~ A PERTAMINAGAS ELECTRICAL CONTRACT NO.: $P-020/PG0330/2013-87 . DOCUMENT NUMBER: ) PT. SURYA CIPTA TEKNIK SLS-75-ELE-CL-005 eS JASA PERANCANGAN PENGADAAN DAN INSTALASI SISTEM OTOMASI, SISTEM METER, SCADA DAN TELEKOMUNIKASI 0.48 kV / 0.4 kV TRANSFORMER SIZING — ARUN APPROVE CONSTRUCTION ‘Approved for Construction Re-Approved for Design 06/03/2014 05/02/2014 29/01/2014 | Approved for Design RP 22/11/2013 | Issued for Approval AS | RP/UM 4/11/2013 | Issued for Review AS | RP/UM By | Check. | Approv. Approv. Revision’! pats Status Code Code PT SURYA CIPTA TEKNIK PERTAGAS. PT.SURYACPTATEKNIK a JASA PERANCANGAN PENGADAAN DAN KONSTRUKS! PEMBANGUNAN INSTALASI SISTEM OTOMASI, SISTEM METER, (77 PRRTARINAGAS SCADA DAN TELEKOMUNIKASI 9 Date : 06/03/2014 SLS-75-ELE-CL-005 | Rev. 0 | 0.48 kV/0.4 kV TRANSFORMER SIZING - ARUN Page 2 of 6 REVISION SHEET Revision Revision Revision Page Page Attachment alelelo|*|2]3 Alele]°|t|213 alele]o|1|2]3 Tale 31 1 x[x amex 32 2 Tel: 33 3 4 [x 34 5 (Xx 35 6 (x|x 36 meal x 37 8 38 9 39 10 40 1 41 12 a2 IL 3 43 14 44 15 45 16 7 18 19 20 21 22 23 24 25 26 2 28 29 30 JASA PERANCANGAN PENGADAAN DAN KONSTRUKS! a PEMBANGUNAN INSTALASI SISTEM OTOMASI, SISTEM METER, PT.SURYACPTA TEKNIK U7 PERTAKINAGAS ‘SCADA DAN TELEKOMUNIKASI a Date : 06/03/2014 SLS-75-ELE-CL-005 | Rev. 0 | 0.48 kV/0.4 kV TRANSFORMER SIZING - ARUN Page 3 of 6 COMMENT SHEET Add Chapter A 7 6 Yes A All All Layout shall be orderly Yes B All All Header shall be orderly Yes Wrong typing shall be B ip 7 a Yes ) PT.SURYA CPTA TEKNIK JASA PERANCANGAN PENGADAAN DAN KONSTRUKS! SCADA DAN TELEKOMUNIKASI 9 L PERTAMINAGAS | PENBANGUNANINSTALAS! SISTEM OTOMASI SISTEM METER, Date : 06/03/2014 SLS-75-ELE-CL-005 | Rev. 0 | 0.48 kV/0.4 kV TRANSFORMER SIZING - ARUN Page 4 of 6 Table of Contents 1 PURPOSE-----~ 2 REFERENCE-—---—- 3. ENVIRONMENT CONDITION 4 BASIS AND ASSUMPTION-—— 5 SYSTEM DESCRIPTION 6 TRANSFORMER SIZING —-- 7 CONCLUSION -- 4 JASA PERANCANGAN PENGADAAN DAN KONSTRUKS! PEMBANGUNAN INSTALAS! SISTEM OTOMASI, SISTEM METER, Pr PERTAMINAGAS ‘SCADA DAN TELEKOMUNIKASI Date : 0603/2014 SLS-75-ELE-CL-005 | Rev. 0 | 0.48 kV/0.4 kV TRANSFORMER SIZING - ARUN Page 5 of 6 1 PURPOSE This document provides transformer sizing due to the installation for Metering Station in the PT. LNG Arun Plant, Arun — Aceh. MCC/Switchgear Room, Control Room, Metering System, SCADA System and Telecomunication system will be installed. Therefore, it is necessary to calculate the Transformer to verify that the total load needed in this area. This calculation to define the capacity of transformer will be used. 2. REFERENCE SLS-75-ELE-DW-002 : Overall One Line Diagram - Arun ‘SLS-70-ELE-DB-001 Electrical Design Basis SLS-70-ELE-SP-014 : Oillmmerse Power Transformer Specification SLS-75-ELE-LI-001 Load List - Arun NEC : National Electrical Code 3. ENVIRONMENT CONDITION The environment condition to be taken into consideration for the sizing cable calculation as follows - Ambient Temperature Max. Temperature suaoiC, Min. Temperature nae 2orG: - Max. Relative Humidity 2 94%, - Altitude not exceed 100 m above sea level. - Environment Atmosphere Tropical. 4 BASIS AND ASSUMPTION The sizing of the Power transformer shall be considered to accommodate the electrical load in the Arun Metering Station based on document no. SLS-75-ELE-LI-001 “Load List — Arun”, 5 SYSTEM DESCRIPTION The Arun Metering Station will be fed from existing electric power in the substation, the existing voltage rating is 480 VAC, 50 Hz and the system in the Arun Metering station is 400 VAC, 50 A J PaRTANINAGAS PEMBANGUNAN INSTALAS! SISTEM OTOMASI, SISTEM METER, PT.SURYACPTATEKNIK JASA PERANCANGAN PENGADAAN DAN KONSTRUKS! | ‘SCADA DAN TELEKOMUNIKASI SLS-75-ELE-CL-005 | Rev. 0 | 0.48 kV/0.4 kV TRANSFORMER SIZING - ARUN Date : 06/03/2014 Page 6 of 6 Hz, It have any difference voltage source rating, in this case, new transformer will be install at ‘Arun Metering station TRANSFORMER SIZING The sizing of Power Transformer: Step 1 For Power Transformer, it is recommended that Transformer rating equal total maximum demand load plus 15% plan future load plus 20% spare capacity. Step 2 Select a standard Transformer Rating Based on the above guidelines, Power Transformer rating can be derived from formulas: Transformer (TR) Capacity = Peak Loads + 15% Planned Future + 20% Spare Capacity Refer to Electrical Load list document number SLS-75-ELE-LI-001 Load List — Arun, the peak loads value is: Power Transformer ARB: 04 Capacity: Peak Load = 98.12 kVA Plan load 15% = 14.72 kVA Spare 20% = 19.62 kVA Transformer Capacity (TR) = 132.46 KVA Conclusion Based on above calculation the power transformers would be selected (ARB-ET-001) is on range 150 kVA, 0.48kV/0.4kV, 50 Hz, 3 Phase.

You might also like