You are on page 1of 9

Analysis of Causes of Delay and Time

Performance in Construction Projects


Pablo González 1; Vicente González, Ph.D. 2;
Keith Molenaar, Ph.D., M.ASCE 3; and Francisco Orozco, Ph.D. 4
Downloaded from ascelibrary.org by National Institute of Technology, Tiruchirapalli on 11/17/17. Copyright ASCE. For personal use only; all rights reserved.

Abstract: Activity delays are a common issue in the construction industry and can increase project schedules and costs. Recent research
efforts have focused on the quantitative evaluation of delay impacts. The literature suggests that the construction industry is in need of
additional research to systematically relate the causes of delays to their impacts. To overcome this limitation, this paper analyzes delay
causes in activities that were not completed as scheduled. The paper contributes to a methodology to examine the qualitative (delay causes)
and quantitative (time performance) dimensions of the delay issue. The paper proposes two indicators, as follows: (1) reason for noncom-
pliance (RNC) as an indicator that characterizes scheduling failures, and (2) delay index (DI) as a time-performance indicator that describes
the impacts of delay on critical and noncritical activities. The paper presents two building projects as case studies, with planning and sub-
contractors as the primary RNCs that have the greatest impact on time performance. Planning was the most harmful delay cause on time
performance. DOI: 10.1061/(ASCE)CO.1943-7862.0000721. © 2013 American Society of Civil Engineers.
CE Database subject headings: Project management; Delay time; Construction management; Scheduling; Costs.
Author keywords: Activity delays; Project planning; Reasons for noncompliance; Relationship; Time performance; Cost and schedule.

Introduction be understood as those problems that prevent the normal activity


progress as planned at the operational level and provoke activity
Activity delays can negatively affect several dimensions of delays. According to Alarcón et al. (2005), field interference, lack
construction-project performance. Delays can lengthen schedules, of labor, subcontractor delays, design changes and delays, and lack
increase project costs, and jeopardize quality and safety. Delays are of materials are among the reasons that cause these problems.
one of the most common problems that affect the competitiveness These reasons can correspond with different project team members
of construction companies (Orozco et al. 2011) and the interests of such as owners, designers, general contractors, subcontractors, and
all stakeholders, including owners, designers, general contractors, materials suppliers. However, more research about the relationships
subcontractors, users, and others (Faridi and El-Sayegh 2006). between delay causes and their impacts in terms of time perfor-
The first step in identifying existing problems in projects and mance is needed. This paper explicitly examines these relationships
developing corrective actions is to determine their causes (Chang and attempts to link qualitative (delay causes) and quantitative
2002). It is not only relevant to quantify delay impacts on perfor- (time performance) dimensions.
mance but also to identify the primary causes of such delays to This paper proposes two indicators that can describe delay
mitigate their effects. Delay analysis in construction has been pri- impacts on critical and noncritical activities. The first indicator,
marily focused on the quantitative impact on the time performance reasons for noncompliance (RNC), is a delay indicator that char-
of projects, leaving little room to address the qualitative dimension acterizes the primary causes or reasons for the noncompletion of
of delays in terms of their causes. In this regard, the writers argue activities as planned in a project that result in scheduling failures
that an approach based on the study of the causes of scheduling (Ballard 2000). The second indicator, a delay index (DI), is a time-
failure (i.e., to analyze causes of delay) could help support the performance indicator. The writers argue that these indicators cover
qualitative dimension for delay analysis. Scheduling failures can the qualitative (i.e., RNC) and quantitative (i.e., DI) dimensions of
delays, and the writers applied these indicators in case study proj-
1 ects to analyze the relationships between these dimensions.
M.Sc., Director of Operations, Resinsa–Polytan, Santiago 7630628,
Chile. E-mail: operaciones@resinsa.com
The subsequent sections describe the research objectives and
2
Lecturer, Dept. of Civil and Environmental Engineering, Univ. of methodology reported in this paper, present relevant literature, dis-
Auckland, Auckland 1142, New Zealand (corresponding author). E-mail: cuss the approach used to relate delay causes and their time im-
v.gonzalez@auckland.ac.nz pacts, and analyze and discuss the primary findings of this paper.
3
Stanton Lewis Chair and Professor, Dept. of Civil, Environmental and
Architectural Engineering, Univ. of Colorado, Boulder, CO 80309-0428.
E-mail: keith.molenaar@colorado.edu Research Objectives and Scope
4
Assistant Professor, Faculty, Escuela de Ingeniería, Univ. Panamericana
Campus Guadalajara, Guadalajara 45010, México. E-mail: faorozco@up The primary objective of this paper is to analyze the relationships
.edu.mx
Note. This manuscript was submitted on March 7, 2012; approved on
between delay causes and their impacts on time performance in
March 29, 2013; published online on April 3, 2013. Discussion period open projects by studying the quantitative influence of RNCs relative
until January 20, 2014; separate discussions must be submitted for indivi- to construction delays characterized by DI. Delay analysis in this
dual papers. This paper is part of the Journal of Construction Engineering paper is first developed at an activity level (over critical and non-
and Management, © ASCE, ISSN 0733-9364/04013027(9)/$25.00. critical activities) and then at a project level. A secondary objective

© ASCE 04013027-1 J. Constr. Eng. Manage.

J. Constr. Eng. Manage., 2014, 140(1): 04013027


is to develop a preliminary methodology for addressing the delay- Delays are also a common problem and an increasing concern
cause and impact relationship. In this regard, the contribution of in the construction industry, according to studies about project
this paper relies on linking the quantitative and qualitative dimen- delays in countries such as Chile, Hong Kong, India, the United
sions of delays such that root-cause impacts can be mitigated. This States, Thailand, Saudi Arabia, Jordan, Kuwait, Nigeria, and Ghana
paper does not propose a new method to quantify delays, but it (Alarcón et al. 2001; Assaf et al. 1995; Augustine and Mangwat
furthers the understanding of delays as they contribute to this com- 2001; Ellis and Thomas 2003; Fereig 2006; Frimponga et al.
plex problem. 2003; Koushki et al. 2005; Kumaraswamy and Chan 1998; Lyer
and Jha 2006; Toor and Ogulana 2008; Odeh and Battaineg 2002).
In some cases, the magnitude of the problem can be substantial. For
Research Methodology instance, Lyer and Jha (2006) reported that 40% of 646 national
Downloaded from ascelibrary.org by National Institute of Technology, Tiruchirapalli on 11/17/17. Copyright ASCE. For personal use only; all rights reserved.

projects in the Indian construction industry were approximately


This research applies a case-study approach (Yin 1994) with an 40% behind schedule. In Chile, a sample of 34 projects showed
in-depth statistical analyses of data obtained from two building an average schedule delay of nearly 20% (Alarcón et al. 2001).
projects. Indicators used in the research reported in this paper ex-
amine the qualitative and quantitative dimensions of delay issues as
follows: (1) the qualitative dimension analyzes RNCs of delay Delay Causes
causes at the activity level, and (2) in the quantitative dimension, Research into the causes of project delay is available from several
the DI is applied to evaluate the activity-delay impact of the RNCs. sources in the construction industry and provides valuable qualitative
These indicators are aggregated to obtain information at the project information about the reasons of delays. A large part of the research
level. On-site data collection for this analysis was exhaustive and involved the collection of data from owners (public and private),
involved gathering a large amount of empirical evidence from the general contractors, subcontractors and specialists. Sources for the
two case study projects. Special attention was given to the meas- information include quantitative project data, case studies, surveys,
urement process for estimating activity delays through DI. and interviews. For example, in Kuwait a survey of construction
The research methodology consisted of five stages, as follows: companies was used to determine the primary causes of delays
(1) an in-depth review of the literature related to project delays, (Fereig 2006), and in Honk Kong, surveys, interviews, and case stud-
(2) definition of indicators for evaluating the qualitative and quan- ies were used (Lo et al. 2006). In the United States, Ellis and Thomas
titative dimensions of delays, (3) development of a methodology (2003) incorporated quantitative analysis in their study of the delay
for linking the qualitative and quantitative indicators, (4) applying issue. One of the most interesting conclusions from these delay stud-
the proposed methodology in two building-project cases, and ies is that the primary causes appear to cluster around management
(5) analyzing and discussing the primary findings of the research issues and the project environment (Abdullah and Koskela 2008).
reported in this paper with project personnel. The writers argue that this conclusion warrants additional research
to address current management practices and negative delay impacts,
and provides motivation for the research described in this paper.
Background

Time is a traditional index for project performance that is typically Quantification of Delay
measured by schedules. The actual time of project completion fre- The need for quantification of delays is apparent during construc-
quently exceeds the planned time, commonly known as a delay or tion for project control and postconstruction for claims analysis.
overrun. Projects consist of collections of activities and delays can For project control, the literature generally applies three approaches
be assessed at the activity or project level. At the activity level, to quantify delays, as follows: (1) critical-path method (CPM) tech-
delays can affect completion of activities, which may or may not niques, (2) scheduling resource allocation, and (3) earned-value
have an impact on succeeding activities. At the project level, analy- analysis. CPM is a standard tool for control (Galloway 2006) that
sis typically focuses on the impact of activity delays relative to is the basis for scheduling resource allocation. These two tech-
project completion (Shi et al. 2001). This section addresses several niques are combined to produce earned-value analyses (Liberatore
issues related to delays in terms of the importance of delay, inci- et al. 2001; Anbari 2003).
dence in the construction industry, and causes for delays. This re- Claims analysis uses various techniques to calculate delays.
view explores available quantification methods, suggests that a These are based largely on the use of CPM schedules in addi-
method to systematically relate the magnitude of a delay to its spe- tion to maintenance of effective documentation and availability of
cific causes during the project control phase is unavailable, and also information (Kartam 1999; Adhikaril et al. 2006; Youngjae et al.
suggests that incremental research is needed. The section concludes 2005). The typical methods cited in the literature are as follows:
with an exploration of the role of an RNC indicator. (1) as-planned versus as-built method, (2) global impact technique,
(3) as-planned technique, (4) impacted as-planned technique, (5) net-
impact technique, (6) time-impact analysis technique, (7) but-for,
Review of Delay Impacts on Construction
(8) isolated delay-type technique, (9) snapshot technique, (10) win-
At the project level, time is frequently used to control performance dows analysis, and (11) simulation (Arditi and Pattanakitchamroon
and its importance can directly affect economic issues (Alwi and 2006; Braimah and Ndekugri 2008; Bubshait and Cunningham
Hampson 2003; Bramble and Callahan 1992; Lyer and Jha 2006). 1998; Kao and Yang 2008; Alkass et al. 1996). More advanced tech-
Flyvbjerg et al. (2004) developed a relevant study that sampled 248 niques such as simulation, fuzzy logic, or expert systems can also be
infrastructure projects from 20 nations around the world over a used to quantify delays in projects (Marzouk et al. 2008; Ordoñez and
period of 70 years, finding “with very high statistical significance, Robinson 2005; Peña-Mora et al. 2008).
that cost escalation was strongly dependent on the length of the In summary, the importance of delays primarily lies in its cost
implementation phase.” Flyvbjerg et al. (2004) also concluded that implications in addition to its effects on other activities and project
cost escalation is even worse in developing countries than in completion. Several methods focus on either the qualitative or
Europe and the United States. quantitative dimensions of delays with different emphasis, scope,

© ASCE 04013027-2 J. Constr. Eng. Manage.

J. Constr. Eng. Manage., 2014, 140(1): 04013027


and research approaches. However, formal methods to link their slack (or float). Any delay to a critical activity will produce a delay
qualitative and quantitative dimensions are not apparent. The next in the project’s final completion date. A noncritical activity has
section proposes a methodology to help deal with the previously slack (or float). A delay to a noncritical activity will not affect
noted limitations in the analysis of delays. the project’s final completion date. However, when a noncritical
activity is delayed beyond its slack, it becomes a critical activity.
Hence, decision makers can choose activities to evaluate based on
Reasons for Noncompliance and Activity Delays factors such as the control effort level, technical complexity, time/
cost incidence, or their own preferences while bearing in mind the
The reasons for nonompliance represent causes that prevent the criticality of the activities. New activities other than those originally
scheduled completion of an activity during a short-term period, typ- planned can theoretically be inserted in the schedule as a result of
Downloaded from ascelibrary.org by National Institute of Technology, Tiruchirapalli on 11/17/17. Copyright ASCE. For personal use only; all rights reserved.

ically one workweek (Ballard 2000). In other words, RNCs can changes in the project design, engineering specifications, or the
characterize problems that affect the project-planning process. project contract agreement between the general contractor and
The writers argue that if an RNC prevents the completion of an the client, among others, which would indicate changes in the criti-
activity, this should imply some level of delay in the activity cal and noncritical activities noted in the original master plan.
and explain the cause of the delay. Therefore, RNCs as causes Furthermore, the dynamic nature of the planning process with
of activity delays and the delays themselves can be related to assess its different levels (long-term, medium-term, and short-term) can
causes and impacts in projects. One important point in this relation- also promote changes in the original plans (Ballard 2000). Thus,
ship is the relative contribution of each RNC to activity delays. In it could be necessary to add new activities as the planning process
other words, the extent of delays in terms of time performance can evolves. However, the methodology proposed in this paper assumes
be different from one RNC to another. This provides motivation for that the master plan is well-defined, and that critical and noncritical
an in-depth study of the RNCs that have the largest impact on time activities are already delineated by the decision makers (e.g., project
performance, first at an activity level and then at a project level. managers). Further research could consider a more dynamic plan-
Several RNCs (such as field interference, poor planning, defective ning process when selecting noncritical and critical activities.
drawings, lack of labor, lack of materials, lack of supervision, sub- The delay analysis methodology in this paper links qualitative
contractor delays, design changes and delays, and poor execution) (delay causes) and quantitative (time performance) by relating
have been proposed (Ballard 2000; Alarcón et al. 2005). This paper RNCs and their corresponding delay impacts at the activity and
proposes a more general RNC list that promotes simple, on-site project levels.
project analysis. For this reason and based on the literature review, Note that the issue of root-cause analysis and preventive actions
the writers decided to use the following general RNCs: (1) design, proposed in this paper are presented as a purely technical exercise.
(2) labor, (3) materials and equipment, (4) subcontracts, (5) weather, However, this process might even promote changes in current
(6) planning, (7) execution of work, and (8) others (Augustine and managerial and organizational practices in projects by identifying
Mangwat 2001; Assaf et al. 1995; Alarcón et al. 2005; Ballard 2000; causes, responsibilities, roles, and impacts. Thus, an ongoing im-
Ellis and Thomas 2003; Fereig 2006; Frimponga et al. 2003; Koushki provement process of the project practices that involve the planning
et al. 2005; Kumaraswamy and Chan 1998; Odeh and Battaineg process could be developed, but this investigation is outside the
2002; Toor and Ogulana 2008). Table 1 provides brief descriptions scope of this paper.
of the writers’ proposed general RNCs. To quantify delays, the paper applies a cumulative progress in-
The following sections describe the proposal of a qualitative and dex (actual and planned). The approach is similar to the earned-
quantitative delay methodology that applies the general RNCs that value technique for relating two cumulative value curves (Anbari
the writers propose. A case study illustrates the methodology and 2003). The goal is to initially measure the variation for each activity
results. between the actual and the planned values for a period of analysis,
and then consolidate them into only one value when the activities
are grouped around a cause of delay at the project level. The ap-
Qualitative and Quantitative Methodology for Delay proach uses a weekly analysis. Fig. 1 illustrates the methodology
Analysis and the steps are described next.

The use of RNCs is only relevant if they allow construction man-


Selection of Critical and Noncritical Activities to be
agers to know the most common causes of delays such that those
Scheduled in the Week
problems can be systematically reduced or even eliminated.
Defining critical and noncritical activities is required to apply In accordance with the master plan and different project priorities,
any activity-delay analysis. A critical activity is one without any management (e.g., the project manager, planning department,

Table 1. General RNCs


RNC Description
Design Covers the causes of delays related to problems with project design and documentation work (e.g., errors, changes, omissions and
complexity, or lack of detail in the drawings)
Labor Includes absenteeism, low productivity, and shortage of workers
Materials and equipment Delays attributable to the lack or shortage of materials and machinery for external reasons not attributable to the administration
(failure of the supplier)
Subcontracts Delays attributable to low productivity or missed deadlines by subcontractors
Weather Includes delays for adverse weather conditions that impede the normal operation of the project
Planning Caused by poor planning, control, and scheduling of the project, including all the disruptions of the project caused by mistakes or
oversights in the project-planning process
Execution of work Includes errors in the execution of tasks and inappropriate construction methods
Others Covers delays attributable to causes not covered by the previous RNCs (e.g., theft)

© ASCE 04013027-3 J. Constr. Eng. Manage.

J. Constr. Eng. Manage., 2014, 140(1): 04013027


Start of
Project

Start of week i 1. Selection of critical (AC) and 4. Initial data collection of the
(i=1…..n) non-critical (ANC) activities to delay cause for each
be scheduled in week i non-completed activity

2. Data collection for each 5. Determination of Reasons for


activity scheduled at the Non Compliance
Downloaded from ascelibrary.org by National Institute of Technology, Tiruchirapalli on 11/17/17. Copyright ASCE. For personal use only; all rights reserved.

beginning of week i: Rei RNCC and RNCGL


and WSi

6. Calculation of Project
3. Data collection for each Delay Indicators
activity scheduled at the (DIC and DINC) and the
end of week i: (Rei+1) weighted average of the
RNC’s

7. Relationship between
i) Does each critical and global RNC’s
activity reached and WA-RNC’s
the scheduled No
progress? (Rei<WSi)

Yes 8. Determination of the


(Rei<WSi) highest impact causes in
week i

ii) Does the


delay Finish of
analysis No Project
continue?

Yes

Fig. 1. Methodology of quantitative delay analysis

production, and planning engineer) selects the activities to be per- Data Collection for Each Activity Scheduled at the End
formed in week i. The selected activities must be separated as being of the Week
critical (AC ) or noncritical (ANC ). It is also recommended that the At the end of week i, project management should measure the
activities should have simple and measurable progress. progress of the scheduled activities. In other words, it should be
checked to see if the activities were performed in accordance with
Data Collection for Each Activity Scheduled at the the requirements stated by management (e.g., physical advance,
Beginning of the Week quality, and details). Management should also gather the actual
weekly production data for each activity, as follows:
At the beginning of each week, along with the scheduling of both • Reiþ1 : Actual weekly cumulative progress by activity at the end
kinds of activities, project management should collect the following of week i (beginning of week i þ 1), i ¼ 1 : : : n, as a percentage
progress data for AC and ANC (Table 2): of the total progress (%); and
• Rei , actual weekly cumulative progress by activity at the begin- • Decision block, asks whether each activity (critical and noncri-
ning of week i, i ¼ 1 : : : n, as a percentage of the total progress tical) reached the scheduled progress; if the answer is no, the
(%); and step in the next section is followed, and if the answer is yes,
• WSi , planned weekly cumulative progress by activity for the the project is finished.
week i, i ¼ 1 : : : n, as a percentage of the total progress (%).
Data Collection of the Delay Cause for Each
Table 2. Example of Step 2 Noncompleted Activity
Activity number Criticality of the activities Rei (%) WSi (%)
When an activity has not reached the planned progress, manage-
1 ANC 5 8 ment should identify the delay cause for each activity (Table 3).
2 AC 20 30 The causes should be assigned in accordance with the general
3 AC 10 15 RNCs (Table 1). The proposed RNCs can be modified and config-
4 ANC 34 56 ured to reflect on-site conditions, project characteristics, construc-
5 AC 25 28
tion contract, management style, and relationships (e.g., general

© ASCE 04013027-4 J. Constr. Eng. Manage.

J. Constr. Eng. Manage., 2014, 140(1): 04013027


Table 3. Example of Step 4 Table 5. Example of Step 6
Whether Activity number Rei WSi Reiþ1
Criticality scheduled and criticality (%) (%) (%) Cause DI
Activity of the project has Rei WSi Reiþ1 Cause of
1, ANC 5 8 8 — —
number activities been reached (%) (%) (%) delay
2, AC 20 30 25 Planning DIðCÞ ¼ 0.5
1 ANC Yes 5 8 8 — 3, AC 10 15 12 Subcontracts DIðCÞ ¼ 0.6
2 AC No 20 30 25 Planning 4, ANC 34 56 40 Subcontracts DIðNCÞ ¼ 0.72
3 AC No 10 15 12 Subcontracts 5, AC 25 28 27 Materials and DIðCÞ ¼ 0.33
4 ANC No 34 56 40 Subcontracts equipment
5 AC No 25 28 27 Materials and
Downloaded from ascelibrary.org by National Institute of Technology, Tiruchirapalli on 11/17/17. Copyright ASCE. For personal use only; all rights reserved.

equipment
and activity progress in terms of production, with Rei as the starting
point for that week. When there is a delay, Reiþ1 reaches a weekly
contractor/client and general contractor/subcontractor), among progress less than WSi and, using a simple linear interpolation ap-
others. To render the results as representative as possible it is im- proach, the delay in terms of time in relation to projected progress
portant to include the most relevant delay causes in the RNCs. for reaching WSi can be estimated. It is also possible to estimate the
delay in terms of production as the difference between WSi and
Rei . Thus, by using the previous notion, DI allows the calculation
Incidence of Reasons for Noncompliance of the delay extent (Table 5) using Eq. (1):
The RNCs are determined for each incomplete activity in week i WSi − Reiþ1
(if any), allocating RNCs for both critical (RNCC ) and global DI ¼ ð1Þ
WSi − Rei
(RNCGL ) activities, i.e., those RNCs considering critical and non-
critical activities. The percentage incidence of RNCC is calculated The weighted average for each RNC can then be calculated for
by considering only critical activities. Otherwise, the incidence of either critical [WA-RNCiðCÞ ] or global [WA-RNCiðGLÞ ] activities in
RNCGL is estimated using all the activities (critical plus noncritical accordance with Eqs. (2) and (3):
activities) see Table 4.
P
DIRNCiðCÞ
WA-RNCiðCÞ ¼ P ð2Þ
Calculation of Project Delay Indexes and the Weighted DIAllðCÞ
Average of the RNCs
P
The DI allows for calculation of the delay between the planned DIRNCiðCþNCÞ
progress and the actual progress for an activity. Fig. 2 illustrates WA-RNCiðGLÞ ¼ P ð3Þ
DIallðCþNCÞ
the method used to estimate the activity delay using the DI.
WSi represents the cumulative planned progress for a given week where WA-RNCiðCÞ = weighted average index for the i RNC con-
sidering only critical activities; DIRNCiðCÞ = sum of DIðCÞ for the
Table 4. Example of Step 5 corresponding RNC; DIallðCÞ = sum of all DIðCÞ ; WA-RNCiðGLÞ =
weighted average index for the i RNC considering all activities
RNCC IncidenceC (%) RNCGL IncidenceGL (%)
(critical and noncritical); DIRNCiðCþNCÞ = sum of all DIðCÞ and
Subcontracts 33.3 Subcontracts 50 DIðNCÞ for the corresponding RNC; and DIallðCþNCÞ = sum of DI
Planning 33.3 Planning 25 for all the incomplete activities.
Materials and 33.3 Materials and 25 Table 6 shows an example of calculations of WA-RNCðCÞ and
equipment equipment WA-RNCðGLÞ for a specific RNC (subcontracts), and Table 7 illus-
trates both indexes for each RNC.

Cumulative
Progress (%) Relationship between Critical and Global RNCs and
WA-RNCs
WSi
CD: Control date of the After calculating both indicators for critical and global activities
scheduling per week i
(i.e., RNCs incidence and WA-RNCs), the indexes are related to
each RNC in the corresponding week. In other words, delay causes
Rei+1 are related to their time impact. In this manner, project management
can deal with both kinds of delay causes but with a different em-
phasis and priority. First, because they can produce direct losses in
Rei
the overall project, time delay causes that affect critical activities
should be resolved as soon as possible. Delay then causes that im-
pact global activities should be managed such they do not damage
Control the overall project performance if they persist (Table 8).
Dates (Time)
CDi CDi+1

Determination of the Highest Impact RNC and WA-RNC


Delay of the
activity in week i Finally, the process is repeated until all the activity data for week i
are processed. This is a key step in evaluating the results of both
Fig. 2. DI calculation
RNC and WA-RNC. After identifying the delay causes with the

© ASCE 04013027-5 J. Constr. Eng. Manage.

J. Constr. Eng. Manage., 2014, 140(1): 04013027


Table 6. Example of WA-RNCðCÞ and WA-RNCðGLÞ Calculation for Subcontractors’ RNC
P P P P P
Activity and criticality DI DIðCÞ DIallðCÞ WA-RNCðCÞ DIRNCðCþNCÞ DIall WA-RNCðGLÞ
3, AC 0.6 0.6 1.43 0.6=1.43 ¼ 0.42 1.32 2.15 1.32=2.15 ¼ 0.61
4, ANC 0.72

Table 7. Summary of WA-RNCðCÞ and WA-RNCðGLÞ Indexes for Each 3. The construction company responsible for managing and
RNC executing these projects has several years of experience in
Cause WA-RNCðCÞ WA-RNCðGLÞ multiunit residential buildings;
Downloaded from ascelibrary.org by National Institute of Technology, Tiruchirapalli on 11/17/17. Copyright ASCE. For personal use only; all rights reserved.

4. Subcontracts held approximately 80% of the principal tasks of


Planning 0.35 0.23
work being controlled in both case studies; and
Subcontracts 0.42 0.61
Materials and Equipment 0.23 0.15
5. During the development of the project, the control department
conducted weekly schedules, which determined what activities
would be done the following week.
The following sections describe the application of the method-
Table 8. Example of Step 7 ology (Fig. 1) and report the primary results for both case studies
Causes RNCC (%) WA-RNCðCÞ RNCGL (%) WA-RNCðGLÞ A and B.
Planning 33.3 0.35 25 0.23
Materials 33.3 0.42 25 0.61 Case Study A: Relationships between Delay Causes
Subcontracts 33.3 0.23 50 0.15 and Time Impact
Fig. 3 illustrates the average percentages (partials) of all the weekly
RNCs (both RNC global and critical) in Case A and the accumu-
highest impacts, project management should carry out actions to lated RNC percentages (RNC global accumulated and RNC criti-
reduce and mitigate the impact of these causes. cal). These indicate that the planning and subcontractor RNCs
The decision block asks whether the methodology process together represent nearly 80% of the most frequent delay causes
continues for the next week or it is stopped (when the project is in both global and critical RNC analyses. The partial percentages
finished). obtained by subcontracts in the global RNCs decreases in the criti-
cal RNCs; otherwise, the partial percentage of planning increases
its incidence from the global RNCs to the critical RNCs. Therefore,
Case Study Illustrations the critical RNC percentages suggest that planning, and not sub-
contracts, is the most critical frequent cause of delay in the project.
To demonstrate the methodology, two multiunit residential building These differences provide noteworthy information about the
projects executed by a construction firm in Santiago, Chile, were project. For instance, the most frequent delay causes that affect
used as illustrative case studies. The research described in this pa- the overall activities may not be the same causes that impact the
per lasted 20 weeks, during which planning measurements of critical activities.
project activities were made. Table 9 details the characteristics The incidence of the primary two RNCs, subcontracts and plan-
of both projects. ning (Fig. 3), are not significantly different in relative terms be-
The following study notes provide additional detail on the case tween the global and critical RNCs. However, the reason for
studies: doing this analysis is to focus not only on global activities, but also
1. Study stage refers to the execution phase in which the activities on critical activities in a project. Thus, different degrees of attention
were controlled: could be necessary and diverse management actions could be ap-
• Concrete work refers to all the activities in terms of struc- plied in accordance with the criticality of the delay causes, allowing
tural components in the building (e.g., columns, slabs, and project management to identify the delay causes with higher inci-
beams); and dence. Furthermore, this analysis allows preliminary identification
• Finishing refers to all the activities related to permanent of those delay causes that have more impacts to avoid the problem
work in the building. These activities do not have a struc- of delay causes being obscured when using simpler analysis of de-
tural nature but are necessary for the proper functioning of lay causes at the global level.
the building (e.g., partition walls, windows, and doors). Fig. 4 illustrates the weighted averages indexes for each RNC
2. Activities controlled refers to number of activities controlled (WA-RNC) in Case A in addition to their cumulative values, show-
by the researchers in each project studied; ing that the most significant delay causes are again planning and
subcontractors with a delay impact close to 80% (global and critical
analysis). In this analysis, planning has the higher impact in terms
of delay, experiencing an increase from the global activities to the
Table 9. Projects’ Characteristics
critical activities, unlike subcontractors, which reduces its delay im-
pact. This indicates that the most significant delay cause in terms of
Description of project component Project A Project B time performance is planning. If the delay analysis considers only
Area (m2 ) 20,000 8,000 global activities, subcontractors are the most important delay cause.
Number of floors 23 15 However, a detailed analysis on critical activities illustrates that
Number of apartments 300 117 planning is the most impacting delay cause considering the esti-
Study stage Interior and Concrete mated damages relative to project time-performance. These results
exterior finishes work–finishing also illustrate that even though a cause may be more common than
Number of activities 40 47 another, this does not indicate that it has the greatest impact on the
controlled
project.

© ASCE 04013027-6 J. Constr. Eng. Manage.

J. Constr. Eng. Manage., 2014, 140(1): 04013027


Downloaded from ascelibrary.org by National Institute of Technology, Tiruchirapalli on 11/17/17. Copyright ASCE. For personal use only; all rights reserved.

Fig. 3. Global and critical RNCs in Case Study A

Case Study B: Relationships between Delay Causes impact on critical activities. The similarities in the results for these
and Time Impact case studies suggest that management’s attention should have been
directed towards both internal (e.g., planning) and external (e.g., sub-
Fig. 5 shows the RNC percentages (partials and accumulated) in
contractors) issues related to the supply chain of the project.
Case B. These indicate that the planning and subcontractor RNCs
Validation of this methodology was carried out by holding a
together represent nearly 80% of the most frequent delay causes
panel discussion with the project personnel (including project
(global and critical), which is similar to Case A. The writers suggest
managers, site engineers, and supervisors) and clients for both
that the same explanation for the behavior of Case A is valid in projects. In general, project personnel reported that the methodol-
Case B for the RNCs incidence patterns. ogy was interesting and robust. In terms of the primary findings,
Similarly, Fig. 6 illustrates the weighted averages indexes for the project personnel and clients were surprised with the results
each RNC (WA-RNC) in Case B and their cumulative values. In because they assumed that the primary reasons for delays were
this case, the most significant delay causes are planning and sub- external (e.g., subcontractors). After this panel, project personnel
contractors, with a delay impact close to 80% (global and critical decided to use this information to change some of their manage-
analysis). The most harmful delays are caused by planning (46%). ment practices. First, they sought to improve their internal planning
Again, given the similar patterns, the explanation for Case A is processes, and second, they involved subcontractors in the plan-
equally valid in Case B. ning process. The clients also assumed responsibility and improved
In summary, both Cases A and B have similar behaviors in their project information-delivery and corresponding communica-
that planning and subcontracts are the most significant causes of de- tion process. Having in mind this feedback, the writers argue that a
lay. However, in both cases the most frequent delay cause for the delay apportionment between the client and general contractor
global activities is subcontracts, whereas the planning RNC has more could be performed effectively if delay causes and responsibilities

Fig. 4. Global and critical WA-RNC in Case Study A

© ASCE 04013027-7 J. Constr. Eng. Manage.

J. Constr. Eng. Manage., 2014, 140(1): 04013027


Downloaded from ascelibrary.org by National Institute of Technology, Tiruchirapalli on 11/17/17. Copyright ASCE. For personal use only; all rights reserved.

Fig. 5. Global and critical RNCs in Case Study B

Fig. 6. Global and critical WA-RNC in Case Study B

are well-defined from the beginning. In fact, the RNCs that were insight into this complex problem. This paper presents a meth-
established in the proposed methodology described in this paper odology for analyzing the qualitative (delay causes) and quanti-
could form the basis for calculating a delay apportionment that tative (time performance) dimensions of the delay issue that uses
could theoretically be weighted and allocated by applying the cor- two indicators, (1) RNC as the cause of delay, and (2) DI as a
responding WA indexes. delay indicator. This methodology was tested in two case studies
In subsequent individual interviews, project personnel recog- of building projects.
nized improvements in short-term and medium-term planning as The methodology provided information for project managers
a result from these changes. They also adopted a new perspective to make better decisions about the delay causes and assisted in
for managing delays in their projects. Even though there are no hard focusing management’s actions toward mitigating delay impacts
data available on the impacts of subsequent performance based on on a weekly basis. Although it is quite common in practice to base
these changes in the management practices, the writers suggest that decisions only on the delay causes that most frequently affect
the opinions from project personnel represent evidence that sup-
project completion, linking delay causes with their impacts on time
ports the value of the delay methodology reported in this paper
performance can be overlooked. The analyses carried out in the
and tested on their projects.
case studies showed that not only the frequency of delay causes,
but also the delay impact and its relationship with its causes,
Conclusions can be properly considered in a methodological framework. In this
regard, the delay causes with the greatest impact on project time-
The writers’ paper reports on the relationship between delay performance could be identified through the weighted average of
causes and their impacts on time performance to provide some the reasons for noncomplianace.

© ASCE 04013027-8 J. Constr. Eng. Manage.

J. Constr. Eng. Manage., 2014, 140(1): 04013027


The methodology also allows for differentiation between delay Bramble, B. B., and Callahan, M. T. (1992). Delay construction claims,
impacts on both global activities (critical and noncritical) and criti- 2nd Ed., Wiley, New York.
cal activities. This analysis helps to prioritize management efforts Bubshait, A. A., and Cunningham, M. J. (1998). “Comparison of delay
over resources and time directed to mitigate the effects of specific analysis methodologies.” J. Constr. Eng. Manage., 124(4), 315–322.
Chang, A. S. (2002). “Reasons for cost and schedule increase for engineer-
delay causes. The writers consider that the implementation of this
ing design projects.” J. Constr. Eng. Manage., 18(1), 29–36.
methodology will help in identifying real causes that affect produc- Ellis, R. D., and Thomas, H. R. (2003). “The root causes of delays in high-
tivity, thereby decreasing wasted resources, time, and money. way construction.” Proc., 82nd Annual Meeting of the Transportation
In the case studies, the main results showed that planning and Research Board, Washington, DC, 1–16.
subcontracts RNCs are the more frequent delay causes and have Faridi, A. S., and El-Sayegh, S. M. (2006). “Significant factors causing
also the larger impact in terms of time performance. The method- delay in the UAE construction industry.” Constr. Manage. Econ.,
Downloaded from ascelibrary.org by National Institute of Technology, Tiruchirapalli on 11/17/17. Copyright ASCE. For personal use only; all rights reserved.

ology demonstrated that the subcontracts RNC was the most im- 24(11), 1167–1176.
portant delay cause at the global level (frequency and impact). Fereig, S. M. (2006). “Managing construction delay in international
However, this pattern was reversed when the analysis was con- projects with special reference to the Arabian Gulf area.” Proc., 3rd
ducted at the critical activities level. As a result, the planning Project Management Institute—College of Scheduling (PMI-COS)
RNC was the most important delay cause. These results reveal that Conf., Orlando, FL.
Flyvbjerg, B., Mette, K., Holm, S., and Buhl, S. L. (2004). “What causes
even though one RNC may occur more frequently than another, it
cost overrun in transport infrastructure projects?” Transp. Rev., 24(1),
does not indicate that the more frequent RNC has the greatest im- 3–18.
pact on the project. These findings were discussed and validated Frimponga, Y., Oluwoyeb, J., and Crawford, L. (2003). “Causes of delay
with the project personnel and clients of both projects. and cost overruns in construction of groundwater projects in a devel-
The methodology proposed in this paper can help identify re- oping countries; Ghana as a case study.” Int. J. Proj. Manage., 21(5),
lationships between RNCs and their impacts on projects that will 321–326.
allow management to direct construction projects more quickly and Galloway, P. D. (2006). “Survey of the construction industry relative to the
effectively. Further research should focus on how to improve the use of CPM scheduling for construction projects.” J. Constr. Eng.
methodology and evaluate assumptions related to estimating delays Manage., 132(7), 697–711.
for more dynamic planning processes. Kao, C. K., and Yang, J. B. (2008). “Comparison of windows-based delay
analysis methods.” Int. J. Proj. Manage., 27(4), 408–418.
Kartam, S. (1999). “Generic methodology for analyzing delay claims.”
References J. Constr. Eng. Manage., 125(6), 409–419.
Koushki, P. A., Al-Rashid, K., and Kartam, N. (2005). “Delays and cost
Abdullah, A., and Koskela, L. (2008). “What can be learned from studies of increases in the construction of private residential projects in Kuwait.”
delay on construction?.” Proc., 16th Annual Conf. of Int., Group for Constr. Manage. Econ., 23(3), 285–294.
Lean Construction, Manchester, UK. Kumaraswamy, M., and Chan, D. W. M. (1998). “Contributors to construc-
Adhikaril, I., Kim, S.-Y., and Lee, Y.-D. (2006). “Selection of appropriate tion delays.” Constr. Manage. Econ., 16(1), 17–29.
schedule delay analysis method: Analytical hierarchy process (AHP).” Liberatore, M. J., Pollack-Jhonson, B., and Smith, C. A. (2001). “Project
Proc., Technology Management for the Global Future, IEEE, management in construction: Software use and research directions.”
New York, 483–488. J. Constr. Eng. Manage., 127(2), 101–107.
Alarcón, L. F., Diethelm, S., Rojo, O., and Calderon, R. (2005). “Assessing Lo, T. Y., Fung, I. W. H., and Tung, K. C. F. (2006). “Construction delays in
the impacts of implementing lean construction.” Proc., Int. Group Hong Kong in civil engineering projects.” J. Constr. Eng. Manage.,
for Lean Construction Annual Conf., Group for Lean Construction, 132(6), 636–649.
Sydney, Australia, 387–393. Lyer, K. C., and Jha, K. N. (2006). “Critical factors affecting schedule per-
Alarcón, L. F., Grillo, A., Freire, J., and Diethelm, S. (2001). “Learning formance: Evidence from Indian construction projects.” J. Constr. Eng.
from collaborative benchmarking in the construction industry.” Manage., 132(6), 636–649.
Proc., 9th Annual Conf. of Int., Group for Lean Construction, Marzouk, M., El-Dokhmasey, A., and El-Said, M. (2008). “Assessing con-
Singapore, 1–10. struction engineering-related delays: Egyptian perspective.” J. Prof.
Alkass, S., Mazerolle, M., and Harris, F. (1996). “Construction delay Issues Eng. Educ. Pract., 134(3), 315–326.
analysis techniques.” Constr. Manage. Econ., 14(5), 375–394. Odeh, A. M., and Battaineg, H. T. (2002). “Causes of construction delay:
Alwi, S., and Hampson, K. (2003). “Identifying the important causes of Traditional contracts.” Int. J. Proj. Manage., 20(1), 67–73.
delay in building construction projects.” Proc., East Asia-Pacific Conf. Ordoñez, A. V., and Robinson, A. (2005). “Fuzzy logic approach for ac-
on Structural Engineering and Construction, Bali, Indonesia. tivity delay analysis and schedule updating.” J. Constr. Eng. Manage.,
Anbari, F. T. (2003). “Earned value project management method and 131(1), 42–51.
extensions.” Proj. Manage. J., 34(4), 12–23. Orozco, F., Serpell, A., Molenaar, K., and Forcael, E. (2011). “Modeling
Arditi, D., and Pattanakitchamroon, T. (2006). “Selecting a delay analysis competitiveness factors and indexes for construction companies: Find-
method in resolving construction claims.” Int. J. Proj. Manage., 24(2), ings of Chile.” J. Constr. Eng. Manage.
145–155. Peña-Mora, F., Han, S., Lee, S., and Park, M. (2008). “Strategic-operational
Assaf, S. A., Al-Khalil, M., and Al-Hazmi, M. (1995). “Causes of delay construction management: Hybrid system dynamics and discrete event
in large building construction projects.” J. Manage. Eng., 11(2), approach.” J. Constr. Eng. Manage., 134(9), 701–710.
45–50. Shi, J., Cheung, S. O., and Arditi, D. (2001). “Construction delay compu-
Augustine, U. E., and Mangwat, J. (2001). “Time-overrun factors in tation method.” J. Constr. Eng. Manage., 127(1), 60–65.
Nigerian construction industry.” J. Constr. Eng. Manage., 127(5), Toor, S. U. R., and Ogulana, S. O. (2008). “Problems causing delays in
419–425. major construction projects in Thailand.” Constr. Manage. Econ.,
Ballard, G. (2000). “The last planner system of production control.” Ph.D. 26(4), 395–408.
dissertation, School of Civil Engineering, Faculty of Engineering, Univ. Yin, R. (1994). Case study research: Design and methods, Sage, Thousand
of Birmingham, Birmingham, UK. Oaks, CA.
Braimah, N., and Ndekugri, I. (2008). “Factors influencing the selection Youngjae, K., Kyungrai, K., and Dongwoo, S. (2005). “Delay analysis
of delay analysis methodologies.” Int. J. Proj. Manage., 26(8), method using delay section.” J. Constr. Eng. Manage., 131(11),
789–799. 1155–1164.

© ASCE 04013027-9 J. Constr. Eng. Manage.

J. Constr. Eng. Manage., 2014, 140(1): 04013027

You might also like