You are on page 1of 6

Very Fast Electromagnetic Transients in Air

Insulated Substations and Gas Insulated Substations


due to Disconnector Switching
Salih Carsimamovic, Zijad Bajramovic Miroslav Ljevak Meludin Veledar
Faculty of Electrical Engineering, Sarajevo Energoinvest, Sarajevo ABB Representation for B&H
Bosnia and Herzegovina Bosnia and Herzegovina Bosnia and Herzegovina
csalih@bih.net.ba z.bajramovic@kfbih.com miroslav.ljevak@smartnet.ba meludin.veledar@hr.abb.com

Abstract. Very fast electromagnetic transients (VFT) in air distance between the disconnector contacts, the contacts
insulated substations (AIS) and gas insulated substations (GIS) geometry, the pressure and characteristics of the SF6 gas
caused by switching operation of disconnectors are investigated. (GIS) as well as relative atmospheric conditions (AIS) at the
Results obtained from very extensive field tests and from digital moment of striking.
simulations as well as a comparison between field tests and
Every strike causes high-frequency currents tending to equalize
calculation results of VFT in AIS and GIS due to disconnector
switching are presented. Field tests of disconnector switching in 220 potentials at the contacts. When the current is interrupted, the
kV air insulated substations Grabovica and Kakanj as well as test voltages at the source side and the loading side will oscillate
circuit of 110 kV GIS section are performed. Digital simulation of independently. The source side will follow the power frequency
VFT for different models of power network are performed using while the loading side will remain at the trapped voltage. As
EMTP-ATP [1]. soon as the voltage between the disconnector contacts exceeds
the dielectric strength of the SF6 gas or the air, at that distance
Key words: electromagnetic compatibility (EMC), very fast between the contacts the restrike will occur, and so on.
transients (VFT), disconnector switching, air insulated substation Successive strikes occuring during the closing and opening
(AIS), gas insulated substation (GIS)
operations of the off-loaded busbar by the disconnector in AIS
are shown in Fig. 1 a and b, and in GIS are shown in Fig. 2 a and
I. INTRODUCTION b, respectively.
When the disconnector is closing, the first strike will occur at the
Switching operation in power stations and substations, high- maximum value of the source voltages. Its values can be positive
voltage faults and lightning cause high level of high frequency or negative. As the time passes a series of successive strikes will
overvoltages that can be coupled with low voltage secondary keep occuring at reduced amplitudes, until the contacts touch.
circuits and electronic equipment unless they are suitable The highest transient overvoltage therefore occurs during the
protected. The function of high-voltage disconnectors is to initial pre-arc, Fig 1 a and 2 a, respectively.
provide electrical isolation of one part of the switchgear. When the disconnector is opening, restrikes occur because of the
Disconnector's standards define that they are able to open or very small initial clearance between the disconnector contacts.
close a circuit if either a neglibile current (≤0.5 A) is switched At the transient beginning, the intervals between particular
or if no significant change occurs in the voltage between the strikes are of the order of a millisecond, while just before the last
disconnector contacts. These values of currents include the strike occures, the interval can reach about one half of cycle at
capacitive charging currents of high-voltage busbars, bushings, power frequency, Fig. 1 b and 2 b, respectively.
connectors, very short lenghts of cables and the current of
voltage transformers. Contacts of disconnector are moving
slowly during opening and closing operation. That causes
numerous strikes and restrikes between the contacts. When
contacts are closed, the capacitive charging current flowing
through the contacts ranges from 0.017⋅10-3 to 1.1⋅10-3 Aeff/m for
voltage levels 72.5-500 kV in AIS [2] and from 0.3 to 1 Aeff in
GIS [3], depending on the rated voltage and lenght of high-
voltage busbar which is being switched. Strikes and restrikes
occur as soon as the dielectric strength of the air (AIS) or SF6
gas under pressure (GIS) between the disconnector contacts is
exceeded by overvoltages. The overvoltage is defined by a)

0-7803-9380-5/05/$20.00 ©2005 IEEE. 382


frequency cycles (i.e. 800-1000 ms), Fig. 1. In GIS, there were
about 7-12 power frequency cycles (i.e. 140-240 ms), Fig. 2.
The maximum value of voltages and maximum value of the
wave-front increasing will take place at the maximum distance
between the disconnector contacts. For the purpose of the
investigation of the insulation strength and induction of
electromagnetic interferences (EMI), the most important are the
first few strikes during the closing operation or the last few
strikes during the opening operation. Each individual strike
causes a traveling wave with the basic frequency of the order of
b) 0.5 MHz (330 kHz-600 kHz) in AIS, Fig 3 and from 100 kHz to
Fig. 1 The voltage due to the disconnector switching in AIS [4] several MHz in GIS, Fig 4.
a) disconnector closing
b) disconnector opening
1- source side voltage, 2-load side voltage

Fig. 3 Very fast transient overvoltage at the load side during the AIS
disconnector closing [4]

a)

Fig. 4 Very fast transient overvoltage at the load side during the GIS
disconnector closing [3]

b) The magnetic field during opening of disconnector in AIS is


Fig. 2 The voltage due to the disconnector switching in GIS [3] proportional to the current, while the electric field depends on
a)disconnector closing
b) disconnector opening the charge. Magnetic field (current) approaches zero in a few µs,
 load side voltage,⋅⋅⋅⋅⋅⋅ source side voltage while electric field (voltage) approaches a constant value
different than zero, due to trapped charges caused by the current
During the switching time of operations of air-insulated interruption by the disconnector.
disconnectors in the air insulated substations Grabovica and In a GIS the electric field (voltage) and magfnetic field (current)
Kakanj up to 500 restrikes were recorded. Switching operation approaches to zero after a short time. Dominant frequencies are
of air-insulated disconnectors lasted for about 40-50 power substantially higher (usually 10 to 100 times) than these in AIS

0-7803-9380-5/05/$20.00 ©2005 IEEE. 383


as well as amplitudes are lower due to the damping of the Grabovica on the River Neretva and the thermo power plant
transients. Also, the metallic enclosure, including its grounding, (TPP) Kakanj are important facilities for operating of electric
is probably one of the main reason for the reduction of fields in power system of Bosnia and Herzegovina. Investigations of
GIS [5]. operating of air disconnector of Centre-Break design were
Compared with conventional AIS, GIS exibits some performed in order to determine switching overvoltage levels,
fundamental differencies: that can lead to the protection relay tripping in the AIS
-the size of the electrical components in GIS are much smaller Grabovica [6] and the AIS Kakanj [4]. During operations of
than in AIS, so the frequencies of multiple reflection of traveling disconnector (synchronization or disconnecting of generator
waves on the busbars of GIS are at least 10 times higher than from network in HPP Grabovica) malfunctions of signalling
those in AIS; devices and burning of auxiliary voltage supply units of
The characteristic impedance of the high-voltage busbars in GIS protection relays occured. Malfunctioning of auxiliary circuits
is about 5 times smaller than that of an AIS (i.e. 60 Ω in GIS were manifested by tripping of differential protection relay of
instead of 300 Ω in AIS). Coaxial conductors of the busbars in the generator, phase '4'-signalization on relay box 'ZB I' and by
GIS have higher specific capacitance to ground in comparison signalling 'fire' in 35 kV control panel. At the same time
with the AIS. Therefore, the capacitive currents of off-loaded sparking between primary terminals of the current transformer
busbars in GIS are larger than such capacitive currents in AIS. (CT) occured. Malfunctioning of auxiliary signalling circuits
Further differences between the characteristics of these two became lower (not eliminated) after installing of shielded cables.
types of substations are lower characteistic surge impedance and The field tests in AIS were perfomed at the test circuit in the
inductance as well as larger gradient of electric field between the HPP Grabovica and the TPP Kakanj, Fig. 5 and Fig. 6,
prestrike and restrike arcs in SF6 gas under pressure in reference respectively.
to grounded enclosure. The overvoltage factors, k, at the load side of disconnector
This leads to an important difference of impedances at the during closing operation of the disconnector in the HPP
junction of the GIS and high-voltage overhead line, bushings, Grabovica were recorded up to 1.16 p.u. (1 p.u.=245√2/√3 kV)
open circuit breaker or disconnector contacts as well as open air with dominant frequency of considered transients, fd, equal to
busbars. These differences are, during switching operations, 0.536 MHz [6].
origins of high standing voltage and current waves (the
H P P G R A B O V IC A L A Y O U T
amplitude of the voltage waves depends directly on the voltage
level and it is comparable to those generated in AIS, whereas the O L T O R P JA B L A N IC A M
B U S B A R S 22 0kV 3 ~ 50 H z, 12 50 A
amplitude of the current waves are inversely proportional to the
characteristic impedance). The metal enclosure of the GIS 0 .2 m H M Dc
12 50 A
presents a shielding discontinuity, i.e. at the junction with high- 24 5 kV
30 0 Ω
voltage overhead lines or cables, it becomes an important source 4 40 0 pF
1 nF VT
2 nF
of radiation. The consequences of these features, during
M CB
switching operations are very high potentials induced in the CVD
0.44 µ F
2n F
grounding system of the substation and in the secondary circuits.
They can be high enough to cause sparkover between metallic
grounded elements which are not in direct contact with each CT

other. These problems are more dangerous in usually small


M OSA
distances in GIS between high-voltage equipment and electronic
equipment.
PT 1
II. RESULTS OF EXPERIMENTAL MEASUREMENTS IN
FIELD TESTS
AG1

The last ten years of extensive analysis of measurements of EMI


R elay ro om
generated by operation of disconnectors (Dc) and circuit
breakers (CB) have confirmed that disconnector operation with
off-loaded busbar is the most important and typical source of Fig. 5 The considered test circuit [6]
interference in secondary circuits of the high-voltage VT-voltage transformer (220/√3/0.1/√3/0.1/√3 kV), CT-current transformer
substations. Measurements of switching overvoltages generated (200/1/1 A), CVD-capacitive voltage divider, CB-circuit breaker with two
interrupting chambers and parallel capacitors (SF6 220 kV, 1600 A), Dc-
during disconnector operation in the air insulated substation disconnector (220 kV, 1250 A), MOSA-metal oxide surge arrester (Ur=199,5 kV,
Grabovica and the air insulated substation Kakanj of voltage 10 kA), PT-power transformer (64 MVA, 242/10,5±5% kV, YD5), AG1-generator
levels 220 kV, were performed. The hydro power plant (HPP) 1 (64 MVA, 10,5±5% kV)

0-7803-9380-5/05/$20.00 ©2005 IEEE. 384


The recorded overvoltage factor, k, at the load side for the
capacitance of the source side C1 equal to 40 nF and for ratio of
BUS BARS II 220kV 3∼50 Ηz, 1250 A CB
capacitance of the source side to the capacitance of the load side
M equal to 5.7, is 1.4 p.u. (1 p.u.=123·√2/√3 kV) with the dominant
frequency, fd, is equal to 195 kHz and an additional frequency is
COUPLING BAY equal to 925 kHz.
When the capacitance of the source side (C1) is equal to 60 nF
and the ratio of capacitance of the source side and the load side
CT
BUS BAR I (C1/C2) is equal to 8.57, the overvoltage factor, k, is equal to
1.78 p.u. and dominant frequency is equal to 192 kHz and an
Dc
300Ω 300Ω
additional frequency is equal to 1.6 MHz.
CVD 1 1nF CVD 2 1nF
III. MODELING OF THE TEST CIRCUITS
OL TO TPP KAKANJ 5

VT

Computer simulations of the AIS test circuits at HPP Grabovica


were performed on the model of test circuits containing elements
Relay room
drawn in Fig. 8 [7]. Overvoltages at the busbars were calculated
during disconnector closing operations, for the same substation
layout on which the measurements were carried out.
Fig. 6 The test circuit at TPP Kakanj [4]
CB-circuit breaker without parallel capacitors (SF6 220 kV, 2500 A), CT- busbars 220 kV
current transformer (600-1200/1/1/1), VT-capacitive-inductive voltage
I
transformer (Cp=4400 pF, 220/√3/0.1/√3), Dc-disconnector (220 kV, 1250 A), I connection CB connection
CVD 1 -capacitive voltage divider (Cp=1 nF, Cs=2.2 µF, ratio 2200, R=300 I Dc arc tube C C wire
Ω),CVD 2-capacitive voltage divider (Cp=1 nF, Cs=0.44 µF, ratio 455, R=300 model of
II
Ω), network 220 kV I
II
I VT PT
stray Ccb
Recorded waveshape of the overvoltage surge at the load side in I
I
the AIS Kakanj is shown in Fig. 3. The overvoltage factors at CT+MOSA
busbars, k, were recorded up to 1.35 p.u. with dominant CVD
frequency of consider transient fd equal to 340 kHz.
The field tests in the test circuit of 110 kV GIS section were
Fig. 8. Model of the test circuit [7]
performed when the capacitors are connected to the source side Arc-4 Ω; stray-200 pF; connection tube Z=370 Ω; CVD-R=300 Ω, C=1 nF; VT-
(C1) as well as at the load side (C2) simulating a real operation 500 pF; CB-2 capacitors, each C≅2 nF, (capacitance of open contacts, each
condition of the disconnector for the actual substation, Fig. 7 [3]. C≅20 pF), Ccb=100 pF; CT-500 pF; MOSA-100 pF; connection wire Z=440 Ω;
Value of capacitor C1 varied from 40 to 60 nF, while the value PT-3.5 nF
of capacitor C2 is equal to 7 nF. The latter value is taken to
simulate equivalent length of the high-voltage busbar of 100 m. The waveshape of simulated overvoltage surge at load side in
the HPP Grabovica is given in Fig. 9. The difference between
magnitude of measured and simulated overvoltages is 5 %. The
dominant frequency of simulated overvoltage is 0.62 MHz.

100
[kV ]
50

-50

-100

-150

Fig. 7. Test circuit in GIS [3] -200


2 .8 5 8 2 .8 6 0 2 .8 6 2 2 .8 6 4 2 .8 6 6 2 .8 6 8 2 .8 7 0 [ms ] 2 .8 7 2
C1-source side capacitance, C2-load side capacitance, CVD-capacitive voltage ( f ile g r a b o - k o n t ro la . p l4 ; x -v a r t ) v : XX0 0 0 7

divider
Fig. 9. Waveshape of simulated overvoltage surge [7]

0-7803-9380-5/05/$20.00 ©2005 IEEE. 385


Computer simulation of the GIS test circuit in detail were mean it is no more necessary to isolate the circuit breaker. The
performed in ref. [3]. The peak values difference for measured disconnecting breaker had to be designed to be safety locked in
and simulated overvoltage were up to 8%. The dominant the open position, and to meet all voltage withstanding
frequency match very well over all period of 16 µs during which capabilities and safety requirements of disconnectors.
the transient has been shown, Fig. 10. Another way of reducing sources of interference emission is to
install CB without paralel capacitors and VT on generator side
of CB.
This suggestions are based on analyses performed on several
circuit models, Fig. 5. [7]:
a) model of CB with two breaking chambers and parallel
capacitors and VT on network side of CB;
b) model of CB with two breaking chambers and without
parallel capacitors and VT on network side of CB
c) model of CB with two breaking chambers and without
parallel capacitors and VT on generator side of CB.
Magnitudes of simulated overvoltages are presented in Table I.
Voltages are measured in point of connection of VT, CT and PT,
Fig. 8.
TABLE I
MAGNITUDES OF SIMULATED OVERVOLTAGES
Fig. 10. Waveshapes of measured and simulated overvoltage surge [3]
Connection point
Comparison between results of measured and calculated VT CT PT
Circuit model
overvoltages certified a good agreement of obtain values. a) model of CB with
two breaking chambers
IV. DESIGN CRITERIA OF EQUIPMENT AND SYSTEMS and parallel capacitors 169 kV 47 kV 51 kV
and VT on network side f=620 kHz f=1,1 MHz f=620 kHz
of CB
There are several actions can be adopted to reduce of the b) model of CB with
electromagnetic interferences [5]: two breaking chambers
• Operating directly on the source of interference, trying and without parallel 177 kV 560 V 165 V
to suppress, or at least to reduce, the disturbances; capacitors and VT on f=900 kHz f=1,4 MHz f=1,4 MHz
network side of CB
• Mitigating the coupling mechanism between sources c) model of CB with
and 'victims' and evaluating the disturbances affecting two breaking chambers
the electronic systems, characterising their working and without parallel 320 V 320 V 160 V
environment; capacitors and VT on f=1,1 MHz f=1,1 MHz f=1,1 MHz
generator side of CB
• Designing equipment and systems to include the
immunity requirements related to the actual
Overvoltages on generator side of the 220 kV CB during
electromagnetic environment.
switching operation of disconnectors could be up to 320 V in the
The purpose of this paper is to suggest measures for reducing
case of installing voltage transformers (VT) on generator side of
sources of interference emission. In order to reduce EMI in
CB without parallel capacitors (near instrument current
secondary auxiliary circuits, the best way is to reduce sources of
transformer CT). This case causes installing of circuit breaker at
interference emission during switching of air-insulated
generator’s voltage (10.5 kV) for synchronization of the
disconnector. One of the ways of reducing of source of
generator to the network (better conditions for synchronization).
interferences in the HPP Grabovica is to install the disconnecting
This solution of installing circuit breakers on generator’s voltage
circuit breaker [8, 9]. Substation disconnectors isolate circuit
resulted from problems have occurred during synchronization of
breakers from rest of the switchgear during maintenance and
the generator with the existing 220 kV CB.
repair. The maintenance requirements for modern SF6 high
voltage circuit breakers are lower than maintenance requirement
IV. CONCLUSION
for disconnectors. That means one of reasons for disconnectors
to be removed. With installing of the disconnecting circuit
Switching overvoltages caused by disconnector operations have
breaker there are no more needs for switching operation of
been analysed on existing 220 kV AIS in the HPP Grabovica and
disconnectors. With disconnecting circuit breakers it is still
the RP Kakanj as well as on the test circuit of 110 kV GIS.
possible to isolate the line, but low maintenance requirements

0-7803-9380-5/05/$20.00 ©2005 IEEE. 386


During the switching time of every operations of air V. REFERENCES
disconnectors at HPP Grabovica and RP Kakanj up to 500
restrikes were registered. Switching operations of disconnector [1] EMTP-ATP, European EMTP-ATP Users Group e.V.
in AIS lasted for about 40-50 power frequency cycles (i.e. 800- [2] D.F.Peelo, J.H.Sawada, B.R.Sunga, R.P.P.Smeets,
1000 ms). In GIS, there were about 7-12 power frequency cycles J.G.Krone, L.Van Der Sluis, 'Current interruption with high
(i.e. 140-240 ms) during every switching operation of GIS voltage air-break disconnectors', CIGRE 2004, paper A3-301
disconnector in the test circuit. [3] Z.Haznadar, S.Carsimamovic, R.Mahmutcehajic, 'More
The results of measurements shown that high frequency voltage Accurate Modeling of Gas Insulated Substation Components
on AIS busbars in the Grabovica occured with amplitudes up to in Digital Simulations of Very Fast Elrectromagnetic
1.160 p.u. and dominant frequencies up to 0.536 MHz as well as Transients', IEEE Transactions on Power Delivery, Vol. PWRD-
on AIS busbars in the Kakanj up to 1.356 p.u. and dominant 7, No. 4, 1991
frequencies up to 0.340 MHz, respectively. [4] 'Overvoltages in primary and secondary circuits in RP Kakanj
High voltage overvoltages on GIS busbars in the test circuit for due to disconnector switching', Faculty of Electrical Engineering,
different ratio of capacitance of the source side to the load side Report No. L1410011/04, Sarajevo, 2004
(C1/C2) were recorded up to 1.78 p.u. with dominant frequencies [5] Guide on EMC in Power Plants and Substations, CIGRE
up to 195 kHz and additional frequencies equal up to 1.6 MHz. WG 36.04, Dec. 1997
The differencies between magnitudes of measured and [6] 'Overvoltages in primary and secondary circuits in HPP
calculated overvoltages at AIS were up to 5 % and 15.6 % on Grabovica due to disconnector switching', Faculty of Electrical
frequency. The peak values differences between measured and Engineering, Report No. L1410010/04, Sarajevo, 2004
simulated overvoltage in the GIS were up to 8%. [7] S.Carsimamovic, Z.Bajramovic, M.Ljevak, M.Veledar and
Comparison of the transient computer simulation with the field N.Halilhodzic, 'Current Switching with High Voltage Air
measurements showed that calculations could be used for Disconnector', IPST'05, paper No. IPST05-229, June 19-23,
assessment of the transient overvoltage caused by disconnector 2005, Montreal, Canada
switching. [8] D.Braun, L.Widenhorn and J.Ischi, 'Impact of the Electrical
In order to reduce EMI in secondary circuits, it is suggested to Layout on the Availability of a Power Plant', 11-th CEPSI
install disconnecting circuit breakers or to install circuit breakers Conference, 21-25 October 1996, Kuala Lumpur, Malaysia
without parallel capacitors to contacts and with installing VT on [9] C-E. Sölver, H-E. Olovsson, W.Lord, P.Neorberg and
generator side of CB. J.Lundquist, ‘Innovative substations with availability using
switching modules and disconnecting circuit breakers’, CIGRE
2000, paper 23-102

0-7803-9380-5/05/$20.00 ©2005 IEEE. 387

You might also like