You are on page 1of 60

ANNUAL REPORT

2016 – 17

RAJASTHAN PROJECT, JODHPUR


OIL INDIA LIMITED

1
1.0 INTRODUCTION:

During the year 2016-17 Rajasthan Project achieved a Natural Gas production of 232.019
MMSCUM and Sales of 227.071 MMSCUM against the revised target of 211.00 MMSCUM
and 209.00 MMSCUM respectively. Additionally, with respect to the quantum of production
vis-à-vis total sale quantity, both were higher than the respective quantity in the previous
year i.e. 2015-2016 which were 206.188 MMSCUM & 201.17 MMSCUM. The percentage
achieved for production of Natural Gas was 109.96% and sale 108.65 % against RE target.

Rajasthan Project continued its endeavour for production and supply of Natural Gas to
Rajasthan Rajya Vidyut Utpadan Nigam Limited (RRVUNL) through the pipeline of M/s
GAIL (India) Ltd. in an efficient manner and thus contributed towards overall annual
performance of OIL INDIA LIMITED.
OIL (Rajasthan Project) bagged the following eight prizes in the 30th Mines Safety
Week 2016, organised by M/s. FCI Aravali Gypsum and Minerals India limited, Jodhpur,
under the aegis of Director of Mines Safety, Ajmer region.
Installation Prize Category
1 Production DND-GPC First Fire Fighting Drill
2 Production DND-GPC First Statutory records keeping
3 Production DND-GPC Third Overall performance
Electrical equipment, lighting and
4 Workover Rig (GTC 100-03) First wiring.
5 Workover Rig (GTC 100-03) First Safety features & Records
6 Workover Rig (GTC 100-03) First Overall performance
Publicity propaganda and house
7 Workover Rig (GTC 100-03) Second keeping
8 Workover Rig (GTC 100-03) Second Drilling & Maintenance

Project has also achieved success in the field of energy conservation by adopting measures
like reducing vehicle movements, using energy efficient lights, maintaining solar lighting
system etc. in the field which resulted in saving of considerable amount of HSD.

1
2.1 TARGETS AND ACHIEVEMENTS :

Activity Target Achievem Excess /


ent Short-fall

1. Drilling (MTRS)
Excess by
Exploratory 1250 1278 0.24 %
Excess by
8000
Developmen 8054 0.67 %
t
2.Natural Gas (MMSCUM)
Production 211 232.019 Excess by
9.96%
Sales 209 227.071 Excess by
8.65%

2.2 STATUS OF PEL / ML:

PEL AREAS:

NELP IV BLOCK RJ-ONN-2002/1: As suggested by Director (E&D), a review study was


carried out on relinquished areas of this block. Few leads were identified within the
block during G&G review and it was planned to validate the leads with additional
seismic data before going for drilling . Accordingly, actions were initiated to carry out
API of 600 GLKM of seismic to reconfirm the structural position and size of the leads
and to upgrade to prospects but the same could not be carried out due to reason
already discussed vide OCR dated 18.12.2009. It is worthwhile to mention here that
one well (Nanuwala-1) drilled north of this block produced crude oil (API 30.33)
during testing. The leads identified in the block are in up-dip direction with respect to
Nanuwala-1 and fall in the same migration pathway. It is suggested to acquire 3D
seismic of around 1000 sq.km covering the identified leads. Alternatively 600 GLKM
2D seismic (2x2 KM grid) can be acquired covering identified leads which was
originally planned for the block. Based on the interpretation of suggested seismic data
drilling may be planned in future.

NELP-VI Block RJ-ONN-2004/2: A review study was carried out on relinquished areas of
this block. Earlier, a G&G review was carried out after heavy oil discovery in Punam-1
well, one independent closure at Jodhpur Formation top level was identified in the
south of Punam structure. The said structure is structurally up dip in respect to
Punam structure and part of greater Baghewala-Punam structural high trend. One
location (Loc.C) was proposed in the structural closure, however, location was not
2
released and the structure could not be probed by exploratory drilling mainly due to
time limitation to fulfill the MWP work and subsequently the area had to be
relinquished (mandatory). As per G&G review to probe hydrocarbon prospects in the
independent structural closure south of Punam structure by drilling an exploratory
well, the same work program of drilling one exploratory well in the block is mooted
again. A request of retaining of about 10.2SQ.KM area covering the discovery area of
Block RJ-ONN-2004/2 for appraisal and Declaration of Commerciality (DOC) has been
submitted to DG, DGH. However, DG, DGH in the meeting regarding “Monitoring of
Nomination Blocks” indicated that OIL can avail the benefits of proposed OALP for
further exploration and production activity in the block.

PI Transfer:
The process of 25% PI transfer to OIL , the matter is still under arbitration process.
Next arbitration of hearing is expected in the month of May/June 2017. Received
communication from DGH to extend the validity of BG till 30.09.2017 with claim
period upto 30.11.2017.

NELP-VI Block RJ-ONN-2004/3:


Block relinquished w.e.f. 21.01.2012. Payment of Rs. 13,60,43,435/- has been made
towards differential cost of un-finished MWP of the Block.

NELP-VII Block RJ-ONN-2005/2:


2nd Extension of Phase-I:

DGH made a communication in connection with our proposal to relinquish the entire
Block. DGH has asked to submit the cost of unfinished MWP as per article 5.6 of PSC
immediately as well as original and copy of data to DGH. Bank Guarantees was
extended by one year for completion of Minimum work Programme in the Block.

As suggested by Director (E&D), a review study was carried out on relinquished areas
of this block. Out of the eleven prospects identified in-house as well as by consultancy
services, two prospects are at much deeper depth than MWP well depths. Moreover,
these new prospect horizons were not visible by old seismic data. Out of these eleven
locations five locations were released by competent authority and out of these two
locations have been drilled by the consortium. The deeper new prospect identified
based on the last 3D seismic survey could not be probed by exploratory drilling as JV
partners did not agree due to higher financial involvement for deeper target depth in
comparison to MWP well Target and additional payment of 30% LD for the third
extension requiring to complete the drilling of the well . There were also some
concern about the reservoir type due to virgin nature of these prospects . However,
subsequent G&G review indicates possible presence of carbonate reservoir at this
depth.

MINING LEASE AREAS:

a. 210 SQ KM ML AREA (BAGHEWALA BLOCK):

3
ML is Valid up to 29.05.2023. Yearly Dead Rent was deposited for period 30.05.2016
to 29.05.2017 .

b. 250 SQ KM ML AREA (JAISALMER BLOCK):


ML is valid up to 31.12.2035. Yearly Dead Rent was deposited for period 01.01.2017 to
31.12.2017.

3.0 BRIEF FINANCIAL SUMMARY:

3.0.1 Revenues Generated:

4
3.0.2 Contribution to Exchequer:

4.1 Budget Performance

 Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/
commitment have been made against ₹ 5,47,15,220.00.

4.2 Austerity Measures introduced:

 The overtime in office jobs is reduced to almost zero.


 The visits to the fields by different officials are clubbed to the extent possible.

 With proper monitoring, control and clubbing of open tenders we could saved INR
23.44 Lakhs in the current financial year. The advertisement cost per tender is
reduced from last year’s cost of INR 3.35 Lakhs to INR 1.96 Lakhs.

 Completed three numbers of drilling wells and one Water Disposal Well in the
stipulated time period.
 Faster ILM in case of both drilling & work-over wells than the stipulated time-frame
as per the provision of the Contract thereby increasing Rig utilization time leading to
overall improvement of performance.
 Optimum utilization of bit life in order to reduce quantity of drill bit consumption vis-
à-vis number of bit trips in a well.
 Use of integrated cementing set-up attached to Work-over Rig for cement
plug/squeeze jobs in almost all the work-over wells.

------------ xx ------------

5
6
5.0 PRODUCTION

5.1.0 Introduction

Year 2016-2017 had been a better year for Team Production (RP) from the point of
view of sale of natural gas produced from Dandewala(DND) and Bagitibba gas fields
as well as the progress made towards heavy oil exploitation in comparison to
previous year. Against the revised targets (RE) of 211.00 MMSCUM and 209.00
MMSCUM of gas production and sales respectively, the achievements were
232.019MMSCUM(109.96%) and 227.071MMSCUM(108.65%) respectively.

5.2.0 Targets & achievements (NATURAL GAS):

5.2.1 Details of Annual Targets & Achievement for the year 2016-2017 of
Production Department are given below:

Target Achievement % of achievement


(RE)
Gas Production 211 232.019 109.96
(MMSCUM)
Gas Sale 209 227.071 108.65
(MMSCUM)

Frequent problems at RRVUNL’s turbines were reported during the year for
which gas supply had to be either curtailed or stopped completely making it not
possible to meet the budgeted target (BE) production of 240 MMSCUM though
production capability was in hand.

5.2.2 A total quantum of 219.410 Kls of condensate was produced (+70 kls
carried over from previous year) and 240.00 Kls were sold to the customer
during the year and another 32.00 kls was utilized at Baghewala– 5 &
Bikampur#1 for chemical stimulation.

5.3.0 Gas production and sales, operation and maintenance of Production


Installation, gas wells:

Gas production and supply targets were planned as per the MOU with GAIL that the
customer would lift gas @ 0.7 MMSCUMD during the year. However, due to various
problems of the turbines of end user M/S. RRVUNL, gas production rate had to be
curtailed as per actual gas off-take by the customer. A total of 5740 hours of turbine
shut- down occurred during the year. As a result the production & supply of NG were

7
marginally below the annual targets (BE). However , the average daily production was
@ 0.64 MMSCUMD against that of @ 0.56 MMSCUMD in the previous year (2015-16) .

5.3.1 Wells on production during the year 2106-17:


Dandewala Field : 19 Nos.
Bagitibba Field : 2 No.

CTU/NPU Deployment: A well activation contract was awarded to M/s. SES


Energy Services India Pvt Ltd, Mumbai to hire well activation and well testing
services on call out basis for 2 years period w.e.f. 18.02.2015 to 17.02.2017, which
was further extended by three months. The CTU/NPU was deployed in all
workover wells completed with permanent packer (DND#4, DND#6, DND#9,
DND#11, DND#14, DND#19, DND#24, DND#25, DND#26, DND#27, DND#28 &
BGT#1) . Loc RBAS(Well Bikampur–1) in Baghewala PML was also activated using
the hired CTU/NPU unit from the contractor.
Workover was also carried out at BGW#5 and hired CTU/NPU was deployed to
activate the well.
5.3.2 Operation & Maintenance of DND-GPC:

The present gas handling capacity of the DND-GPC is 1.0 MMSCUMD. The plant
is on continuous operation since 1996. Due to ingress of formation water in
the produced fluid and continued operation of the plant, maintaining the
equipments to its capacity has been a challenging job.

The overall operation and maintenance of the plant was carried out
satisfactorily during the FY 2016-17.

5.3.3 Work-Over Operations:

Increase in water production and build up of annulus pressure in some of the


wells is a matter of serious concern. Few wells are in production through N-80
tubing which is not desirable in CO2 environment. Hence, it was planned to
carry out workover of 19 identified wells during FY 2015-16 & 2016-17.
Three (3) wells (DND#6, DND#11 & BGT#1) ) having water ingress and four
(4) wells (DND#4, DND#9, DND#14, DND#19)having annulus pressure
buildup were undertaken for workover operation. Also five (5) new wells
previously drilled (DND#24, DND#25, DND#26, DND#27, DND#28) were
undertaken for workover for production testing. In total, workover was carried out
successfully in twelve (12) nos of gas wells of Jaisalmer PML of Rajasthan and one
(1) heavy oil well (BGW#5) of Baghewala during the year.

5.3.4 Drilling and Field Development:


8
It was proposed to drill five wells in Dandewala field to sustain the gas
production potential from the Jaisalmer Basin. Two development wells
namely, DND#24(Loc.RJBH) & DND#25 (Loc. RJBJ) were completed
successfully in 2015-16. The production testing of these wells was carried out
with workover outfit in the year 2016-17. Drilling of DND#26(Loc. RJBI) was
completed in 2016-17 along with DND#27 & DND#28. Production testing for
these wells was also carried out during this period. Moreover a water disposal
well(WDW) was also drilled during this period for disposal of effluent water.

The contract for laying SS flow lines for these wells is already in place and job
is under progress. Already work is completed for BGT#1 and the well is
flowing through the new layed line .

5.3.5 Production & Disposal of Formation Water:

Total quantity of Formation Water Produced: 35253.39 Kls.


Total quantity of Formation Water stored in evaporation pit: 35253.39 Kls.
The produced formation water is stored in a concrete evaporation Pit near
adjacent to the plant.

5.4.0 Heavy Oil Production/Exploitation :

5.4.1 New well completion:

In the year 2016-17, drilling of one well Loc RBAS (Bikampur-1) was
completed and production testing is presently under progress.

5.4.2 Exploitation of heavy oil from BGW # 1, BGW#4 & BGW#5


At BGW#4, a surface unit of SRP was installed (shifted from Punam#1) for
artificial lift and experimental production started in the month of November,
2016 after installation of a reducer gear box.

After workover operation at BGW#1 in the year 2015-16, the well was bought
into production with the help of artificial lift (SRP). The surface unit was
received from field Headquaters, Duliajan and installed in the month of
December, 2016 and experimental production was started after installation of
a reducer gear box.
Workover operation was carried out at BGW#5 in January, 2017 and a hired
unit of SRP was installed to bring the the well into production. Experimental
production from the well started since the month of February, 2017. The
details of the production of heavy oil from the wells are as under :

9
WELL NO PRODUCTION (BBLS) PRODUCTION (Kls)
BGW#1 672.00 112.0
BGW#4 1097.3 183.0
BGW#5 36 6.0

Out of the total production, we have dispatched 249.2 bbls of heavy oil to M/s
ONGCL, Mehsana through hired bowser services.

5.4.3 Exploitation of Heavy oil from Baghewala Field:


Based on the results of the experimentation, it was decided to drill one no of
vertical well and one no of horizontal well as pilot wells at Baghewala field. As
a part of the project it was decided to hire consultancy services having
adequate knowledge and past experience in the field of Heavy Oil production.
Accordingly, a contract was awarded to M/s. Belgrave Oil and Gas Corporation
(BOGC) from Canada. A final report was submitted by the consultant and the
same is under review at present.
A timeline has been prepared for the pilot project and accordingly various
services and material procurement have been either initiated or completed.
We intend to use Progressive Cavity Pump & Electric Down Hole Heater in the
proposed horizontal well for which procurement process is almost complete.
Necessary actions have also been initiated for revival and relocation of the
boilers at Baghewala for hot production from the proposed wells.

5.5.0 Instrumentation:

Major Activities:

1. Maintenance & calibration of all field instruments of DND-GPC carried out as


per schedule.
2. Calibration of Portable Explosive Gas Detectors of Production installations
under Rajasthan Project carried out as per schedule.
3. Preventive Maintenance of SCADA (Supervisory Control & Data Acquisition)
system of DND-GPC, TOT-GGS, TVC & Jodhpur consisting of Remote Terminal
Units (RTU), Engineering Stations, Operator Display Stations, Servers carried
out by M/s Yokogawa India Limited as per AMC . A new Annual Maintenance
Contract for SCADA system for another 3 years was put into force with M/s
Yokogawa w.e.f. 01.10.2016.
4. Joint calibration of the field instruments of Custody Transfer carried out with
GAIL (India) Ltd. as per calibration schedule.
5. One no. of Turbine Flowmeter for Condensate Sale measurement of DND-GPC
calibrated at NABL accredited Laboratory.
6. Two nos. of Turbine Flowmeter of Gas Custody Transfer calibrated at NABL
accredited Calibration Laboratory in presence of GAIL’s representative as per
provision under Gas Sale Agreement with GAIL (India) Ltd.

10
7. Validation & Preventive Maintenance of two nos. of Flow Computer of Gas
Custody Transfer carried out on 16.11.2016 in presence of GAIL (India)
Limited.
8. All the Master Test Equipments including Sound Level Meter of DND-GPC
calibrated at M/s EQDC, Vadodara (NABL accredited Calibration Laboratory).
9. New Online Dew Point Transmitter (Make: GE) installed & commissioned
successfully by using the existing sampling system of old Dew Point Meter. The
same is hooked up with SCADA system.
10. Reboiler Burner Management System was successfully hooked up with SCADA
system for monitoring & operation of the boiler remotely from SCADA.
11. Implementation of Security Access Control System for OIL House.
12. Actions taken to revive the boilers & ancillaries at Baghewala for proposed
pilot project towards exploitation of Heavy Oil.

5.6.0 Mines Safety Week Celebration :

30th Mines Safety Week 2017 was organised by Ajmer Zone of Directorate General of
Mines Safety from 19th to 24th Dec, 2016 with the final day function at Jodhpur, on
13.01.2017. Installation, DND GPC won various prizes in the categories as mentioned
below:

Installation Prize Category


DND-GPC First Fire Fighting Drill
DND-GPC First Statutory records
keeping
DND-GPC Third Overall performance

5.7.0 Promotions & Transfers:

SL. No. Item Description Number


1 Promotion 1
2 Transferred from RP 1
3 Transferred to RP 2

5.8.0 Conservation of Energy:

1. Production department has achieved success in the field of energy conservation by adopting
measures like reducing vehicle movements, using energy efficient lights, maintaining solar
lighting system etc. in the field which resulted in saving of considerable amount of HSD.
During the year under review the consumption of HSD is as follows:

11
Sl.No Location HSD Consumed
(Liters)
1 TVC 20989
2 DND – GPC 12447
3 RANAO WATER POINT 10485
4 WELL LOGGING 9470
Total 53391

2. Two numbers of acoustic Gen sets has been ordered to replace the existing ones to
reduce diesel consumption.
3. Gas flaring has been reduced as compared to last year.
4. Consumption of HSD has come down as compared to previous year.

5.9.0 Cost saving measures:

1. All out efforts were made to control operational cost by taking timely action on
maintaining production equipments.
2. In spite of having shortage of manpower in the department, all jobs were
carried out within the optimum period, thereby reducing the downtime,
overtime etc.
3. Consumption of HSD for running generator-set etc was maintained within the
stipulated limit and there was considerable reduction in consumption of HSD
with availability of RSEB power to DND GPC. During the year under review a
total of 53391 Liters of HSD has been consumed. Moreover installation of two
numbers of acoustic Gen sets are in progress to replace the existing ones and
likely to reduce diesel consumption substantially.
4. Gas Flaring was kept at bare minimum level. The NG flared during the year
under review is 0.470353 MMSCUM.

5.10.0 Safety Audits:

1. During the year under review, Safety audits like Internal Safety Audits & Fire
safety audits were carried out. Inspection team nominated by Directorate General
of Mines Safety Ajmer region inspected Production Mines on 24.12.2016. External
Safety Audits of DND – GPC installations by DDMS (Mechanical) was carried out in
the month of March-2017. Besides the above Safety Audits, regular inspection of
the installations helped in improvement of the safety standards. Regular mock fire
drill in every month is conducted at DND GPC.

5.11.0 HSE policy Implementations:


12
Systematic effort to generate a general awareness to Safety is the best tool to achieve
outstanding HSE performance. With this in mind, the department has initiated actions
at the grass root level to develop safety awareness on the entire spectrum of people
in the department. In pursuance towards this we went beyond compliance with
existing regulation to meet or exceed accepted good practice in health, safety and
environmental management. Some notable actions initiated for the compliance are
mentioned below:

 Prepared bridging document with service provider of DND GPC where


responsibilities demarcated without any ambiguity.
 Monthly safety committee meeting held where contract employees were
encouraged to raise issues related to safety.
 Mock fire drills conducted even in odd hours.
 Tool box meetings conducted regularly.
 Communication facilities provided at the processing area so that instructions can
be passed down to operator from control room as and when required without any
time loss.
 Walkie-talkies provided to operators to communicate with field personnel.
 Near miss reporting encouraged.
 Workmen inspector was appointed to visit the field frequently and reports back
safety related issues.
 All records maintained in the desired formats
 Testing of all surface equipments along with SRVS carried out

 Emergency Response: The Disaster Management Plan & Contingency plan of


Dandewala- GPC, Pipelines & Drilling Rig of Oil India Limited was updated during
the current year. QRA & ERDMP for DND-GPC as per ERDMP regulations 2010 by
PNGRB is under preparation.

 During the current year the mutual aid scheme agreement for firefighting aid
between M/s. Oil India Limited, Jodhpur & M/s. ONGCL, Jodhpur was renewed for a
period of five years.

5.12.0 Man-Power:

In spite of serious shortage of executive manpower in the department, all out efforts
were made to complete all planned activities within the stipulated time. Followings
are the details of manpower in the department during the year under review.

Executives Qty. Break-up


Production 7 L-3/4: 1 and L-1:6
Instrumentation 2 L-1:2 (One new executive trainee joined on

13
20.02.2017)
Workmen 14

5.13.0 Training & Seminars:

In-House In Country Abroad


Executives 3 2 NIL
Workmen NIL 2 NIL
5.14.0 Transfers & Superannuation:

1. An executive in L1 was transferred and replaced by another executive.


2. An Executive Trainee has joined Instrumentation dept.
3. An employee is transferred to another dept. within the Project.

**********************************************************************************

14
6.0 GEOSCIENCE DEPT:

6.1.0 Jaisalmer Mining Lease (250 Sq. Km) & Baghewala Mining Lease (210 Sq.
Km )

a) Gas field Maintenance and Monitoring: The cumulative gas production in the year 2016-
17 from three gas fields (viz Tanot, Dandewala & Bagitibba) was 232.019 MMSCM with an
average gas production rate of 0.64 MMSCMD during the year. The cumulative condensate
production in the year 2016-17 from Dandewala, Bagitibba & Tanot fields was 219.410 KLs
along with cumulative water production of around 35253.390 KLs. Well-wise, reservoir-wise
gas, condensate and water production rates were maintained regularly in the data base.
Pressure-production plots of each pool was prepared and maintained. The performance of all gas
pools of different field were regularly monitored to ensure optimum production from each
well/pool.

b) Workover Operations: Oil India Limited engaged a 500 HP Mobile Workover Rig from M/s
GTC, Ahmedabad to carry out workover operations since 06.02.2015. On completion of the
contracted period, the rig was de-hired on 05.02.2017 after completing a total of 28 number of
workover jobs. During the FY 2016-17, a total of thirteen numbers of workover jobs have been
completed in thirteen wells in Jaisalmer PML and Baghewala PML, resulting in a gas production
potential gain of 0.18 MMSCMD. As on 31.03.2017, available production potential of the gas
fields is estimated at 0.95 MMSCMD post workover & drilling operations. Selection of well,
issuing & finalization of workover program, monitoring the operation and course correction
during the job execution etc were carried out in the following wells.
Srl. Well No. Start date Completion date
1 DND-14 20/03/2016 01/05/2016
2 DND-19 01/05/2016 18/06/2016
3 DND-11 18/06/2016 15/07/2016
4 DND-9 15/07/2016 14/08/2016
5 DND-8 14/08/2016 30/08/2016
6 DND-25 30/08/2016 09/09/2016
7 DND-24 09/09/2016 04/10/2016
8 DND-22 04/10/2016 18/11/2016
9 DND-26 18/11/2016 04/12/2016
10 DND-4 04/12/2016 23/12/2016
11 BGT-1 23/12/2016 13/01/2017
12 DND-6 13/01/2017 21/01/2017
13 BGW-5 21/01/2017 05/02/2017

c) Wire-Line Logging:

i) Logging Operations: The well logging operation of Rajasthan Project has been monitored
by Geoscience Department. Well Logging section in Geoscience Department provides all the
essential wire-line logging services of Rajasthan Project except advance services like CAST
and RMT were provided by the Contractor, HLSA . Due to non-availability of the advance tool,
CAST and RMT Jobs were done by HLSA using in-house Logging unit with their personnel.
Apart from field job monitoring, crew movement, explosives requirement/storage, WL Truck
related documents preparation etc. were also executed by Geoscience Department.

15
During the Financial Year 2016-17 total number of 198 logging jobs were done. Out of this 182
jobs were done by Well Logging Section and remaining 16 no of jobs were done by the
Contractor (HLSA) using in house Well Logging Unit.

The details of In-house Logging Operations is shown in detail below:


- Open –hole Services = 65 nos. (Fig-1)
- Cased –hole Services = 117 nos. (Fig-2)
ii) Well Log Interpretation: Log Interpretation is being regularly carried out using ULTRA
software by the FHQ, Interpretation team. The PETROSITE processing software is also used for
processing advance tools such as WSTT and XRM.

iii) Equipment Available: Following major equipment are available at the TVC workshop for
carrying out Logging jobs and maintenance of tools.

- Logging Unit – 01 no. with open hole and cased hole tools with accessories.
- Pressure control system for Through Tubing Operation = 01 set.
- LOGIQ Lab System = 01 no.

iv) Health, Safety & Environment: Use of highly hazardous materials like explosives and
radioactive source in our operation requires strict adherence to safety norms, which were
followed meticulously. Necessary measures for environmental protection and pollution control
with respect to radioactive sources and explosives were adopted and monitored strictly.

Necessary safety briefing were given to all the field going Executives and Employees on regular
basis. No untoward incident calling for immediate remedial action took place during this period.

16
FIG-1

FIG-2

d) Mud logging Unit : Mud logging jobs were carried out in Wells DND – 26, DND-27, DND28,
and BKM-1 with M/s Geologging India Limited . Mud logging contract with M/s Geologging
India Limited expired on 28/03/2017. For the new tender for Mud logging services, six (6)
offers received. Price bid opened on 27.03.2017. The L1 party is M/s. Cyratron Techmation
& Oilex syestem Ltd.

17
e) Drilling Locations:

i) DND-26 (Loc. RJBI): The well was spudded-in on 30.03.2016. The well was drilled
down to 2115.3 m and cemented 5.1/2" casing with shoe at 2105.37 m. The rig was
released on 10.05.2016 for ILM to next forward loc. WDW-1. The well testing was
carried out by deploying the workover outfit from M/s GTC from 17.11.2016 and
ended on 15.12.2016.

ii) WDW 1: The well was spudded-in on 20.05.2016 and drilled down to 1053 m and
cemented 5.1/2" casing with shoe at 1046.82 m. The rig was released on 06.06.2016.

iii) DND-27 (Loc. RJBG): The well was spudded-in on 20.06.2016. The well was
drilled down to 2131 m and cemented 5.1/2" casing with shoe at 2123.70 m. The rig
was released on 09.08.2016 for ILM to next forward loc. DND 28.

iv) DND-28 (Loc. RJBF): The well was spudded-in on 19.08.2016. The well was
drilled down to 2865m and cemented 5.1/2" casing with shoe at 2826.30 m. The rig
was released on 11.12.2016 for ILM to next forward loc. BKM 1.

v) BKM-1 (Loc. RBAS): The well was spudded-in on 26.12.2016. The well was
drilled down to 1278 m and cemented 5.1/2" casing with shoe at 1269.06 m. The rig
was released on 16.03.2017.

f) Environmental Clearance:

i)Jaisalmer PML: Consent to Establish (CTE) for the drilling of Six (6) wells in
Jaisalmer PML from RSPCB, Jaipur was received and Consent to operate (CTO) is yet
to be received.
ii)Baghewala PML: Consent to Establish (CTE) and Consent to operate (CTO) for the
drilling of Six (3) wells in Baghewala PML from RSPCB, Jaipur were received.

6.2.0 NELP IV BLOCK RJ-ONN-2002/1: As suggested by Director (E&D), a review study


was carried out on relinquished areas of this block. Few leads were identified within
the block during G&G review and it was planned to validate the leads with additional
seismic data before going for drilling . Accordingly, actions were initiated to carry out
API of 600 GLKM of seismic to reconfirm the structural position and size of the leads
and to upgrade to prospects but the same could not be carried out due to reason
already discussed vide OCR dated 18.12.2009. It is worthwhile to mention here that
one well (Nanuwala-1) drilled north of this block produced crude oil (API 30.33)
during testing. The leads identified in the block are in up-dip direction with respect to
Nanuwala-1 and fall in the same migration pathway. It is suggested to acquire 3D
seismic of around 1000 sq.km covering the identified leads. Alternatively 600 GLKM
2D seismic (2x2 KM grid) can be acquired covering identified leads which was
originally planned for the block. Based on the interpretation of suggested seismic data
drilling may be planned in future.

18
6.3.0 NELP-VI Block RJ-ONN-2004/2: A review study was carried out on relinquished
areas of this block. Earlier, a G&G review was carried out after heavy oil discovery in
Punam-1 well, one independent closure at Jodhpur Formation top level was identified
in the south of Punam structure. The said structure is structurally up dip in respect to
Punam structure and part of greater Baghewala-Punam structural high trend. One
location (Loc.C) was proposed in the structural closure, however, location was not
released and the structure could not be probed by exploratory drilling mainly due to
time limitation to fulfill the MWP work and subsequently the area had to be
relinquished (mandatory). As per G&G review to probe hydrocarbon prospects in the
independent structural closure south of Punam structure by drilling an exploratory
well, the same work program of drilling one exploratory well in the block is mooted
again. A request of retaining of about 10.2SQ.KM area covering the discovery area of
Block RJ-ONN-2004/2 for appraisal and Declaration of Commerciality (DOC) has been
submitted to DG, DGH. However, DG, DGH in the meeting regarding “Monitoring of
Nomination Blocks” indicated that OIL can avail the benefits of proposed OALP for
further exploration and production activity in the block.

PI Transfer:
The process of 25% PI transfer to OIL , the matter is still under arbitration process.
Next arbitration of hearing is expected in the month of May/June 2017. Received
communication from DGH to extend the validity of BG till 30.09.2017 with claim
period upto 30.11.2017.

6.4.0 NELP-VI Block RJ-ONN-2004/3:


Block relinquished w.e.f. 21.01.2012. Payment of Rs. 13,60,43,435/- has been made towards
differential cost of un-finished MWP of the Block.

6.5.0 NELP-VII Block RJ-ONN-2005/2:


2nd Extension of Phase-I:

DGH made a communication in connection with our proposal to relinquish the entire
Block. DGH has asked to submit the cost of unfinished MWP as per article 5.6 of PSC
immediately as well as original and copy of data to DGH. Bank Guarantees was
extended by one year for completion of Minimum work Programme in the Block.

As suggested by Director (E&D), a review study was carried out on relinquished areas
of this block. Out of the eleven prospects identified in-house as well as by consultancy
services, two prospects are at much deeper depth than MWP well depths. Moreover,
these new prospect horizons were not visible by old seismic data. Out of these eleven
locations five locations were released by competent authority and out of these two
locations have been drilled by the consortium. The deeper new prospect identified
based on the last 3D seismic survey could not be probed by exploratory drilling as JV
partners did not agree due to higher financial involvement for deeper target depth in
comparison to MWP well Target and additional payment of 30% LD for the third
extension requiring to complete the drilling of the well . There were also some

19
concern about the reservoir type due to virgin nature of these prospects . However,
subsequent G&G review indicates possible presence of carbonate reservoir at this
depth.

6.6.0 Publication of Notes/Reports:

REGN 64: Prospect Evaluation of Relinquished NELP Blocks in Rajasthan. By RS Ram & SS
Deb
Depth Data Drilling Policy (DDDP) & GTO of wells WDW 1, DND 27 (Loc. RJBG), DND
28( Loc. RJBF), BKM 1( Loc. RBAS)

Reserve Appraisal Note No. 50: A Report on Oil and Gas Reserves of Oil India Limited as
on 01.04.2016 (Assam, Arunachal Pradesh and Rajasthan). Co-author: S. Gupta

Potential Note No. 3: Well - Wise Details and Production Potential of Oil India Limited’s
fields in Rajasthan Project as on 01.04.2016. Author: S. Gupta.
RGON-129: Initial Well Testing Programme Of DND-25 (LOC. RJBJ)
RGON-130: Initial Well Testing Programme Of DND-24 (LOC. RJBH).
RGON-131: Initial Well Testing Programme Of DND-26 (LOC. RJBI).
RGON-132: Initial Well Testing Programme Of DND-28 (LOC. RJBF).
RGON-134: Initial Well Testing Programme of BKM-1(RBAS).

Sri S. Gupta, S E (Reservoir) presented a Paper and a Poster titled "Well Integrity
Diagnostics and Reservoir Monitoring in Ageing Completions to Arrest Decline in Gas
Production: Experience from Dandewala Gas Field, Rajasthan, India" in the 4th SPWLA-
India Symposium held in Mumbai.

6.7.0 Reserve Appraisal:

The estimation of Crude Oil, Natural Gas and Condensate Reserves of Oil India Limited in
its operational areas in Assam, Arunachal Pradesh and Rajasthan as on 01.04.2016 was
carried out in compliance with the SPE PRMS reserve definition and guidelines. The
estimation was jointly carried out by G&R Department, Duliajan and Geosciences
Department, Rajasthan Project in a time bound manner and a joint report for the same
titled “Reserves Appraisal Note (RAN) No. 50 was published.

Gas Position of Rajasthan Project as on 01.04.2016 as estimated vide Reserves Appraisal


Note (RAN) No. 50 is given below:

Gas Position of Rajasthan Project As On 01.04.2016


(All Figures in MMSCM)
Natural Gas
LE BE HE
Gas-Initially-in-place (GIIP) 7834 11350 16071
Estimated Ultimate Recovery (EUR) 5386 8425 12624
Remaining Producible Volume (RPV) 1909 4948 9148
20
The Field/structure wise heavy oil in-place contingent resources of Jodhpur Sandstone
formation as estimated vide Reserves Appraisal Note (RAN) No. 50 is given below:

Heavy Oil In-place Volume of Jodhpur Sandstone As On 01.04.2016


Contingent Resources (All Figures in MMT)
Field/Structures
1P 2P 3P
Baghewala 10.75 12.53 14.42
Tavriwala-2 0.79 1.01 1.26
Grand Total 11.54 13.54 15.68

The Annual estimation of Oil and Gas Reserves of Oil India Limited as on 01.04.2017 is
presently under progress . The report is being prepared jointly by G&R Department,
Duliajan and Geosciences Department, Rajasthan Project on ‘Oil and Gas Reserves of Oil
India Limited as on 01.04.2017 (Assam, Arunachal Pradesh and Rajasthan)’ and shall be
presented as Reserves Appraisal Note (RAN) No. 51.

6.8.0 Service Contract monitoring: Total six (06) numbers of service contracts have been
initiated, executed and monitored by the department.

6.9.0 Unconventional Hydrocarbon Exploration:

i) Coal Bed Methane gas exploration: Collection of data from different coal /lignite mines
in west Rajasthan area by visiting different active mines and findings were presented in a
geo-scientific note.

ii) Shale gas/oil exploration: Detail analysis of available data for shale gas potential
available in OIL's operational area of Rajasthan and findings were presented in a geo-
scientific note.

6.10.0 Jobs carried out in other sphere:


Wellsite Duty: Geoscientist from RP has performed well site duty in KG basin and Cauvery
basins for drilling operation.

6.11.0 Other Jobs: Preparation of Presentation for OC, MC and Review meeting for the NELP
blocks. Conduct OC/TC meetings for NELP blocks. Preparation of OC/MC minutes and
incorporation of JV partners view/comments and final submission to DGH/MoP&NG after
obtaining JV partners signature. Proposal for approval of LD, BG from competent authority
and subsequent correspondence with DGH/MoP&NG/JV partners. Preparation of Cash call
for payments and related quarries from JV pertaining to expenditure. Preparation of
presentations for VIPs /guests on OIL's activities and future planning etc were carried out
by Geoscience Department from time to time . Reply for numbers of Parliamentary
questions was also prepared by Geoscience Department . Additionally a number of
quarries from Auditors, CAG, Internal Audit, Directorate of Petroleum ; Govt. of Rajasthan,
DGH, MoP&NG and Ministry of Environment & Forest were also addressed by Geoscience
Department (RP) . In absence of separate Planning Department number of planning related
(ML license, ML/PEL fee advice, legal documentation with State Govt. etc) jobs were
carried out by Geoscience Department.

21
6.12.0 Manpower Position: Manpower position of Geoscience Department as on 31.03.2017 is
as follows:

Category Level/Grade Nos. Total


Level 4 1
Level 3 1
Executives: 9
Level 2 1
Level 1 6
EG Grade IV 3
EG Grade III 2
EG Grade II -
*Workmen: Grade VIII 2 11
Grade VII -
Grade V 2
Grade IV 2
Grand Total 20

Note: * 2 (Two) WCL’s are working in Geoscience Department in addition to the above.

6.13.0 Induction of New Technology: Land Mark Decision Space Software was installed for
Interpretation.

6.14.0 Training / Workshop:

Sr.
Name of Executive Course Title Period Venue
No.
Sh N. R Hazarika, GM- Senior Management IIM
1 7 – 12 Nov, 2016
Geoscience Program Bangalore
Sh N. R Hazarika, GM- Disha – A new journey 13 – 14 MTDC
2
Geoscience post retirement February, 2017 Duliajan
Sh. S.S. Deb
3 Petrotech Conference 4 – 7 Dec, 2016 New Delhi
DGM Geoscientist
Effective Interpersonal
Sh. Pankaj K Chetia
4 Skills for Team Building 11-12 July, 2016 Jodhpur
Suptg. Geologist
Development Program
Sh. Pankaj K Chetia Petrophysics for
5 17-19 Oct'16 New Delhi
Suptg. Geologist professions
Sh. Bhola Kumar, Sr. Effective Interpersonal
6 Engineer (Well Skills for Team Building 11-12 July, 2016 Jodhpur
Logging) Development Program

Sh. S Gupta, Suptg. Presented technical paper SPWLA,


7 11-12 Feb, 2017
Engineer (R) & poster. Mumbai

6.15.0 Cost Cutting & Energy Conservation: Completion of drilling well during the financial
year 2016-17 was done successfully. With an idea to achieve cost control it was decided to

22
carry out production testing in the drilling wells using workover outfit instead of the
drilling rig . Additionally, based on the current p roduction behavior and neighboring well
correlation, we were able to cut down drilling depths instead of drilling down to earlier
planned objective depths in one well which saved us drilling time as well as drilling cost of
the reduced metreage . All possible measures were adopted in the Department to cut down
cost and conserve energy consumption. Electrical appliances were used judiciously only
when required .

**********************************************************************************

23
7.0 CHEMICAL DEPTARTMENT:
Chemical Department continued to support Drilling as well as Production activity of
the Project by providing various services like Drilling Fluid Engineering , Laboratory
facilities and Reservoir Data Acquisition .

7.1 Targets and achievements and reason for shortfall, if any, along with remedial
measures adopted during the year.

Chemical Department (RP) carried out the following field and laboratory activities in
Rajasthan Project during the period April 2016 to March 2017. The department provided the
required services in fields as well as in the laboratory as per the job demand and apparently
there was no shortfall in achieving the various targets .
Field Activities:
a) Drilling fluid services were provided to 3 (Three) Development Wells viz.; Loc. RJBI
(DND#26), Loc. RJBG (DND#27) & Loc. RJBF (DND#28) and 1(one) water disposal
well viz. WDW#1 at Dandewala field with a cumulative drilling meterage of 8054m
for Development well . All the Development wells were completed without any
drilling fluid related problem .
b) Provided drilling fluid services to 1 (One) Exploratory Well viz.; Loc. RBAS
(Bikampur#1) at Bikaner Nagur Basin with a drilling meterage of 1278m . During
drilling of exploratory well, Loc. RBAS, severe loss circulation was encountered
throughout the drilling of isolation and oil string stage. However, the well was
completed successfully.
c) Total drilling meterage during the year vis-à-vis target was as follows:

Type of Well No. of Wells Target (m) Achievement (m)


Exploratory 01 1250 1278
Development 04 8000 8054
Total Cumulative drilling meterage 9332

d) Provided Work-over fluid services to 14 (Fourteen) no of jobs including


abandonment of one difficult well (DND#09). Except Loc. DND#19 (fishing problem),
all other Work-over wells were completed without any difficulties. Sodium format
solution was incorporated for all the Work-over wells as Packer fluid.
e) Designed cement formulations for the wells in association with M/s WEAFRI, Nigeria
and carried out the primary/secondary cementation jobs successfully using
cementing unit of M/s WEAFRI .
f) As a part of Gas Field Development Program and Heavy Oil Exploration Project, BHP
contract has been awarded to M/s Naithani Oil & Gas Services Pvt. Ltd.

24
Laboratory Activities:
a) Analysis of custody transfer composite gas samples from OIL’s DND-GPC were carried
out fortnightly for determination of composition and calorific value for billing to M/s
GAIL(India) Limited .
b) Analysis of natural gas samples from OIL’s Gas Processing Centre, Dandewala (DND-
GPC) and from different gas producing wells were carried out regularly for
monitoring gas composition and determination of calorific value.
c) Planning and procurement of various drilling fluid additives and work over fluid
additives continued as per requirement and phasing.
d) Total numbers of various samples analyzed in the laboratory during the year are:

Sl. No. Type of Sample No. of Sample analyzed


2016-17 2015-16
1 Natural Gas Sample 24 24
(Custody Transfer)
2 Natural Gas Sample 40 36
(Individual Well)
3 Crude Oil Sample 08 14
4 Tender Sample 22 0
5 Glycol Sample 72 38
6 Condensate Sample 12 8
7 Water Sample 134 40

e) Analyzed total 312 nos of samples, 97% more than the last FY 15-16 (total analyzed
sample 158 nos) .

7.2.0 Adoption of all state-of-the art technologies, innovations and performance of


excellence with resultant benefits attained there from.
a. The oil string stage drilling of Development well Loc. RJBF (well depth 2865m)
where bottom hole temperature was higher than anticipated (218 degF), was
carried out using 9.9 ppg KCl-polymer mud with proper mud parameters. The
oil string hole was true gauge throughout and and there was no problem
towards lowering oil string casing.
b. Designed and executed oil string cementation (thermal) with M/s Weafri at
Loc: RJBF (BHT: 218 F) successfully, though there was no provision of high
temperature cementing chemicals in the cementing contract.
c. Low density Bentonitic Cement slurry of controlled setting time was highly
successful in controlling mud loss at Loc. RBAS.
d. DND#14, one cement plug was placed in an unconventional way to repair 5 ½”
casing leakages and successfully set WF spool.
e. Incorporation of Sodium Format solution in Work Over wells as Packer fluid
which itself is a Corrosion Inhibitor and also environment friendly. It is likely
to resist Casing damage (Production Casing) by preventing Corrosion
especially for Gas Wells.
7.3.0 All outstanding achievements and records made, breakthroughs achieved and
milestone crossed.
25
A notable breakthrough was achieved during drilling of Loc. RBAS, where severe loss
circulation was encountered and well progress was very low for hole instability combined
with hole cleaning. A unique High Concentration Unswelled Bentonite (HCUB) pill was
developed and found to be highly successful in addressing hole instability and loss
circulation problem and the well could be completed successfully.

7.4.0 Cost saving measures adopted and cost saved in terms of money.
Strict and round-the-clock monitoring had helped in controlling cost in terms of
consumption of drilling fluid chemicals in drilling of the aforesaid wells . Minimized cost on
travel to fields by combining with Drilling/ Geological Personnel .

7.5.0 Energy conservation measures adopted and resultant saving in terms of energy
and money.
All possible measures were adopted in the department to contribute towards energy
consumption. All electrical appliances were used judiciously.

7.6.0 Environmental protection and pollution control measures adopted with


resultant benefits attained there from.
All drilling effluents were stored in HDPE lined effluent pit. No effluent was allowed
to flow out of effluent pits.

7.7.0 Other relevant points, viz. any significant seminars held, conferences
organized, awards won and recognitions received from any national or,
international bodies of repute.
None.

7.8.0 HR related issues: Manpower position, joining & separation, training,


promotions etc.
Manpower Position:
Manpower position of Chemical Department at RP as on 31.03.2017 is as follows:
Financial Year Position of No Position of No Total
Executive Employee Strength
in
Chemical
(RP)
2015-16 Level-1 02 EG Grade-IV 01
Level-2 01 EG Grade-II 01
Grade-SR 01
MP Grade-VII 01
MP Grade-VI 01
Sub Total 03 Sub Total 05 Total 08
2016-17 Level-1 02+02* EG Grade-IV 01
Level-2 01 EG Grdae-II 01
MP Grade-IX 01
MP Grade-VII 01
MP Grade-VII 01
26
Sub Total 03+02* Sub Total 05 Total 08

* Two (02) nos. of Contract Chemists were deployed on temporary basis from
01.04.2016 to 29.11.2016.

Training:
a) Sri Dhrubajyoti Bhuyan has attended “Effective Interpersonal Skills for Team Building
Development Program” at Jodhpur on 11.07.16 & 12.07.16.
b) Sri Dhrubajyoti Bhuyan has attended “General Management cum leadership Program
for Junior Level Executives of OIL” at ASCI, Hyderabad from 12.09.16 to 23.09.16.
c) Sri HK Barua has attended a training on “Leadership from Inside Out” at Noida on 13-
14 June, 2016.
Transfer/Joining:
a) Sri Bishnu Medhi, Suptdg. Chemist, S/code: 6072, transferred to Field Head Quarter
Duliajan on 10.05.2016.
b) Sri Dhrubajyoti Bhuyan, Senior Chemist, S/code: 200583 joined Rajasthan Project on
02.05.2016 after his transfer from Field Head Quarter.
Promotions:
a) Sri Subrata Kumar Biswas, S/code: 201249, promoted to Grade ‘C’ from Grade ‘B’
w.e.f. 01.01.2016.
b) Sri A. N. Asopa, OIL ID: 99469, promoted to Supervising Assistant (Grade-IX) w.e.f.
01.05.2016.
c) Sri. Dharmveer Singh, OIL ID: 109826, promoted to MP Grade-VII w.e.f 01.01.2017.

**********************************************************************************

27
8.0 TECHNICAL SERVICES DEPARTMENT:
During the year under review, different sections of TS department namely Civil, Electrical,
Mechanical, Fire & Environment, provided all the required technical support and services to drilling
and production activities of RP besides supporting/carrying out technical maintenance of OIL House,
Guest House and other installations.

In addition, TS was in charge of Renewable Energy, generation from two wind farms and three solar
plants. Some of the major jobs carried out during the year by the different sections of the department
are high-lighted below:

8.1.0 CIVIL ENGINEERING SECTION:

During the year 2016-17, Civil Engineering Section played a key role in drilling and
production processes, and other operations/ activities of Rajasthan Project by extending all
the required civil engineering support. Civil personnel , leading from the front , performed in-
house survey works and stacked location coordinates in the middle of sand dunes under hostile
weather conditions.

Despite difficulties such as defence related restrictions by BSF in Dandewala area or villagers’
obstructions in Bikampur area from time to time, the section could deliver locations on time for
drilling operations as per TDP of RP .

Necessary supports were provided for Work Over and other production related activities as and
when required by the user department.

OIL’s operational roads, close the international border region, were maintained perennially to
facilitate uninterrupted road connectivity to remote wells and installations, amidst the Thar desert.

General maintenance works at Wells, Installations, Stores, Office and Guest Houses were carried out
from time to time ..

Some of the jobs execute during the year are as follows:

Field Works (Drilling / Work-Over):


a) Preparation of drilling site for Loc. RJBG (100% completed)
b) Preparation of drilling site for Loc. RJBF (100% completed)
c) Preparation of drilling site for Loc. RBAS (100% completed)
d) Preparation of drilling site for Loc. RBAT(95% completed)
e) Extending necessary support for Work-Over operations in wells.
f) Maintenance of OIL’s operational road network in Tanot, DND & Baghewala field.
g) Re-casting of cellar foundation at DND-9.

Other Civil Jobs:

28
a) Construction of Boundary Wall at Hamira Godown including Security Room, Patrol Track,
drainage etc.
This 1.2km long wall was a long pending requirement of the Hamira Stores. The installation
had a porous fencing system since inception which made the godowns vulnerable with regard
to security aspects.
b) Construction of 2 Nos Toilet blocks, Main Gate and a Piao under CSR Scheme for Govt.
Model Hr. Sec. School, Village Raghwa, Ramgarh, Jaisalmer District.
This CSR project is in connection with the Renewal Energy Installations set up in Raghwa
village of Jaisalmer district. This project goes a long way in providing decent wash-room
facilities and drinking water to the boys and girls of the school. Also the construction of a
main gate has added beauty to the school . This also paves the way for maintaining goodwill
between OIL and the villagers of Raghwa.
c) Construction of Toilets, Resting Shed and underground 5KL tanks at locations BGW-1 and
BGW-4.
d) Construction of 36KL crude oil tank at location BGW-5
e) Day to day maintenance works of OIL House, Guest House & Clubs premises in Jodhpur.
f) Carrying out repairing and maintenance works at Hamira Stores, DND-GPC and Tanot.

8.2.0 ELECTRICAL / MECHANICAL ENGINEERING SECTION:

This section was involved in the operation, upkeep and maintenance of all electrical and mechanical
equipment at various field-installations, office, guest houses. Every attempt was made to ensure that
power supply remained uninterrupted and that all equipment like AC systems, pumps, DG sets, etc. in
various installations like DND GPC, TVC, OIL House, Ranau Water Point, Guest House, etc. functioned
normally. In case of power supply disruption from the state grid, prompt action was initiated to
restore supply either through rectification of faults or supply of power through stand-by generating
sets.

Major activities of electrical section:

 Carrying out electrical inspection during pre-spud racee at well sites.

 Making power available for SRP units through DG sets.

 Ensuring standby power availability at TVC, DND GPC, OIL House, Guest House.

 Procurement, installation and commissioning of 62.5 KVA rating acoustic DG set at Guest
House to replace the existing non-accoustic and ageing DG set .

 Procurement, installation and commissioning of 30 KVA rating acoustic DG set at Hamira


Stores to replace the existing ageing DG set .

 Installation of two numbers of high-mast lights (each high-mast consisting of 8 x 2 x 400


watts =6.4KW lights) at Hamira Stores to provide adequate area-lighting and improve
security aspects.

29
 Twelve numbers of new-generation split-type air conditioners installed at Guest House as
replacement of old ACs and two numbers were also installed at Hamira Stores Office as
replacement .

 In order to provide adequate cooling in the open space meant for staff seating area within
OIL House premises during the peak summer months when temperatures shoot up to around
50 degree centigrade, additional air conditioning using 80 TR VRV units were installed and
commissioned during the year .

 The registration of the Well Logging truck was transferred from Assam to Rajasthan. This
long pending initiative will result in yearly savings of additional road taxes , besides meeting
statutory requirements.

 Maintenance of electrical equipment like motors, alternators, electrical panels at various


field-installations, offices, guest house, etc.

 Budgeting and procurement activities to meet requirement of electrical equipment for


drilling, production processes and also for office/guest house installations.

8.3.0 RENEWABLE ENERGY:

 Renewable Energy Projects : There are five existing Renewable Energy Projects , as under:

1. 13.6 MW Wind Power Plant at Ludharva near Jaisalmer : The plant comprising of 16
Wind turbines @ 850 KW each was installed & commissioned on 31.03.2012.
2. 54 MW Wind Power Plant at Dangri : The plant comprising of 27 Wind turbines @
2.0 MW each was installed & commissioned on 30.03.2013.

3. 100KW Solar Power Plant at Tanot : The plant comprising of 416 SPV Poly
Crystalline Modules @ 230 W each and electrical energy generated from the plant is
directly connected to Tanot Village Complex for captive use. The plant was
commissioned on 15.03.2013.

4. 5 MW Solar Photovoltaic Power Plant at Ramgarh : The plant, with generation from
solar SPV Poly Crystalline Modules was commissioned on 23.01.2014 and the
electrical energy generated from the plant is evacuated through a transmission line to
nearby Ramgarh GSS and fed into the state grid system.

5. 9 MW Solar Photovoltaic Power Plant at Ramgarh : The plant, with generation from
solar SPV Poly Crystalline Modules was commissioned on 25.02.2016 and the
electrical energy generated from the plant is evacuated through a transmission line to
nearby Ramgarh GSS and fed into the state grid system.

RENEWABLE ENERGY TARGETED/ESTIMATED ACTUAL REMARKS


PLANT GENERATION FOR GENERATION
2016-17 FOR 2016-17

30
1 13.6 MW Wind Power 2,72,33,463 KWh 1,99,83,915 73.38 % of
Plant at Ludharwa KWh Estimated
Generation

2 54 MW Wind Power 10,97,02,964 KWh 7,69,23,718 70.12 % of


Plant at Dangri KWh Estimated
Generation

3 5 MW Solar Power 89,15,346 KWh 91,32,880 102.44 % of


Plant at Ramgarh KWh targeted
generation

4 9 MW Solar Power 1,49,60,522 KWh 1,64,58,070 110.01 % of


Plant at Ramgarh KWh targeted
generation

 REVENUE DETAILS FROM RE-PROJECTS: Revenue from the following RE Projects (except
100 KW Solar, which is for captive use) connected to the Grid Sub-Stations has generated
substantial revenue under the provisions of Power Purchase Agreement(PPA) and other
incentives. Revenue generation during the year 2016-17 by these projects is given below
along with revenue figures for the year 2015-16 :

Revenue in Crores Revenue in Crores


Sl
Project name of Rupees for the of Rupees for the
No
year 2016-17 year 2015-16

13.6 MW Wind Power As per PPA


1 8.83 8.07
Plant at Ludharva rate
As per PPA
54 MW Wind Power Plant 39.33 34.79
2 rate
at Dangri
GBI 3.70 3.36
As per PPA
2.92 3.40
5 MW Solar Power Plant at rate
3
Ramgarh
REC sale 2.14 1.83

As per PPA
9 MW Solar Power Plant at 5.30 0.4571
4 rate
Ramgarh
REC Sale 0.19 --

Total Revenue 62.41 51.9

Status of Renewable Energy Certificates (RECs) as on 31st March 2017:

In addition to the revenue earned from the state discoms through sale of power from OIL’s
solar plants , Renewable Energy Certificates, (RECs) are also issued to OIL at the rate of 01
REC for every 1000 KWh of power injected into the state grid. The RECs are

31
traded/redeemed in the Power Exchanges at the rate of INR 3,500.00 per REC for earning
additional revenue .

RECs from 5 MW Plant

Total RECs issued since commissioning of plant 64,441 Nos.

Total number of RECs traded/redeemed as on 12,445 Nos.


31.03.2017

Balance RECs 51,996 Nos.

RECs from 9 MW Plant

Total RECs issued since commissioning of plant 9,594 Nos.

Total number of RECs traded/redeemed as on 548 Nos.


31.03.2017

Balance RECs 9,046 Nos.

8.4.0 FIRE and SAFETY

During the year, Fire Safety & Environment section of Rajasthan Project took all measures to
ensure the highest levels of safety in our installations, operations and practices. There was
monitoring of Occupational Health of the work persons exposed to Occupational Health
Hazards , monitored & promoted clean environment at Rajasthan Project . Proactive
approach was taken in HSE related issues for effective implementation of company’s HSE
policies and guidelines. We strive for continuous development of the communities in which
we operate.

Following are the achievements of the section in brief for the year under review :

8.4.1 SAFETY

During the year under review, the section continuously worked and has steadily taken some
strategic steps for improving the safety standards in the company and for the benefit of all.

32
Good standards of Safety for the people and processes have been established and maintained
at Rajasthan Project. There was no Mining Accident (Zero Accident) reported at Rajasthan
project during the year 2016-17.

A total of 05 no. near misses were reported at DND-GPC and preventive measures were taken
immediately to avoid the re-occurrence.

(a) Safety Audits

During the year under review, Safety Audits of Drilling Rig and DND – GPC were carried out.
Inspection team nominated by Directorate General of Mines Safety Ajmer region inspected
the Drilling & Production Mines on 16.04.2016 & 24.12.2016. Dy. Director Mines Safety
(Mech) inspected Production Mine on 24.03.2017.

Besides the above inspections, regular audits of the installations have also helped in
improvement of overall safety standards at Rajasthan Project.

(b) Statutory and other reporting

The following Statutory and other reports were compiled and sent:

I. Mines Annual Report to DGMS.


II. OISD Quarterly ESA status.
III. Weekly HSE reports.

(c) Mines Safety Week

Mines Safety Week was observed at Rajasthan Project from 19th to 24th December 2016
under the aegis of “Director of Mines Safety, Ajmer Region” along with other mines of Ajmer region.

As a part of safety week celebration, safety slogan, safety poem & safety poster competitions were
organized among the OIL employees / executives & their children at Rajasthan Project. Few numbers
of safety drawings of our children were selected for publication in the Mines Safety Calendar. Trade
Test examination for employees of Oil Mines in connection with 30th Mines Safety Week Celebration
– 2016 was conducted at Oil India Limited, Jodhpur on 30.11.2016 for the following categories:

1. Knowledge of Operation
2. Knowledge of Maintenance
3. Conscious worker
Trade test competitions were held among participants from M/s. ONGCL, M/s. Cairn India & M/s. Oil
India Limited.

Fire Drill Competition: As a part of Mines Safety week, for the first time Fire Fighting Drill
competition was organized at DND-GPC on 06.12.2016 amongst the fire fighting teams of M/s.
ONGCL Gamnewala, M/s. NLC India Ltd, Barsinagar Project, M/s. Focus Energy, Jaisalmer & M/s. Oil
India Limited DND-GPC.

OIL (Rajasthan Project) bagged the following eight prizes in the 30th Mines Safety Week
2016, organised by M/s. FCI Aravali Gypsum and Minerals India limited, Jodhpur, under the aegis of

33
Director of Mines Safety, Ajmer region.

Installation Prize Category


1 Production DND-GPC First Fire Fighting Drill
2 Production DND-GPC First Statutory records keeping
3 Production DND-GPC Third Overall performance
Electrical equipment, lighting and
4 Workover Rig (GTC 100-03) First wiring.
5 Workover Rig (GTC 100-03) First Safety features & Records
6 Workover Rig (GTC 100-03) First Overall performance
Publicity propaganda and house
7 Workover Rig (GTC 100-03) Second keeping
8 Workover Rig (GTC 100-03) Second Drilling & Maintenance

The prizes were distributed during the concluding function held at Jodhpur on 13.01.2017.

(d) Emergency Response:

The Disaster Management Plan & Contingency Plan of Dandewala- GPC, Pipelines & Drilling
Rig of Oil India Limited was updated during the current year. QRA & ERDMP for DND-GPC as per
ERDMP regulations 2010 by PNGRB is under preparation.

During the current year the mutual aid scheme agreement for firefighting aid between M/s.
Oil India Limited, Jodhpur & M/s. ONGCL, Jodhpur was renewed for a period of five years.

8.4.2 ENVIRONMENT

Through regular monitoring and proper co-ordination, the Safety & Environment section could
successfully abate the pollution problems arising out of the Company’s various operational
activities during the year 2016-2017. Periodical jobs like obtaining Consents from statutory
authorities and all time bound information were furnished to the State Pollution Control Board
regularly.

During the year, Oil India Limited, Rajasthan Project has been accorded Environmental Clearance
(EC) from Ministry of Environment and Forest, for drilling 20 Developmental wells at Baghewalla
PML , District Jaisalmer . Consent to Establish (CTE) was granted for Drilling Locations RJBH, RJBI,
RJBJ, RJBG, RJBF, WDW, RBAS, RBAU & RBAT by Rajasthan State Pollution control Board.

No public pollution complaints were received during the current financial year.

“World Environment Day” on 5th June was organized at Rajasthan Project in a befitting manner to
pass the message of Environmental Protection amongst employees and the public as well.

34
8.4.3 FIRE SERVICE

During financial year 2016-17, following are the details of the major activities of fire service
at Rajasthan Project:

a) No. of personnel attending First-aid fire fighting training = 281

b) No. of Fire Mock Drill Conducted =15

c) Fire Extinguisher Inspection = 392

d) Fire Call Reported = Nil

e) Fire Service Stand by = 42

Fire Service Week was observed at Rajasthan Project from 14th to 20th of April, 2016.

New fire extinguishers of Dry Chemical Powder of 25 kg, 50 kg & 75 Kg capacity have been
procured for Rajasthan project.

8.4.3 SAKSHAM - 2017

Pursuant to the directive of Ministry of Petroleum and Natural Gas, Govt. of India, Oil India
Limited, Rajasthan Project observed Oil and Gas Conservation, mass awareness campaign
‘SAKSHAM-2017’ from 16th January 2017 – 15th February 2017 with various plans and programs.

The campaign was to sensitize the masses about the conservation and efficient use of
petroleum products towards achieving twin objectives of better health & environment and securing
availability of oil & gas for future generations.

The inaugural function of this campaign was held at OIL House, DND-GPC & Loc RBAS, Baghewala
on 16th January 2017 with taking of the “Oil & Gas Conservation Pledge” and formation of Human
chain as well as Save oil & gas march. An Auto Emission (PUC) Check up camp for vehicles was
organised on 25.01.2017. A publicity van was sent to nearby villages on 03.02.2017 for distribution
of leaflets, booklets & posters carrying the message of oil and gas conservation. Renewable
appliances such as solar heater & solar panel were also exhibited in front of OIL House on
07.02.2017. Drawing & essay competitions for school children wére conducted at RSM International
School on 08.02.2017 to spread awareness among school children on oil & gas conservation.
Concluding function comprising of Open Quiz Competition was held on 15.02.2017 at OIL House
Auditorium.
.

8.5.0 COST & ENERGY SAVING MEASURES, ENVIRONMENT PROTECTION AND NEW
TECHNOLOGY ADOPTION:

8.5.1 Cost Saving Measures:


 Combined contracts for construction of multiple Drilling Locations were prepared with
the help of Contracts Section which saved tangible tendering fees as well as intangible
time and man-days of the company.
35
 Surveys were conducted with the help of GPS coordinates and real-time Google map
images requiring minimal manpower and time.
8.5.2 Energy Conservation Measures:
 Autoclaved Aerated Concrete (AAC) Blocks are used in TVC Extension building at
Tanot. AAC Blocks are highly insulating material which would substantially save
electricity in running ACs during summer scorching heat of Tanot.
 High efficiency, low power consumption ACS of 5 Star ratings were installed at Guest
House to lower power consumption.
8.5.3 Environment Protection and Pollution Control Measures:
 Replacement of non-accoustic DG sets with eco-friendly (noise and emission) DG sets at Guest
House and Hamira Stores.
 ACs with eco-friendly gas were installed at Guest House, Hamira Stores and OIL House.
 AAC Blocks used in TVC Extension building are eco-friendly building material recommended
by IGBC (Indian Green Building Council) / GRIHA (Green Rating for Integrated Habitat
Assessment). This material makes use of fly ash which is an industrial waste. Moreover, it has
lesser Embodied Energy, which means it requires less energy in process of its manufacturing
in comparison to conventional bricks.
8.6.0 New Technologies:
 CAD (Computer Aided Design) software including AutoCAD and Sketchup are extensively
used for designing, planning and executions.
 Surveys are conducted based on GPS coordinates and real-time Google map images.

**********************************************************************************

36
9.0 DRILLING DEPARTMENT:

9.1 Target and Achievement (Drilling & Work-over Activities):

Type of Target Achievement Percentage


Well (m) (m) (%)
Exploratory 1250 1278 100.24
Development 8000 8054 100.67
Overall 9250 9332 100.88

 Development wells drilled in the financial year 2016-2017 are Loc: RJBI (DND#26),
Loc: WDW#1, Loc: RJBG (DND#27) and Loc: RJBF (DND#28) in Jaisalmer PML area of
Jaisalmer basin. The development well RJBF was drilled down to 2865 m with
conventional coring in (2555 m – 2575 m ); (2680 m-2698 m);( 2698 m- 2717 m) &
(2738 m – 2750 m) in stages, Also Side Wall Coring was taken in this well from
2780.5 m – 2512 m.
 Exploratory well RBAS (Bikampur #1) drilled in the financial year 2016-2017 in
Baghewala PML area of Bikaner Nagur basin. The well (Loc: RBAS) was spudded on
26.12.2016 and at the end on the F.Y. the well was drilled down to 1278 m. Total mud
loss occurred at 559 mtrs in 12.1/4” section in upper carbonate formation. The loss
could not be arrested even after placing 22 no. LCM pills and 11 no. of cement plugs.
Subsequently lowered 9.5/8” casing at 559 mtrs and cemented. The well was
subsequently drilled to 1278 mtrs with no return to partial return. The innovative
way of putting two bentonitic cement plugs and eight numbers of high concentration
unswelled bentonite LCM pills before each pulling out bit trip helped to achieve the
mud return. 5.1/2” casing was landed at 1269 mtrs and cemented with partial return
(80- 85) % of mud. Subsequent log showed moderate to good cementation against
Bilara and Jodhpur (pay zone) formations The Drilling Rig (John#12) De- hired on
16.03.2017 at 7.00AM.
 Work-over achievement in terms of number of jobs completed was 14 (fourteen) as
against annual target of 13 jobs. Work-over jobs were carried out in the following
locations
DND#14,DND#19,DND#11,DND#9,DND#8,DND#25,DND#24,DND#22,DND#26,DND
#04,BGT#01 & DND#06(live perforation) ,BGW#5 . At the end of the extended
contract period , the Work over Rig GTC-100-03 was de-hired on 05-02-2017.
 In the financial year 2016 - 2017, Rajasthan project have achieved drilling meterage
of 9332 m as against 9250 m of annual target and completed a total of 14 number
work-over jobs as against annual target of 13 jobs with one Drilling Rig and one
Work-over Rig operation in Rajasthan Project . For the last two consecutive years,
our achievement in drilling and work-over front in RP was more than 100% of annual
target . This commendable performance could be achieved because of sincere &
dedicated efforts put forward by all of us involved directly or indirectly in field
operations.

9.2 Reasons for shortfall from Target –

37
Drilling & work-over targets in RP were achieved by 100.88 %.

9.3 Tendering and Contractual Progress -

LOA of Contract (No. 6208205) for hiring the services of one 1000 HP Mobile Drilling
Rig Package (John#29) against Baghewala PML area of Bikaner Nagur basin has been
issued. The tendering process for hiring Cementing and BHP services; Coring services;
Horizontal drilling and Liner Hanger services are on progress . Procurement process
of L80 casing for two horizontal and two vertical drilling wells is on progress. The
above services are required towards drilling of well with thermal completion in
Baghewala PML area of Bikaner Nagur Basin in Rajasthan.

9.4 Cost Saving Measures -

 Completed five numbers of drilling wells including one Water Disposal Well within the
stipulated time period.
 Faster ILM in case of both drilling & work-over wells than the stipulated time-frame as per
Contract thereby increasing Rig utilization time resulting in overall improvement of
performance.
 Optimum utilization of bit life in order to reduce quantity of drill bit consumption vis-à-vis
number of bit trips in a well.
 Use of integrated small cementing set-up attached to Work-over Rig for cement plug/squeeze
jobs in almost all the work-over wells.

9.5 Energy Conservation Measures -

1. Use of Rig & Mud Pump Engines on load requirement basis only.
2. Maintaining the Power Packs/Engines in switch-off mode during well-logging &
production testing operations.
3. Use of Portable Gen-Set for lighting purpose at night.
4. Strict adherence to periodic servicing & pro-active maintenance of Engines resulted
in fuel efficiency thereby saving HSD & lubricants.

9.6 Environment Protection & Pollution Control Measures -

1. Effluent disposal was restricted to the pit lined with HDPE sheet to prevent flow of
effluent to surrounding areas and percolation of the same to the soil underneath.
2. Use of environmental friendly water base mud system in drilling well minimized
pollution control hazards.
3. Erection of brick-wall bunds around diesel storage tank, power-packs minimized
pollution risk caused by accidental spillage of HSD.
4. Use of acoustic Gen-Set at well-sites & camps helped reducing noise pollution to a
great extent.
5. Use of ear & nose muffs to minimizing noise & health pollution.
6. Collection of burnt lube oil in drums during servicing of power-packs/engines in
drilling & work-over wells and safe disposal thereafter.

38
************************************************************

39
10. FINANCE & ACCOUNTS SECTION:

10.1.0 Organization:
.
10.1.1 Management: The department is headed by Chief Manager (F&A) who is
assisted by three Level -1 executives one level -2 executive (Chief Manager-1, Managers-2 &
Deputy Managers-1) to carry out all departmental activities.
10.1.2 Manpower Strength: Manpower strength in the department was -

2015-16 2016-17
Executives (nos) 5 5
Workmen (nos) 8 8
10.1.3 Transfers: Shri G.P. Saha (MFA) has been transferred from the project during
the last part of the current year.
10.1.4 Retirements : Nil
10.1.5 Training: Following executives attended training & seminar programme:-

(i) Shri Om Prakash – GST at Jaipur & New Delhi

10.1.6 Infrastructure: Infrastructure(major items only) facilities available in


Finance & Accounts department are :-

SN Description Numbers
1.6.1 PC 12
1.6.2 Printers 11
1.6.3 Cash Vault 2
1.6.4 SAP based phones 1
1.6.5 DoT Phones 2
1.6.6 Intercom 12

10.2.0 Transaction Processing:


10.2.1 Cash and Bank Documents-
(Documents in Nos.)
Desctiption 2015-16 2016-17
Cash 228 569
Bank 2942 3982

10.3.0 Revenue:
(Amount in ` Lakhs)
SN Description 2015-16 2016-17

3.1.1 Natural Gas Sales 9355.15 6934.88

40
3.1.2 MGO 618.13 -
3.1.3 Condensate Sale 39.58 56.62
3.1.4 Heavy Oil - -
3.1.5 Interest on Short Term Deposits 16.26 19.92
3.1.6 Renewable Energy Revenue 5115.63 6241.00

10.4.0 Contribution to Exchequer:

(A) State Government


(Amount in ` Lakhs)
SN Description 2015-16 2016-17

4.1 Royalty
4.1.1 Natural Gas 850.47 630.44
4.1.2 Condensate 17.39 9.89
4.1.3 Heavy Oil - -

4.2 Sales Tax (VAT/CST)


4.2.1 Natural Gas 371.95 391.33
4.2.2 Condensate 1.06 1.14
4.2.3 Heavy Oil -

4.3 Entry Tax 6.26 32.52

(B) Central Government


(Amount in ` Lakhs)
SN Description 2015-16 2016-17

4.3 Cess
4.3.1 Condensate 6.198 10.39

4.4 TDS Deposited


4.2.1 Employees 627.44 590.611
4.2.2 Contractors 88.32 237.97

10.5.0 Income Tax Demand Notices:

DCIT (TDS), Income Tax Department, Jodhpur after surveying our accounts and records
for the FY 2007-08 and 2008-09 issued two demand notices for `.223 Lakh alleging short
41
recovery of TDS from the contractors/sub-contractors. The demand notices of DCIT (TDS)
were challenged before the CIT (Appeals), Jodhpur and our appeal was pending adjudication
before CIT (Appeals), Jodhpur as on 31.03.2011. Subsequently, CIT (A), Bikaner has passed
the appellate order on 31.10.2011. In the order of CIT (A), commissioner has decided that
rate of TDS will be 10% as per section 194 J & 194 I . However, since all the contractors have
filed their return of total income and therefore, TDS short deducted in previous years i.e.
10% minus 2%, can not be recovered from OIL but interest on such short deduction shall be
leviable & recoverable from the company. Matter was discussed with taxation cell/
consultant & accordingly, we have filed the appeal before ITAT which is pending.
Subsequently, Case was heard on various dates in ITAT, Jodhpur. After hearing the case at
ITAT, Jodhpur thereafter on various dates, the verdict was given in our favour on
31.07.2013. Later on, we have got a refund of INR 1.70 crores from the Income Tax
department. However , Income tax department has filed an appeal against the ITAT order
in Rajasthan High court .

Meanwhile, we have received another notice for similar type of case for the Financial
year 2009-10 & 2010-11 and an appeal is being filed for the same with the help of our local
tax consultant . We also received notice for the F.Y. 2011-12, 2012-13 & 2013-14 for the
similar type of issue from the department which is dealt with by engaging a consultant. All
the cases from FY 2009-10 to 2013-14 have been settled in favour of OIL by CIT (A) in the
month of March 2016.

10.6.0 Service Tax & Excise Cases:

a)Service Tax : OIL had availed services of cementing from a foreign contractor & made a
payment of ` 2.60 crores approx. However, applicable service tax was not deposited due to
lack of clarity on the rulings. Later on, OIL deposited the service tax along with interest
amounting to ` 28,83,637 & ` 10,79,457 respectively .However, vide order dtd 30.03.2012 ,
department imposed penalty of `28,83,637. We have filed an appeal against the order on 25th
June,2012 with Commissioner (Appeals-II) & stay application is pending before the
appellate authority.

b) Excise Cases: Show cause notice from the office of Commissioner of Central Excise,
Jaipur (C.No.V(27)Adj.11/JPR-II/43/2014/1484 dated 28.02.2014) was received
alleging OIL of evading payment of Rs.14,32,03,934/- on clearance of Natural Gas during
the period February 2009 to December 2013 .

After filing of reply , an amount of Rs.4,45,47,248 deleted for the period from Feb 2009 to
March 2011 and AO maintained a demand of Rs.9,86,56,676/- and in addition to that a
penalty of Rs.4,93,28,338/- and Rs.20,00,000/-imposed (Total Rs.14,99,85,014)for the
period from April 2011 to December 2013. OIL have filed an appeal to CESTAT ,New Delhi
on 22.12.2014 against the order of AO. And Appeal was accepted by CESTAT ,New Delhi
on19/02/2015 .

42
Further show cause notice was issued by Commissioner of Central Excise, Jaipur for the
period from Jan 2014 to Oct 2014 . After our reply to notice AO maintained the demand for
Rs. Rs.3,12,65,906/- along with interest Rs.25,00,000/- and penalty Rs. 1000000/- (Total
Rs.3,47,65,906 /-). OIL have filed an appeal to CESTAT,New Delhi on 02/04/2015 against the
order of AO. And Appeal was accepted by CESTAT,New Delhi.

Further show cause notice was issued by Asst .Commissioner of Central Excise, Jodhpur for
the period March 2014,April 2014 and December 2014 for Rs.1,48,470 dated 23.03.2015 .
Oil filed reply to notice AO on 27.07.2016 . However AO maintained the demand . OIL have
filed an appeal before Honourable Commissioner (Appeals) on 08/10/2016 against
the order of AO.

Further show cause notice was issued by Commissioner of Central Excise, Jaipur for the
period from Nov 2014 to March 2015 for Rs.2,09,86,361 dated 30.11.2015 . Oil filed reply
to AO on 09.01.2016 . The case is decided in favour of Oil India Limited on 21/12/2016
.

10.7.0 Outstanding amount with GAlL: An amount Rs.1.78 crores was receivable from M/S
Gail (India) Limited on account of MGO and interest thereon . After Intervention of Director
(F) and Director (E&D) and a subsequent discussion between OIL and M/S Gail(India)
Limited officials at Jodhpur. M/s GAIL(I) Ltd paid an amount of Rs 0.63 lacs to OIL on
account of two MGOs and for another MGO of Rs.1.04 cr, M/s GAIL requested to consider the
period as force Majeure . Accordingly , a proposal was put up and competent authority
agreed to their request that there was no fault of either side in maintaining Gas supply . For
interest on MGO, competent authority agreed to the request made by GAIL for waiver of
interest on MGO .

10.8.0 Receipt of outstanding amount from RUVNL: In wind power plants payment is
always delayed , beyond credit period allowed as per PPA . RUVNL offered for releasing the
payment upto Dec,2016 subject to waiver of LPS by 50% . Competent authority of M/s OIL
accepted the offer of RUVNL and received an amount of Rs.42.00 cr on 31.03.2017 towards
the pending bills up to Dec 2016 and Reduced LPS.

10.9.0. Accounting:

43
Quarterly Accounts pertaining to Rajasthan Business Area have been completed well within
the target date set by General Manager (F&A) FHQ. The quality of books of accounts has been
maintained at the desired level. So far, there is no adverse comment from the auditors on the
Accounts of RP up to the 3rd Quarter FY 2016-17. Fourth Quarter Accounts for FY 2016-17
are under audit.

10.10.0 E-Payment:

E-payment is considered to be the most transparent method of effecting remittance to


various vendors. During the year 2016-17, payment to the vendors through E-Payment
mode, were successfully made. Almost all kinds of payments have been brought under E-
Payment mode and the quantum of payment through E-Payment mode has been increasing
day by day. Presently, E-Payment has been achieved to the extent of 90-98 % against the
target of 90% in terms of value of the total payment.

10.11.0 Austerity & cost control Measures

In terms of the directives of Director (Finance) vide letter dated 11th November 2016 ,
efforts are on to control the expenditure on various items indicated in these circulars. We
shall try to implement austerity measures in totality in compliance to the circular. Some of
the items of expenditure strictly controlled are as under:-

1-Maintenance of building, office equipments, travel, transport, communication,


stationary, furniture etc.

2-Organizing conferences/seminars/workshop etc.

3-Civil & electrical works.

4- Judicious use of stationary especially paper, shall be made. E-mail communication


shall be encouraged.

5- Judicious use of Office car/Pool cars & avoidance of the wasteful expenditure.

6- overtime

7.Advertisement

Out of the austerity measures mentioned above, we have already taken action on few points
to ensure the reduction in the expenditure. However, this will be further taken forward to
ensure further visible reduction in the expenses.

44
10.12.0 Joint Venture Accounting :

The following Joint Ventures under NELP are handled by the project during F.Y. 2016-17 :
Participating
Joint Venture Partners STATUS
Interest (%) OPERATOR
OIL 60% Two Wells completed in
Block in Ist Exploration
RJ-ONN-
HOEC 20% OIL Phase. Block stands
2005/2
relinquished w.e.f.
HMEL 20% 25.12.2015.
OIL 60%
RJ-ONN- Relinquished in
GGR 25% OIL
2004/3 January 2012
HPCL 15%
Highly viscous heavy oil
found in exploratory
well drilled in Phase-I of
the block. MWP of
drilling 1 well in Phase-
II completed. Phase-II
expired on 20.07.2015.
OIL 75%
RJ-ONN- Government’s decision
OIL
2004/2 on OIL’s application for
GGR 25%
grant of additional time
period for carrying out
appraisal Work
Programme and
retention of 10.24
SQKM area under
Mining Lease is awaited.
OIL 60%
RJ-ONN-
OIL Relinquished
2002/1
ONGC 40%
OIL 70%
RJ-ONN-
OIL Relinquished
2001/1
ONGC 30%
RJ-ONN-
OIL 100% OIL Relinquished
2000/1
RELIANCE 60%

GK-OSJ-3 OIL 15% Relinquished


RELIANACE
ONGC 25%

45
In respect of operated block RJ-ONN- 2004/2, under NELP VI and RJ-ONN- 2005/2
under NELP VII, the total expenditure during FY 2015-16 was `12.51 crores & `37.36
respectively and during FY 2016-17, the expenditure (provisional) in these blocks have been
to the tune of `0.50 crore & `1.24 crores respectively.

In addition to the above expenditure, during FY 2014-15, OIL has paid LD amounting
to `1.08 crore for block RJ-ONN-2004/2 for seeking 6 Month’s Extension in Phase-II of the
block. During FY 2015-16, OIL has paid LD amounting to `1.87 crore for seeking 2nd
Extension of 6 Months in Phase-I of block RJ-ONN-2005/2 and has paid LD amounting to
`27.82 crore towards LD for Unfinished Minimum Work Programme of Phase-I for the block
. Block RJ-ONN-2005/2 is relinquished w.e.f. 25.12.2015 after completion of Phase-I
exploration period.

10.13.0 Bill Tracking System:

Bill Tracking system implemented in the department is running smoothly and all the
SES based bills etc are recorded in system while receiving and while sending them back.
However, this system needs to be strengthened further for optimum results.

10.14.0 Online Tax Payment:

Payment of Direct Taxes (TDS/TCS) is being done through ONLINE payment Gateway
of SBI Bank using OLTAS (Online Tax Accounting System).

Payment of Indirect Taxes (Service Tax, Royalty, Entry Tax, CST, VAT etc.) is being
done through ONLINE Payment Gateway of State Bank of India.

**********************************************************************************

46
11.0 MATERIALS & CONTRACT DEPT.:
11.1.0 Material management is an approach for planning, organizing, and controlling all those
activities principally concerned with the flow of materials and hiring of services required for an
organisation. It is a business function for planning, purchasing, moving, storing material in an
optimum way which help organisation to minimize the various costs like inventory, purchasing,
material handling and distribution costs. The fundamental objectives of the Materials Management
function, often called the famous 5 Rs of Materials Management, are acquisition of materials and
services:

a. of the right quality b. at the right time c. at the right price


d. in the right quantity e. from the right source
11.1.1 The basic objective of Materials & Contract Department at Rajasthan Project is:
 To buy at the lowest price, consistent with desired quality and service.
 To maintain a high inventory turnover, by reducing excess storage, carrying costs and inventory
losses occurring due to deteriorations, obsolescence and pilferage.
 To maintain continuity of supply, preventing interruption of flow of materials and services to
users.
 To maintain the specified material quality level and a consistency of quality which permits
efficient and effective operation.
 To develop reliable alternate sources of supply to promote a competitive atmosphere in
performance and pricing.
 To minimize the overall cost of acquisition by improving the efficiency of operations and
procedures.
 To develop and maintain good supplier relationships in order to create a supplier attitude and
desire to furnish the organisation with new ideas, products, and better prices and service.
 To achieve a high degree of cooperation and coordination with user departments.
 To maintain good records and controls that provides an audit trail and ensures efficiency and
honesty.
 To participate in Make or Buy decisions.

11.2.0 The major achievement of the department in the current financial year are:
i Saved INR 23.44 Lakhs in advertisement cost of tender.
The advertisement cost per tender is reduced from INR 3.35 Lakhs to INR 1.96
ii
Lakhs
Reduced the inventory by INR 798.72 Lakhs in the current financial year i.e. a
iii
reduction by 35.93 %.
11.2.1 The statistical data related to procurement of goods, services and inventory
management during the period 2014-15, 2015-16 and 2016-17 is furnished below:
A. Purchase Requisition (PR) Processed
Year-> 2014-15 2015-16 2016-17
Nos. / Value of PR Processed Nos. Value (L) Nos. Value (L) Nos. Value (L)
Stock 17 142 20 481 33 1397
Direct Charge & Capital 108 5404 102 11318 73 7041
Service PR 49 6124 92 24154 65 16924
Spot Purchase 211 9 250 21 202 21
Development NIL 1 6.24 NIL
Total 385 11679 465 35980 373 25383
47
% Increase 20.78 208.08 -19.78 -29.45
B. Tender Floated
(i) Material Procurement (Goods)
Year-> 2014-15 2015-16 2016-17
Nos. /Value of Tender floated
Nos. Value (L) Nos. Value (L) Nos. Value (L)
Limited Tender (Manual) 33 75 20 76 22 78
Limited Tender (e-Tender) 1 206 0 0 0 0
Press Tender (Manual) 0 0 0 0 0 0
Press Tender (e-Tender) 5 11250 12 6967 21 4096
Total 39 11531 32 7043 43 4174
% Increase -17.95 -38.92 34.38 -40.74
(ii) Service / Works Contract
Year-> 2014-15 2015-16 2016-17
Nos. / Value of Tender floated Nos. Value (L) Nos. Value (L) Nos. Value (L)
Limited Tender (Manual) 5 428 3 20 5 37
Limited Tender (e-Tender) 1 400 1 4863 0 0
Press Tender (Manual) 7 65 2 15 0 0
Press Tender (e-Tender) 23 15987 18 7021 19 8083
Total 36 16880 24 11919 24 8120
% Increase -33.33 -29.39 0.00 -31.87
C. Purchase Order (PO) Placed
Year-> 2014-15 2015-16 2016-17
Nos. /Value of PO placed Nos. Value (L) Nos. Value (L) Nos. Value (L)
Stock 18 435.08 12 212.52 17 297.62
Direct Charge & Capital 59 223.26 43 10902.31 40 359.58
Spot Purchase 182 8.00 191 19.77 145 15.57
Development 0 0 1 6.24 0 0
Total 259 666.3 247 11140.8 202 672.8
% Increase -4.63 1571.95 -18.22 -93.96

D. Service / Works Contract Awarded


Year-> 2014-15 2015-16 2016-17
Nos. /Value of Service Contract Nos. Value (L) Nos. Value (L) Nos. Value (L)
placed during period
Total 39 8888 71 21756 48 10841
% Increase 82.05 144.78 -32.39 -50.17

48
E. Lead Time for Procurement of Goods & Services
(i) Lead Time for Procurement of Goods:
Year-> 2014-15(days) 2015- 2016-
16(days) 17(days)

Stock-Indigenous 118 - 119


Stock-Foreign 268 232 232
DC-Indigenous 89 77 156
DC-Foreign - 291 300

(ii) Lead Time for Procurement of Services:


Year-> 2014-15 2015-16 2016-17
Indigenous 155 78 127
Foreign 202 - 271

F. Warehousing at Hamira
Year-> 2014-15 2015-16 % Increase 2016-17 % Increase
Inventory in Lakhs 3283.52 2222.83 (-)32.30 1424.11 -35.93 Wit
Consignment Received 63 92 46.03 121 31.52 h
Good Receipt Documents 46 78 69.56 62 -20.51 pro
Goods Issue Documents 74 190 156.76 556 192.63 per
Road Permit Issued 62 91 46.77 121 32.97 ma
Stock Items Physically Verified 920 979 6.41 1088 11.13 nag
ement and controlling of placement of Purchase Orders (inflow of goods) including issue of
goods (outflow) we could reduce the inventory by INR 798.72 Lakhs in the current financial
year i.e. a reduction by 35.93 % . Due to continuous drilling and work-over operation
throughout the year there is 192.63% increase in the number of materials issue documents.

G. Major PO & Service Contract Placed During 2016-17


SL Purchase Brief Description of Goods/Services Value (in
Order Lakhs)
1 7118415 Casing N-80, 13.3/8”-400M & 9.5/8”-3400 M 144.16
2 7951031 PUMP-WELL SERVICING 140.97
3 7118662 Cement API Class G, 50 Kg Bag-18000 MT 79.20
4 7600831 SS X-Mass tree assy. 65.08 mm bore – 6 Nos. 46.03
5 7907942 GENERATING SET – 2 Nos. 33.15
6 7907943 AIR CONDITIONERS 33.12
7 7908299 TANK-RECTANGULAR – 4 Nos. 25.16
8 7117915 Barytes Powder-300 MT 23.08
SL Service Brief Description of Goods/Services Value (in
Contract Lakhs)
1 6207762 Hiring of Drilling Rig-1400+ HP for KGB 5176.29

49
2 6208205 HIRING OF 1 NO. MOBILE DRILLING RIG 2346.63
3 6207621 Hiring of MUD ENGINEERING & DWM for KGB 1100.87
4 6109841 Consultancy Services for Exploitation of Heavy Oil 558.61
5 6109961 Hiring of Skilled/Unskilled Manpower 160.45
6 6207666 Hiring of Tractor Trailer unit 112.50
7 6208237 Providing day to day miscellaneous civil works 85.68
8 6110645 Hiring of 20 KL Bowser 79.56
9 6110297 Construction of Drill. Loc at BGW 78.73
10 6110081 TVC Extension 72.12
11 6110298 Construction of Approach Roads 70.26
12 6110612 CHARTER HIRE OF SRP SURFACE UNITS 70.17
13 6109850 O&M of DND-GPC, Tanot GGS & TVC 69.85
14 6109917 Hiring of Mud Logging Services 65.47
15 6110651 3 Years AMC of SCADA System 63.74
16 6110429 AMC for Kingdom Software 63.17
17 6208290 Hiring of Materials handling at Hamira 50.34
18 6207667 Hiring of 10 T capacity Crane on call-out 47.36
19 6208204 HIRING OF BHP DATA ACQUISTION SERVICES 41.30
20 6110675 HIRING OF MOBILE PUMPING UNIT SERVICES 23.20
21 6110669 CAMC for HVAC at OIL HOUSE 19.68
22 6110112 Hiring of 20'Long 7.5 MT Truck 17.61
23 6110619 Housekeeping Services for OIL House 12.84
24 6110246 Construction of toilet block, gate etc. 12.40
25 6109967 TRANSPORT SERVICE WITH 1 NO. AC4WD CAR 11.90
26 6110105 Housekeeping services for OIL House 11.70

H. Press Advertisement Cost


Year-> 2014-15 2015-16 2016-17
Nos. Value (L) Nos. Value (L) Nos. Value (L)
Press Tender Nos. & Cost
37 281.90 34 113.77 46 90.33
Advertisement Cost Per Tender 7.62 3.35 1.96
% Increase -8.11 -56.04 35.29 -41.49

With proper monitoring, control and clubbing of open tenders we could save INR 23.44
Lakhs in the current financial year. The advertisement cost per tender is reduced from
last year’s cost of INR 3.35 Lakhs to INR 1.96 Lakhs in the current financial year.

I. Manpower
Executive L-4 L-3 L-2 L-1 Total Short
Sanctioned - 1 1 4 6
Existing 1 - 2 2 5 1
Workman 7

Note:
50
(i) One L-1 executive from Production Department is working part time with us for dealing with service PR
for civil, transport and miscellaneous jobs.
(ii) One L-1 executive looking after Hamira Godown retired on 30.06.2015 and has been engaged on contract
basis up to 21.04.2017
J. Training
Program Title Grade Name Program Institute Venue
Category
DISHA A NEW JOURNEY POST H VK SAHU IN HOUSE 6TH SENSE RESOURCES DULIAJA
RETIREMENT PVT. LTD., BANGALORE N
INTERPERSONAL RELATIONS FOR H VK SAHU IN HOUSE DR. SOURABH SETHI JODHPU
TEAM BUILDING R
KEEP IN TOUCH H VK SAHU IN HOUSE OIL INDIA LTD JODHPU
R
INTERPERSONAL RELATIONS FOR F PRAKASH IN HOUSE DR. SOURABH SETHI JODHPU
TEAM BUILDING MAZUMDAR R
KEEP IN TOUCH F PRAKASH IN HOUSE OIL INDIA LTD JODHPU
MAZUMDAR R
KEEP IN TOUCH F ANITA DAM IN HOUSE OIL INDIA LTD JODHPU
R

11.2.2 Vendor Meet: It has always been an endeavour of M&C department to


encourage more and more participation of vendors against its tenders and to achieve the
same, understanding of Company’s Procurement Procedures is very essential on the part of
the vendors. It was, therefore, felt very essential to organise a “Vendor Awareness Program”
at Jodhpur to bring in awareness among the vendors of Rajasthan Project and accordingly,
Vendor Awareness Program was arranged on 11th November 2016 at Hotel Taj, Hari Mahal,
Jodhpur to share the procurement procedure and e-tendering process of OIL. The event was
conducted very successfully wherein around 36 members from vendor representing 22
vendors attended the program. An interactive session was conducted between the
participating vendors and Panel of senior executives from OIL towards the end of the
program, wherein the vendors/representatives were asked to put forward their issues, if
any, as well as suggestions to OIL. The interactive session went-off very well with very
positive feedback from the participating vendors. The presence of Independent External
Monitor (IEM) added value to the sessions. There was also representation from OIL’s other
spheres and vigilance department as well as representation from other PSU like ONGC,
Jodhpur.

**********************************************************************************

51
12.0 ADMINISTRATION DEPARTMENT

12.1.0 Introduction
Oil India Limited established its Project Office at Jodhpur in the year 1983 for exploration of
hydrocarbon in the THAR DESERT of Western Rajasthan. From the date of inception of
Rajasthan Project, Administration department is playing a key role in managing various
Administration and ER functions of the project as well as liaison with State & Central Govt.
authorities for obtaining speedy approvals for execution of the related jobs. During the year
under review, Administration Department has carried out all the responsibilities effectively
and with great enthusiasm towards maintaining industrial harmony and cordial relations
between Management and Union members providing the required administrative services
and support . Following are detailed activities under Administration department during the
year 2016-2017.

12.2.0 Administrative Matters.


1. Executive Strength as on 31.3.2017 : 48
2. Board Sanctioned : 51

Break-up of executives department-wise:


Sl. No. Department Strength
01 ED (RP) Section 02
02 Administration 04
03 Finance & Accounts 04
04 Chemical 03
05 Drilling 05
06 Geoscience 09
07 Materials 07
08 Technical Service 06
09 Vigilance 01
10 Production 07

12.2.1 Executives on short term contractual appointment as on 31.03.2017 : 02

12.2.2 Work persons strength as on: 31.03.2017 : 93


Sanctioned strength :80+(16sportsperson
supernumeraries)
12.2.3 New Recruitment for the year 2016-2017 : NIL

Department-wise beak-up of work person:


Sl. No. Department Strength
01 ED (RP)’s Section 02
02 Administration 25 (including 9 sports person)

52
03 Accounts 07 (including 1 sports person)
04 Drilling 04 (including 1 sports person)
05 Chemical 05 (including 1 sports person)
06 Materials & Contract 08 (including 1 sports person)
07 Geo science 11 (including 1 sports person)
08 TS/Civil 17
09 Production 13 (including 1 sportsperson)
10 Vigilance 01 (Sports person)

TOTAL (As on 31.3.2017): 93

NOTE: Two workpersons Superannuated on 30.06.2016 & 28.02.2017

12.2.4 Reserved categories


1. S.C. : 14
2. S.T : 01
3. Physical Handicapped : 02
4. OBC : 20 (as per Govt. Of India notified list)
5. General : 56
12.2.5 Employment generated during the year 2016-2017 : NIL

12.2.6 Industrial Relations


Industrial relations with employees remain cordial, harmonious and peaceful during the
year under review.

12.2.7 Training and Development


For development of executives and work persons , OIL (RP) has been regularly organizing
training programmes . During the year, following executives/ workperson were nominated
for residential training/in-house programmes .

Executives
Sr.No. Name of Executive Course Title Period Venue
01 Sh. Om Prakash, Sr.M. 37th Regional 26-27 Aug., Jaipur
(F&A) Conference of CIRC 2016
02 Sh. D. Bhuyan, Sr. General Management 11-24 Hyderabad
Chemist cum Leadership Sept., 2016
Programme.
3 Sh. Abjhit Dam, DGM Leadership from Inside 13-14 NOIDA
(TS) & Sh. H.K. Barua, Out. June, 2016
CC (RP)
4 Sh. P.K. Chetia, SG Petrophysics for 17-19 Oct. New Delhi
Professionals 2016
5 Sh. Om Prakash Seminar on GST devising 27.10.2016 New Delhi
Implementation
Strategies & Redefining
53
Process
6 Sh. R. Tumung, Dy.CE Transformational 08.11.2016 NOIDA
(Pdn) & HK Leadership under
Choudhary, Dy.CE Project Udaan.
(Drilling)
7 Sh. H.K. Barman, Sr. M Implementation of 21-23 Oct. Darjeeling
(OL) Official Language 2016
8 Sh.D.K. Das, CE Renewable Energy 08-09 Dec . Guwahati
(Electricals) Generation, Integration, 2016
Sh. Abhijit Dam, DGM Forecasting Issues and
(TS) Role of Smart Grid.

In-house Training Programme attended by Executives


Executives
Sr.No. Name of Executive Course Title Period Venue
01 17 executives Effective 11-12 July, Hotel Park
Interpersonal 2016 Plaza
Relations for Team
Building.

Workperson
NIL

12.2.9 Important Programmes:


a) World Environment Day was celebrated on 5th June, 2016 in a befitting manner. It
included pledge taking and tree sapling plantation in OILHOUSE, Jodhpur premise.

b) Yoga Day Celebrated: 2nd International Yoga Day was celebrated at OIL House, Jodhpur
on 21st June, 2016. On this day, noted yoga trainer, Shri Vinod Acharya imparted yoga
training to about 100 nos. of participants including executives and employees of Rajasthan
Project, Jodhpur and their family members.

c) Workshop on RTI: One day workshop on “Best Practices On RTI” was held on 28.02.2017
at Jodhpur Office. The workshop is aimed at providing the information about the best practices
prevalent in the industry with respect to RTI Act.

12.2.10 Social Welfare activities


(a) OIL’s provided financial assistance of Rs. 0.20 Lakhs to JIET, Jodhpur for organizing
two days National Workshop on Advanced Solar Photovoltaic.
(b ) OIL SUPER 30 at Jodhpur for providing coaching to under privileged students for
preparation for admission to IIT/NIT and other reputed Engineering institutes. Total cost of
the project is Rs. 54.45 Lakhs.
(c) Financial Assistance of Rs. 0.30 Lakhs to JIET for organizing National Conference on
Recent Advances in Environment Science and Engineering Technology.
54
(d) Financial assistance of Rs. 12.04 Lakhs (2nd instalment) for repairs of conference hall
in collectorate office complex Jaisalmer.

12.2.11 Executives Transferred from RP


Sl. No Name Designation Date of Release
1 Sh. M. Konwar Dy.Mgr. (Materials) 14.04.2016
2 Shri D. Sen Sr. AO 07.05.2016
3 Shri Bishnu Medhi Suptg. Chemist 07.05.2016
4 Shri S. Deb Dy. CED 14.05.2016
5 Sh. Pradeep Singh Dy. SG 25.06.2016
6 Sh. N. Vashisht GM (A&ER) 25.06.2016
7 Sh. AK Agarwal CE (FS) 05.08.2016
8 Sh. KK Deka Dy. CE (P) 01.10.2016
9 Sh. S.K. Sinha S.E. (IT) 01.12.2016
10 Sh. G.P. Saha Manager (F&A) 18.02.2017

12. 2.12 Executives Transferred to R.P


Sl. No Name Designation Date of Joining
1 Sh. A.K. Meena Admin. Officer 01.04.2016
2 Sh. T.N. Singh SE (Wlg.) 12.04.2016
3 Sh. Mobia Gambo Sr. CE 16.04.2016
4 Sh. G. Goel Dy. CE (FS) 18.04.2016
5 Sh. Madhurjya Barua CM (A&ER) 20.04.2016
6 Sh. H.K. Choudhary Dy. CE (D) 25.04.2016
7 Sh. D. Bhuyan Sr. Chemist 02.05.2016
8 Sh. MM Pegu Sr. Engr (IT) 15.11.2016
9 Sh.B. Baskota Electrical Engr 28.12.2016
10 Sh. P. Dutta ASO/PO 28.01.2017
11 Sh. M. Dutta Engr. (Instt.) 20.02.2017
12 Sh. D. Shankar Manager (Mat.) 07.03.2017

12.2.13 Retirement : Shri N.Kalla (Manager-Admin) & Sh. GP Sharma (Sr. Store
Officer) superannuated on 30.06.16 and 31.01.2017 respectively

12.2.14 Resignation : Nil

12.2.15 Implementation of Official Language


Official Language is implemented at RP as per the directive of Ministry of Home Affairs and
Department of Official Language . As per the roster being maintained the executives &
employees were trained in Hindi Shikshan. Hindi Fortnight was celebrated from 01-15
September 2016 . Rajyabasha Samaroh was celebrated on 15.09.2016 . 4 nos. of Hindi

55
Workshop was organized during the year with maximum participation of executives and
employees .
12.2.16 Medical
For providing best possible medical services to its employees and their eligible dependents
OIL has recognized 7 hospitals in Jodhpur. We are also managing a dispensary with AMA on
retainership basis. Deserving cases are referred for specialized treatment on AMA’s
recommendation and with approval of the authority as per company’s rule. Medical facility
available at Tanot Village Complex was also providing primary medical facility not only to
our employees but to the villagers too. In the absence of any medical facility at Tanot and
nearby villages, the setup proves to be a blessing for all the villagers.

12.2.17 Sports
We have two teams (Basket ball and volley ball) who represents OIL at various
State/National level tournaments in addition to PSPB. The following are the details of
various tournaments in which OIL’s team participated during the period.
a. Volley Ball

Sl. No. Tournament Level Venue Position


1 XXXVII PSPB PSPB Debradun Third
from 01-04
December,
2016

b. Basketball
Sl. No. Tournament Level Venue Position
1 NA NA NA

12.2.18 Austerity Measures


As directed by the competent authority, Administration Department has taken all possible
steps towards reducing the avoidable expenditures during the current financial year. The
jobs have been planned in such a way that OT incurred is zero. We have reduced the hiring
of callout vehicles by using car pool method for serving in the Fields at Jaisalmer/Bikaner.
The unutilized capital budgets were surrendered.

12.2.19 Golden Memories of 2016-17

 OIL, Rajasthan Project, Jodhpur has shown remarkable progress in the use of Official
Language Hindi for which OIL, RP, was awarded with Rajbasha Mukutmoni Shied
by the Bharatiya Bhasha avong Sanskriti Kendra, New Delhi on 23.10.2016.

 Oil India Ltd., Rajasthan Project, Jodhpur has shown remarkable progress in the use
of Official Language Hindi for which OIL, RP, Jodhpur has been awarded with 1st

56
Position in Rajyabasha Shield by the Town Official Language Implementation
Committee, Jodhpur on 20th December, 2016.

******************************************************************************

57
13.0 Information Technology

13.1 PREAMBLE
The goal of the IT department is to meet the information requirements of all activities at
different levels within the organization by leveraging the latest technology in the best
possible and most cost effective manner to achieve higher productivity.

13.2 The major regular activities of the Department are listed below:

13.2.1 IT Security

 Ensuring perimeter security through Firewalls


 User Authentication through Microsoft Active Directory
 Antivirus Server and Client management
 IT Security audit & implementation of audit recommendations

13.2.2 User support


 Support to Email users
 Providing and supporting Internet connectivity to users
 Anti-virus, AD front-end support
 SAP ERP front-end support.
 Other applications user support.
 ERP related support

13.2.3 Network management


 Maintenance and administration of LAN
 Maintenance and administration of WAN - VSAT, MPLS
 Maintenance and administration SCADA network between Tanot to Jodhpur
 Maintenance and support of Satellite Phone
 Maintenance and support of Voice communication between Tanot, GGS & Dandewala

13.2.4 Hardware management


 IT Infrastructure Planning, procurement, maintenance of Desktops, Laptops, Servers,
Printers, Scanners etc.
 IT Asset management
 Preventive maintenance of generic IT assets
 Maintenance and support of EPABX telephone exchange

13.2.5 Planning & Administration


 Payments of all the IT related contract and Purchase Orders
 Preparing departmental reports, annual reports etc.
 Co-ordinating matters related to the Rajasthan Project:
 Annual report of the project
 Annual Capital and Revenue budget of the project
 Monitoring and utilization of capital and revenue budget of the project
 Closing of not used / unutilised budget of the project
58
13.3 ACHIEVEMENTS
 Implementation of Access Control System : It is an electronic smart card based
access control system to ensure that only authorised persons are allowed to enter a
physical room, building or any gated infrastructure. The system is also integrated into
the Fire Detection and Alarm System (FDAS) placed in OIL House ensuring safety to
the working personnel.
 Implementation of Biometric Attendance System : It is a biometric based
attendance recording and monitoring system which can generate multiple reports
related to attendance in workplace with flexible parameters.
 Implementation of CCTV system : To enhance the perimeter security of OIL House,
CCTV system with 21 cameras has been installed. It allows for live view, playback and
storage of CCTV footage, giving a complete video surveillance solution.
Implementation of Visitor Management System: In order to keep track and give controlled
access of OIL House to visitors, a visitor management system has been implemented in OIL House.
The information of the visitors is kept in a database and report can be generated accordingly. It is
integrated to Access Control System to give controlled access to visitors.

15.0 ACKNOWLEDGMENT
We acknowledge with sincere gratitude the assistance, co-operation and guidance extended
to Rajasthan Project by Chairman and Managing Director, Director (Exploration &
Development) and Director (Finance) for its sustainability, encouraging the activities in
Heavy Oil project and NELP blocks in a progressive manner. This has ushered the Project
into a period of opportunity.
We also offer our thanks to Director (HR&BD) as well as Director(Operations), the
officers and staff in corporate office, field headquarters, all Projects and spheres for their
kind help and co-operation in carrying out the activities in the Project successfully. The
unstinted support and co-operation received from all the executives and staffs of Rajasthan
Project are thankfully acknowledged .

***************************************

59

You might also like