performed or finally
in place. The Contractor shall make the
(End of clause) computations based on the surveys for any
periods for which progress payments are re-
[48 FR 42478, Sept. 19, 1983, as amended at 60 quested.
FR 34761, July 3, 1995]
52.236–17 Layout of Work.
52.236–16 Quantity Surveys.
As prescribed in 36.517, insert the fol-
As prescribed in 36.516, the con-
lowing clause in solicitations and con-
tracting officer may insert the fol-
lowing clause in solicitations and con- tracts when a fixed-price construction
tracts when a fixed-price construction contract is contemplated and use of
contract providing for unit pricing of this clause is appropriate due to a need
items and for payment based on quan- for accurate work layout and for siting
tity surveys is contemplated: verification during work performance:
QUANTITY SURVEYS (APR 1984) LAYOUT OF WORK (APR 1984)
(a) Quantity surveys shall be conducted, The Contractor shall lay out its work from
and the data derived from these surveys Government-established base lines and bench
shall be used in computing the quantities of marks indicated on the drawings, and shall
work performed and the actual construction be responsible for all measurements in con-
completed and in place. nection with the layout. The Contractor
(b) The Government shall conduct the shall furnish, at its own expense, all stakes,
original and final surveys and make the com- templates, platforms, equipment, tools, ma-
putations based on them. The Contractor
terials, and labor required to lay out any
shall conduct the surveys for any periods for
part of the work. The Contractor shall be re-
which progress payments are requested and
shall make the computations based on these sponsible for executing the work to the lines
surveys. All surveys conducted by the Con- and grades that may be established or indi-
tractor shall be conducted under the direc- cated by the Contracting Officer. The Con-
tion of a representative of the Contracting tractor shall also be responsible for main-
Officer, unless the Contracting Officer taining and preserving all stakes and other
waives this requirement in a specific in- marks established by the Contracting Officer
stance. until authorized to remove them. If such
(c) Promptly upon completing a survey, marks are destroyed by the Contractor or
the Contractor shall furnish the originals of through its negligence before their removal
all field notes and all other records relating is authorized, the Contracting Officer may
to the survey or to the layout of the work to replace them and deduct the expense of the
the Contracting Officer, who shall use them replacement from any amounts due or to be-
as necessary to determine the amount of come due to the Contractor.
progress payments. The Contractor shall re-
tain copies of all such material furnished to
(End of clause)
the Contracting Officer.

(End of clause) 52.236–18 Work Oversight in Cost-Re-


imbursement Construction Con-
Alternate I (APR 1984). If it is deter- tracts.
mined at a level above that of the con- As prescribed in 36.518, insert the fol-
tracting officer that it is impracticable
lowing clause in solicitations and con-
for Government personnel to perform
the original and final surveys, and the tracts when cost-reimbursement con-
Government wishes the contractor to struction contracts are contemplated:
perform these surveys, substitute the WORK OVERSIGHT IN COST-REIMBURSEMENT
following paragraph (b) for paragraph CONSTRUCTION CONTRACTS (APR 1984)
(b) of the basic clause:
The extent and character of the work to be
(b) The Contractor shall conduct the origi- done by the Contractor shall be subject to
nal and final surveys and surveys for any pe- the general supervision, direction, control,
riods for which progress payments are re- and approval of the Contracting Officer.
quested. All these surveys shall be conducted
under the direction of a representative of the
Contracting Officer, unless the Contracting
Officer waives this requirement in a specific

278

VerDate Aug<31>2005 10:43 Nov 14, 2006 Jkt 208202 PO 00000 Frm 00288 Fmt 8010 Sfmt 8010 Y:\SGML\208202.XXX 208202

You might also like