METHOD STATEMENT
TRANSFORMER REF RELAY
TESTING WORK
ELE/MS/TLC59/08-R0
CONSTRUCTION OF NEW HAFEET 2 X 20MVA PSS WITH 2 Nos. 33KV INCOMING FEEDERS
PROJECT IN NORTH BATINAH GOVERNATE
CLIENT MAJAN ELECTRICITY COMPANY S.A.O.C
CONTRACTOR CIVIL CONTRACTING Co. LLC
Doc. No ELE/MS/TLC59/08-R0 Rev No. 0 Date 20-11-17
INDEX
S No. DESCRIPTION PAGE No.
1.0 Purpose 03
2.0 Scope 03
3.0 Applicable Specifications & Standards 03
4.0 Difinition 03
5.0 Tools & Tackles 04
6.0 Job Safety Plan 04
6.1 Hazard Identification 04
6.2 Action by execution team 04
7.0 Responsibilities 04
7.1 Site Engineer/Testing Engineer 04
7.3 Safety Supervisor 04
8.0 Work Procedure 05
8.1 Notes & Precautions 05
8.2 Testing Procedure 06
8.2.1 Transformer Relay 06
9.0 Documents & Records 07
Page 2 of 6
CONSTRUCTION OF NEW HAFEET 2 X 20MVA PSS WITH 2 Nos. 33KV INCOMING FEEDERS
PROJECT IN NORTH BATINAH GOVERNATE
CLIENT MAJAN ELECTRICITY COMPANY S.A.O.C
CONTRACTOR CIVIL CONTRACTING Co. LLC
Doc. No ELE/MS/TLC59/08-R0 Rev No. 0 Date 20-11-17
1.0 PURPOSE
This Method Statement describes a proper work procedure shall be carried out during the relay
testing activities as per specification and contract drawings.
2.0 SCOPE
This document applies to the activities carried out by CIVILCO during the pre-commissioning testing
includes the secondary injection testing of protection relays protecting all the electrical equipment
in the New Hafeet Primary Substaion Project Owned by MJEC
• Scope of work
• General Specification
• Approved Relay Settings
• Approved Scheme drawings
• Relay Manual
• Test kit Manual
• Issued Method Statements
4.0. DEFINITION
• PM - Project Manager
• PE - Protection Engineer
• TE - Testing Engineer
• EE - Electrical Engineer
• QA/QC - Quality Assurance/Quality Control
• PTW - Permit to Work
• LOA - Limitation Of Access
• SFT - Sanction For Test
• CT - Current Transformer
• PT/VT - Potential Transformer / Voltage Transformer
• AC - Alternating Current
• DC - Direct Current
• DMT - Definite Minimum Time
• IDMT - Inverse Definite Minimum Time
• TMS - Time Multiplier Setting
• LED - Light Emitting Diode
• SCADA - Supervisory Control And Data Acquisition
• CB - Circuit Breaker
• E/S - Earth Switch
• Portable Tools
Page 3 of 6
CONSTRUCTION OF NEW HAFEET 2 X 20MVA PSS WITH 2 Nos. 33KV INCOMING FEEDERS
PROJECT IN NORTH BATINAH GOVERNATE
CLIENT MAJAN ELECTRICITY COMPANY S.A.O.C
CONTRACTOR CIVIL CONTRACTING Co. LLC
Doc. No ELE/MS/TLC59/08-R0 Rev No. 0 Date 20-11-17
• Digital Multimeter
• Megger
• Omicron Secondary Injection Testing Set
• PEP
• Tripping Hazard
• Trappinghazard
• Unguarded opening
• High Voltage
7.0 RESPONSIBILITY
Site engineer shall be overall responsible for the safe execution of complete Activity including but
not limited to.
• Organizing tools and equipment required for the work.
• Assigning work crew.
• Confirming the materials-handling in safe manner.
• Ensure all materials are inspected prior to utilizing at site.
• Ensure the availability of required technical documents like approved method statement,
Approved Drawings/Doc., calibration certificates at work place.
• Responsible for ensuring the all Testing activities are as per project requirement.
The safety supervisor shall be responsible for safe work execution at site.
Page 4 of 6
CONSTRUCTION OF NEW HAFEET 2 X 20MVA PSS WITH 2 Nos. 33KV INCOMING FEEDERS
PROJECT IN NORTH BATINAH GOVERNATE
CLIENT MAJAN ELECTRICITY COMPANY S.A.O.C
CONTRACTOR CIVIL CONTRACTING Co. LLC
Doc. No ELE/MS/TLC59/08-R0 Rev No. 0 Date 20-11-17
After meeting complete requirements , the following works are carried out for specified relay
❖ Clean the protection relay, check the relay components and the relay circuits before
secondary injection is carried out.
❖ Check that the current circuit shorting terminals at the base of the relay is making proper
contact when the relays are drawn out.
❖ Check that the auxiliary supply to the relay is within the specified limits of the relay.
❖ No electric protection alarms should be there in local control alarm panel and at the remote
alarm panel before commencement of test.
❖ Even though for current operated relays, internal current circuit shorting terminals are
provided, as far as possible avoid racking out / removing the relays when the equipment
protected is in service.
❖ Carry out the secondary injection test when the feeder is in isolated condition from any out
side supply feeding back.
❖ In case of OHL lines or transformer feeders, if only one end of the feeder is isolated, care
should be taken that the relays do not give a trip order to the other end of feeder which is
energised.
❖ Use test plugs / test blocks if provided for current / voltage injection. The CT secondaries
should be isolated / shorted and the current / voltage injected only to the relay.
❖ While testing the pick up and drop out of relays, always keep the time multiplier setting to
the minimum.
❖ While injecting current / voltage to the relay care should be taken that the current / voltage
injected does not exceed the continuous current / voltage rating of that particular relay.
❖ If the relays are connected to all the 3 phases, tests should be conducted for all the 3 phases
❖ The relay operating time should be tested at the adopted settings of the relay.
❖ Adjustment of pick up, drop out and operating time to be done only as per the relevant relay
instruction manual.
❖ If any other features or characteristics of the relay other than that described in this work
instruction are to be checked, carry out the testing as detailed in the relevant relay
instruction manual.
❖ Ensure that the flag/LED indications of the relay, alarm indication in local alarm panel and
at remote control panel/SCADA is received and the breaker trip circuit is energised as per
the relevant schematic diagram.
❖ After completion of test, disconnect the test circuits, test plugs and remove any CT circuit
shortings made, normalise CT/PT links removed. Take care that the test block cover is put
back.
Page 5 of 6
CONSTRUCTION OF NEW HAFEET 2 X 20MVA PSS WITH 2 Nos. 33KV INCOMING FEEDERS
PROJECT IN NORTH BATINAH GOVERNATE
CLIENT MAJAN ELECTRICITY COMPANY S.A.O.C
CONTRACTOR CIVIL CONTRACTING Co. LLC
Doc. No ELE/MS/TLC59/08-R0 Rev No. 0 Date 20-11-17
❖ After the test, confirm that all the settings are kept at the adopted settings, the relay flag
indications/LED are reset and all the alarm indications at matrix panel / local alarm panel
and at remote alarm panel are reset.
❖ Note that all the test values obtained are within limit prescribed in the particular relay
manual as per the approved settings
The protection relays will be tested by secondary injection after complete installation of the
feeder & concerned equipment as described below:
8.2.1 Create Over current module in the OCC file and configure Test test hard ware and enter the
settings as per the rely settings.
8.2.2 Inject the relay rated current current through the relay coil and check the measurements as per
the CT ratio in the Relay
8.2.3 Inject the current through the relay coil and measure the value at which the relay picks up.
8.2.4 Inject a current of 1.5 times the set value and note down the time for relay operation at the set
value of TMS.
8.2.5 Remove the current source and inject a voltage across the relay coil and stabilising resistance.
Measure the voltage at which the relay operates. This gives the approximate voltage developed
by the current transformer to cause relay operation.
8.2.6 Check the Relay LED and Output contact operation as per the relay configuration and scheme
drawing
1. Mark-Up drawings
2. Test Reports
Page 6 of 6